ATCH_11_Phase3.pdf

PDF 5 MB Posted

Attached to
RECOVERY - CUSTER NATIONAL FOREST, FY09 West Fork Rock Creek Road Reconstruction
Solicitation number
AG-0355-S-09-0004
Issued by

About this file

ATCH 11 Phase III Staking

View the file

Other files

File Type Posted
AMENDMENT 4_West Fork_SF_30.doc DOC document
AMENDMENT 3_West Fork_SF_30.doc DOC document
Amd 3 Sch of Items.pfd.pdf PDF
Geotech_ Attachments.pdf PDF
Amendment 2_Section J_Page 31 of 48.doc DOC document
Phase 4 Revised D-8.pdf PDF
Phase 4 REVISED C-3_Amendment_2.pdf PDF
Phase 3_D-11 Grade Sag_Amendment_2.pdf PDF
Phase 4_Revised D-15_Amendment_2.pdf PDF
Phase 3 Revised D-2.pdf PDF
Atch 2 Ph III page 20_amendment_2.doc DOC document
Amendment 2_WEST FORK_COVER_SHEET.doc DOC document
AMENDMENT 2_West Fork_SF_30.doc DOC document
Amendment_2_SF1442.doc DOC document
Phase 4 Spec_403.01 page 39.doc DOC document
Amendment_2_Schedule_B.doc DOC document
Q-A_5-7-09.doc DOC document
Pre-bid meeting.PDF PDF
Amendment_1_SF1442-Pre-Bid_Mtg_amendment_1.doc DOC document
Amendment 1_Section J_Page 31 of 48.doc DOC document
Amendment 1_SEC F_FAR 52.211-10_Page 14 of 48.doc DOC document
Amendment 1_ATCH 18_FINAL ROAD LOG PHASE 3.xls XLS spreadsheet
Amendment 1_WEST FORK_COVER_SHEET.doc DOC document
Amendment_1_Subparagaph o-page 12 of 48.doc DOC document
Amendment 1 ATCH 3 Spec 156.04 page 17.doc DOC document
Amendment 1_PHASE IV_Spec 255.02.6_Page_29.doc DOC document
Amendment 1_FAR 52.204-11.doc DOC document
Amendment 1_Revised Phase 4_D-10.pdf PDF
WEST FORK_COVER_SHEET.doc DOC document
ATCH_1_wage_determination_HWY.doc DOC document
ATCH_10_Phase3.pdf PDF
ATCH_3_Phase4.doc DOC document
ATCH_5_Map.pdf PDF
ATCH_6_Phase3.pdf PDF
ATCH_17_OF-17.pdf PDF
ATCH_8_Phase3.pdf PDF
ATCH_14_Phase4.pdf PDF
ATCH_7_Phase3.pdf PDF
ATCH_16_Phase4.pdf PDF
CONSTRUCTION_IFB.doc DOC document
ATCH_13_Phase4.pdf PDF
ATCH 4_sf24_f.pdf PDF
ATCH_15_Phase4.pdf PDF
ATCH_2_Phase3.doc DOC document
ATCH_12_Phase4.pdf PDF
ATCH_9_Phase3.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AG-0355-S-09-0004

West Fork Rock Creek Road #2071 Phase 3&4

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 Cross Section Staking Data File Project: M551103 Roadway: centerline

Start station: 0+00 End station: 289+49.47 Maximum left offset: 100.000000 Maximum right offset: 60.000001 Maximum elevation: 7892.970323 Minimum elevation: 6907.517883 Total number of sections 781 Station/Description Offset Elevation 0+00 Subgrade: Datum #1 -58.94 7884.89 -46.77 7876.78 -43.77 7877.78 -42.67 7877.81 -0.00 7879.09

7.00 7878.88

8.10 7878.85

11.10 7877.85

14.30 7876.25 0+50 Subgrade : Datum #1 -18.38 7883.71 -11.10 7878.85 -8.10 7879.85 -7.00 7879.88 -0.00 7880.09

7.00 7879.88

8.10 7879.85

11.10 7878.85

13.62 7880.53 1+00 Subgrade: Datum #1 -17.94 7882.98 -11.10 7878.42 -8.10 7879.42 -7.00 7879.45 -0.00 7879.53

7.00 7879.32

8.10 7879.28

11.10 7878.28

13.98 7880.20 1+53.15 Subgrade: Datum #1 -14.20 7876.49 -11.10 7878.04 -8.10 7879.04 -7.00 7879.07

0.00 7878.93

17.81 7878.39

18.91 7878.36

21.91 7877.36

30.27 7873.18 1+70

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 Subgrade: Datum #1 -16.40 7875.26 -11.10 7877.91 -8.10 7878.91 -7.00 7878.94

0.00 7878.74

19.74 7878.14

20.84 7878.11

23.84 7877.11

34.80 7871.63 1+84.69 Subgrade: Datum #1 -14.12 7876.17 -11.10 7877.68 -8.10 7878.68 -7.00 7878.72

0.00 7878.57

19.18 7877.99

20.28 7877.96

23.28 7876.96

38.37 7869.42 2+00 Subgrade: Datum #1 -12.64 7876.67 -11.10 7877.45 -8.10 7878.45 -7.00 7878.48

0.00 7878.40

17.00 7877.89

18.10 7877.85

21.10 7876.85

33.24 7868.76 2+50 Subgrade: Datum #1 -18.48 7881.59 -11.10 7876.67 -8.10 7877.67 -7.00 7877.70 -0.00 7877.83

7.00 7877.62

8.10 7877.59

11.10 7876.59

11.57 7876.90 2+77.18 Subgrade: Datum #1 -19.19 7881.63 -11.10 7876.24 -8.10 7877.24 -7.00 7877.28 -0.00 7877.49

7.00 7877.28

8.10 7877.24

11.10 7876.24

17.22 7873.19 3+00 Subgrade: Datum #1 -19.73 7881.77 -11.10 7876.02

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 -8.10 7877.02 -7.00 7877.06 -0.00 7877.27

7.00 7877.06

8.10 7877.02

11.10 7876.02

17.87 7872.63 3+50 Subgrade: Datum #1 -20.98 7882.66 -11.10 7876.08 -8.10 7877.08 -7.00 7877.11

0.00 7877.32

17.00 7876.81

18.10 7876.78

21.10 7875.78

25.39 7873.63 3+89 Subgrade: Datum #1 -11.77 7876.99 -11.10 7876.54 -8.10 7877.54 -7.00 7877.57

0.00 7877.78

17.00 7877.27

18.10 7877.24

21.10 7876.24

26.21 7873.68 4+00 Subgrade: Datum #1 -11.30 7876.79 -11.10 7876.66 -8.10 7877.66 -7.00 7877.69

0.00 7877.90

17.00 7877.39

18.10 7877.36

21.10 7876.36

25.27 7874.27 4+43.82 Subgrade: Datum #1 -13.56 7878.81 -11.10 7877.17 -8.10 7878.17 -7.00 7878.20

0.00 7878.41

7.59 7878.19

8.69 7878.15

11.69 7877.15

14.90 7875.55 4+50 Subgrade: Datum #1 -13.14 7878.77 -11.10 7877.41 -8.10 7878.41 -7.00 7878.44 -0.00 7878.65

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007

7.00 7878.44

8.10 7878.41

11.10 7877.41

15.54 7875.19 5+05.65 Subgrade: Datum #1 -11.53 7878.45 -11.10 7878.16 -8.10 7879.16 -7.00 7879.20

0.00 7879.41

7.00 7879.20

8.10 7879.16

11.10 7878.16

15.94 7875.75 5+37.18 Subgrade: Datum #1 -11.63 7878.74 -11.10 7878.39 -8.10 7879.39 -7.00 7879.42 -0.00 7879.63

7.00 7879.42

8.10 7879.39

11.10 7878.39

14.72 7876.58 5+50 Subgrade: Datum #1 -11.28 7878.54 -11.10 7878.42 -8.10 7879.42 -7.00 7879.46

0.00 7879.67

7.00 7879.46

8.10 7879.42

11.10 7878.42

14.33 7876.81 6+00 Subgrade: Datum #1 -23.23 7886.67 -11.10 7878.58 -8.10 7879.58 -7.00 7879.62 -0.00 7879.83

7.00 7879.62

8.10 7879.58

11.10 7878.58

14.00 7877.14 6+49.27 Subgrade: Datum #1 -21.39 7885.64 -11.10 7878.78 -8.10 7879.78 -7.00 7879.82 -0.00 7880.03

7.00 7879.82

8.10 7879.78

11.10 7878.78

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007

15.13 7876.77 7+00 Subgrade: Datum #1 -18.36 7883.24 -11.10 7878.40 -8.10 7879.40 -7.00 7879.43

0.00 7879.64

17.00 7879.13

18.10 7879.10

21.10 7878.10

28.92 7874.19 7+16.83 Subgrade: Datum #1 -18.04 7882.60 -11.10 7877.97 -8.10 7878.97 -7.00 7879.00

0.00 7879.21

17.00 7878.70

18.10 7878.67

21.10 7877.67

26.37 7875.03 7+50 Subgrade: Datum #1 -17.42 7880.84 -11.10 7876.63 -8.10 7877.63 -7.00 7877.67

0.00 7877.88

17.00 7877.37

18.10 7877.33

21.10 7876.33

25.97 7873.90 7+92.95 Subgrade: Datum #1 -17.66 7878.25 -11.10 7873.88 -8.10 7874.88 -7.00 7874.91

0.00 7875.12

8.46 7874.86

9.56 7874.83

12.56 7873.83

21.19 7869.51 8+00 Subgrade: Datum #1 -17.69 7877.78 -11.10 7873.39 -8.10 7874.39 -7.00 7874.42 -0.00 7874.63

7.00 7874.42

8.10 7874.39

11.10 7873.39

20.04 7868.92 8+31.81 Subgrade: Datum #1

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 -16.58 7875.92 -11.10 7872.26 -8.10 7873.26 -7.00 7873.30

0.00 7873.51

7.00 7873.30

8.10 7873.26

11.10 7872.26

18.28 7868.67 8+50 Subgrade: Datum #1 -15.89 7874.94 -11.10 7871.75 -8.10 7872.75 -7.00 7872.78 -0.00 7872.99

7.00 7872.78

8.10 7872.75

11.10 7871.75

16.56 7869.02 8+77.72 Subgrade: Datum #1 -16.23 7874.40 -11.10 7870.98 -8.10 7871.98 -7.00 7872.02 -0.00 7872.23

7.00 7872.02

8.10 7871.98

11.10 7870.98

14.40 7869.33 9+00 Subgrade: Datum #1 -17.04 7874.31 -11.10 7870.35 -8.10 7871.35 -7.00 7871.38 -0.00 7871.59

7.00 7871.38

8.10 7871.35

11.10 7870.35

11.54 7870.13 9+38.29 Subgrade: Datum #1 -16.12 7872.36 -11.10 7869.02 -8.10 7870.02 -7.00 7870.05

0.00 7870.26

8.59 7870.00

9.69 7869.97

12.69 7868.97

16.36 7867.14 9+50 Subgrade: Datum #1 -13.86 7870.34 -11.10 7868.50 -8.10 7869.50

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 -7.00 7869.53

0.00 7869.74

10.34 7869.43

11.44 7869.40

14.44 7868.40

19.15 7866.04 9+77.96 Subgrade: Datum #1 -11.36 7867.14 -11.10 7867.27 -8.10 7868.27 -7.00 7868.30

0.00 7868.51

17.00 7868.00

18.10 7867.97

21.10 7866.97

28.76 7863.13 10+00 Subgrade: Datum #1 -11.49 7866.60 -11.09 7866.34 -8.09 7867.34 -6.99 7867.37

0.00 7867.58

17.00 7867.07

18.10 7867.04

21.10 7866.04

29.40 7861.89 10+22 Subgrade: Datum #1 -11.97 7866.00 -11.09 7865.42 -8.09 7866.42 -6.99 7866.45

0.00 7866.66

17.00 7866.15

18.10 7866.12

21.10 7865.12

30.03 7860.65 10+50 Subgrade: Datum #1 -11.22 7864.37 -11.08 7864.28 -8.08 7865.28 -6.98 7865.31

0.00 7865.52

12.60 7865.14

13.70 7865.11

16.70 7864.11

20.74 7862.09 11+00 Subgrade: Datum #1 -18.82 7867.04 -11.07 7861.88 -8.07 7862.88 -6.97 7862.91

0.00 7863.12

7.00 7862.91

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007

8.10 7862.88

11.10 7861.88

13.34 7860.76 11+50 Subgrade: Datum #1 -30.33 7865.01 -21.10 7858.85 -18.10 7859.85 -17.00 7859.88

0.00 7860.39

7.00 7860.18

8.10 7860.15

11.10 7859.15

19.26 7855.07 11+71.26 Subgrade: Datum #1 -28.21 7862.05 -21.48 7857.57 -18.48 7858.57 -17.38 7858.60

0.00 7859.12

7.00 7858.91

8.10 7858.88

11.10 7857.88

13.89 7856.48 12+00 Subgrade: Datum #1 -24.81 7858.11 -21.24 7855.73 -18.24 7856.73 -17.14 7856.77

0.00 7857.28

7.00 7857.07

8.10 7857.04

11.10 7856.04

11.95 7856.61 12+50 Subgrade: Datum #1 -26.21 7855.13 -21.10 7851.73 -18.10 7852.73 -17.00 7852.76 -0.00 7853.27

7.00 7853.06

8.10 7853.03

11.10 7852.03

12.48 7852.95 13+00 Subgrade: Datum #1 -13.81 7848.57 -11.12 7846.78 -8.12 7847.78 -7.02 7847.82

0.00 7848.03

7.00 7847.82

8.10 7847.78

11.10 7846.78

11.98 7847.37

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 13+12.27 Subgrade: Datum #1 -13.06 7846.87 -10.90 7845.43 -7.90 7846.43 -6.80 7846.47 -0.00 7846.67

7.00 7846.46

8.10 7846.43

11.10 7845.43

11.48 7845.68 13+30 Subgrade: Datum #1 -11.08 7843.64 -10.93 7843.54 -7.93 7844.54 -6.83 7844.57 -0.00 7844.77

7.00 7844.56

8.10 7844.53

11.10 7843.53

12.33 7844.35 13+50 Subgrade: Datum #1 -11.43 7842.44 -10.95 7842.12 -7.95 7843.12 -6.85 7843.15 -0.00 7843.36

7.00 7843.15

8.10 7843.12

11.10 7842.12

13.53 7840.90 14+00 Subgrade: Datum #1 -12.42 7838.33 -11.01 7839.03 -8.01 7840.03 -6.91 7840.06 -0.00 7840.27

7.00 7840.06

8.10 7840.03

11.10 7839.03

14.59 7837.29 14+10 Subgrade: Datum #1 -13.89 7837.58 -11.03 7839.01 -8.03 7840.01 -6.93 7840.04 -0.00 7840.25

7.00 7840.04

8.10 7840.01

11.10 7839.01

17.03 7836.04 14+50

-28.64 7850.62

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 -11.07 7838.91 -8.07 7839.91 -6.97 7839.94 -0.00 7840.15

7.00 7839.94

8.10 7839.91

11.10 7838.91

22.42 7833.25 14+70.08 Subgrade: Datum #1 -26.19 7848.92 -11.10 7838.86 -8.10 7839.86 -7.00 7839.89

0.00 7840.10

7.00 7839.89

8.10 7839.86

11.10 7838.86

20.65 7832.49 15+00 Subgrade: Datum #1 -27.11 7851.01 -11.10 7840.33 -8.10 7841.33 -7.00 7841.36

0.00 7841.57

7.00 7841.36

8.10 7841.33

11.10 7840.33

26.47 7832.64 15+50 Subgrade: Datum #1 -21.70 7853.46 -11.10 7842.86 -8.10 7843.86 -7.00 7843.89 -0.00 7844.10

7.00 7843.89

8.10 7843.86

11.10 7842.86

11.85 7842.48 15+66.55 Subgrade: Datum #1 -26.64 7853.88 -11.10 7843.51 -8.10 7844.51 -7.00 7844.55 -0.00 7844.76

7.00 7844.55

8.10 7844.51

11.10 7843.51

12.39 7842.87 16+00 Subgrade: Datum #1 -16.20 7848.28 -11.10 7844.87 -8.10 7845.87 -7.00 7845.91

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 -0.00 7846.12

7.00 7845.91

8.10 7845.87

11.10 7844.87

16.98 7841.94 16+50 Subgrade: Datum #1 -11.48 7846.26 -11.10 7846.45 -8.10 7847.45 -7.00 7847.49

0.00 7847.70

17.00 7847.19

18.10 7847.15

21.10 7846.15

24.74 7844.33 17+00 Subgrade: Datum #1 -12.40 7847.36 -11.10 7846.49 -8.10 7847.49 -7.00 7847.52

0.00 7847.73

17.00 7847.22

18.10 7847.19

21.10 7846.19

25.55 7843.97 17+13 Subgrade: Datum #1 -14.14 7848.58 -11.10 7846.56 -8.10 7847.56 -7.00 7847.59

0.00 7847.80

15.13 7847.35

16.23 7847.31

19.23 7846.31

23.37 7844.25 17+13.69 Subgrade: Datum #1 -14.19 7848.63 -11.10 7846.56 -8.10 7847.56 -7.00 7847.60

0.00 7847.81

15.03 7847.36

16.13 7847.32

19.13 7846.32

23.25 7844.27 17+50 Subgrade: Datum #1 -11.26 7847.28 -11.10 7847.17 -8.10 7848.17 -7.00 7848.20

0.00 7848.41

7.00 7848.20

8.10 7848.17

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007

11.10 7847.17

13.89 7845.77 17+63.23 Subgrade: Datum #1 -16.43 7850.89 -11.10 7847.34 -8.10 7848.34 -7.00 7848.37 -0.00 7848.58

7.00 7848.37

8.10 7848.34

11.10 7847.34

15.23 7845.27 18+00 Subgrade: Datum #1 -16.82 7851.52 -11.10 7847.70 -8.10 7848.70 -7.00 7848.74

0.00 7848.95

7.00 7848.74

8.10 7848.70

11.10 7847.70

16.05 7845.23 18+50 Subgrade: Datum #1 -16.87 7851.48 -11.10 7847.64 -8.10 7848.64 -7.00 7848.67

0.00 7848.88

7.00 7848.67

8.10 7848.64

11.10 7847.64

14.04 7849.60 18+74.99 Subgrade: Datum #1 -15.70 7850.61 -11.10 7847.54 -8.10 7848.54 -7.00 7848.58

0.00 7848.79

7.00 7848.58

8.10 7848.54

11.10 7847.54

12.47 7846.86 19+00 Subgrade: Datum #1 -18.21 7852.23 -11.10 7847.49 -8.10 7848.49 -7.00 7848.52

0.00 7848.73

7.00 7848.52

8.10 7848.49

11.10 7847.49

17.51 7844.29 19+50

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 Subgrade: Datum #1 -39.06 7857.44 -22.35 7846.31 -19.35 7847.31 -18.25 7847.34

0.00 7847.89

7.00 7847.68

8.10 7847.65

11.10 7846.65

22.48 7840.96 20+00 Subgrade: Datum #1 -33.60 7852.53 -21.06 7844.17 -18.06 7845.17 -16.96 7845.20

0.00 7845.71

7.00 7845.50

8.10 7845.47

11.10 7844.47

21.46 7839.29 20+50 Subgrade: Datum #1 -29.56 7846.97 -21.09 7841.32 -18.09 7842.32 -16.99 7842.36

0.00 7842.86

7.00 7842.65

8.10 7842.62

11.10 7841.62

15.91 7839.22 20+69.58 Subgrade: Datum #1 -22.75 7844.50 -16.60 7840.41 -13.60 7841.41 -12.50 7841.44

0.00 7841.81

7.00 7841.66

8.10 7841.63

11.10 7840.63

13.89 7839.23 21+00 Subgrade: Datum #1 -12.55 7839.97 -11.09 7838.99 -8.09 7839.99 -6.99 7840.03

0.00 7840.24

7.00 7840.21

8.10 7840.18

11.10 7839.18

11.22 7839.26 21+41.23 Subgrade: Datum #1 -13.64 7838.78 -11.10 7837.09

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 -8.10 7838.09 -7.00 7838.12 -0.00 7838.33

6.89 7838.47

7.99 7838.44

10.99 7837.44

12.24 7838.28 21+50 Subgrade: Datum #1 -13.42 7838.27 -11.10 7836.72 -8.10 7837.72 -7.00 7837.75

0.00 7837.96

7.12 7838.15

8.22 7838.12

11.22 7837.12

12.43 7837.92 22+00 Subgrade: Datum #1 -11.18 7834.71 -11.10 7834.66 -8.10 7835.66 -7.00 7835.69

0.00 7835.90

17.00 7836.36

18.10 7836.33

21.10 7835.33

35.91 7827.92 22+09.99 Subgrade: Datum #1 -11.52 7834.75 -11.10 7834.48 -8.10 7835.48 -7.00 7835.51

0.00 7835.72

17.00 7836.08

18.10 7836.04

21.10 7835.04

35.88 7827.65 22+35 Subgrade: Datum #1 -13.03 7833.23 -11.10 7834.19 -8.10 7835.19 -7.00 7835.22

0.00 7835.43

17.00 7835.53

18.10 7835.50

21.10 7834.50

31.79 7829.16 22+37.33 Subgrade: Datum #1 -12.32 7833.61 -11.10 7834.22 -8.10 7835.22 -7.00 7835.25

0.00 7835.46

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007

17.00 7835.54

18.10 7835.51

21.10 7834.51

31.56 7829.27 22+50 Subgrade: Datum #1 -13.21 7835.80 -11.10 7834.39 -8.10 7835.39 -7.00 7835.43

0.00 7835.64

17.00 7835.58

18.10 7835.55

21.10 7834.55

29.12 7830.54 23+00 Subgrade: Datum #1 -13.48 7836.75 -11.10 7835.16 -8.10 7836.16 -7.00 7836.20

0.00 7836.41

7.00 7836.20

8.10 7836.16

11.10 7835.16

11.29 7835.07 23+50 Subgrade: Datum #1 -11.18 7835.83 -11.10 7835.87 -8.10 7836.87 -7.00 7836.90

0.00 7837.11

7.00 7836.90

8.10 7836.87

11.10 7835.87

14.99 7833.92 24+00 Subgrade: Datum #1 -20.06 7842.32 -11.10 7836.35 -8.10 7837.35 -7.00 7837.38

0.00 7837.59

7.00 7837.38

8.10 7837.35

11.10 7836.35

11.47 7836.59 24+28.08 Subgrade: Datum #1 -18.73 7840.51 -11.10 7835.42 -8.10 7836.42 -7.00 7836.45

0.00 7836.66

7.00 7836.45

8.10 7836.42

11.10 7835.42

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007

13.61 7834.16 24+50 Subgrade: Datum #1 -14.21 7836.37 -11.10 7834.30 -8.10 7835.30 -7.00 7835.33

0.00 7835.54

7.00 7835.33

8.10 7835.30

11.10 7834.30

11.87 7833.91 25+00 Subgrade: Datum #1 -11.18 7831.43 -11.10 7831.38 -8.10 7832.38 -7.00 7832.41

0.00 7832.62

7.00 7832.41

8.10 7832.38

11.10 7831.38

15.01 7829.42 25+57 Subgrade: Datum #1 -11.36 7829.69 -11.10 7829.51 -8.10 7830.51 -7.00 7830.55

0.00 7830.76

7.00 7830.55

8.10 7830.51

11.10 7829.51

20.62 7824.75 25+82.58 Subgrade: Datum #1 -12.34 7829.59 -11.10 7828.76 -8.10 7829.76 -7.00 7829.80

0.00 7830.01

7.00 7829.80

8.10 7829.76

11.10 7828.76

13.29 7827.67 26+00 Subgrade: Datum #1 -13.21 7829.97 -11.01 7828.51 -8.01 7829.51 -6.91 7829.54

0.00 7829.75

7.00 7829.54

8.10 7829.50

11.10 7828.50

12.78 7827.66 26+50

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 -11.49 7828.58 -10.73 7828.08 -7.73 7829.08 -6.63 7829.11

0.00 7829.31

7.00 7829.10

8.10 7829.07

11.10 7828.07

16.76 7825.24 26+75 Subgrade: Datum #1 -10.76 7827.97 -10.60 7827.87 -7.60 7828.87 -6.50 7828.90

0.00 7829.10

7.00 7828.89

8.10 7828.85

11.10 7827.85

18.82 7823.99 27+00 Subgrade: Datum #1 -12.07 7828.44 -10.46 7827.37 -7.46 7828.37 -6.36 7828.40

0.00 7828.59

7.00 7828.38

8.10 7828.35

11.10 7827.35

19.64 7823.08 27+50 Subgrade: Datum #1 -13.61 7828.58 -10.19 7826.30 -7.19 7827.30 -6.09 7827.34 -0.00 7827.52

7.00 7827.31

8.10 7827.28

11.10 7826.28

23.88 7819.88 28+00 Subgrade: Datum #1 -13.09 7826.10 -11.10 7824.77 -8.10 7825.77 -7.00 7825.81 -0.00 7826.02

7.00 7825.81

8.10 7825.77

11.10 7824.77

16.11 7822.27 28+50 Subgrade: Datum #1 -31.06 7830.24 -21.01 7823.54 -18.01 7824.54

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 -16.91 7824.57 -0.00 7825.08

7.00 7824.87

8.10 7824.83

11.10 7823.83

15.74 7821.51 29+00 Subgrade: Datum #1 -34.43 7831.54 -21.10 7822.65 -18.10 7823.65 -17.00 7823.69 -0.00 7824.20

7.00 7823.99

8.10 7823.95

11.10 7822.95

15.23 7820.89 29+50 Subgrade: Datum #1 -32.87 7828.89 -21.10 7821.04 -18.10 7822.04 -17.00 7822.07 -0.00 7822.58

7.00 7822.37

8.10 7822.34

11.10 7821.34

17.26 7818.26 29+73.97 Subgrade: Datum #1 -31.33 7827.00 -21.10 7820.17 -18.10 7821.17 -17.00 7821.21 -0.00 7821.72

7.00 7821.51

8.10 7821.47

11.10 7820.47

17.84 7817.10 30+00 Subgrade: Datum #1 -30.02 7825.15 -21.52 7819.48 -18.52 7820.48 -17.42 7820.51 -0.00 7821.04

7.00 7820.83

8.10 7820.79

11.10 7819.79

16.95 7816.87 30+19 Subgrade: Datum #1 -28.41 7823.46 -21.55 7818.88 -18.55 7819.88 -17.45 7819.92

0.00 7820.44

7.00 7820.23

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007

8.10 7820.20

11.10 7819.20

17.42 7816.04 30+50.95 Subgrade: Datum #1 -24.81 7821.67 -20.89 7819.06 -17.89 7820.06 -16.79 7820.09 -0.00 7820.60

7.00 7820.39

8.10 7820.35

11.10 7819.35

14.88 7817.46 31+00 Subgrade: Datum #1 -11.22 7819.53 -11.10 7819.45 -8.10 7820.45 -7.00 7820.49

0.00 7820.70

12.40 7820.33

13.50 7820.29

16.50 7819.29

29.03 7813.03 31+22.97 Subgrade: Datum #1 -11.23 7819.44 -11.10 7819.50 -8.10 7820.50 -7.00 7820.53

0.00 7820.74

17.00 7820.23

18.10 7820.20

21.10 7819.20

32.98 7811.28 31+50 Subgrade: Datum #1 -16.39 7822.60 -11.10 7819.07 -8.10 7820.07 -7.00 7820.11

0.00 7820.32

17.00 7819.81

18.10 7819.77

21.10 7818.77

34.16 7810.07 31+95.72 Subgrade: Datum #1 -16.75 7819.78 -11.10 7816.01 -8.10 7817.01 -7.00 7817.05

0.00 7817.26

11.96 7816.90

13.06 7816.87

16.06 7815.87

28.18 7809.81

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 32+00 Subgrade: Datum #1 -16.11 7818.97 -11.10 7815.63 -8.10 7816.63 -7.00 7816.67

0.00 7816.88

11.31 7816.54

12.41 7816.50

15.41 7815.50

26.82 7809.80 32+50 Subgrade: Datum #1 -15.86 7815.28 -11.10 7812.10 -8.10 7813.10 -7.00 7813.14

0.00 7813.35

7.00 7813.14

8.10 7813.10

11.10 7812.10

16.49 7809.41 33+00 Subgrade: Datum #1 -19.45 7815.18 -11.10 7809.61 -8.10 7810.61 -7.00 7810.65 -0.00 7810.86

7.00 7810.65

8.10 7810.61

11.10 7809.61

13.80 7808.27 33+50 Subgrade: Datum #1 -15.85 7810.99 -11.10 7807.82 -8.10 7808.82 -7.00 7808.85 -0.00 7809.06

7.00 7808.85

8.10 7808.82

11.10 7807.82

13.44 7806.65 33+68.27 Subgrade: Datum #1 -14.02 7809.53 -11.10 7807.58 -8.10 7808.58 -7.00 7808.62 -0.00 7808.83

7.00 7808.62

8.10 7808.58

11.10 7807.58

16.15 7805.06 33+87

-12.39 7806.68

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 -11.10 7807.33 -8.10 7808.33 -7.00 7808.36

0.00 7808.57

7.00 7808.36

8.10 7808.33

11.10 7807.33

19.46 7803.15 34+00 Subgrade: Datum #1 -12.00 7807.82 -11.10 7807.22 -8.10 7808.22 -7.00 7808.25

0.00 7808.46

7.00 7808.25

8.10 7808.22

11.10 7807.22

13.75 7805.89 34+08.78 Subgrade: Datum #1 -13.09 7807.88 -12.36 7807.39 -9.36 7808.39 -8.26 7808.43

0.00 7808.68

7.00 7808.47

8.10 7808.43

11.10 7807.43

13.07 7806.45 34+50 Subgrade: Datum #1 -28.63 7813.28 -21.10 7808.26 -18.10 7809.26 -17.00 7809.29

0.00 7809.80

7.00 7809.59

8.10 7809.56

11.10 7808.56

14.59 7806.82 34+75 Subgrade: Datum #1 -28.23 7813.55 -21.10 7808.79 -18.10 7809.79 -17.00 7809.83

0.00 7810.34

7.00 7810.13

8.10 7810.09

11.10 7809.09

17.48 7805.90 35+00 Subgrade: Datum #1 -28.69 7814.60 -21.10 7809.54 -18.10 7810.54 -17.00 7810.57

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007

0.00 7811.08

7.00 7810.87

8.10 7810.84

11.10 7809.84

12.83 7808.98 35+50 Subgrade: Datum #1 -15.50 7813.81 -11.10 7810.88 -8.10 7811.88 -7.00 7811.91 -0.00 7812.12

7.00 7811.91

8.10 7811.88

11.10 7810.88

12.46 7811.78 35+84.26 Subgrade: Datum #1 -14.16 7812.53 -11.10 7810.49 -8.10 7811.49 -7.00 7811.52 -0.00 7811.73

7.00 7811.52

8.10 7811.49

11.10 7810.49

11.74 7810.92 36+00 Subgrade: Datum #1 -11.94 7810.74 -11.10 7810.18 -8.10 7811.18 -7.00 7811.21 -0.00 7811.42

7.00 7811.21

8.10 7811.18

11.10 7810.18

11.41 7810.03 36+50 Subgrade: Datum #1 -27.21 7813.24 -21.10 7809.16 -18.10 7810.16 -17.00 7810.19 -0.00 7810.70

7.00 7810.49

8.10 7810.46

11.10 7809.46

14.30 7807.86 36+86.16 Subgrade: Datum #1 -24.68 7810.85 -21.10 7808.46 -18.10 7809.46 -17.00 7809.49 -0.00 7810.00

7.00 7809.79

8.10 7809.76

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007

11.10 7808.76

12.11 7808.26 37+00 Subgrade: Datum #1 -26.83 7812.01 -21.10 7808.19 -18.10 7809.19 -17.00 7809.22

0.00 7809.73

7.00 7809.52

8.10 7809.49

11.10 7808.49

11.10 7808.49 37+41.23 Subgrade: Datum #1 -18.35 7808.51 -13.35 7805.19 -10.35 7806.19 -9.25 7806.22 -0.00 7806.50

7.00 7806.29

8.10 7806.25

11.10 7805.25

11.62 7805.60 37+50 Subgrade: Datum #1 -14.49 7806.66 -11.10 7804.40 -8.10 7805.40 -7.00 7805.44

0.00 7805.65

7.00 7805.44

8.10 7805.40

11.10 7804.40

11.57 7804.72 37+81 Subgrade: Datum #1 -14.37 7803.59 -11.09 7801.40 -8.09 7802.40 -6.99 7802.44

0.00 7802.65

7.00 7802.44

8.10 7802.40

11.10 7801.40

11.39 7801.59 38+00.53 Subgrade: Datum #1 -13.59 7801.19 -11.08 7799.51 -8.08 7800.51 -6.98 7800.55 -0.00 7800.75

7.00 7800.54

8.10 7800.51

11.10 7799.51

11.26 7799.62 38+50

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 Subgrade: Datum #1 -12.03 7795.50 -11.10 7794.88 -8.10 7795.88 -7.00 7795.91 -0.00 7796.12

7.00 7795.91

8.10 7795.88

11.10 7794.88

11.93 7795.43 38+80.88 Subgrade: Datum #1 -12.07 7791.55 -11.10 7792.03 -8.10 7793.03 -7.00 7793.07

0.00 7793.28

7.00 7793.07

8.10 7793.03

11.10 7792.03

11.51 7791.83 39+00 Subgrade: Datum #1 -11.37 7790.45 -11.10 7790.27 -8.10 7791.27 -7.00 7791.30

0.00 7791.51

7.00 7791.30

8.10 7791.27

11.10 7790.27

13.00 7789.32 39+18 Subgrade: Datum #1 -11.79 7789.07 -11.10 7788.61 -8.10 7789.61 -7.00 7789.65

0.00 7789.86

7.00 7789.65

8.10 7789.61

11.10 7788.61

14.41 7786.96 39+50 Subgrade: Datum #1 -11.58 7785.92 -11.10 7785.60 -8.10 7786.60 -7.00 7786.63

0.00 7786.84

7.00 7786.69

8.10 7786.66

11.10 7785.66

14.55 7783.93 40+00 Subgrade: Datum #1 -14.02 7783.47 -11.10 7781.52

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 -8.10 7782.52 -7.00 7782.56

0.00 7782.77

12.92 7782.88

14.02 7782.84

17.02 7781.84

22.80 7778.95 40+20.72 Subgrade: Datum #1 -17.32 7784.32 -11.10 7780.18 -8.10 7781.18 -7.00 7781.21

0.00 7781.42

17.00 7781.78

18.10 7781.75

21.10 7780.75

28.71 7776.94 40+50 Subgrade: Datum #1 -11.31 7778.37 -11.10 7778.23 -8.10 7779.23 -7.00 7779.26

10.00 7779.60

17.00 7779.74

18.10 7779.71

21.10 7778.71

30.15 7774.18 40+90.99 Subgrade: Datum #1 -12.18 7776.21 -11.10 7775.49 -8.10 7776.49 -7.00 7776.52

0.00 7776.73

17.00 7777.09

18.10 7777.06

21.10 7776.06

34.19 7769.51 41+00 Subgrade: Datum #1 -11.68 7775.35 -11.10 7774.97 -8.10 7775.97 -7.00 7776.00

0.00 7776.21

15.20 7776.45

16.30 7776.41

19.30 7775.41

30.07 7770.03 41+50 Subgrade: Datum #1 -12.37 7773.19 -11.10 7772.34 -8.10 7773.34 -7.00 7773.38

0.00 7773.59

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007

7.00 7773.49

8.10 7773.45

11.10 7772.45

13.43 7771.29 41+60.18 Subgrade: Datum #1 -12.80 7772.96 -11.10 7771.82 -8.10 7772.82 -7.00 7772.86 -0.00 7773.07

7.00 7772.92

8.10 7772.89

11.10 7771.89

12.91 7770.98 42+01.17 Subgrade: Datum #1 -14.82 7772.44 -11.10 7769.96 -8.10 7770.96 -7.00 7770.99

0.00 7771.20

7.00 7770.99

8.10 7770.96

11.10 7769.96

12.31 7769.35 42+50 Subgrade: Datum #1 -12.34 7768.78 -11.10 7767.95 -8.10 7768.95 -7.00 7768.99 -0.00 7769.20

7.00 7768.99

8.10 7768.95

11.10 7767.95

15.08 7765.96 42+63.11 Subgrade: Datum #1 -11.59 7767.74 -11.10 7767.42 -8.10 7768.42 -7.00 7768.45 -0.00 7768.66

7.00 7768.45

8.10 7768.42

11.10 7767.42

15.68 7765.13 43+00 Subgrade: Datum #1 -14.29 7768.23 -11.10 7766.10 -8.10 7767.10 -7.00 7767.14 -0.00 7767.35

7.00 7767.14

8.10 7767.10

11.10 7766.10

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007

13.56 7764.87 43+50 Subgrade: Datum #1 -12.61 7763.91 -11.10 7764.66 -8.10 7765.66 -7.00 7765.70 -0.00 7765.91

7.00 7765.70

8.10 7765.66

11.10 7764.66

16.82 7761.81 43+67 Subgrade: Datum #1 -15.71 7763.08 -13.28 7764.29 -10.28 7765.29 -9.18 7765.32 -0.00 7765.60

7.00 7765.39

8.10 7765.36

11.10 7764.36

17.59 7761.11 43+96.64 Subgrade: Datum #1 -25.69 7767.52 -20.15 7763.82 -17.15 7764.82 -16.05 7764.86 -0.00 7765.34

7.00 7765.13

8.10 7765.09

11.10 7764.09

14.80 7762.25 44+00 Subgrade: Datum #1 -27.56 7768.08 -21.10 7763.77 -18.10 7764.77 -17.00 7764.81 -0.00 7765.32

7.00 7765.11

8.10 7765.07

11.10 7764.07

14.50 7762.37 44+50 Subgrade: Datum #1 -29.65 7769.46 -21.10 7763.76 -18.10 7764.76 -17.00 7764.80 -0.00 7765.31

7.00 7765.10

8.10 7765.06

11.10 7764.06

14.31 7762.46 45+00

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 -30.11 7769.75 -21.10 7763.74 -18.10 7764.74 -17.00 7764.77 -0.00 7765.28

7.00 7765.07

8.10 7765.04

11.10 7764.04

13.89 7762.64 45+11.11 Subgrade: Datum #1 -26.83 7768.46 -19.52 7763.59 -16.52 7764.59 -15.42 7764.63 -0.00 7765.09

7.00 7764.88

8.10 7764.85

11.10 7763.85

11.81 7763.49 45+53.84 Subgrade: Datum #1 -13.49 7764.66 -11.16 7763.11 -8.16 7764.11 -7.06 7764.14 -0.00 7764.35

7.00 7764.14

8.10 7764.11

11.10 7763.11

13.29 7762.02 46+00 Subgrade: Datum #1 -11.78 7762.76 -11.11 7762.32 -8.11 7763.32 -7.01 7763.35

0.00 7763.56

7.00 7763.35

8.10 7763.32

11.10 7762.32

16.03 7759.85 46+08.74 Subgrade: Datum #1 -11.44 7762.38 -11.10 7762.16 -8.10 7763.16 -7.00 7763.19

0.00 7763.40

7.00 7763.19

8.10 7763.16

11.10 7762.16

15.73 7759.84 46+50 Subgrade: Datum #1 -12.12 7761.72 -11.10 7761.04 -8.10 7762.04

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007 -7.00 7762.07

0.00 7762.28

12.48 7761.91

13.58 7761.87

16.58 7760.87

23.23 7757.55 47+00 Subgrade: Datum #1 -14.28 7761.03 -11.10 7758.91 -8.10 7759.91 -7.00 7759.94

0.00 7760.15

18.33 7759.60

19.43 7759.57

22.43 7758.57

26.01 7756.78 47+30.32 Subgrade: Datum #1 -18.89 7762.72 -11.10 7757.53 -8.10 7758.53 -7.00 7758.56

0.00 7758.77

17.00 7758.26

18.10 7758.23

21.10 7757.23

21.86 7756.85 47+50 Subgrade: Datum #1 -18.21 7761.55 -11.10 7756.81 -8.10 7757.81 -7.00 7757.84

0.00 7758.05

13.08 7757.66

14.18 7757.63

17.18 7756.63

17.27 7756.69 47+73.02 Subgrade: Datum #1 -16.89 7760.01 -11.10 7756.15 -8.10 7757.15 -7.00 7757.18

0.00 7757.39

8.49 7757.14

9.59 7757.10

12.59 7756.10

12.63 7756.13 48+00 Subgrade: Datum #1 -14.99 7758.21 -11.10 7755.61 -8.10 7756.61 -7.00 7756.65

0.00 7756.86

7.87 7756.62

Beartooth Ranger District, Custer National Forest

Phase 3

Project: M551103 January 8, 2007

8.97 7756.59

11.97 7755.59

13.39 7754.88 48+25 Subgrade: Datum #1 -14.33 7757.51 -11.10 7755.35 -8.10 7756.35 -7.00 7756.39

0.00 7756.60

7.87 7756.36

8.97 7756.33

11.97 7755.33

14.45 7754.09 48+50 Subgrade: Datum #1 -13.09 7756.64 -11.10 7755.32 -8.10 7756.32 -7.00 7756.35

0.00 7756.56

7.87 7756.33

8.97 7756.29

11.97 7755.29

13.65 7754.45 48+87 Subgrade: Datum #1 -12.18 7756.40 -11.10 7755.68 -8.10 7756.68 -7.00 7756.71

0.00 7756.92

15.00 7756.47

16.10 7756.44

19.10 7755.44

28.12 7750.93 49+00 Subgrade: Datum #1 -12.21 7756.67 -11.10 7755.93 -8.10 7756.93 -7.00 7756.96

0.00 7757.17

17.00 7756.66

18.10 7756.63