AG-03R6-S-10-0051
South Fork Fish Creek Stewardship IRSC / Lolo NF
Appendix A-4, Supplemental Specifications, Page 1 of 23
Table of Contents
Table of Contents Preface 101 - Terms, Format, and Definitions 102 - Bid, Award, and Execution of Contract 103 - Scope of Work 104 - Control of Work 105 - Control of Material 106 - Acceptance of Work 107 - Legal Relations and Responsibility to the Public 108 - Prosecution and Progress 109 - Measurement and Payment 151 - Mobilization 155 - Schedules for Construction Contracts 157 - Soil Erosion Control 203 - Removal of Structures and Obstructions 211 - Closing, Obliteration, or Treatment of Existing Roads 622 - Rental Equipment 625 - Turf Establishment 680 - Noxious Weed Treatment
Appendix A-4, Supplemental Specifications, Page 2 of 23
Preface Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, U.S. Department of Agriculture, has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions 101.00_nat_us_07_25_2005
101.01_nat_us_04_04_2007
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
http://www.nist.gov/�
Appendix A-4, Supplemental Specifications, Page 3 of 23
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges.
Under these FP specifications this term will replace the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Appendix A-4, Supplemental Specifications, Page 4 of 23
Figure 101-1—Illustration of road structure terms.
Appendix A-4, Supplemental Specifications, Page 5 of 23
102 - Bid, Award, and Execution of Contract 102.00_nat_us_02_16_2005
Delete Delete Section 102 in its entirety.
103 - Scope of Work 103.00_nat_us_02_16_2005
Deletions Delete all but Subsection 103.01 Intent of Contract.
104 - Control of Work 104.00_nat_us_06_16_2006
Deletions
Delete Subsections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
Appendix A-4, Supplemental Specifications, Page 6 of 23
105 - Control of Material 105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work 106.01_nat_us_03_29_2005
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed
Appendix A-4, Supplemental Specifications, Page 7 of 23 value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site.
If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price.
Four methods of determining conformity and accepting work are described in Subsections
106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
(2) Number of samples;
(3) Sample transport;
(4) Test procedures;
(5) Testing laboratories;
(6) Reporting;
(7) Estimated time and costs; and
(8) Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed
Appendix A-4, Supplemental Specifications, Page 8 of 23
Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07_nat_us_05_11_2004
106.07 Delete
Delete Subsection 106.07.
Appendix A-4, Supplemental Specifications, Page 9 of 23
107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
Appendix A-4, Supplemental Specifications, Page 10 of 23
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress 108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment 109.00_nat_us_02_17_2005
109 Deletions Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Change “Contract quantity.” To “(b) Design Quantity (DQ).” These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units DESIGNATED IN THE SCHEDULE OF ITEMS may be authorized under any of the following conditions:
(1) Changes in the work authorized by the CO.
(2) A determination by the CO that errors exist in the original design that cause a PAY ITEM quantity to change by 15 percent or more.
(3) A written request submitted to the CO showing evidence of errors in the original design that cause the quantity of a PAY ITEM to change by 15 percent or
Appendix A-4, Supplemental Specifications, Page 11 of 23 more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definitions:
(q) Actual Quantities (AQ). These quantities are determined from measurements of completed work.
151 - Mobilization
Delete Section 151 in its entirety and replace with the following.
Description
151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site;
obtaining of permits, insurance, and bonds. This work also includes washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands, according to the requirements within.
Construction Requirements
151.02 Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.
Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.
Notify the CO in writing at least 72 hours before moving any construction equipment onto the national forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.
Use methods of cleaning and locations for cleaning approved by the CO.
For work at a commercial washing facility, use an approved facility.
New infestations of noxious weeds of concern to Forest Service and identified by either Contractor or Forest Service, in the Project Area or on the haul route, will be promptly reported to the other party. Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found.
Appendix A-4, Supplemental Specifications, Page 12 of 23
A current list of noxious weeds of concern to Forest Service is available at each Forest Service office.
Measurement
151.03 Clean all track equipment prior to moving onto this project. The initial cleaning will not be included in the measurement for payment. Payment for cleaning will only be made if subsequent cleanings are ordered by the CO. Measurement shall be on an “each” basis, meaning one complete cleaning of all equipment required for this contract.
Subsequent cleanings necessitated by the Contractor’s actions but not directed by the CO will not be included in the measurement for payment.
Measure mobilization according to Subsection 109.02.
Payment
151.04 The accepted quantity, measured as provided in Subsection 109.02, will be paid at the contract price per unit of measurement for the Section 151 pay item shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section.
See Subsection 109.05.
Progress payments for mobilization lump sum will be paid as follows:
(a) If applicable, bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.
(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.
(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.
(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.
Include all costs associated with the initial cleaning of equipment in the unit bid price for Mobilization. Cleaning for subsequent move-ins will not be paid for unless after a suspension ordered by the CO.
155 - Schedules for Construction Contracts
155 Delete.
Delete Section 155 in its entirety.
Appendix A-4, Supplemental Specifications, Page 13 of 23
157 - Soil Erosion Control
Material
157.02 Material
Add the following:
Provide bales, wattles, logs and rolls from a certified noxious weed free source.
Construction Requirements
157.03 General
Prior to the start of construction, submit a written plan for review that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Include methods to minimize disturbance to the stream and prevent run off from the construction site entering directly into the stream.
The “Soil Erosion Control Plan” must address construction activities that have the potential for stream sedimentation.
203 - Removal of Structures and Obstructions
203.01 Description.
Delete and replace with the following:
This work consists of salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions. The work shall also include construction slash and debris, unless specified to use for windrows, site scatter, or other final site preparation or erosion controls.
203.00_01_us_10_11_2006
203.03 Salvaging Material.
Delete this subsection and add the following:
Unless shown on the plans, remove all designated material from the project area and National Forest land.
Appendix A-4, Supplemental Specifications, Page 14 of 23
203.04_nat_us_02_18_2005
203.05 Disposing of Material.
(a) Remove from project.
Delete this paragraph and add the following:
(a) All material designated for removal becomes the property of the Contractor unless otherwise shown on the plans. Dispose of all items not designated to be salvaged for the Government in any legal manner.
Delete the following:
(b) Burn.
(c) Burn.
(e) Scattering. Scatter pieces of wood less than 3 inches in diameter and 3 feet in length within the clearing limits. Do not place construction slash in lakes, meadows, streams, or streambeds. Immediately remove construction slash that interferes with drainage structures.
Delete Section 211 in its entirety and replace with the following:
211 – Closing, Obliteration, or Treatment of Existing Roads
Description
211.01 Work. Treat roadways by removing rigid material, including culverts and cross drains, constructing water bars, recontouring or scarifying the roadbed, restoring stream crossings and drainage facilities to their original hydrologic function, installing gradient control structures in stream channels; removing selected fill; scattering slash material;
and re-vegetating. This work also includes, all mobilization of road decommissioning equipment from site to site.
211.02 Performance. Begin work at the road end or designated start location and progress out towards the permanent road closure.
211.03 Clearing and Slash Treatment. When necessary to access the project, clearing will occur concurrently with corresponding closure level treatments. Material generated during clearing shall be shall be placed along the edge of the road where it can be used to scattered along the ripped roadbed or re-contoured surface. Material generated does not need to be limbed and lopped. Do not place slash on the constructed waterbars.
Appendix A-4, Supplemental Specifications, Page 15 of 23
211.04 Treatment of Roadway. Treat the roadway using one of the following methods, as specified in the SCHEDULE OF ITEMS:
(a) Closure Level 3S. Shape the roadway as SHOWN ON THE DRAWINGS to drain water. Loosen the roadbed by ripping or scarifying along the entire width to provide a seedbed, and promote establishment of vegetation. Rip the roadbed to a depth of 6 inches. Do not rip the roadway at waterbar locations. Complete at least one pass using a non linear pattern during the ripping procedure. To prevent re-compacting the surface, rip the roadbed in a sequence that will ensure that equipment will not be driven back over the areas. Construct waterbars as SHOWN ON THE DRAWINGS. Remove culverts when SHOWN ON THE PLANS and treat as specified in Section 203.05. Remove all other structures, such as metal or wooden open top cross drains, rubber belt water diverters and other plastic or metal materials when SHOWN ON THE PLANS. Scatter slash evenly along the ripped roadbed. Fully re-contour 150’ at the entrance of the roadway when SHOWN ON THE PLANS.
(b) Closure Level 3D. Shape the roadway as SHOWN ON THE DRAWINGS to drain water. Loosen the roadbed by ripping or scarifying along the entire width to provide a seedbed, and promote establishment of vegetation. Rip the roadbed to a minimum depth of 18 inches and a maximum depth of 24 inches. Do not rip the roadway at waterbar locations. Complete at least one pass using a non linear pattern during the ripping procedure. To prevent re-compacting the surface, rip the roadbed in a sequence that will ensure that equipment will not be driven back over the areas. Construct waterbars AS SHOWN ON THE DRAWINGS. Remove culverts when SHOWN ON THE PLANS and treat as specified in Section 203.05. Remove all other structures, such as metal or wooden open top cross drains, rubber belt water diverters and other plastic or metal materials when SHOWN ON THE PLANS. Scatter slash evenly along the ripped roadbed. Fully re-contour 150’ at the entrance of the roadway. WHEN SHOWN ON
THE PLANS.
(c) Full Road Recontour, Closure Level 5. Pull all major embankments and deposit this material on the ripped roadbed and contour it to the adjacent side slopes as SHOWN ON THE DRAWINGS. Leave in an un-compacted condition. Do not place material outside the original roadway limits. Scatter large and small woody debris on the newly recontoured surface. Remove all culverts and treat as specified in Subsection 211.05 or 203.05.
211.05 Stream Channel Restoration. Treat all drainages with defined channels in accordance with the following:
(a) Treatment of restored channel
Work identified will be AS SHOWN ON THE DRAWINGS and will include proper disposal of all associated culverts as per Subsection 203.05.
Construction and maintenance of permanent and temporary erosion and sediment control measures as per Section 157 and AS SHOWN ON THE DRAWINGS.
Appendix A-4, Supplemental Specifications, Page 16 of 23
(b) Channel Restoration Performance.
Excavate the roadway fill in the existing draw to the width of the natural channel.
Excavate to the elevation of the original channel or the gradient of the pipe channel, whichever is lower. Slope the stream banks to match the original stream bank contours.
Place excavated material on the road prism against the back slopes along the roadbed. Ensure that this material is free from slash and/or concentrations of woody debris, frozen soil, ice and snow. Contour the excavated material to match the adjacent slopes as SHOWN ON THE DRAWINGS. Leave the recontoured slopes in an un-compacted condition.
Scatter slash and woody debris over the newly recontoured area.
Install gradient control structures perpendicular to the stream flow as SHOWN ON THE DRAWINGS and as directed by the CO. Logs or rocks to be used for this purpose will be designated at or near the stream channel to be restored (the logs may require felling or bucking into the proper lengths). If an insufficient number of logs or rocks are available at a particular site, the CO can designate additional logs or rocks outside the riparian area to meet the contract requirements. Additional work may be performed under Section 622.
211.06 Removing Minor Culverts. Minor culverts and road fills where drainage has not been provided are to be removed as per Subsection 203.04. After removing the existing culvert and road fill, re-shape the roadbed as SHOWN ON THE DRAWINGS.
Removal and disposal of minor culverts and will be a separate PAY ITEM under Section 203.
211.07 Removing Major Culverts. Major culverts are to be removed as per Subsection 203.04. After removing the existing culvert, re-shape the roadbed as SHOWN ON THE DRAWINGS. Removal and disposal of major culverts will be a separate PAY ITEM under Section 203.
211.08 Establishing Vegetative Cover. Seed all disturbed areas as specified in Section 625 or as SHOWN ON THE DRAWINGS.
211.09 (No Text Available)
211.10 Waterbars. Construct waterbars as SHOWN ON THE DRAWINGS to divert surface water.
211.11 Method. Use the method of measurement that is DESIGNATED IN THE
SCHEDULE OF ITEMS.
Appendix A-4, Supplemental Specifications, Page 17 of 23
No separate measurement will be made for clearing and grubbing.
211.12 Basis. The quantities will be paid for at the contract unit price for each PAY
ITEM DESIGNATED IN THE SCHEDULE OF ITEMS.
No separate payment will be made for clearing and grubbing, this work will be incidental to the item listed below.
211(03)
622 - Rental Equipment
622.02 Rental Equipment
Delete the first two sentences of the first paragraph and add the following:
Hydraulic Excavator. Provide a track mounted hydraulic excavator, 1990 model year or newer. Bucket must be equipped with a hydraulic "thumb". It is anticipated that an excavator of a size capable of performing the excavation needs for the project, i.e.
structure excavation, riprap construction, etc., will be of an adequate size to be acceptable for any work that the Contractor may be directed to perform under this section.
625 - Turf Establishment
625.03 General
Delete this entire subsection and add the following:
Apply all seed, fertilizer, and/or mulch, as specified in the pay items, to the areas shown on the drawings, in the work lists, or other disturbed ground surfaces and as discussed herein. Do not apply materials during windy weather, or when the ground is excessively wet, frozen, or snow covered.
Assure that all seed and mulch conforms to the weed free requirements of Section 713.
Time of seed application shall be specified as follows:
1) During the periods of April 15 to June 1 and September 15 to October 30.
Appendix A-4, Supplemental Specifications, Page 18 of 23
2) Within 7 days following the establishment of cut and fill slopes and prior to crusting or glazing of slopes.
3) First half of seed application as specified in (2) above. Second half of seed application as specified in (1) above, but not within 30 days of first application.
625.04 Preparing Seedbed.
Delete this subsection and add the following.
Soil for broadcast seeding should be left in a roughened condition favorable to the retention and germination of seed. A minimum of one half inch of surface soil shall be in a loose condition, unless otherwise specified. Lightly raking the soil to cover seeds is beneficial.
Care and protection of the seedbed will be done prior to final acceptance of the revegetation work. Contractors will be responsible for repairing and reseeding areas damaged (compacted or disturbed surfaces) by construction operations, unless otherwise specified.
625.06 Fertilizing
Add the following:
Fertilizer shall not be used, unless specified. If specified, use 16-0-0 nitrogen fertilizer for grass dominated sites, but if forbs are present a 10-16-10 or 16-16-16 mix shall be used.
When specified, fertilize at a rate of 100-200 pounds per acre depending on site conditions and fertility.
When seed and fertilizer are applied from the same bin, they shall not be mixed for more than four hours prior to application by the dry method or one hour by the hydraulic method.
625.07 Seeding.
Add the following:
Seed Mixes
The kinds and mixtures of seed to be furnished and the amounts to be applied in terms of pure live seed are as specified and in accordance with the following approved mixes.
Typically seed application rates range from 20-50 viable seeds per square foot depending on species and site conditions.
Appendix A-4, Supplemental Specifications, Page 19 of 23
Seed Mix A: Dry warm and relatively dry cool sites (Native and introduced species) Low to mid elevation sites with a high susceptibility to noxious weed invasion. All aspects at low to mid-elevations and south and west-facing aspects at higher elevations. Moisture and temperature conditions may vary by aspect but are subjected to dry or droughty periods.
Generally, Douglas Fir and Ponderosa Pine habitat types with a bunchgrass understory component. Most competitive Lolo mix for weedy, dry and or harsh sites.
Species Pounds PLS per Acre Annual Ryegrass (I) Lolium multiflorum 4 Mountain Brome (N) Bromus marginatis (Bromar) 4 Sheep Fescue (I) Festuca ovina (Covar) 6 Thickspike Wheatgrass (N) Elymus lanceolatus (Critana) 4 Pubsecent Wheatgrass (I) Agropyron intermedium (Manska, Luna) 5 Slender Wheatgrass (N) Elymus trachycaulus (Pryor) 9 Total 32*
*Minimum seeding rates: When broadcast seeding on crusted soils, harsh sites or in competition with noxious weeds, higher seeding rates (80+ seeds/ ft²) are recommended.
Seed Procurement
Order bulk seed by listed PLS rates outlined in the seed mix.
Have seed suppliers label each bag with the needed pounds of seed per acre to obtain the PLS rates listed in the seed mixes.
Unopened seed that is stored, but purchased in accordance with these specifications and within one-year of the construction date will be accepted.
Seed Certification
Certified, blue-tagged seed shall be used where a name variety or cultivar is specified.
Blue tags, that are removed to mix or spread the seed will be saved and provided to the
COR.
All seed purchased will be certified free of seeds from weeds listed on the current "All States Noxious Weeds List." Test results from a certified seed analyst and seed analysis labels attached to the bags will be provided to the COR. Lab testing for noxious weeds will be conducted prior to seed mixing. Only after a finding and documentation in writing of no weeds on the current "All States Noxious Weeds List" will the seed be accepted and used.
To avoid weed contaminated seed, each lot must be tested by a certified seed laboratory against the all State noxious weed lists and documentation of the seed inspection test provided.
Appendix A-4, Supplemental Specifications, Page 20 of 23
The origin of Wildland native seeds is verified by a certification of the Source Identified Class with an attached yellow tag.
When using commercially purchased seed check with the supplier for the seed source point of origin. Point of origin should be as close to the revegetation project as possible.
Seeding elevations should be within 1000 feet below or 500 feet above the seed origin elevation.
625.08 Mulching
Mulch material will be certified (tagged) weed free straw or grass hay only.
Wood cellulose fiber or paper mulch may be applied by hydraulic equipment with water as the carrying agent. Continuous agitation of the mulch will be maintained to provide uniform suspension and distribution of the material. Apply mulch from the top of the slope to the toe of the slope at a rate of 2,000 pounds/acre.
Commercially available tackifiers can be used as mulch binders. Application should be evenly distributed over the revegetation site. Refer to manufactures product guidelines for recommended uses, application methods and rates.
Determine the pounds of seed to be furnished per acre by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.
Example 5 lbs. pure live seed/acre . commercial =
0.90 x 0.85 seed per acre; purity = 90% and germination = 85%
Add the following section entirely:
Section 680 – Noxious Weed Treatment
Description
680.01 Work. Furnish and spray herbicides by hand or with ground-based equipment along the designated roadways to the limits SHOWN ON THE DRAWINGS.
The objective of herbicide spraying in this contract is to eradicate any of the following invasive plant species known or suspected to occur in the specified treatment area:
Appendix A-4, Supplemental Specifications, Page 21 of 23
Scientific Name Common Name Cardus nutans musk thistle
Centaurea diffusa diffuse knapweed Centaurea maculosa spotted knapweed
Chrysanthemum leucanthemem oxeye daisy Circium arvense Canada Thistle
Cynoglossum officinale houndstongue Euphorbia esula Leafy Spurge
Hieracium aurantiacum orange hawkweed Hieracium pratense yellow hawkweed
Hypericum perforatum St. Johnswort Linaria dalmatica dalmatian toadflax Linaria vulgaris common toadflax Potentilla recta sulfur cinquefoil
Tanacetum vulgare common tansy
Materials
680.02 Requirements. The following herbicides are approved for use:
Picloram (Tordon 22-K, or approved equal)
2,4-D (Weedar 64, Formula 40, or approved equal)
Construction
680.03 General. Spray all roads designated for decommissioning prior to move-in of construction equipment.
Notify the Forest Service 48 hours prior to spraying. Do not begin application without authorization from the CO.
680.04. Safety. Comply with all Worker Protection Act Guidelines.
At least 28 days before beginning spraying operations, submit a written plan for acceptance that details the measures to be used for protecting the environment, public, private property and workers. Include in the plan the following:
(a) Manufacturer’s material safety data sheets and product data sheets for all herbicides.
(b) Emergency spill procedures
Appendix A-4, Supplemental Specifications, Page 22 of 23
680.05 Applicator Qualifications and Supervision. Mix and apply herbicides under the direct supervision of a person licensed by the State of Montana Department of Agriculture for commercial application of restricted chemicals.
680.06 Mixing. Use safe handling practices that conform to the manufacturer’s safety data sheet and instructions. Transport herbicides daily to the project site. Transport only the quantity needed for that day’s work. Transport concentrate in containers that will hold 150 percent of the amount of concentrate, in a manner that will prevent tipping, or spilling. Transport concentrate in a compartment that is isolated from food, clothing and safety equipment.
Transport mixing and cleaning water in labeled containers separate from water used for other purposes. Water may be used from live streams. If streams are used, provide a method by which water can be pumped into the holding vehicle at least 100 feet from the stream. Include a valve to prevent back siphoning. Attend equipment at all times during pumping.
Mix all herbicides onsite. Do not mix or load equipment within 200 feet of any stream, open water or private land. Do not mix or load equipment near areas of concentrated public use (i.e.
dispersed recreation sites, etc.). Include purple dye in all herbicide mixtures at a rate of 1 ounce per gallon. Load hand equipment on a double layer of 5-mil plastic large enough to contain any spills. Load and mix motorized equipment on an impervious surface that will not allow mix to flow toward water.
Where two herbicides are to be sprayed at the same site, clean tanks prior to changing herbicides.
Use water to triple rinse tanks and spraying equipment. Dispose of rinse residue according to herbicide label restrictions.
680.07 Application. The Contractor is responsible for selection of appropriate chemicals for site-specific conditions with the following restrictions:
a.) Do not apply Picloram (Tordon 22-K) within riparian areas, in ditches that lead to creeks or areas with shallow ground water tables as evidence by local vegetation.
b.) Do not spray open water with any chemical.
Select application methods and rates to minimize potential for drift and non-target impacts while meeting the weed control objectives. Do not exceed the following application rates:
a.) Picloram (Tordon 22-k); 2 pints herbicide per acre.
b.) 2,4-D (Wedar 64, Formula 40): 2 quarts herbicide per acre.
Monitor weather conditions before and during all spraying operations. Do not spray when any of the following conditions exist:
a. Hand-held equipment: Temperature exceeds 98 degrees F.; humidity is less than 20 percent; wind exceeds 15 miles per hour.
b. Truck-mounted equipment: Temperature exceeds 95 degrees F.: humidity is less than 30 percent; wind exceeds 10 miles per hour.
Appendix A-4, Supplemental Specifications, Page 23 of 23
Do not spray herbicides when rain is expected within six (6) hours of completion of the treatment.
Do not spray within 30 feet of open water without prior approval from the CO.
Use backpack sprayers or hand-held sprayers from mobile tanks to apply liquid herbicides. Do not use truck-mounted sprayers unless approved by the CO. Use equipment that is in good mechanical condition. Inspect all equipment prior to beginning work. Calibrate all equipment and furnish calibration documentation to the CO prior to beginning work. Submit equipment for spot inspection by the CO if requested.
Use nozzles and other technology that will minimize drift and potential for non-target impacts.
Use nozzles made of stainless steel or ceramic material. Do not exceed 20 psi spray pressure to avoid drift.
Use a tight fitting lid on all spray tanks.
Inspect all equipment for leaks daily.
Remove all herbicide containers from National Forest Land and dispose of them in accordance with all local, state and federal requirements.
680.08 Method. Use the method of measurement that is DESIGNATED IN THE
SCHEDULE OF ITEMS.
Base area computations on surface measurements.
680.09 Basis. The accepted quantities will be paid for at the contract unit price for each
PAY ITEM DESIGNATED IN THE SCHEDULE OF ITEMS.
| Table of Contents |
| Preface |
| 101 - Terms, Format, and Definitions |
| 101.03 Abbreviations. |
| 101.04 Definitions. |
| 102 - Bid, Award, and Execution of Contract |
| Delete |
| 103 - Scope of Work |
| Deletions |
| 104 - Control of Work |
| Deletions |
| 104.06 Use of Roads by Contractor |
| 105 - Control of Material |
| 105.02 Material Sources. |
| 105.02(a) Government-provided sources. |
| 105.05 Use of Material Found in the Work. |
| 106 - Acceptance of Work |
| 106.01 Conformity with Contract Requirements. |
| 106.07 Delete |
| 107 - Legal Relations and Responsibility to the Public |
| 107.05 Responsibility for Damage Claims. |
| 107.06 Contractor’s Responsibility for Work. |
| 107.09 Legal Relationship of the Parties. |
| 107.10 Environmental Protection. |
| 108 - Prosecution and Progress |
| 108 Delete. |
| 109 - Measurement and Payment |
| 109 Deletions |
| 109.02 Measurement Terms and Definitions. |
| 151 - Mobilization |
| 155 - Schedules for Construction Contracts |
| 155 Delete. |
| 157 - Soil Erosion Control |
| 157.02 Material |
| 203 - Removal of Structures and Obstructions |
| 203.01 Description. |
| 203.03 Salvaging Material. |
| 203.05 Disposing of Material. |
| 211 – Closing, Obliteration, or Treatment of Existing Roads |
| 211.02 Performance. Begin work at the road end or designated start location and progress out towards the permanent road closure. |
| 622 - Rental Equipment |
| 622.02 Rental Equipment |
| 625 - Turf Establishment |
| Section 680 – Noxious Weed Treatment |
| Common Name |
| Tanacetum vulgare |
| Scientific Name |
| Materials |