Fire_Protection_Compiled.pdf

PDF 3 MB Posted

Attached to
Building 26 Remodel, Fort Missoula
Solicitation number
AG-03R6-S-14-0058
Issued by

About this file

17 - Drawings (Fire Protection)

View the file

Other files

File Type Posted
S140058FinalAmendment0007QAs.pdf PDF
S140058FinalAmendment0006ScheduleB.pdf PDF
S140058FinalAmendment0005QAs.pdf PDF
S140058FinalAmendment0004QAs.pdf PDF
S140058FinalAmendmen0003QAs.pdf PDF
S140058FinalAmendmen0002QAs.pdf PDF
S140058FinalAmendmen0001QAs.pdf PDF
20140812SignInSheet.PDF PDF
SpecsVolume1B.pdf PDF
MT140064WageDeter.pdf PDF
Arch_Compiled_Part6.pdf PDF
Electrical_Compiled_Part1.pdf PDF
Structural_Compiled.pdf PDF
Plumbing_Compiled.pdf PDF
SpecsVolume2B.pdf PDF
Security_Compiled.pdf PDF
Arch_Compiled_Part4.pdf PDF
Mechanical_Compiled.pdf PDF
Electrical_Compiled_Part2.pdf PDF
Arch_Compiled_Part3.pdf PDF
Arch_Compiled_Part5.pdf PDF
FinalAG03R6S140058ShortSetBuild26ConsRFP.pdf PDF
FinalAG03R6S140058CompletePkgBuild26ConsRFP.pdf PDF
Arch_Compiled_Part2.pdf PDF
SpecsVolume2A.pdf PDF
Arch_Compiled_Part1.pdf PDF
SpecsVolume1C.pdf PDF
SpecsVolume1A.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SEISMIC BRACING REQUIREMENTSEARTHQUAKE PROTECTION NOTES:

A. ALL EARTHQUAKE BRACING TO BE IN ACCORDANCE WITH NFPA-13 2007 OR CURRENT EDITION APPROVED BY

LOCAL AHJ.

B. LISTED FLEXIBLE COUPLINGS SHALL ONLY BE INSTALLED WHERE REQUIRED BY NFPA-13.

C. FLEXIBLE COUPLINGS SHALL BE LOCATED IN ACCORDANCE WITH NFPA-13 AS FOLLOWS:

1. WITHIN 24" FROM THE TOP AND BOTTOM OF ALL RISERS.

2. WITHIN 12" ABOVE AND 24" BELOW FLOORS IN MULTISTORY BUILDINGS.

3. WITHIN 1' OF ALL CONCRETE AND MASONRY WALL PENETRATIONS UNLESS CLEARANCE IS PROVIDED BY

SECTION 9.3.4.

4. WITHIN 24" OF BUILDING EXPANSION JOINTS.

5. WITHIN 24" OF THE TOP OF DROPS EXCEEDING 15' IN LENGTH TO PORTIONS OF SYSTEMS SUPPLYING MORE

THAN ONE SPRINKLER, REGARDLESS OF SIZE

6. ABOVE AND BELOW ANY INTERMEDIATE POINTS OF SUPPORT FOR A RISER OR OTHER VERTICAL PIPE.

1. CLEARANCE SHALL BE PROVIDED AROUND ALL PIPING EXTENDING THROUGH WALLS, FLOORS, PLATFORMS, AND FOUNDATIONS, INCLUDING DRAINS, FDCS, AND OTHER AUXILIARY PIPING PER SECTION 9.3.4 OR FLEXIBLE

COUPLINGS SHALL BE PROVIDED.

2. LONGITUDINAL SWAY BRACING SPACED AT A MAXIMUM OF 80 FEET SHALL BE PROVIDED FOR FEED AND CROSS

MAINS AND NOT MORE THAN 40 FEET FROM THE END.

3. TOPS OF RISERS OVER 3 FEET SHALL BE SECURED AGAINST DRIFTING IN ANY DIRECTION USING A 4-WAY

BRACE.

4. LATERAL SWAY BRACING SPACED AT A MAXIMUM OF 40 FEET SHALL BE PROVIDED FOR FEED AND CROSS

MAINS.

5. BRACING SHALL BE ATTACHED DIRECTLY TO FEED AND CROSS MAINS.

6. THE LAST LENGTH OF PIPE AT THE END OF FEED OR CROSS MAINS SHALL BE PROVIDED WITH A LATERAL BRACE. LATERAL BRACES SHALL BE ALLOWED TO ACT AS A LONGITUDINAL BRACE IF THEY ARE WITHIN 24" OF

THE CENTERLINE OF THE PIPING BRACED.

7. SWAY BRACING IS NOT REQUIRED FOR BRANCH LINES 2" AND SMALLER.

8. THE END SPRINKLER ON EACH BRANCH LINE SHALL BE RESTRAINED AGAINST EXCESSIVE MOVEMENT BY

APPROVED MEANS.

9. C-TYPE CLAMPS (INCLUDING BEAM AND LARGE FLANGE CLAMPS) WITH OR WITHOUT RETAINING STRAPS, SHALL

NOT BE USED TO ATTACH BRACES TO THE BUILDING STRUCTURE.

10. ALL BEAM HANGERS SHALL BE EQUIPPED WITH RETAINER STRAPS.

GENERAL NOTES:

A. SUBMIT ALL SHOP DRAWINGS TO LOCAL AUTHORITY HAVING JURISDICTION (AHJ) AND RECEIVE APPROVAL PRIOR

TO STARTING CONSTRUCTION.

B. COORDINATE ALL PIPING WITH OTHER TRADES PRIOR TO STARTING CONSTRUCTION.

C. ALL MATERIALS & INSTALLATIONS OF THIS AUTOMATIC FIRE SPRINKLER SYSTEM TO CONFORM TO NFPA 13 & 14

(2007 EDITION) OR CURRENT EDITION APPROVED BY LOCAL AHJ.

D. UNDERGROUND PIPING TO BE PROVIDED BY OTHERS. TEST AND FLUSHING CERTIFICATION TO BE PROVIDED

BEFORE FPS IS TO CONNECT TO ANY PIPING.

E. FIRE PROTECTION CONTRACTOR (FPC) WILL PROVIDE A RELIABLE MODEL A4 SPARE HEAD CABINET WITH A MINIMUM OF EACH TYPE OF SPRINKLER HEAD USED PER NFPA 13. WITH THE APPROPRIATE HEAD WRENCH FOR

EACH HEAD USED AS OUTLINED IN THE SPRINKLER HEAD LEGEND.

F. IT IS THE OWNERS RESPONSIBILITY TO PROVIDE ADEQUATE HEAT.

G. DRAINS WILL BE PROVIDED IN ACCORDANCE WITH NFPA 13. FPS DRAINS TO BE PIPED TO OUTSIDE OR AS

INDICATED ON DRAWINGS.

H. ALL SYSTEM PIPING SHALL BE HYDROSTATICALLY TESTED AT 200 PSI OR AT 50 PSI ABOVE THE SYSTEM

OPERATING PRESSURE, WHICHEVER IS GREATER.

I. ALL ELECTRICAL WIRING, CONDUIT, DETECTION, AND ALARM/CONTROL PANELS TO BE DONE BY ELECTRICAL

CONTRACTOR. TAMPER AND FLOW SWITCHES SHALL BE BY FPC.

J. ALL PAINTING, IF REQUIRED, DONE BY OTHERS.

K. PIPE SIZING PER HYDRAULIC CALCULATIONS.

L. MAIN PIPING 2-1/2" - 4" TO BE ANSI/ASTM A-795, EITHER SCHEDULE 40 BLACK SPRINKLER PIPING WITH THREADED ENDS AND ANVIL CAST IRON FITTINGS, OR GROOVED ENDS AND VICTAULIC GROOVED COUPLINGS AND FITTINGS

(UNLESS SHOWN OTHERWISE).

M. BRANCH LINE PIPING 2" AND SMALLER TO BE ANSI/ASTM A-795, EITHER SCHEDULE 40 BLACK SPRINKLER PIPING WITH THREADED ENDS AND ANVIL CAST IRON FITTINGS, OR GROOVED ENDS AND VICTAULIC GROOVED FITTINGS.

N. ALL GROOVED COUPLINGS TO BE "VICTAULIC" #005 ZERO-FLEX RIDGED COUPLINGS AND "VICTAULIC" #075 FLEX

COUPLINGS.

O. FPC TO START WORK AT POINT 1'-0" ABOVE FINISHED FLOOR.

P. SPRINKLER HEADS IN AREAS WITH DROPPED CEILINGS TO BE WHITE CONCEALERS NOT REQUIRED TO BE

INSTALLED IN CENTER OF CEILING TILES.

Q. SPRINKLER HEADS IN AREAS EXPOSED TO THE DECK TO BE UPRIGHT HEADS.

R. CUTTING, PATCHING, AND RESTORATION OF FLOORS, WALLS, AND CEILING TO BE DONE BY FPC.

S. SIGNS, HYDRAULIC PLACARDS AND SYSTEM INFORMATION DISPLAYS PROVIDED BY FPS WILL BE MANUFACTURED

BY FPPI INC.

T. FIRE STOPPING USED WILL BE HILTI FS-ONE

U. REFER TO ARCHITECTURAL PLANS FOR SECTION VIEWS OF BUILDINGS.

V. REFER TO ARCHITECTURAL CEILING PLAN FOR EXISTING HISTORICAL CEILINGS TO REMAIN.

W. COORDINATE ALL CONCRETE PENETRATIONS WITH STRUCTURAL DRAWINGS TO VERIFY HOW AND WHERE

CONCRETE CAN BE CUT.

X. COORDINATE REMOVAL OF PIPING WITH ASBESTOS ABATEMENT CONTRACTOR.

Y. FIRE SPRINKLER CONTRACTOR SHALL COORDINATE WITH MECHANICAL AND ELECTRICAL CONTRACTORS TO

ENSURE THAT HVAC AND LIGHT FIXTURES DON’T CONFLICT WITH SPRINKLERS.

Z. REFER TO ARCHITECTURAL REFLECTED CEILING PLANS SO THAT SPRINKLER HEADS DON’T RUIN THE CEILING

AESTHETICS

FIRE SPRINKLER CONTRACTOR SHALL ORDER A HYDRANT

FLOW TEST PRIOR TO DESIGN TO VERIFY PRESSURE.

STATIC PRESSURE HAS BEEN MEASURED AT 78 PSI ON THE

12 INCH WATER LINE IN THE STREET. SEE FIGURE BELOW.

HYDRANT FLOW TEST

18 BUILDING WATER LINES IMAGE

F0.1: F0.1 SCALE: NOT TO SCALE

REFER TO STRUCTURAL SPECIFICATIONS FOR SEISMIC

DESIGN REQUIREMENTS.

FI

R

E

PR

O T

EC

T

IO

N

S

PE

C

IF

IC

A

T

IO

N S

F0.1

BU

IL

D

IN

G

P H

A

SE

SO

U

T H

W

IN

G R

EN

O

V A

T

IO

N

U S

FO

R

ES

T

S

ER

V

IC

E, N

O R

T H

ER

N

R

EG

IO

N

R

EG

IO

N A

L O

FF

IC

E www.aearchitects.com

O W

N E

R

ISSUE DATE

REVISIONS

P R

O

JE

C T

D R

A W

IN

G

PROJECT No 13104.00 7.14.14

6 0 8 N O R T H 2 9 T H B I L L I N G S, M T 59101

PH 4 0 6 . 2 4 8 . 2 6 3 3

FAX 4 0 6 . 2 4 8 . 2 4 2 7

2 2 2 N O R T H H I G G I N S M I S S O U L A, M T 59802

PH 4 0 6 . 7 2 1 . 5 6 4 3

FAX 4 0 6 . 7 2 1 . 1 8 8 7

ARCHITII ECTSP

C

2014 MORRISON-MAIERLE, INC.

8DI

8CI

4C I

6C I

D

I

78.04 PSI

FO

R

T M

IS

S

O U

LA

R

O A

D

H ROAD

CAP

4" FIRE SERVICE

RETRO WATERSTOP

EXISTING SLAB

3" MIN

UNDISTURBED

SOILS (COMPACTED)

4000 PSI CONCRETE

BACKFILL

6.5' MIN BURY

EXISTING GROUND

WINDOW

18 FIRE SERVICE ENTRANCE DETAIL

F1.0: F1.0 SCALE: NOT TO SCALE

FI

R

E

PR

T

EC

T

IO

N

P

LA

N S

IT

E

PL

A

N

USFS BUILDING 26 -FIRE PR0TECTION PLAN SITE PLAN16

F1.0 : F1.0 3/32" = 1'-0"

NORTH

F1.0

BU

IL

D

IN

G

P H

A

SE

SO

U

T H

W

IN

G R

EN

O

V A

T

IO

N

U S

FO

R

ES

T

S

ER

V

IC

E, N

O R

T H

ER

N

R

EG

IO

N

R

EG

IO

N A

L O

FF

IC

E www.aearchitects.com

O W

N E

R

ISSUE DATE

REVISIONS

P R

O

JE

C T

D R

A W

IN

G

PROJECT No 13104.00 7.14.14

6 0 8 N O R T H 2 9 T H B I L L I N G S, M T 59101

PH 4 0 6 . 2 4 8 . 2 6 3 3

FAX 4 0 6 . 2 4 8 . 2 4 2 7

2 2 2 N O R T H H I G G I N S M I S S O U L A, M T 59802

PH 4 0 6 . 7 2 1 . 5 6 4 3

FAX 4 0 6 . 7 2 1 . 1 8 8 7

ARCHITII ECTSP

C

2014 MORRISON-MAIERLE, INC.

KEY NOTES:

1. PROVIDE SADDLE FOR 4” FIRE LINE TO CONNECT TO EXISTING 12” DUCTILE IRON WATER MAIN AND INSTALL THRUST BLOCKING AT ALL CONNECTIONS AND BENDS. INSTALL GATE VALVE ON THE 4” FIRE SERVICE LOCATED 5' FROM THE MAIN AND BRING TO SURFACE IN VALVE BOX

WITH PVC AND TRACER WIRE.

2. LOCATE 6' AND 4” CAST IRON WATER MAINS TO ENSURE THEY ARE MAINTAINED IN PLACE AND THAT THEY CAN BE CROSSED EFFICIENTLY TO

MAINTAIN SEPARATION WITH THE NEW 4” FIRE SERVICE.

3. PROVIDE A THREE POINT MONITORING SYSTEM OF THE WIDTH AND LENGTH OF ALL CRACKS IN BUILDING WALLS AND FLOORS WITHIN 10 FEET OF EXCAVATIONS. DOCUMENT CRACK WIDTHS AT TWO LOCATIONS ADJACENT TO EXCAVATIONS AND MONITOR AS WORK PROGRESSES TO ENSURE STRUCTURAL INTEGRITY OF THE BUILDING. IN THE EVENT THAT CRACKS BEGIN TO SPREAD OR CREEP, STOP WORK IMMEDIATELY, SHORE UP ALL WORK, AND CONTACT OWNER. PROVIDE 4000 PSI CONCRETE BACKFILL BENEATH FOOTING LOCATION AND LOCATED ON UNDISTURBED

COMPACTED SOILS.

4. REMOVE A MAXIMUM OF 3' BY 3' PORTION OF THE FLOOR TO INSTALL 4” FIRE SERVICE THROUGH. PROVIDE A CAST IN PLACE PIPE SEAL AROUND PIPE AND RETROFIT WATER STOP AT CONCRETE TO CONCRETE CONNECTIONS. PROVIDE GR. 60 DEFORMED REINFORCEMENT BARS DOWELED AND EPOXIED INTO EXISTING CONCRETE ON 12” MAXIMUM SPACING EACH WAY. INSTALL CONCRETE FLOOR PATCH EXTENDING 3” BELOW EXISTING SLAB AND MECHANICALLY VIBRATE EXCESS AIR POCKETS OUT FROM BELOW EXISTING SLAB.

1. CONTRACTOR SHOULD MAKE AN INITIAL SITE VISIT TO DETERMINE EXACT EXTENTS OF WORK PRIOR TO BIDDING THE PROJECT.

2. CONTACT UTILITY LOCATES PRIOR TO STARTING WORK.

3. LOCATE 12” DUCTILE IRON WATER MAIN FOR 4” FIRE SERVICE TAP AND LOCATE FIRE SPRINKLER RISER LOCATION TO PROVIDE A DIRECT

ROUTE FOR CONNECTION.

4. PROVIDE AND MAINTAIN A CITY OF MISSOULA APPROVED TRAFFIC CONTROL PLAN.

5. COORDINATE AND OBTAIN ALL PERMITS FOR WORK WITH MOUNTAIN WATER COMPANY PRIOR TO COMMENCING WITH CONSTRUCTION.

6. SALVAGE 8' LONG PIN DOWN CURB FOR REPLACEMENT BY CONTRACTOR.

7. MAINTAIN A MINIMUM OF 8' HORIZONTALLY FROM TRENCH EDGE TO EDGE OF TREES, CUT, TRIM, AND REPAIR BRANCHES AND ROOTS ACCORDING TO THE CITY OF MISSOULA'S URBAN FORESTRY DIVISION REQUIREMENTS TO ENSURE TREE LONGEVITY.

8. SALVAGE GRASS AND TOPSOIL FOR REPLACEMENT IN LANDSCAPING AREAS.

9. PROVIDE DEWATERING OF TRENCH EXCAVATIONS TO ENSURE WORK IS COMPLETED IN DRY CONDITIONS.

10. LOCATE ANY IRRIGATION LINES FOR TEMPORARY CAPPING TO ENSURE WATER IS NOT WASTED. PROVIDE A FULLY FUNCTIONAL IRRIGATION SYSTEM THAT IS DEMONSTRATED TO WORK PROPERLY AND ENSURE GRASS WILL TAKE IN REPLACEMENT AREAS.

11. SAW CUT FULL DEPTH ALL ASPHALT OR CONCRETE SURFACES TO PROVIDE A CLEAN UNIFORM MATCH LINE. REPLACE ROAD SECTION, ASPHALT, CURB AND SIDEWALK BASE, CONCRETE CURB, CONCRETE SIDEWALK, LANDSCAPING TOP SOIL, TO NEW CONDITION EQUALING

EXISTING SECTION THICKNESS.

12. ONLY REMOVE CONCRETE AT EXISTING JOINTED LOCATIONS TO MAINTAIN UNIFORM JOINTING THROUGHOUT.

13. OBTAIN A PROCTOR TEST FOR ALL MATERIALS ENCOUNTERED AND PROVIDE COMPACTION OF LIFTS NOT GREATER THAN 8” IN LOOSE DEPTH. MAINTAIN THE MOISTURE CONTENT OF FILL SOILS WITHIN PLUS OR MINUS 3% OF OPTIMUM MOISTURE AND COMPACT TO 98% OF MAXIMUM LABORATORY DENSITY AS DETERMINED BY AASHTO T99. OBTAIN A MINIMUM OF 2 COMPACTION TESTS FOR EACH 2' OF VERTICAL FILL PLACEMENT, BUT NOT LESS THAN 6 TESTS OUTSIDE THE BUILDING AND 2 TESTS INSIDE THE BUILDING.

14. OBTAIN CONCRETE TEST CYLINDERS FOR EACH TRUCK DELIVERED AND OBTAIN COMPACTION TESTING EQUAL TO OR GREATER THAN 95% OF THE MAXIMUM THEORETICAL DENSITY (RICE) AS DETERMINED BY ASTM D2041 FOR EACH DAY OF PAVING CONDUCTED.

15. ALL CONCRETE AND ASPHALT INSTALLATIONS SHALL MEET THE CITY OF MISSOULA STANDARDS FOR EQUIVALENT APPLICATIONS.

16. REPLACE ALL ROAD MARKINGS OR PAINT TO MATCH EXISTING MARKINGS.

17. PROVIDE A MEANS OF CONVEYING STORM WATER FLOWS AWAY FROM OPEN EXCAVATIONS AND ALLOWING FLOWS TO TRAVEL TO THEIR

HISTORIC DRAINAGE LOCATIONS.

18. CONDUCT ALL WORK IN ACCORDANCE WITH MONTANA PUBLIC WORKS STANDARD SPECIFICATIONS (MPWSS), SIXTH EDITION DATED APRIL, 2010. IN CONJUNCTION WITH THE MPWSS CONTRACTOR SHALL PERFORM ALL WORK IN ACCORDANCE WITH CITY OF MISSOULA, MISSOULA

COUNTY, AND THE MOUNTAIN WATER COMPANY STANDARDS.

19. OBTAIN NECESSARY PERMITS THROUGH ALL AGENCIES WITH JURISDICTION.

GENERAL NOTES:

WHWH

WH

WH BOILER

BOILER

DF DF

STAIR

RESTROOM

MECH / ELECT

TELE/DATA

ELEVATOR

MACHINE

ELEVATOR

VESTIBULE VESTIBULE

UP UP

UP

DOWN 17"

DOWN

17"

DOWN

17"

DOWN 17"

UP UP

UP

UP

ELECTRICAL

UP

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: GENERAL OFFICE SPACE

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE - OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: WET

FIRE

SPRINKLER

RISER

FUTURE CONSTRUCTION PHASE:

DO NOT PROVIDE FIRE SPRINKLER COVERAGE

UNDER THIS PHASE OF CONSTRUCTION

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: IT/ TELE DATA -ELECT ROOM

DOUBLE-INTERLOCKED SYSTEM REQUIRED.

PROVIDE AUTOMATIC FLOW CONTROL VALVE

IN BRANCH PIPING SERVING THIS AREA. VALVE TO

BE INTERLOCKED WITH A CEILING-MOUNTED HEAT

AND/OR SMOKE DETECTOR.

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE - OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: WET

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: MECHANICAL ROOM

ORDINARY HAZARD (GROUP I): 0.15 GPM/1500 SF

COMBINED INSIDE - OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: WET

NEW 4" FIRE SERVICE - REFER TO SITE PLAN

FOR CONTINUATION

THIS CEILING AREA (SHOWN HATCHED) IS

PLANNED FOR PIPING AND UTILITIES. ROUTE

PIPING MAINS TIGHT TO CEILING.

WET FIRE SPRINKLER MAIN

APPROXIMATELY 45 FT TO 12

IN. MAIN FOR CONNECTION.

SEE SHEET F1.0

DRY FIRE SPRINKLER MAIN

POTENTIAL FUTURE

PHASE RISER LOCATION

POTENTIAL FIRE

RISER LOCATION

POTENTIAL FIRE

RISER LOCATION

FUTURE CONNECTION

POINT FOR FUTURE

PHASE INSTALLATION

PROVIDE PROVISIONS FOR

FUTURE CONNECTION FOR

INSTALLATION OF SYSTEM

DURING FUTURE PHASES

FIRE DEPARTMENT

CONNECTION.

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: EXTERIOR CANOPY

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE/OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: DRY

FUTURE CONSTRUCTION PHASE:

DO NOT PROVIDE FIRE SPRINKLER COVERAGE

UNDER PHASE 1 CONSTRUCTION

APPROXIMATE

CONSTRUCTION

AREA OF WORK

FUTURE AREA OF

PHASED WORK. FUTURE AREA OF

PHASED WORK.

FUTURE AREA OF

PHASED WORK.

APPROXIMATE

CONSTRUCTION

AREA OF WORK

PLANNED CONSTRUCTION PHASES:

1. THESE CONSTRUCTION DOCUMENTS ARE

LIMITED TO THE IDENTIFIED

CONSTRUCTION AREA. THE FIRE

SPRINKLER SYSTEM TO BE INSTALLED FOR

THIS PHASE SHALL PROVIDE FULL

COVERAGE IN ACCORDANCE WITH NFPA 13

REQUIREMENTS BUT IS TO BE LIMITED TO

THE PLAN AREAS IDENTIFIED. NOTE THAT

SOME OF THE WORK REQ'D FOR THIS

PHASE OF CONSTRUCTION EXTENDS INTO

FUTURE AREAS. COORD. W/ GEN. CONT'R.

2. CONSTRUCTION AREAS INDICATED BY

"FUTURE AREA OF PHASED WORK" ARE

FOR REFERENCE ONLY AND ARE NOT PART

OF THIS CONTRACT.

3. THE FIRE SPRINKLER WATER SERVICE,

RISER, BACKFLOW AND OTHER PRIMARY

EQUIPMENT FOR THIS FIRST PHASE OF

CONSTRUCTION SHALL BE DESIGNED FOR

THE ENTIRE BUILDING (ALL PHASES). THE

DESIGN SHALL CONSIDER EASE OF

EXPANSION INTO FUTURE CONSTRUCTION

PHASES.

4. ALL FIRE PROTECTION WORK SHALL BE

APPROVED BY THE AHJ (FIRE MARSHALL)

PRIOR TO THE STARTING OF ANY

PLANNING, DESIGN AND/OR

CONSTRUCTION.

WET SYSTEM - LIGHT HAZARD

0.10 GPM/1500 SF

COMBINED HOSE ALLOWANCE: 250 GPM @ 60-90 MIN.

WET SYSTEM - ORDINARY HAZARD

0.10 GPM/1500 SF

COMBINED HOSE ALLOWANCE: 250 GPM @ 60-90 MIN.

DRY OR GLYCOL SPRINKLERS

(REQUIRED IN UNCONDITIONED SPACES SUCH AS

ATTICS AND EXTERIOR OVERHANGS

CONSTRUCTED OF COMBUSTIBLE MATERIALS)

A D E F G H KCB J

BA

SE

M

EN

T F

IR

E

PR

O

T

EC

T

IO

N P

LA

N

USFS BUILDING 26 - BASEMENT FIRE PR0TECTION PLAN 16

F2.0 : F2.0 1/8" = 1'-0"

NORTH

F2.0

BU

IL

D

IN

G

P H

A

SE

SO

U

T H

W

IN

G R

EN

O

V A

T

IO

N

U S

FO

R

ES

T

S

ER

V

IC

E, N

O R

T H

ER

N

R

EG

IO

N

R

EG

IO

N A

L O

FF

IC

E www.aearchitects.com

O W

N E

R

ISSUE DATE

REVISIONS

P R

O

JE

C T

D R

A W

IN

G

PROJECT No 13104.00 7.14.14

6 0 8 N O R T H 2 9 T H B I L L I N G S, M T 59101

PH 4 0 6 . 2 4 8 . 2 6 3 3

FAX 4 0 6 . 2 4 8 . 2 4 2 7

2 2 2 N O R T H H I G G I N S M I S S O U L A, M T 59802

PH 4 0 6 . 7 2 1 . 5 6 4 3

FAX 4 0 6 . 7 2 1 . 1 8 8 7

ARCHITII ECTSP

COMPACT FRIDGE

MICRO

DOWN DOWN

DOWN DOWN

DOWNDOWN

UP UP

RAMP

DOWN

RAMP

DOWN

RAMP

DOWN

DOWN DOWN

UP

MICRO

UP

(E)

SWR

(N)

FSR

(N)

FSR R R R

R R R R

12"Ø

EXHAUST

12"Ø

EXHAUST

BOILER

VENT

BOILER

VENT

R

R

R

R

R

R

R

R

R

6"Ø 8"Ø

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: EXTERIOR CANOPY

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE/OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: DRY

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: EXTERIOR CANOPY

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE - OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: DRY

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: GENERAL OFFICE SPACE

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE - OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: WET

FUTURE CONSTRUCTION PHASE:

DO NOT PROVIDE FIRE SPRINKLER COVERAGE

UNDER PHASE 1 CONSTRUCTION

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: GENERAL OFFICE SPACE

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE/OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: WET

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: EXTERIOR CANOPY

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE/OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: DRY

POTENTIAL

FUTURE PHASE 2

RISER LOCATION

POTENTIAL FIRE

RISER LOCATION POTENTIAL FIRE

RISER LOCATION

GENERAL NOTE:

1. FIRE SPRINKLER CONTRACTOR SHALL

COORDINATE WITH MECHANICAL AND

ELECTRICAL CONTRACTORS TO ENSURE

THAT HVAC AND LIGHT FIXTURES DON’T

CONFLICT WITH SPRINKLERS.

2. REFER TO ARCHITECTURAL REFLECTED

CEILING PLANS SO THAT SPRINKLER

HEADS DON’T RUIN THE CEILING

AESTHETICS (TYPICAL ALL SPACES).

PROVIDE SIDEWALL HEADS OR ROUTE

PIPING IN JOIST SPACE AS NECESSARY.

COORDINATE WITH GENERAL

CONTRACTOR.

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

PLANNED CONSTRUCTION PHASES:

1. THESE CONSTRUCTION DOCUMENTS ARE

LIMITED TO THE IDENTIFIED

CONSTRUCTION AREA. THE FIRE

SPRINKLER SYSTEM TO BE INSTALLED FOR

THIS PHASE SHALL PROVIDE FULL

COVERAGE IN ACCORDANCE WITH NFPA 13

REQUIREMENTS BUT IS TO BE LIMITED TO

THE PLAN AREAS IDENTIFIED. NOTE THAT

SOME OF THE WORK REQ'D FOR THIS

PHASE OF CONSTRUCTION EXTENDS INTO

FUTURE AREAS. COORD. W/ GEN. CONT'R.

2. CONSTRUCTION AREAS INDICATED BY

"FUTURE AREA OF PHASED WORK" ARE

FOR REFERENCE ONLY AND ARE NOT PART

OF THIS CONTRACT.

3. THE FIRE SPRINKLER WATER SERVICE,

RISER, BACKFLOW AND OTHER PRIMARY

EQUIPMENT FOR THIS FIRST PHASE OF

CONSTRUCTION SHALL BE DESIGNED FOR

THE ENTIRE BUILDING (ALL PHASES). THE

DESIGN SHALL CONSIDER EASE OF

EXPANSION INTO FUTURE CONSTRUCTION

PHASES.

4. ALL FIRE PROTECTION WORK SHALL BE

APPROVED BY THE AHJ (FIRE MARSHALL)

PRIOR TO THE STARTING OF ANY

PLANNING, DESIGN AND/OR

CONSTRUCTION.

FUTURE AREA OF

PHASED WORK.

APPROXIMATE

CONSTRUCTION

AREA OF WORK

APPROXIMATE

CONSTRUCTION

AREA OF WORK

A D E F G H KCB J

WET SYSTEM - LIGHT HAZARD

0.10 GPM/1500 SF

COMBINED HOSE ALLOWANCE: 250 GPM @ 60-90 MIN.

WET SYSTEM - ORDINARY HAZARD

0.10 GPM/1500 SF

COMBINED HOSE ALLOWANCE: 250 GPM @ 60-90 MIN.

DRY OR GLYCOL SPRINKLERS

(REQUIRED IN UNCONDITIONED SPACES SUCH AS

ATTICS AND EXTERIOR OVERHANGS

CONSTRUCTED OF COMBUSTIBLE MATERIALS)

FI

R

ST

F

LO

O

R F

IR

E

PR

O

T

EC

T

IO

N P

LA

N

USFS BUILDING 26 - FIRST FLOOR FIRE PROTECTION PLAN 16

F2.1 : F2.1 1/8" = 1'-0"

NORTH

F2.1

BU

IL

D

IN

G

P H

A

SE

SO

U

T H

W

IN

G R

EN

O

V A

T

IO

N

U S

FO

R

ES

T

S

ER

V

IC

E, N

O R

T H

ER

N

R

EG

IO

N

R

EG

IO

N A

L O

FF

IC

E www.aearchitects.com

O W

N E

R

ISSUE DATE

REVISIONS

P R

O

JE

C T

D R

A W

IN

G

PROJECT No 13104.00 7.14.14

6 0 8 N O R T H 2 9 T H B I L L I N G S, M T 59101

PH 4 0 6 . 2 4 8 . 2 6 3 3

FAX 4 0 6 . 2 4 8 . 2 4 2 7

2 2 2 N O R T H H I G G I N S M I S S O U L A, M T 59802

PH 4 0 6 . 7 2 1 . 5 6 4 3

FAX 4 0 6 . 7 2 1 . 1 8 8 7

ARCHITII ECTSP

DOWNDOWN

DOWN

DOWNDOWN

DOWNDOWN

DOWN

DOWNDOWN

DOWN

DOWN

(E)

SWR

(N)

FSR

BOILER

VENT

BOILER

VENT

R

R

R

R R

12"Ø

EXHAUST

12"Ø

EXHAUST

6"Ø 8"Ø

APPROXIMATE

CONSTRUCTION

AREA OF WORK

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: EXTERIOR CANOPY

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE - OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: DRY

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: GENERAL OFFICE SPACE

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE - OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: WET

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: EXTERIOR CANOPY

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE/OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: DRY

FUTURE CONSTRUCTION PHASE:

DO NOT PROVIDE FIRE SPRINKLER COVERAGE

UNDER THIS PHASE OF CONSTRUCTION

POTENTIAL

FUTURE PHASE

RISER LOCATION

POTENTIAL FIRE

RISER LOCATION

POTENTIAL FIRE

RISER LOCATION

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

EXISTING

PLASTER

CEILINGS

GENERAL NOTE:

1. FIRE SPRINKLER CONTRACTOR SHALL

COORDINATE WITH MECHANICAL AND

ELECTRICAL CONTRACTORS TO ENSURE

THAT HVAC AND LIGHT FIXTURES DON’T

CONFLICT WITH SPRINKLERS.

2. REFER TO ARCHITECTURAL REFLECTED

CEILING PLANS SO THAT SPRINKLER

HEADS DON’T RUIN THE CEILING

AESTHETICS (TYPICAL ALL SPACES).

PROVIDE SIDEWALL HEADS OR ROUTE

PIPING IN JOIST SPACE AS NECESSARY.

COORDINATE WITH GENERAL

CONTRACTOR.

FUTURE AREA OF

PHASED WORK.

PLANNED CONSTRUCTION PHASES:

1. THESE CONSTRUCTION DOCUMENTS ARE

LIMITED TO THE IDENTIFIED

CONSTRUCTION AREA. THE FIRE

SPRINKLER SYSTEM TO BE INSTALLED FOR

THIS PHASE SHALL PROVIDE FULL

COVERAGE IN ACCORDANCE WITH NFPA 13

REQUIREMENTS BUT IS TO BE LIMITED TO

THE PLAN AREAS IDENTIFIED. NOTE THAT

SOME OF THE WORK REQ'D FOR THIS

PHASE OF CONSTRUCTION EXTENDS INTO

FUTURE AREAS. COORD. W/ GEN. CONT'R.

2. CONSTRUCTION AREAS INDICATED BY

"FUTURE AREA OF PHASED WORK" ARE

FOR REFERENCE ONLY AND ARE NOT PART

OF THIS CONTRACT.

3. THE FIRE SPRINKLER WATER SERVICE,

RISER, BACKFLOW AND OTHER PRIMARY

EQUIPMENT FOR THIS FIRST PHASE OF

CONSTRUCTION SHALL BE DESIGNED FOR

THE ENTIRE BUILDING (ALL PHASES). THE

DESIGN SHALL CONSIDER EASE OF

EXPANSION INTO FUTURE CONSTRUCTION

PHASES.

4. ALL FIRE PROTECTION WORK SHALL BE

APPROVED BY THE AHJ (FIRE MARSHALL)

PRIOR TO THE STARTING OF ANY

PLANNING, DESIGN AND/OR

CONSTRUCTION.

A D E F G H KCB JA D E F G H KCB J

WET SYSTEM - LIGHT HAZARD

0.10 GPM/1500 SF

COMBINED HOSE ALLOWANCE: 250 GPM @ 60-90 MIN.

WET SYSTEM - ORDINARY HAZARD

0.10 GPM/1500 SF

COMBINED HOSE ALLOWANCE: 250 GPM @ 60-90 MIN.

DRY OR GLYCOL SPRINKLERS

(REQUIRED IN UNCONDITIONED SPACES SUCH AS

ATTICS AND EXTERIOR OVERHANGS

CONSTRUCTED OF COMBUSTIBLE MATERIALS)

SE

C

O N

D F

LO

O

R F

IR

E

PR

O

T

EC

T

IO

N P

LA

N

USFS BUILDING 26 - SECOND FLOOR FIRE PROTECTION PLAN 16

F2.2 : F2.2 1/8" = 1'-0"

NORTH

F2.2

BU

IL

D

IN

G

P H

A

SE

SO

U

T H

W

IN

G R

EN

O

V A

T

IO

N

U S

FO

R

ES

T

S

ER

V

IC

E, N

O R

T H

ER

N

R

EG

IO

N

R

EG

IO

N A

L O

FF

IC

E www.aearchitects.com

O W

N E

R

ISSUE DATE

REVISIONS

P R

O

JE

C T

D R

A W

IN

G

PROJECT No 13104.00 7.14.14

6 0 8 N O R T H 2 9 T H B I L L I N G S, M T 59101

PH 4 0 6 . 2 4 8 . 2 6 3 3

FAX 4 0 6 . 2 4 8 . 2 4 2 7

2 2 2 N O R T H H I G G I N S M I S S O U L A, M T 59802

PH 4 0 6 . 7 2 1 . 5 6 4 3

FAX 4 0 6 . 7 2 1 . 1 8 8 7

ARCHITII ECTSP

302.1

C

302.2

C

302.3

C

303.1

C

303.2

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: UNCONDITIONED ATTIC

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE/OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: DRY

FUTURE CONSTRUCTION PHASE:

DO NOT PROVIDE FIRE SPRINKLER COVERAGE

UNDER THIS PHASE OF CONSTRUCTION

HYDRAULIC DESIGN AREA

ALLOWABLE DESIGN: UNCONDITIONED ATTIC

LIGHT HAZARD: 0.10 GPM/1500 SF

COMBINED INSIDE/OUTSIDE HOSE ALLOWANCE:

250 GPM@60-90 MIN.

SYSTEM TYPE: DRY

POTENTIAL

FUTURE PHASE 2

(DRY) RISER

LOCATION

POTENTIAL (DRY)

FIRE RISER LOCATION

POTENTIAL (DRY)

FIRE RISER LOCATION

FUTURE AREA OF

PHASED WORK.

APPROXIMATE

CONSTRUCTION

AREA OF WORK

APPROXIMATE

CONSTRUCTION

AREA OF WORK

PLANNED CONSTRUCTION PHASES:

1. THESE CONSTRUCTION DOCUMENTS ARE

LIMITED TO THE IDENTIFIED

CONSTRUCTION AREA. THE FIRE

SPRINKLER SYSTEM TO BE INSTALLED FOR

THIS PHASE SHALL PROVIDE FULL

COVERAGE IN ACCORDANCE WITH NFPA 13

REQUIREMENTS BUT IS TO BE LIMITED TO

THE PLAN AREAS IDENTIFIED. NOTE THAT

SOME OF THE WORK REQ'D FOR THIS

PHASE OF CONSTRUCTION EXTENDS INTO

FUTURE AREAS. COORD. W/ GEN. CONT'R.

2. CONSTRUCTION AREAS INDICATED BY

"FUTURE AREA OF PHASED WORK" ARE

FOR REFERENCE ONLY AND ARE NOT PART

OF THIS CONTRACT.

3. THE FIRE SPRINKLER WATER SERVICE,

RISER, BACKFLOW AND OTHER PRIMARY

EQUIPMENT FOR THIS FIRST PHASE OF

CONSTRUCTION SHALL BE DESIGNED FOR

THE ENTIRE BUILDING (ALL PHASES). THE

DESIGN SHALL CONSIDER EASE OF

EXPANSION INTO FUTURE CONSTRUCTION

PHASES.

4. ALL FIRE PROTECTION WORK SHALL BE

APPROVED BY THE AHJ (FIRE MARSHALL)

PRIOR TO THE STARTING OF ANY

PLANNING, DESIGN AND/OR

CONSTRUCTION.

A D E F G H KCB JA D E F G H KCB J

WET SYSTEM - LIGHT HAZARD

0.10 GPM/1500 SF

COMBINED HOSE ALLOWANCE: 250 GPM @ 60-90 MIN.

WET SYSTEM - ORDINARY HAZARD

0.10 GPM/1500 SF

COMBINED HOSE ALLOWANCE: 250 GPM @ 60-90 MIN.

DRY OR GLYCOL SPRINKLERS

(REQUIRED IN UNCONDITIONED SPACES SUCH AS

ATTICS AND EXTERIOR OVERHANGS

CONSTRUCTED OF COMBUSTIBLE MATERIALS)

A T

T

IC

F

IR

E

PR

O T

EC

T

IO

N

P

LA

N

USFS BUILDING 26 - ATTIC PLAN FIRE PROTECTION PLAN 16

F2.2 : F2.2 1/8" = 1'-0"

NORTH

F2.3

BU

IL

D

IN

G

P H

A

SE

SO

U

T H

W

IN

G R

EN

O

V A

T

IO

N

U S

FO

R

ES

T

S

ER

V

IC

E, N

O R

T H

ER

N

R

EG

IO

N

R

EG

IO

N A

L O

FF

IC

E www.aearchitects.com

O W

N E

R

ISSUE DATE

REVISIONS

P R

O

JE

C T

D R

A W

IN

G

PROJECT No 13104.00 7.14.14

6 0 8 N O R T H 2 9 T H B I L L I N G S, M T 59101

PH 4 0 6 . 2 4 8 . 2 6 3 3

FAX 4 0 6 . 2 4 8 . 2 4 2 7

2 2 2 N O R T H H I G G I N S M I S S O U L A, M T 59802

PH 4 0 6 . 7 2 1 . 5 6 4 3

FAX 4 0 6 . 7 2 1 . 1 8 8 7

ARCHITII ECTSP

LESSTHAN 6"

ADD'L "AP" OR STANDARD

SPRINKLERS AS REQ'D

MORE

THAN 4'-0"

" M

IN

"BB"

NO ADD'L

SPRINKLER

REQ'D.

6" MIN.

4'-0" OR

LESS

" M

IN

"BB"

"SD"

'-0

" M

IN

"BB" = BACK-TO-BACK DUAL DIRECTIONAL ATTIC SPRINKLER

"SD" = SINGLE DIRECTIONAL ATTIC SPRINKLER

"HIP" = TYCO MODEL HIP ATTIC SPRINKLER

"AP" = TYCO MODEL AP (ATTIC PLUS) SPRINKLER

STD. = STANDARD SPRAY SPRINKLER

" M

A X

" M

IN

4-12

FOR ROOF PITCH LESS THAN

4:12, 12" MAX. BELOW PEAK

AND 1" MIN. BELOW BOTTOM

OF TOP CHORD OR RAFTER

"BB", "SD",

OR "HIP"

" M

IN

SCISSOR TRUSS

BOTTOM CHORD "BB" OR "SD"

6'-0" MAX. - 4'-0" MIN.

RIDGE

TRUSS

"AP" OR STD.

7'-0" MIN. FOR "AP" - 6'-0" MIN. FOR STD.

RIDGE

TRUSS

ATTIC

SPRINKLER

BRANCH

LINE

"BB", "SD"

OR "HIP"

6" MIN.

RIDGE

TRUSS

"BB" OR "HIP"

" M

A X

" M

IN

6" MAX.

6'-

0"

MAX.

"BB"

6'- 0"

MAX.

10'-0" MAX. "BB" SPAN

"AP" COVERAGE

6'- 0"

MAX.

"AP" @ 7'-0" TO

8'-0" O.C.

6'- 0"

MAX.

10'-0" MAX. "SD" SPAN

"AP" COVERAGE

4'- 0"

MIN

ADD'L "AP" OR STANDARD

SPRINKLERS AS REQ'D

BRANCH

LINE

ADD'L "AP" OR STANDARD

SPRINKLERS AS REQ'D

"AP" @ 7'-0" TO

8'-0" O.C.

NOTE:

THERE IS AN ANTIFREEZE SYSTEM REMOTE FROM THE SYSTEM RISER (SEE PLANS). MOUNT PLACARD ON THE SYSTEM RISER INDICATING: "1 REMOTE ANTIFREEZE SYSTEM". MOUNT AN ADDITIONAL PLACARD ON THE ANTIFREEZE SYSTEM MAIN VALVE INDICATING: SOLUTION, MANUFACTURER, CONCENTRATION, AND VOLUME OF ANTIFREEZE USED IN THE SYSTEM.

*-IF APPLICABLE TO PROJECT

2'-6" A.F.F.

1'-0"

A.F.F. FIN. FLR.

6' -0

M

IN

2" CLR. ALL AROUND

3 4 4

9 HEAD BOX

2" BALL

DRIP

2'-6" A.F.F.

HANGER ROD

TURN BUCKLE (AS

REQUIRED)

INSULATION

PIPE

SHEET METAL

SADDLE INSERT

CLEVIS TYPE HANGER FOR

PIPE 2" & LARGER

HANGER ROD

TURN BUCKLE

(AS REQUIRED)

INSULATION

PIPE

SHEET METAL

SADDLE INSERT

PIPE STRAP TYPE HANGER

FOR PIPE LESS THAN 2"

4-WAY ADAPTER

QUICK

CLAMP

SPRINKLER PIPE

1"Ø SCHED. 40

PIPE

CONNECT TO STRUCTURE

PER APPLICABLE PIPE

SUPPORT DETAIL

HANGER ROD SIZE

PER SCHEDULE

HANGER ROD SIZE

PER SCHEDULE

PIPE SIZE ROD SIZE

4"Ø & LESS 3

8"Ø 5, 6 & 8"Ø 10 & 12"Ø

2"Ø

8"Ø

SPRINKLER PIPE

1"Ø SCHED. 40

PIPE

QUICK

CLAMP

SUPPORT STRUCTURE

ANCHORAGE

SUPPORT STRUCTURE

F9.1 : F2.3 SCALE: NOT TO SCALE

ATTIC SPRINKLER DETAILS12

F9.1 : F2.0 SCALE: NOT TO SCALE

FIRE SERVICE RISER DETAIL16

11 2-WAY SWAY BRACE DETAIL 15 4-WAY SWAR BRACE DETAIL

14 PIPE HANGER DETAILS

F9.1: F2.0, F2.1, F2.3 SCALE: NOT TO SCALE

SCALE: NOT TO SCALESCALE: NOT TO SCALEF9.1: F2.0, F2.1, F2.3 F9.1: F2.0, F2.1, F2.3

D

ET

A

IL

S

F9.1

BU

IL

D

IN

G

P H

A

SE

SO

U

T H

W

IN

G R

EN

O

V A

T

IO

N

U S

FO

R

ES

T

S

ER

V

IC

E, N

O R

T H

ER

N

R

EG

IO

N

R

EG

IO

N A

L O

FF

IC

E www.aearchitects.com

O W

N E

R

ISSUE DATE

REVISIONS

P R

O

JE

C T

D R

A W

IN

G

PROJECT No 13104.00 7.14.14

6 0 8 N O R T H 2 9 T H B I L L I N G S, M T 59101

PH 4 0 6 . 2 4 8 . 2 6 3 3

FAX 4 0 6 . 2 4 8 . 2 4 2 7

2 2 2 N O R T H H I G G I N S M I S S O U L A, M T 59802

PH 4 0 6 . 7 2 1 . 5 6 4 3

FAX 4 0 6 . 7 2 1 . 1 8 8 7

ARCHITII ECTSP