AMEND_9.pdf
PDF 30 KB Posted
- Solicitation number
- AG-52B1-S-15-0007
About this file
AMENDMENT 9
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMEND_12.pdf | ||
| AMEND_11.pdf | ||
| AMEND_10.pdf | ||
| LINE_ITEM_SCHEDULE_30JAN2015.pdf | ||
| INSTRUCTIONS_FOR_QUOTES_30JAN2015.pdf | ||
| AMEND_7.pdf | ||
| AMEND_6.pdf | ||
| AMEND_5.pdf | ||
| PWS_21JAN2015.pdf | ||
| Location_of_Services_and_Line_Item_Schedule_21JAN2015.pdf | ||
| AMEND_4_01152015.pdf | ||
| AMEND_3_14JAN2015.pdf | ||
| AMEND_2.pdf | ||
| Location_of_Services_and_Line_Item_Schedule_7JAN2015.pdf | ||
| AMEND_1_5JAN2015.docx | DOCX document | |
| QASP_.pdf | ||
| PastPerformanceQuestionaire.doc | DOC document | |
| ATTACHMENTS_1.pdf | ||
| CTR_INFORMATION.pdf | ||
| LINE_ITEM_LOCATION_PWS.pdf | ||
| WAGE_DET_FOREST_9DEC2014.pdf | ||
| AG-52B1-S-15-0007_18DEC2014.pdf |
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation: AG-52B1-S-15-0007 Vegetation Management at the Mark Twain National Forest
Amendment 9:
CHANGES:
1. The line item schedule has been changed to reflect the estimated quantities for each of the six districts. Six line item schedules have been posted. The checked box on the first page of the line item schedule indicates which area it corresponds to. In order to be considered for award the revised line item schedule(s) with the revision date of 30 January 2015 must be submitted for each area you are quoting. Line item schedules must contain prices for all line items for each area included in your quote.
2. Instructions for the Preparation of Quotes has been revised (30 January 2015). Items a(1) and a(2) have been revised for the change in line item schedules. Items a(10) and a(11) were also updated to reflect the revised date for question submission and notes that the site visit/pre-quote meeting already occurred on 9 January 2015.
3. The following provision is hereby incorporated by reference 52.216-27, Single or Multiple Awards (Oct 1995).
4. “ADDITIONAL CONTRACT INFORMATION, REQUIREMENTS AND/OR
TERMS AND CONDITIONS” is hereby changed as follows:
FROM:
4. CONTRACT VALUE:
The Government is under no obligation to issue any task orders against contracts resulting from this solicitation. In addition, the cumulative total for the life of the contract (cumulative total of all six contracts) is $4,860,000.00. Task orders SHALL NOT be issued for work exceeding the cumulative maximum total for all six contracts of $4,860,000.00.
TO:
4. CONTRACT VALUE:
The Government is under no obligation to issue any task orders against contracts resulting from this solicitation. The cumulative total for the life of the contracts (cumulative total of all six contracts) is $4,860,000.00. Task orders WILL NOT be issued for work exceeding the cumulative maximum of $4,860,000.00. Multiple contracts with different maximum values for the life of each contract have been identified. Awards will be made with the maximum total values identified below:
CONTRACT AREA:
AVA/CASSVILLE/WILLOW RANGER DISTRICTS: $520,000.00
DONIPHAN/ELEVEN POINT RANGER DISTRICTS: $1,250,000.00
HOUSTON/ROLLA/CEDAR CREEK RANGER DISTRICTS: $520,000.00
POPLAR BLUFF RANGER DISTRICT: $855,000.00
POTOSI/FREDRICKTOWN RANGER DISTRICTS: $730,000.00
SALEM RANGER DISTRICT: $985,000.00
5. The solicitation close date is changed as follows:
FROM: 10 FEBRUARY 2015, 1:00 P.M. (EST)
TO: 12 FEBRUARY 2015, 1:00 P.M. (EST)