| West Fork Rock Creek Road #2071 | |||||||||||||||||||
| Road Log | CULVERT TABLE | Culvert Table | |||||||||||||||||
| 1/23/09 | 21"x15" CMPA | 28"x20" CMPA | 49"x33" CMPA | 57"x38" CMPA | 81"x59" CMPA | CMPA Lengths (ft)by Diameter Size | |||||||||||||
| Station | MP from Pavement End | Description | Station | MP from Pavement End | Design Length | As-Built Length | Design Length | As-Built Length | Design Length | As-Built Length | Design Length | As-Built Length | Design Length | As-Built Length | 21"x15" | 28x20 | 49x33 | 57x38 | 81x59 |
| 213+34 | 1.39 | Existing 18"x31' culvert, remove and replace with 49"x33"x44' cmpa(Live Water) Riprap inlet & outlet | 213+34 | 1.39 | 44 | 44 | |||||||||||||
| 188+33.5 | 1.85 | Existing 57"x38" cmap. Place riprap on channel bank, approximately 10 CY | 188+33.5 | 1.85 | |||||||||||||||
| 181+42 | 1.98 | Install new 28"x20"x32' cmpa with 30' leadoff ditch (State Land Section Erosion ) | 181+42 | 1.98 | 32 | 32 | |||||||||||||
| 183+54.6 | 2.09 | Existing 18" culvert, remove and replace with 21"x15"x28' cmpa | 183+54.6 | 2.09 | 28 | 28 | |||||||||||||
| 2.21 | Centerline Bridge - No Work | 2.21 | |||||||||||||||||
| 161+94.5 | Install new 28"x20"x46 cmpa, riprap inlet & outlet. | 161+94.5 | 46 | 46 | |||||||||||||||
| 158+72 | 2.41 | Existing 18" culvert, remove and replace with 21"x15"x28' cmpa | 158+72 | 2.41 | 28 | 28 | |||||||||||||
| 154+51 | 2.49 | Install new 21"x15"x36' cmpa | 154+51 | 2.49 | 36 | 36 | |||||||||||||
| 151+85 | 2.54 | Install new 21"x15"x28' cmpa(at low spot) | 151+85 | 2.54 | 28 | 28 | |||||||||||||
| 146+67.9 | 2.62 | Existing 18" culvert, remove and replace with 21"x15"x40' cmpa(at 25 mph sign) | 146+67.9 | 2.62 | 40 | 40 | |||||||||||||
| 143+51 | 2.68 | Install new 21"x15"x26' cmpa (at low spot) | 143+51 | 2.68 | 26 | 26 | |||||||||||||
| 141+81 | Install new 21"x15"x20' cmpa approach culvert | 141+81 | 20 | 20 | |||||||||||||||
| 140+93.7 | 2.73 | Existing 18" culvert, remove and replace with 28"x20"x32' cmpa | 140+93.7 | 2.73 | 32 | 32 | |||||||||||||
| 137+76 | 2.79 | Install new 28"x20"x32' cmpa, outslope road, new grade sag, 3' flat bottom ditch to Cascade Creek (station 137+26.2), 40 yds riprap slope. Live water | 137+76 | 2.79 | 32 | 32 | |||||||||||||
| 137+26.2 | 2.81 | Cascade Creek, Existing 48"x32' culvert, remove and replace with 81"x 59"x 54' cmpa, live water. | 137+26.2 | 2.81 | 54 | 54 | |||||||||||||
| 133+12.9 | 2.88 | Existing 18" culvert, remove and replace with 21"x15"x36' cmpa | 133+12.9 | 2.88 | 36 | 36 | |||||||||||||
| 129+84.2 | 2.94 | Existing 18" culvert, remove and replace with 21"x15"x30' cmpa | 129+84.2 | 2.94 | 30 | 30 | |||||||||||||
| 127+85 | Install new 21"x15"x30' cmpa | 127+85 | 30 | 30 | |||||||||||||||
| 125+43 | 3.00 | Install new approach culvert 21"x15"x26' cmpa | 125+43 | 3.00 | 26 | 26 | |||||||||||||
| 122+00 | 3.08 | Existing 18" culvert, remove and replace with 21"x15"x28' cmpa | 122+00 | 3.08 | 28 | 28 | |||||||||||||
| 112+41.3 | 3.26 | Existing 18" culvert, remove and replace with 21"x15"x36' cmpa | 112+41.3 | 3.26 | 36 | 36 | |||||||||||||
| 106.81.1 | 3.37 | Existing 18" culvert, remove and replace with 21"x15"x30' cmpa | 106.81.1 | 3.37 | 30 | 30 | |||||||||||||
| 3.49 | Centerline of Bridge - No Work | 3.49 | |||||||||||||||||
| 95+79.7 | 3.57 | Existing 18" culvert, remove and replace with 21"x15"x28' cmpa | 95+79.7 | 3.57 | 28 | 28 | |||||||||||||
| 92+18.8 | 3.63 | Existing 18" culvert, remove and replace with 21"x15"x30' cmpa | 92+18.8 | 3.63 | 30 | 30 | |||||||||||||
| 3.76 | Centerline of Bridge - No Work | 3.76 | |||||||||||||||||
| 75+86.3 | 3.94 | Existing 24" culvert, remove and replace with 28"x20"x44' cmpa | 75+86.3 | 3.94 | 44 | 44 | |||||||||||||
| 72+52.8 | 4.00 | Existing 18" culvert, remove and replace with 21"x15"x34' cmpa | 72+52.8 | 4.00 | 34 | 34 | |||||||||||||
| 69+36 | 4.06 | Install new 28"x20" x 44' culvert, live stream. Rechannel approximately 40' to creek and 20' toward Rock Creek 5 cy riprap | 69+36 | 4.06 | 44 | 44 | |||||||||||||
| 4.07 | Camp Senia Turnoff Left | 4.07 | |||||||||||||||||
| 65+50 | Install new 21"x15"x30' cmpa | 65+50 | 30 | 30 | |||||||||||||||
| 63+23.6 | Place existing wateline through 40 ft of 6" schedule 40 pvc sleeve | 63+23.6 | |||||||||||||||||
| 62+20 | 4.19 | Existing 18" culvert, remove and dispose | 62+20 | 4.19 | |||||||||||||||
| 62+00 | Install new 21"x15"x36' cmpa | 62+00 | 36 | 36 | |||||||||||||||
| 60+91.3 | 4.22 | Existing 12" culvert, remove and replace with new 21"x15"x26' cmpa | 60+91.3 | 4.22 | 26 | 26 | |||||||||||||
| 58+36 | 4.26 | Existing 18" culvert, remove and replace with 21"x15"x36' cmpa | 58+36 | 4.26 | 36 | 36 | |||||||||||||
| 56+77 | 4.29 | Construct new grad sag | 56+77 | 4.29 | |||||||||||||||
| 55+47 | 4.31 | Install new 21"x15"x36' cmpa | 55+47 | 4.31 | 36 | 36 | |||||||||||||
| 53+88.7 | 4.35 | Senia Creek, remove existing culvert, Install new 57"x 38" x 40' cmpa, live stream. 20 cy riprap | 53+88.7 | 4.35 | 40 | 40 | |||||||||||||
| 50+19 | 4.42 | Install new 21"x15"x36' cmpa | 50+19 | 4.42 | 36 | 36 | |||||||||||||
| 48+87.4 | 4.44 | Existing 18" culvert, remove and replace with 21"x15"x40' cmpa | 48+87.4 | 4.44 | 40 | 40 | |||||||||||||
| 48+35.7 | Install new 21"x15"x22' cmpa approach culvert | 48+35.7 | 22 | 22 | |||||||||||||||
| 21"x15" CMPA | 28"x20" CMPA | 49"x33" CMPA | 57"x38" CMPA | 81"x59" CMPA | |||||||||||||||
| Station | MP from Pavement End | Description | Station | MP from Pavement End | Design Length | As-Built Length | Design Length | As-Built Length | Design Length | As-Built Length | Design Length | As-Built Length | Design Length | As-Built Length | |||||
| 46+53.3 | 4.48 | Existing 18" culvert, remove and replace with 21"x15"x40' cmpa. Place existing waterline in 40 ft of 6" schedule 40 pvc sleeve. Offset 10' from culvert. | 46+53.3 | 4.48 | 40 | 40 | |||||||||||||
| 45+47 | 4.5 | Install new 21"x15"x36' cmpa | 45+47 | 4.5 | 36 | 36 | |||||||||||||
| 43+66.7 | 4.53 | Existing 18" culvert, remove and replace with 21"x15"x30' cmpa | 43+66.7 | 4.53 | 30 | 30 | |||||||||||||
| 39+18.2 | 4.62 | Existing 18" culvert, remove and replace with 21"x15"x30' cmpa | 39+18.2 | 4.62 | 30 | 30 | |||||||||||||
| 37+81 | Install new 21"x15"x34' approach culvert | 37+81 | 34 | 34 | |||||||||||||||
| 37+.05 | 4.65 | Remove and replace with 28"x 20" x 30' live stream, place riprap | 37+.05 | 4.65 | 30 | 30 | |||||||||||||
| 36+47 | 4.67 | Ex 18" Cross Drain, remove and replace with 21"x15"x40' | 36+47 | 4.67 | 40 | 40 | |||||||||||||
| 34+74.9 | Reset existing 18" cmp approach culvert. | 34+74.9 | |||||||||||||||||
| 33+87.4 | 4.71 | Existing 18" culvert, remove and replace with 21"x15"x30' cmpa | 33+87.4 | 4.71 | 30 | 30 | |||||||||||||
| 31+21.1 | 4.77 | Existing 18" culvert, remove and replace with 21"x15"x38' cmpa | 31+21.1 | 4.77 | 38 | 38 | |||||||||||||
| 30+94.7 | 4.775 | Install new 21"x15"x40' cmpa, live water, 20 cy surfacing | 30+94.7 | 4.775 | 40 | 40 | |||||||||||||
| 30+19.1 | 4.78 | Existing 18" culvert, remove and replace with 21"x15"x40' cmpa | 30+19.1 | 4.78 | 40 | 40 | |||||||||||||
| 27+27 | 4.84 | Install new 21"x15"x36' cmpa (live water) | 27+27 | 4.84 | 36 | 36 | |||||||||||||
| 26+74.5 | 4.85 | Existing 18" culvert, remove and replace with 21"x15"x30' cmpa | 26+74.5 | 4.85 | 30 | 30 | |||||||||||||
| 25+56.8 | 4.87 | Existing 18" culvert, remove and replace with 21"x15"x32' cmpa | 25+56.8 | 4.87 | 32 | 32 | |||||||||||||
| 22+34.5 | 4.93 | Existing 18" culvert, remove and replace with 21"x15"x38' cmpa | 22+34.5 | 4.93 | 38 | 38 | |||||||||||||
| 17+59 | 5.02 | Install new 21"x15"x40' cmpa | 17+59 | 5.02 | 40 | 40 | |||||||||||||
| 14+09.7 | 5.08 | Existing 18" culvert, remove and replace with 21"x15"x34' cmpa | 14+09.7 | 5.08 | 34 | 34 | |||||||||||||
| 13+30 | Install new 21"x15"x24' cmpa approach culvert | 13+30 | 24 | 24 | |||||||||||||||
| 10+21.6 | 5.15 | Existing 18" culvert, remove and replace with 21"x15"x38' cmpa | 10+21.6 | 5.15 | 38 | 38 | |||||||||||||
| 3+89.4 | 5.26 | Existing 18" culvert, remove and replace with 21"x15"x38' cmpa | 3+89.4 | 5.26 | 38 | 38 | |||||||||||||
| 2+83 | 5.28 | Install new 21"x15"x50' cmpa | 2+83 | 5.28 | 50 | 50 | |||||||||||||
| 1+69.4 | 5.29 | Existing 31"x30' cmp, remove and replace with 57"x38"x50' cmpa, 20 cy surfacing, new grade sag, 40 cy riprap. Live stream. Riprap inlet & outlet | 1+69.4 | 5.29 | 50 | 50 | |||||||||||||
| TOTAL LENGTH | 1494 | 260 | 44 | 90 | 54 | Total Lengths by Diameter | |||||||||||||
| NOTE: 1. Contractor shall be required to divert water at all live stream crossings and implement erosion control measures for full compliance with permits. | 1494 | 260 | 44 | 90 | 54 | ||||||||||||||
| NOTE: 2. Design lengths for culverts are approximate. Contractor shall survey and measure each culvert in the field to determine actual length, gradient, and alignment prior to ordering materials. | |||||||||||||||||||
| NOTE: 3. All removed culverts shall become the property of the Contractor and shall be removed and disposed of in a lawfull manner off of National Forest System Lands. |