SF_30_007_0829.pdf
PDF 804 KB Posted
- Solicitation number
- AG-32SC-S-13-0008
About this file
SF 30 Mod 0007
View the file
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION
NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.
IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
INSTRUCTIONS
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1)
(2)
(3)
(4)
(5)
For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contacting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a)
(b)
(c)
(d)
(e)
(f)
Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Item 9, (Amendment of Solicitation No. - Dated), and 10, (Modification of Contract/Order No. - Dated). Check the appropriate box and in the corresponding blanks insert the number and date of the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data).
When appropriate, indicate the impact of the modification on each affected accounting classification by inserting one of the following entries.
(2) Accounting classification Net decrease $
Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i)
NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document
Indicate the impact of the modification on the overall total contract price by inserting one of the following entries:
(i) Total contract price increased by $
(ii) Total contract price decreased by $
(iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g)
(h)
When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1)
(2)
(3)
(4)
(5)
(6)
STANDARD FORM 30 (REV. 10-83) BACK
(1) Accounting classification Net increase $
General Decision Number: PA130005 07/26/2013 PA5
Superseded General Decision Number: PA20120005
State: Pennsylvania
Construction Type: Building
Counties: Delaware, Montgomery and Philadelphia Counties in Pennsylvania.
BUILDING CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories)
Modification Number Publication Date 0 01/04/2013 1 01/18/2013 2 03/22/2013 3 04/05/2013 4 04/12/2013 5 05/03/2013 6 05/10/2013 7 05/17/2013 8 06/07/2013 9 06/14/2013 10 06/28/2013 11 07/05/2013 12 07/19/2013 13 07/26/2013
ASBE0014-001 05/01/2013
Rates Fringes
Asbestos Workers/Insulator Includes the application of all insulating materials, protective coverings, coatings, and finishes to all types of mechanical systems..........$ 41.79 28.90
BOIL0013-001 01/01/2011
Rates Fringes
BOILERMAKER......................$ 37.35 30.01
BRPA0001-003 05/01/2013
CHESTER, DELAWARE (Except Haverford and Radnor Township), AND
MONTGOMERY
Rates Fringes
BRICKLAYER.......................$ 35.68 22.30
BRPA0001-006 05/01/2013
PHILADELPHIA COUNTY
Rates Fringes
BRICKLAYER.......................$ 35.68 22.78
BRPA0001-007 05/01/2013
DELAWARE AND MONTGOMERY COUNTIES
Rates Fringes
MASON - STONE....................$ 36.18 22.42
BRPA0001-008 05/01/2013
Rates Fringes
TILE SETTER......................$ 37.36 21.57
BRPA0001-010 05/01/2013
MONTGOMERY COUNTY (Except Cheltenham and Upper Moreland Townships)
BRICKLAYER.......................$ 35.68 22.30
BRPA0001-011 05/01/2013
PHILADELPHIA COUNTY
Rates Fringes
MASON - STONE....................$ 36.18 22.42
BRPA0035-001 05/01/2013
Rates Fringes
Pointer, caulker and cleaner.....$ 37.01 21.94
CARP0454-006 05/01/2013
Rates Fringes
PILEDRIVERMAN....................$ 39.65 29.67
Footnote: PAID HOLIDAYS: Washington's Birthday, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day (provided the employee works the day before the holiday and the day after the holiday).
CARP0845-001 05/01/2013
Philadelphia County
Rates Fringes
Carpenter/Lather Delaware, and Montgomery Counties....................$ 36.40 24.94 Philadelphia County.........$ 39.90 24.94
CARP1823-001 05/01/2012
Rates Fringes
FLOOR LAYER: Carpet Delaware and Montgomery Counties....................$ 38.76 24.84 Philadelphia County.........$ 39.16 24.84
CARP1906-001 07/01/2012
Rates Fringes
MILLWRIGHT.......................$ 36.11 27.88
ELEC0098-003 04/28/2013
DELAWARE COUNTY: That portion east of a line following State Highway 320 from Montgomery County to Maple, then along the Springfield Road to Saxer Ave, along Saxer Avenue to Powell Road, along Powell Road to State Highway 420 and continuing in a straight line to the Delaware River.
MONTGOMERY COUNTY: That portion southeast of a line following Lower State Road from Bucks County southwest to the Bethlehem Pike (U.S Highway 309), south on the Bethlehem Pike to the Penllyn Pike, southwest on the Penllyn and Blue Bell Pikes to the Wissahickon Creek, southeast on the Wissahickon Creek to the Butler Pike to North Lane near Conshohocken Borough, southwest on North Lane to Schuylkill River and continuing southeast in a line to the Spring Mill Road and southwest on the Spring Mill Road to Delaware County.
PHILADELPHIA COUNTY - in its entirety
ELECTRICIAN......................$ 49.65 59.5%+1.49
ELEC0313-004 06/01/2011
DELAWARE COUNTY: (That portion south of U.S. Highway no. 1, and west of U.S. Highway no. 202)
ELECTRICIAN......................$ 35.00 23.70
ELEC0375-002 06/01/2013
MONTGOMERY COUNTY (Upper Hanover in its entirety)
Rates Fringes
ELECTRICIAN......................$ 38.83 14.13
ELEC0380-002 09/03/2012
DELAWARE COUNTY - That portion of Radnor Township north of U.S.
Highway 30 and west of State Highway 320.
MONTGOMERY COUNTY - That portion northwest of a line following Lower State Road from Bucks County southwest to the Bethlehem Pike (U.S. Highway 309), south on Bethlehem Pike to the Penllyn Pike, southwest on the Penllyn and Blue Bell Pikes to the Wissahickon Creek to the Butler Pike, southwest Wissahickon Creek to the Butler Pike, southwest on the Butler Pike, to North Lane near Conshohocken Borough, southeast on North Lane to the Schuylkill River and continuing southeast in a line to the Spring Mill Road, southwest on the Spring Mill Road to Delaware County; but excluding Upper Hanover, Douglas, Upper Pottsgrove, West Pottsgrove Townships and also excluding that portion of the Borough of Pottstown north and west of a line drawn northeast on Keim Street from the schuylkill river to the Reading Railroad northwest on the railroad to Madison Street, to High Street, east on High Street to Green Street, north on Green Streeet and northeast on Mintzer Street to the Lower Pottsgrove Township Line, along this township line and the borough line northwest to Adams Street and the Beehive Road, northeast on Beehive Road to the Township Line at Mervine Street in the State of Pennsylvania.
ELECTRICIAN......................$ 39.86 27.54
ELEC0654-002 07/30/2012
DELAWARE COUNTY: That portion south of U.S. Highway 30 and north of that part of U.S. Highway 1 between U.S. Highway 202 and the Chester County Line, and east of that part of U.S.
Highway 202 betwen U.S. Highway 1 and the Delaware Line, and west of a line extending from' Montgomery County along State Route 320 to Maple, then along the Springfield Road to Saxer Avenue, along Saxer Avenue to Powell Road; along Powell Road to State Highway 420; along 420 and continuing in a straight line to the Delaware River in the State of Pennsylvania.
ELECTRICIAN......................$ 39.23 23.19
ELEC0743-003 09/01/2010
MONTGOMERY COUNTY (Douglas, Upper Pottsgrove, West Pottsgrove, and Pottstown Twps.)
ELECTRICIAN......................$ 31.87 3%+15.50
ELEV0005-001 01/01/2013
Rates Fringes
ELEVATOR MECHANIC................$ 49.84 25.185
FOOTNOTES FOR ELEVATOR MECHANICS:
A. PAID VACATION: Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% for 6 months to 5 years of service.
B. Eight Paid Holidays (provided employee has worked 5 consecutive days before and the working day after the holiday): New Years's Day; Memorial Day; Independence Day;
Labor Day; Veteran's Day; Thanksgiving Day and the Friday after Thanksgiving Day, and Christmas Day.
* ENGI0542-002 05/01/2013
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 40.81 25.55+A
GROUP 1a....................$ 43.80 26.45+A
GROUP 2.....................$ 40.56 25.48+A
GROUP 2a....................$ 43.57 26.36+A
GROUP 3.....................$ 36.48 24.27+A
GROUP 4.....................$ 36.17 24.19+A
GROUP 5.....................$ 34.45 23.68+A
GROUP 6.....................$ 33.46 23.34+A
FOOTNOTE: A. PAID HOLIDAYS: New Year's Day; Memorial Day;
Independence Day; Labor Day; Thanksgiving Day and Christmas Day
***TOXIC/HARARDOUS WASTE REMOVAL***
Add 20 per cent to basic hourly rate for all classifications
POWER EQUIPMENT OPERATORS CLASSIFICATIONS
GROUP 1: Handling steel and stone in connection with erection, cranes doing hook work, any machine handling machinery, helicopters, concrete pumps building machines similar to the above, including remote control equipment.
GROUP 1a: Machines handling steel, or the functional equivalent, and stone in connection with erection 15 ton and over factory rating; Cranes doing hook work 15 ton and over factory rating; Any machines handling machinery; HIgh Rail/Burro Crane 15 ton and over factory rating; Rail Loader (Winch Boom Type) 15 ton and over factory rating;
Concrete Pumps (Building) 120 feet of Boom length or less (200 yard pour or less); Machines similar to above, including remote control equipment; Equipment in this Wage Group that does not require an oiler.
GROUP 2: All types of cranes, All types of backhoes, Cableways, Draglines, Keystones, all types of shovels, Derricks, Pavers 21E and over, Trenching machines, Trench shovel, Gradalls, Front-End loaders, Boat Captain, Pippin type backhoes, Tandems scrapers, Towers type crane operation erecting, Dismantling, Jumping or Jacking, Drills (self-containes), (drillmaster type) forklift (20 ft. and over), Moter patrols (fine grade), Batch plant with mixer, Carryalls, Scraper, Trounapulls, Roller (Hith Grade Finishing), Spreaders (asphalt), Bulldozers and Tractors, Mechanic welder, Conveyor loaders (euclid-type wheel), Concrete pump, Milling Machines, Hoist with two towers, Building hoist double drum (unless used as a single drum), Mucking machines in tunnel, All auto grade and concrete finishing machines, Bundle pullers/extractors (tublar), bobcat. side broom, directional boring machines, vermeer saw type machines(other than than hand held tractor mounted hydro axe, chipper with boom, all) machine similar to the above including remote control equipment.
GROUP 2a: Crawler backhoes and Crawler gradalls over one cubic yard factory rating; Hydraulic backhoes over one cubic yard factory rating; All types of cranes 15 ton and over factory rating; Cherry picker type machinery and equipment 15 ton and over factory rating; Concrete Pumps (Heavy/Highway); Machines similar to above, including remote control equipment; Equipment in this Wage Group that does not require an oiler.
GROUP 3: Asphalt plant engineers, Well drillers, Ditch witch (small trencher), Motor patrols, Fine grade machines, Ten-ton roller (grade fill stone base), Concrete breaking machines, Guilloline only, Stump grinder, Conveyors (except building conveyors), Fork lift trucks of all types, High pressure boliers Elevator Operator (New Construction) Machine similar to the above,including remote control equipment
GROUP 4: Seaman, Pulverzer form line grader, Farm tractors, road finishing, Concrete spreader, Power broom (self-contained), Seed spreader, Grease truck, toxic/hazardous wate removal rate 20 per cent added to all classifications and machiines similar to the above.
GROUP 5: Compressors pumps, Well point pumps, Welding machines Tireman, Power equipment, Maintenance engineer (power boats),Elevator Operators (Renovations) and machine similar to the above .
GROUP 6: Fireman, Oilers and deck hands (personnel boats), grease truck.
IRON0401-002 01/01/2012
DELAWARE (North of a line running along State Route 352 to right of State Route 291 to State Line); MONTGOMERY (Remainder); and PHILADELPHIA COUNTIES
IRONWORKER, STRUCTURAL AND
ORNAMENTAL.......................$ 44.70 27.15
IRON0405-002 07/01/2013
DELAWARE (North of line running along State Route 352 to right on State Route 291 to State Line); MONTGOMERY (Remainder); and
PHILADELPHIA COUNTIES
IRONWORKER, REINFORCING..........$ 39.63 25.60
The following holidays shall be observed and when work is performed thereon it shall be paid for at twice the base rate: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day. Employees shall be off Christmas Eve Day and receive four hours pay.
Employees who have to work on Christmas Eve Day shall work four hours and be paid for eight hours pay for the holiday.
Any time worked beyond fours hours shall be paid at the double time rate plus the four hours holiday pay. To receive holiday pay, the employee must work the day before Christmas Eve and the first working day after Christmas Day.
IRON0405-004 07/01/2013
DELAWARE (North of a line running along State Route 352 to right on State Route 291 to State Line); MONTGOMERY (Remainder); and PHILDELPHIA COUNTIES
IRONWORKER (Rigger and Machinery Mover).................$ 37.00 25.00
The following holidays shall be observed and when work is performed thereon it shall be paid for at twice the base rate: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day. Employees shall be off Christmas Eve Day and receive four hours pay.
Employees who have to work on Christmas Eve Day shall work four hours and be paid for eight hours pay for the holiday.
Any time worked beyond fours hours shall be paid at the double time rate plus the four hours holiday pay. To receive holiday pay, the employee must work the day before Christmas Eve and the first working day after Christmas Day.
IRON0420-003 07/01/2012
MONTGOMERY COUNTY (Anise, Bergey, Congo, Douglas, East Greenfield, East Limerick, East Salford, East Zieglerville, Engelsville, Fagleysville, Ford, Gilbertsville, Green Lane, Hanover, Hopenville, Lower Pottsgrove, Marlboro, New Hanover, New Perkionenville, Nianto, Palm, Obelish, Pennsburg, Pottstown, Perkiomen, Royerford, Roytown, Sassamansville, Tylerport, Upper Hanover, Upper Pottsgrove, Upper Woxall, West Limerick, West Salford, and West Zieglerville Townships)
Ironworkers:
Projects $200,000,000 and over, All Work..............$ 31.00 23.00 Projects less than $200,000,000................$ 30.00 23.00
IRON0451-005 07/01/2012
DELAWARE COUNTY (Remainder)
Rates Fringes
Ironworkers: (STRUCTURAL, ORNAMENTA, and REINFORCING)......$ 33.60 25.40
The following holidays shall be observed, and when work is performed thereon it shall be paid for at twice the base wage rate: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day.
LABO0400-001 05/01/2009
Rates Fringes
Laborers:
GROUP 1.....................$ 23.85 21.65
GROUP 2.....................$ 23.95 21.65
GROUP 3.....................$ 24.00 21.65
GROUP 4.....................$ 24.15 21.65
GROUP 5.....................$ 24.25 21.65
GROUP 6.....................$ 23.99 21.65
GROUP 7.....................$ 25.10 21.65
GROUP 8.....................$ 25.15 21.65
GROUP 9.....................$ 25.25 21.65
GROUP10.....................$ 25.40 21.65
LABORERS CLASSIFICATIONS
GROUP 1: Stripping and dismantling concrete form work, loading, carry and handling of all reinforced steel and steel mesh, handling lumber and other building materials, operating jackhammers, paving breakers and all other pheumatic tools, building scaffolds, raking shoveling and tamping of asphalt, spading and concrete pit work, grading, form pinning, shoring, demolition except burners, laying conduits and ducts, sheathing, lagging, laying nonmetallic pipe and caulking, all other types of laborers
GROUP 2: Mason tender, power buggies, burners on demolition
GROUP 3: Wagon drill operator (single)
GROUP 4: Powdermen, wagon drill operator (multiple), circular caissons excavation: caisson groundmen, underpinning excavation: laborers, working at depth of 8 feet or under
GROUP 5: Caisson bottom man
GROUP 6: Yard workers
GROUP 7: Trackmen, Brakemen, Groutmen, Bottom Shaft Men, and All other Men in Free Air Tunnels
GROUP 8: Form Setters
GROUP 9: Blasters, Driller, Pneumatic Shield Operators
GROUP 10: Asbestos abatement laborers, hazardous waste laborers, and lead abatement laborers
LABO0413-004 04/01/2013
Rates Fringes
Landscape Laborer Farm Tractor Driver, hydroseeder Nozzleman and Mulcher Nozzleman...........$ 19.11 21.35+A
FOOTNOTE:
A. PAID HOLIDAYS: Independence Day, Labor Day, and Thanksgiving Day.
MARB0001-003 05/01/2012
Rates Fringes
MARBLE FINISHER..................$ 29.27 20.07
TERRAZZO FINISHER................$ 33.06 19.31
TILE FINISHER....................$ 29.77 20.55
MARB0003-002 05/01/2012
Rates Fringes
MARBLE SETTER....................$ 35.25 21.95
TERRAZZO WORKER/SETTER...........$ 26.40 21.95
* PAIN0021-001 05/01/2013
Rates Fringes
Painters:
Brush, Roller...............$ 34.70 21.58 Spray, Steel, and Swing.....$ 35.95 21.58
* PAIN0021-012 05/01/2013
Rates Fringes
DRYWALL FINISHER/TAPER...........$ 35.05 23.21
PAIN0252-001 06/01/2008
Rates Fringes
Window Tinter....................$ 19.85 6.61
PAIN0252-006 05/01/2012
Rates Fringes
GLAZIER..........................$ 38.35 25.15
PLAS0008-001 05/01/2013
Rates Fringes
PLASTERER........................$ 34.70 25.55
PLAS0592-011 05/01/2013
Rates Fringes
CEMENT MASON/CONCRETE FINISHER...$ 33.05 28.36
PLUM0420-008 05/01/2013
Rates Fringes
Steamfitter Delaware, Montgomery, and Philadelphia Counties.......$ 48.03 27.73
PLUM0690-002 05/01/2013
Rates Fringes
PLUMBER..........................$ 44.53 29.21
ROOF0030-001 05/01/2012
Rates Fringes
Roofers:
Composition.................$ 31.05 26.45+A Shingles....................$ 31.05 26.45+A Slate and Tile..............$ 31.05 26.45+A
FOOTNOTE (Composition Roofer only):
A. PAID HOLIDAY: Election Day
SFPA0692-001 05/01/2013
Rates Fringes
SPRINKLER FITTER.................$ 48.65 24.57
SHEE0019-008 05/01/2012
Rates Fringes
SHEET METAL WORKER (Sign Makers & Hangers)................$ 23.92 16.72 Sheet metal worker...............$ 39.66 32.42
TEAM0107-001 05/01/2013
Rates Fringes
TRUCK DRIVER (BUILDING
CONSTRUCTION)
GROUP 1.....................$ 28.17 14.82+a+b GROUP 2.....................$ 28.27 14.82+a+b GROUP 3.....................$ 28.52 14.82+a+b Truck drivers: (SITE
PREPARATION, PAVING AND
UTILITIES ON BUILDING
CONSTRUCTION)
GROUP 1.....................$ 28.17 14.82+a+b GROUP 2.....................$ 28.27 14.27+a+b GROUP 3.....................$ 28.52 14.82+a+b
TRUCK DRIVERS CLASSIFICATIONS (BUILDING CONSTRUCTION)
GROUP 1 - Stake body truck (single axle), 11/2 ton and under vehicles
GROUP 2 - Truck driver over 11/2 tons, dump trucks, tandem and batch trucks, semi-trailers, agitator mixer trucks and dumcrete type vehicle, asphalt distributors, farm tractors when used for transportation, stake body truck (tandem)
GROUP 3 - Euclid type, off-highway equipment - back or belly dump trucks and double-hitched equipment, straddle (ross) carrier, lowbed trailers
TRUCK DRIVERS CLASSIFICATIONS (SITE PREPARATION, PAVING AND
UTILITIES ON BUILDING CONSTRUCTION)
GROUP 1 - Stake body truck (single axle), dumpster
GROUP 2 - Dump trucks, tandem and batch trucks, semi-trailers, agitator mixer trucks, and dumpcrete type vehicles, asphalt distributors, farm tractor when used for transportation, stake body truck (tandem)
GROUP 3 - Euclid type, off-highway equipment or bell dump trucks and double hitched equipment, staddle (ross) carrier, low-bed trailers
FOOTNOTE:
A. PAID HOLIDAYS: Memorial Day, Independence Day, Labor Day, Thanksgiving Day and five personal holidays provided employee works at least one day in the three work days before and at least one day in the three work days after the said holiday. Emloyee earns a personal holiday every two months, provided employee has worked twenty-six day in each consecutive two month period, up to a maximum of five per calendar year. After 130 work days the employee is entitled to all five personal holidays.
B. PAID VACATION: Employee will earn one vacation day for every two months, provided employee has worked twenty-six day in each consecutive two month period, up to a maximum of five vacation days per calendar year. After 130 workdays the employee is entitled to all five days of vacation. Employees with 5 years of seniority, earn an additional week of vacation, accrued in the same way.
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is union or non-union.
Union Identifiers
An identifier enclosed in dotted lines beginning with characters other than "SU" denotes that the union classification and rate have found to be prevailing for that classification. Example: PLUM0198-005 07/01/2011. The first four letters , PLUM, indicate the international union and the four-digit number, 0198, that follows indicates the local union number or district council number where applicable , i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination.
The date, 07/01/2011, following these characters is the effective date of the most current negotiated rate/collective bargaining agreement which would be July 1, 2011 in the above example.
Union prevailing wage rates will be updated to reflect any changes in the collective bargaining agreements governing the rates.
0000/9999: weighted union wage rates will be published annually each January.
Non-Union Identifiers
Classifications listed under an "SU" identifier were derived from survey data by computing average rates and are not union rates; however, the data used in computing these rates may include both union and non-union data. Example: SULA2004-007 5/13/2010. SU indicates the rates are not union majority rates, LA indicates the State of Louisiana; 2004 is the year of the survey; and 007 is an internal number used in producing the wage determination. A 1993 or later date, 5/13/2010, indicates the classifications and rates under that identifier were issued as a General Wage Determination on that date.
Survey wage rates will remain in effect and will not change until a new survey is conducted.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
Solicitation AG-32SC-S-13-0008
PRICE SCHEDULE
Item No.
Qty
Total Price
Transition Period
9/1/13 – 9/30/13
1 mos.
Item No.
Qty
Monthly Price
Total Price
Base Period – Routine Work 10/1/13 – 9/30/14
Total Firm Fixed Price for labor, material and equipment to perform all routine work as specified in Section C, except for additional work specifically identified as being included in the Indefinite Delivery/Indefinite Quantity portions of the contract
2(A)
Work Management
12 mos.
2(B)
Administrative Services
12 mos.
2(C)
Safety
12 mos.
2(D)
Utilities Services
12 mos.
2(E)
Facility Services
12 mos.
Total Routine Work - Base Period 2(A) – 2(E)
Base Period – Additional Work (Davis Bacon Act (DBA))
Provide a fully burdened labor rate for the categories that may be required in order to perform any additional work required in performance of this contract.
Item No.
Labor Category
Estimated DBA Hours
Fully Burdened Hourly Rate DBA
Total Price
2(F)
Electrician
2(G)
Roofer
2(H)
Building/Sheet Metal Worker
2(I)
Carpenter
2(J)
Painter
2(K)
Plumber/Steamfitter
2(L)
Boiler Maker
2(M)
Elevator Mechanic
2(N)
Heavy Equipment Operator Group I
2(O)
Heavy Equipment Operator Group II
2(P)
Heavy Equipment Operator Group III
2(Q)
Laborer – Group I
2(R)
Laborer – Group II
2(S)
Laborer – Group III
2(T)
Cement Mason
2(U)
Bricklayer
2(V)
Teamster
Total DBA Work 2(F)-2(V) Base Period
Base Period – Additional Work (Service Contract Act (SCA))
Provide a fully burdened labor rate for the categories that may be required in order to perform any additional work required in performance of this contract.
Item No.
Labor Category
Estimated SCA Hours
Fully Burdened Hourly Rate SCA
Total Price
2(W)
Housekeeping
2(X)
General Clerk II
2(Y)
Security Guard
2(Z)
Laborer Grounds Maintenance
2(AA)
N/A
2(BB)
Shipping/Receiving Clerk
2(CC)
Electrician
2(DD)
General Maintenance
2(EE)
HVAC Research
2(FF)
Maintenance Trades Helper
2(GG)
Painter
2(HH)
Pipefitter
2(II)
Plumber
2(JJ)
Boiler Operator
2(KK)
Electronics Technician
Total SCA Work 2(W)-2(KK) Base Period
Item No.
Qty
Monthly Price
Total Price
Option Period I – Routine Work 10/1/14 – 9/30/15
Total Firm Fixed Price for labor, material and equipment to perform all routine work as specified in Section C, except for additional work specifically identified as being included in the Indefinite Delivery/Indefinite Quantity portions of the contract
3(A)
Work Management
12 mos.
3(B)
Administrative Services
12 mos.
3(C)
Safety
12 mos.
3(D)
Utilities Services
12 mos.
3(E)
Facility Services
12 mos.
Option Period I Total Routine Work 3(A) – 3(E)
Option Period I – Additional Work (Davis Bacon Act (DBA))
Provide a fully burdened labor rate for the categories that may be required in order to perform any additional work required in performance of this contract.
Item No.
Labor Category
Estimated DBA Hours
Fully Burdened Hourly Rate DBA
Total Price
3(F)
Electrician
3(G)
Roofer
3(H)
Building/Sheet Metal Worker
3(I)
Carpenter
3(J)
Painter
3(K)
Plumber/Steamfitter
3(L)
Boiler Maker
3(M)
Elevator Mechanic
3(N)
Heavy Equipment Operator Group I
3(O)
Heavy Equipment Operator Group II
3(P)
Heavy Equipment Operator Group III
3(Q)
Laborer – Group I
3(R)
Laborer – Group II
3(S)
Laborer – Group III
3(T)
Cement Mason
3(U)
Bricklayer
3(V)
Teamster
Total DBA Work 3(F) - 3(V) Option Period I
Option Period I – Additional Work (Service Contract Act (SCA))
Provide a fully burdened labor rate for the categories that may be required in order to perform any additional work required in performance of this contract.
Item No.
Labor Category
Estimated SCA Hours
Fully Burdened Hourly Rate SCA
Total Price
3(W)
Housekeeping
3(X)
General Clerk II
3(Y)
Security Guard
3(Z)
Laborer Grounds Maintenance
3(AA)
N/A
3(BB)
Shipping/Receiving Clerk
3(CC)
Electrician
3(DD)
General Maintenance
3(EE)
HVAC Research
3(FF)
Maintenance Trades Helper
3(GG)
Painter
3(HH)
Pipefitter
3(II)
Plumber
3(JJ)
Boiler Operator
3(KK)
Electronics Technician
Total Bid SCA work Option Period I
Item No.
Qty
Monthly Price
Total Price
Option Period II – Routine Work 10/1/15 – 9/30/16
Total Firm Fixed Price for labor, material and equipment to perform all routine work as specified in Section C, except for additional work specifically identified as being included in the Indefinite Delivery/Indefinite Quantity portions of the contract
4(A)
Work Management
12 mos.
4(B)
Administrative Services
12 mos.
4(C)
Safety
12 mos.
4(D)
Utilities Services
12 mos.
4(E)
Facility Services
12 mos.
Option Period II Total Routine Work 4(A) – 4(E)
Option Period II – Additional Work (Davis Bacon Act (DBA))
Provide a fully burdened labor rate for the categories that may be required in order to perform any additional work required in performance of this contract.
Item No.
Labor Category
Estimated DBA Hours
Fully Burdened Hourly Rate DBA
Total Price
4(F)
Electrician
4(G)
Roofer
4(H)
Building/Sheet Metal Worker
4(I)
Carpenter
4(J)
Painter
4(K)
Plumber/Steamfitter
4(L)
Boiler Maker
4(M)
Elevator Mechanic
4(N)
Heavy Equipment Operator Group I
4(O)
Heavy Equipment Operator Group II
4(P)
Heavy Equipment Operator Group III
4(Q)
Laborer – Group I
4(R)
Laborer – Group II
4(S)
Laborer – Group III
4(T)
Cement Mason
4(U)
Bricklayer
4(V)
Teamster
Total DBA Work 4(F) - 4(V) Option Period II
Option Period II – Additional Work (Service Contract Act (SCA))
Provide a fully burdened labor rate for the categories that may be required in order to perform any additional work required in performance of this contract.
Item No.
Labor Category
Estimated SCA Hours
Fully Burdened Hourly Rate SCA
Total Price
4(W)
Housekeeping
4(X)
General Clerk II
4(Y)
Security Guard
4(Z)
Laborer Grounds Maintenance
4(AA)
N/A
4(BB)
Shipping/Receiving Clerk
4(CC)
Electrician
4(DD)
General Maintenance
4(EE)
HVAC Research
4(FF)
Maintenance Trades Helper
4(GG)
Painter
4(HH)
Pipefitter
4(II)
Plumber
4(JJ)
Boiler Operator
4(KK)
Electronics Technician
Total Bid SCA work Option Period II
Item No.
Qty
Monthly Price
Total Price
Option Period III – Routine Work 10/1/16 – 9/30/17
Total Firm Fixed Price for labor, material and equipment to perform all routine work as specified in Section C, except for additional work specifically identified as being included in the Indefinite Delivery/Indefinite Quantity portions of the contract
5(A)
Work Management
12 mos.
5(B)
Administrative Services
12 mos.
5(C)
Safety
12 mos.
5(D)
Utilities Services
12 mos.
5(E)
Facility Services
12 mos.
Option Period III Total Routine Work 5(A) – 5(E)
Option Period III – Additional Work (Davis Bacon Act (DBA))
Provide a fully burdened labor rate for the categories that may be required in order to perform any additional work required in performance of this contract.
Item No.
Labor Category
Estimated DBA Hours
Fully Burdened Hourly Rate DBA
Total Price
5(F)
Electrician
5(G)
Roofer
5(H)
Building/Sheet Metal Worker
5(I)
Carpenter
5(J)
Painter
5(K)
Plumber/Steamfitter
5(L)
Boiler Maker
5(M)
Elevator Mechanic
5(N)
Heavy Equipment Operator Group I
5(O)
Heavy Equipment Operator Group II
5(P)
Heavy Equipment Operator Group III
5(Q)
Laborer – Group I
5(R)
Laborer – Group II
5(S)
Laborer – Group III
5(T)
Cement Mason
5(U)
Bricklayer
5(V)
Teamster
Total DBA Work 5(F) - 5(V) Option Period IV
Option Period III – Additional Work (Service Contract Act (SCA))
Provide a fully burdened labor rate for the categories that may be required in order to perform any additional work required in performance of this contract.
Item No.
Labor Category
Estimated SCA Hours
Fully Burdened Hourly Rate SCA
Total Price
5(W)
Housekeeping
5(X)
General Clerk II
5(Y)
Security Guard
5(Z)
Laborer Grounds Maintenance
5(AA)
N/A
5(BB)
Shipping/Receiving Clerk
5(CC)
Electrician
5(DD)
General Maintenance
5(EE)
HVAC Research
5(FF)
Maintenance Trades Helper
5(GG)
Painter
5(HH)
Pipefitter
5(II)
Plumber
5(JJ)
Boiler Operator
5(KK)
Electronics Technician
Total Bid SCA Work Option Period IV
Item No.
Qty
Monthly Price
Total Price
Option Period IV – Routine Work 10/1/17 – 8/31/18
Total Firm Fixed Price for labor, material and equipment to perform all routine work as specified in Section C, except for additional work specifically identified as being included in the Indefinite Delivery/Indefinite Quantity portions of the contract
6(A)
Work Management
11 mos.
6(B)
Administrative Services
11 mos.
6(C)
Safety
11 mos.
6(D)
Utilities Services
11 mos.
6(E)
Facility Services
11 mos.
Option Period IV Total Routine Work 6(A) – 6(E)
Option Period IV – Additional Work (Davis Bacon Act (DBA))
Provide a fully burdened labor rate for the categories that may be required in order to perform any additional work required in performance of this contract.
Item No.
Labor Category
Estimated DBA Hours
Fully Burdened Hourly Rate DBA
Total Price
6(F)
Electrician
6(G)
Roofer
6(H)
Building/Sheet Metal Worker
6(I)
Carpenter
6(J)
Painter
6(K)
Plumber/Steamfitter
6(L)
Boiler Maker
6(M)
Elevator Mechanic
6(N)
Heavy Equipment Operator Group I
6(O)
Heavy Equipment Operator Group II
6(P)
Heavy Equipment Operator Group III
6(Q)
Laborer – Group I
6(R)
Laborer – Group II
6(S)
Laborer – Group III
6(T)
Cement Mason
6(U)
Bricklayer
6(V)
Teamster
Total DBA Work 6(F) - 6(V) Option Period IV
Option Period IV – Additional Work (Service Contract Act (SCA))
Provide a fully burdened labor rate for the categories that may be required in order to perform any additional work required in performance of this contract.
Item No.
Labor Category
Estimated SCA Hours
Fully Burdened Hourly Rate SCA
Total Price
6(W)
Housekeeping
6(X)
General Clerk II
6(Y)
Security Guard
6(Z)
Laborer Grounds Maintenance
6(AA)
N/A
6(BB)
Shipping/Receiving Clerk
6(CC)
Electrician
6(DD)
General Maintenance
6(EE)
HVAC Research
6(FF)
Maintenance Trades Helper
6(GG)
Painter
6(HH)
Pipefitter
6(II)
Plumber
6(JJ)
Boiler Operator
6(KK)
Electronics Technician
Total Bid SCA work Option Period IV
Total Price – Transition Period
Total Price – Base Period
Total Price – Option Period I
Total Price – Option Period II
Total Price – Option Period III
Total Price – Option Period IV
Total Contract Price
(Transition Period, Base Period & ALL Options)
Section B – Page 1
1.2
C:\PERFORM\FORMS\S30.FRP
Forms Management
C:PERFORMFORMSS30.FRP
Acrobat PDFWriter 2.01 for Windows D:19971010095222 D:19990614133004 Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (If applicable)
7. ADMINISTERED BY (If other than Item 6)
CODE
STANDARD FORM 30 (REV. 10-83) Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
CHECK ONE
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE OF PAGES
6. ISSUED BY
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer) NSN 7540-01-152-8070 Previous edition unusable
INSTRUCTIONS
Instructions for items other than those that are self-explanatory, are as follows:
Item 1 (Contract ID Code). Insert the contract type identification code that appears in the title block of the contract being modified.
Item 3 (Effective date).
(1) (2) (3) (4) (5) For a solicitation amendment, change order, or administrative change, the effective date shall be the issue date of the amendment, change order, or administrative change.
For a supplemental agreement, the effective date shall be the date agreed to by the contracting parties.
For a modification issued as an initial or confirming notice of termination for the convenience of the Government, the effective date and the modification number of the confirming notice shall be the same as the effective date and modification number of the initial notice.
For a modification converting a termination for default to a termination for the convenience of the Government, the effective date shall be the same as the effective date of the termination for default.
For a modification confirming the contacting officer's determination of the amount due in settlement of a contract termination, the effective date shall be the same as the effective date of the initial decision.
(a) (b) (c) (d) (e) (f) Item 6 (Issued By). Insert the name and address of the issuing office. If applicable, insert the appropriate issuing office code in the code block.
Item 8 (Name and Address of Contractor). For modifications to a contract or order, enter the contractor's name, address, and code as shown in the original contract or order, unless changed by this or a previous modification.
Item 9, (Amendment of Solicitation No. - Dated),and 10, (Modification of Contract/Order No. -Dated). Check the appropriate box and in the corresponding blanks insert the number and dateof the original solicitation, contract, or order.
Item 12 (Accounting and Appropriation Data). When appropriate, indicate the impact of themodification on each affected accounting classification by inserting one of the following entries.
(2) Accounting classification Net decrease $ Include subject matter or short title of solicitation/contract where feasible.
Item 16B. The contracting officer's signature is not required on solicitation amendments. The contracting officer's signature is normally affixed last on supplemental agreements.
(i) NOTE: If there are changes to multiple accounting classifications that cannot be placed in block 12, insert an asterisk and the words "See continuation sheet".
Item 13. Check the appropriate box to indicate the type of modification. Insert in the corresponding blank the authority under which the modification is issued. Check whether or not contractor must sign this document. (See FAR 43.103.)
Item 14 (Description of Amendment/Modification).
Organize amendments or modifications under the appropriate Uniform Contract Format (UCF) section headings from the applicable solicitation or contract. The UCF table of contents, however, shall not be set forth in this document Indicate the impact of the modification on the overall total contract price by inserting one of the following entries: (i) Total contract price increased by $ (ii) Total contract price decreased by $ (iii) Total contract price unchanged.
State reason for modification.
When removing, reinstating, or adding funds, identify the contract items and accounting classifications.
(g) (h) When the SF 30 is used to reflect a determination by the contracting officer of the amount due in settlement of a contract terminated for the convenience of the Government, the entry in Item 14 of the modification may be limited to --
(i) A reference to the letter determination; and
(ii) A statement of the net amount determined to be due in settlement of the contract.
(1) (2) (3) (4) (5) (6)
STANDARD FORM 30 (REV. 10-83) BACK
(1) Accounting classification Net increase $
| 9A. AMENDMENT OF SOLICITATION NUMBER: 0007 |
| 9A. AMENDMENT OF SOLICITATION NUMBER: AG-32SC-S-13-0008 |
| 7. CODE: |
| 12. ACCOUNTING AND APPROPRIATION DATA (If required): |
| 13A. THIS CHANGE ORDER IS ISSUED PURSUANT TO. Specify authority. THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.: |
| 13C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF: |
| 13D. OTHER. Specify type of modification and authority.: |
| 15A. NAME AND TITLE OF SIGNER. Type or print.: |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER. Type or print.: Janice M. Speth |
| 14. DESCRIPTION OF AMENDMENT OR MODIFICATION (Organized by UCF section headings, including solicitation or contract subject matter where feasible.): The purpose of this amendment is to: Extend Bid Date, Answer questions as posed by interested Contractors, as well as include additional information as requested to clarify the Contract documents. Incorporate documents as below: |
Extend Bid Date to September 10, 2013, SF 30 Amendment 006, Answers to Questions Mod #0006
| FACILITY CODE: |
| 6. ISSUED BY: USDA ARS EBSC Acquisition Branch |
Attn: Mark Volk 1815 N. University St.
Peoria, IL 61604
| 8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code): |
| 7. ADMINISTERED BY (If other than Item 6): |
| 1. CONTRACT ID CODE: |
| 4. REQUISITION/PURCHASE REQUISITION NUMBER: |
| 10A. MODIFICATION OF CONTRACT/ORDER NUMBER: |
| 5. PROJECT NUMBER. If applicable.: |
| PAGE: 1 |
| PAGES: |
| 3. EFFECTIVE DATE. Enter 2 digit month, 2 digit day and 4 digit year.: 2013-08-29 |
| 9B. DATED. SEE ITEM 11. Enter 2 digit month, 2 digit day and 4 digit year.: 2013-07-03 |
| 10B. DATED. SEE ITEM 13. Enter 2 digit month, 2 digit day and 4 digit year.: |
| 9A. AMENDMENT OF SOLICITATION NUMBER: 1 |
| 10A. MODIFICATION OF CONTRACT/ORDER NUMBER: 0 |
| 11. The above numbered solicitation is amended as set forth in Item 14. : 1 |
| 13A. THIS CHANGE ORDER IS ISSUED PURSUANT TO. Specify authority. THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A.: 0 |
| 13B. THE ABOVE NUMBERED CONTRACT OR ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES. Such as changes in paying office, appropriation date, etc. SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103b.: 0 |
| 13C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF: 0 |
| 13D. OTHER Specify type of modification and authority.: 0 |
| 13E. IMPORTANT: Contractor is not required to sign this document and return copies to the issuing office.: 0 |
| 13E. IMPORTANT: Contractor is required to sign this document and return copies to the issuing office.: 1 |
| 11. The hour and date specified for receipt of Offers is extended : 1 |
| 11. The hour and date specified for receipt of Offers is not extended : 0 |
| 15B. CONTRACTOR OR OFFEROR. Signature of person authorized to sign. Digital Signature.: |
| 16C. DATE SIGNED. Enter 2 digit month, 2 digit day and 4 digit year.: |
| number of copies: 1.00000000 |
| number of copies: 1.00000000 |
File details come from the government source that posted it. Updated .