Statement of Work 2

View the file

Other files

File Type Posted
Pre-Bid Meeting Summary.docx DOCX document
SF 30 Amendment 3.pdf PDF
Pre-Bid Attendees Sign In Sheet.PDF PDF
Location map.pdf PDF
Final Plans.pdf PDF
SF 30 Amendment 2.pdf PDF
SF 30 Amendment.pdf PDF
Building Photos 3.pdf PDF
Final Specs.pdf PDF
DBA.pdf PDF
Plans 1.pdf PDF
Layout Plan 2.pdf PDF
SF 1442 Cont _ 0554.docx DOCX document
Camp Nesbit - Building Photos 2.pdf PDF
Work Restrictions.pdf PDF
SF 1442 Cover Pg.pdf PDF
Camp Nesbit Description Photo 4.pdf PDF
Photo 1.pdf PDF
Camp Nesbit Construction Notes 01.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Camp Nesbit Improvements – Environmental Educational Youth Camp – Roofing & Staining

R9 Unique AAP Project No. CIM-0900-24F-16-0907-02

STATEMENT OF WORK

PROJECT NAME: Camp Nesbit Improvements – Environmental Educational

Youth Camp – Roofing & Staining Project

REQUESTING UNIT:

Ottawa National Forest

E6248 US2

Ironwood, MI 49938

GOVERNMENT PROJECT MANAGER:

Eric R. Johnson Ottawa National Forest

E6248 US 2

Ironwood, MI 49938

(906) 932-1330 x 322

The following scope of work describes the services requested at the Camp Nesbit Recreation Site within the Ottawa National Forest in Michigan. Work shall be in accordance with this Statement of Work (SOW) and the project plans and specifications.

Background: The facilities at this recreation site were originally constructed in the 1930s by the Civilian Conservation Corps (CCC), and are eligible for listing in the National Register of Historic Places. Exterior maintenance performed on many visible components / elements of these facilities, in many instances, needs to visually appear as it did upon completion of original construction in the 1930s in order to maintain its National Register eligibility. Also, “in-kind” materials are often required to be utilized to preserve this appearance.

The intent of this project is to:

1. Repair, by replacement, 15 roofs and

2. Stain the exterior of 23 buildings located in the Camp Nesbit Complex.

In the past, the roofs on all of the buildings had been changed from wood shake to asphalt shingle. This change of materials and visual appearance did not change National Register eligibility for these facilities. The roofing portion of project will replace the existing three-tab shingles on designated buildings with architectural / dimensional / multi-thickness style shingles; see below and the specifications for details.

The color of the stain may have slightly changed over the years, and the chemical make-up of the stain most likely has changed over the years. The staining portion of this project will match (as close as feasible) the color of the stain after the facilities original construction, utilizing stain with a more current chemical make-up, to provide maximum, longer lasting exterior wood surface protection than the older stains; see below and the specifications for details.

Projects summary description: The Contractor shall provide all coordination, phasing, labor, material, equipment, incidentals, and supervision to accomplish and complete all of the Work in accordance with any / all drawings / photos and specifications, to accomplish the intent of this project.

Any material which is demolished or removed by the Contractor and not salvaged by the Government becomes the property of the Contractor. Said material shall be removed from Government property and properly disposed. The contractor shall provide a copy of all disposal slips from the accredited landfill to the COR (Contracting Officer’s Representative).

Any damage to structure components and/or surrounding environment during demolition / construction may require repair / replacement at the Contractor’s expense, if the Contracting Officer (CO) determines such action is necessary.

All work shall be accomplished by (and not limited by or to) complying with the most current versions of applicable and / or salient parts of the following standards, guidelines, recommendations, regulations, codes, and laws: Occupational Safety and Health Administration (OSHA), Architectural Barriers Act Accessibility Guidelines, Forest Service Handbook (FSH), Forest Service Manual (FSM), International Building Code (IBC), International Energy Conservation Code, Code of Federal Regulations (CFR), American National Standards Institute (ANSI), American Society for Testing and Materials (ASTM), etc.

The Work includes, but is not limited to:

1. Camp Nesbit Roof Replacement (15 Buildings): Mess Hall (Building #16), Storage Building (Building #20), Infirmary (Building #18), Boathouse (Building #23), Cabins #1 thru #8 (Buildings #1 thru #8) and Cabins #10 thru #12 (Buildings #10 thru #12).

a. Removing existing roof covering (including, but not limited to, shingles, felt, felt underlayment, flashing, drip edge, non-compliant sheathing, etc.),

b. Installing new roof covering (including, but not limited to, shingles, felt, felt underlayment, flashing, drip edge, non-compliant sheathing, etc.).

c. Building #16 approximate roofing surface area is 2,100 square feet.

d. Building #20 approximate roofing surface area is 1,100 square feet.

e. Building #18 approximate roofing surface area is 700 square feet.

f. Building #23 approximate roofing surface area is 200 square feet.

g. Buildings #1 thru #8, and #10 thru #12 approximate roofing surface area is 700 square feet each; totaling 7,700 square feet.

2. Camp Nesbit Building Staining (23 ITEMS):

a. Examination of surfaces to be stained, for repairs (via replacement, puttying and sanding, and / or other) prior to staining.

b. Repairing (via replacement, puttying and sanding, and / or other) prior to staining.

c. Prepare (clean, dirt removal, mold removal if any, wash as necessary, etc.)

surfaces for staining.

d. Mask and protect adjacent surfaces (panes of glass, portions of rock / stone chimneys / fireplaces, etc.) not being stained.

e. Staining all the wood elements / components that make up the exterior of the buildings mentioned below, from the lowest wood components of the building (generally the board & batten siding, or flooring system rim joist) all the way up to the metal drip edge / roof sheathing interface (i.e. all exterior exposed wood surfaces); see the staining specification for more details.

f. Mess Hall (Building #16) approximate staining surface area is 2,450 square feet.

g. Recreation Hall (Building #17) approximate staining surface area is 2,200 square feet.

h. Men’s Comfort Station (Building #13) approximate staining surface area is 1,175 square feet.

i. Women’s Comfort Station (Building #14) approximate staining surface area is 1,175 square feet

j. Combined Comfort Station (Building #15) approximate staining surface area is 1,175 square feet.

k. Cabins #1 thru #12 (Buildings #1 thru #12) approximate staining surface area is 15,600 square feet (1,300 square feet per each building).

l. Custodial Dwelling (Building #19) approximate staining surface area is 1,300 square feet.

m. Infirmary (Building #18) approximate staining surface area is 1,300 square feet.

n. Storage Building (Building #20) approximate staining surface area is 1,400 square feet.

o. Boathouse (Building #23) approximate staining surface area is 500 square feet.

p. Pump House (Building #22) approximate staining surface area is 450 square feet.

q. Generator Building (Building #21) approximate staining surface area is 550 square feet.

3. Submitting all materials/equipment data sheets, test results, warranty/guarantee, as-built drawings (as applicable) and certificates to the Government for records/files.

4. Keeping work-site clean and orderly throughout the course of the work.

DELIVERABLES

Address for submittals:

Eric Johnson, Facilities Engineer

E6248 US 2

Ironwood, MI 49938 906/932-1330, ext. 322 906/932-0122 (fax)