SF-30Amendment4.pdf

PDF 168 KB Posted

Attached to
Wetland Restoration - Hendry Co. , Florida - USDA-NRCS
Solicitation number
AG-2B46-S-16-0045
Issued by

About this file

SF-30 Amendment 4

View the file

Other files

File Type Posted
Bid_Abstract_-_Aspring_WRP.pdf PDF
Aspring_Final_Geotechnical_Report-6Pages59-60.pdf PDF
SF-30Amendment_5.pdf PDF
Aspring_Final_Geotechnical_Report-5Pages_36-58.pdf PDF
Aspring_Final_Geotechnical_Report_Part1.pdf PDF
Aspring_Final_Geotechnical_Report_Part3.pdf PDF
Aspring_Final_Geotechnical_ReportPart7.pdf PDF
Aspring_Final_Geotechnical_Report-4Pages_31-35from.pdf PDF
Aspring_Final_Geotechnical_Report_Part2.pdf PDF
MoreQuestionsandAnswersSite_Visit9_1_16.pdf PDF
Aspring_Summary_of_Changes.pdf PDF
Questions_from_September_8th_Site_Visit.pdf PDF
Site_Vist_Attendees9_8_16.pdf PDF
Revised_pages_from_Aspring_Corrected_Final_Design_Construction_Specifications.pdf PDF
Aspring_Sheet_C520.pdf PDF
SF-30Amendment_3.pdf PDF
Aspring_Bid_Meeting_Minutes_QuestionsandAnswers9_1_16.pdf PDF
Amendment_2.pdf PDF
Site_Showing_Attendees_9-1-16.pdf PDF
Pages34-43AspringConstruction_PlansRevised8_29_16.pdf PDF
Pages24-33AspringConstruction_PlansRevised8_29_16.pdf PDF
Pages44-49AspringConstruction_PlansRevised8_29_16.pdf PDF
Pages15-23AspringConstruction_PlansRevised8_29_16.pdf PDF
Pages7-14AspringConstruction_PlansRevised8_29_16.pdf PDF
Pages1-6_AspringConstruction_PlansRevised8_29_16.pdf PDF
AspringSpecificationsRevised8_29_16.pdf PDF
SF1442Aspring.pdf PDF
DesignPlansPages39-45.pdf PDF
DesignPlansPages46-49.pdf PDF
DesignPlansPages31-38.pdf PDF
Special_Provisions.pdf PDF
DesignPlansPages8-14.pdf PDF
DesignPlansPages23-30.pdf PDF
DesignPlansPages1-7.pdf PDF
IFBConstruction_Aspring_WRP_Restoration.pdf PDF
Design_Construction_PlansPages15-22.pdf PDF
Aspring_Corrected_Final_Design_Construction_Specifications.pdf PDF
FL144Wage_Determination.txt TXT text file
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

AG-2B46-S-16-0045

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

NRCS-TN-124741

NASHVILLE TN 37203

801 BROADWAY

675 USCH

USDA-NRCS-TENNESSEE STATE OFFICE

WASHINGTON DC 20250

NRCS-HQ-122B46

ROOM 6801-S

1400 INDEPENDENCE AVENUE, SW

USDA-NRCS CONTRACTING TEAM 2

NRCS-HQ-122B46

07/27/2016000004

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

07/27/2016

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Amendment 4 provides two sets of questions and answers, site showing attendee list from

9/8/16, and the following summary of changes:

Aspring Summary of Changes 9-9-2016

Drawings:

Sheet C520: Borrow Area Detail Note 6 was removed. The borrow areas will be seeded and mulched the same as all other disturbed areas in accordance with Construction Specification

440, Vegetative Measures.

Specifications:

Sheet 7-5: Section 9.a.(5) III. The requirement of two (2) signed and sealed hard copies was changed to four (4).

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

NANCY W. HARRIS

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

AG-2B46-S-16-0045/000004

Sheet 21-4: Section 9.a. Bid Item No. 17, Channel

(CH1) was included in this section, since it was omitted from the specifications previously.

Sheet 21-4: Section 9.b. Subsidiary Item, Excavation, Common Borrow: Item 5 was added which states ¿All rocks larger than 6 inches in diameter must be stockpiled and removed from the site.¿ Also, Bid Item No. 12, Structure for Water

Control (SWC4) and Bid Item No. 17, Channel (CH1) were removed from the list of pay items for this subsidiary item.

Sheet 21-5: Section 9.c. Subsidiary Item, Excavation, Common, Structural: Item 2 was added which states¿ All rocks larger than 6 inches in diameter must be stockpiled and removed from the site.¿ Also, Bid item No. 12, Structure for Water

Control (SWC4) was removed from the list of pay items for this subsidiary item.

Sheet 21-5: Section 9.d: Bid Item No. 12, Structure for Water Control (SWC4) and Bid Item

No. 17, Channel (CH1) were removed from the list of pay items for this subsidiary item.

Sheet 21-6: Section 9.e. Subsidiary Item, Excavation, Common, Structure Removal: Item 3 was added which states¿ All rocks larger than 6 inches in diameter must be stockpiled and removed from the site.¿

Sheet 23-6: Section 10.a. Bid Item No. 12

Structure for Water Control (SWC4) was removed since this item is paid for in specification 442.

Also, in item 3 the compaction method stating

¿¿compacted by at least three (3) passes over the entire surface by a 10 ton vibrating steel-wheeled roller¿¿ was changed to ¿¿compacted by at least three (3) passes over the entire surface by at least an 8 ton vibrating steel-wheeled roller or crawler-type tractor¿¿

Sheet 23-7: Section 10.b. Bid Item No. 16, Road

Modification: In item 3, the compaction method stating ¿¿compacted by at least three (3) passes over the entire surface by a 10 ton vibrating steel-wheeled roller¿¿ was changed to ¿¿compacted by at least three (3) passes over the entire surface by at least an 8 ton vibrating steel-wheeled roller or crawler-type tractor¿¿

Sheet 23-8: Section 10.e. Bid Item No. 16, Road

Modification: In item 3, the compaction method stating ¿¿compacted by at least three (3) passes over the entire surface by a 10 ton vibrating steel-wheeled roller¿¿ was changed to ¿¿compacted

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

AG-2B46-S-16-0045/000004

by at least three (3) passes over the entire surface by at least an 8 ton vibrating steel-wheeled roller or crawler-type tractor¿¿

Sheet 42-5 Section 11.a.(2) the wall thickness requirement was changed to 2.5 inches for SWC1, SWC2 and SWC3.

Sheet 61-4: Section 8.a Item 4 was added and states ¿Contractor will provide engineer with

FDOT certification letter prior to beginning riprap work.¿

Sheets 441-1 through 441-4: Construction

Specification 441-3 Invasive Exotic Plant Species

Treatment. Extensive changes were made to this specification to direct the efforts of the

Contractor to preventing the spread of invasive species on and around the site rather than necessarily treating all invasive species in the construction work area.

Sheet 442-6 Section 7.a. in item 1 the statement

¿Method of payment shall be per square feet.¿ Was deleted, since this item is paid as each. In item

3, the compaction method stating ¿¿compacted by at least three (3) passes over the entire surface by a 10 ton vibrating steel-wheeled roller¿¿ was changed to ¿¿compacted by at least three (3) passes over the entire surface by at least an 8 ton vibrating steel-wheeled roller or crawler-type tractor¿¿ In item 6, all the subsidiary items were removed.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

2016-09-09T15:13:35-0500
NANCY HARRIS