Solicitation.doc

DOC document 263 KB Posted

Attached to
Jim Brown Culvert Replacement Federal contract opportunity
Solicitation number
AG-02RC-S-13-0019
Issued by
Department of Agriculture Forest Service R1-Northern Region

About this file

Solicitation

View the file

Other files for this federal contract opportunity

Other files attached to Jim Brown Culvert Replacement, newest first.
File Type Posted
JIM_BROWN_CREEK_BOX_CULVERT_ADDENDUM.docx DOCX document
Schedule_B.doc DOC document
p3_oblit_detail-11x17.pdf PDF
p2_summary_-11x17.pdf PDF
Amendment_0002.pdf PDF
p4_road_location.pdf PDF
p1_title_-11x17.pdf PDF
section_c.doc DOC document
Amendment_0001.pdf PDF
workers_comp_form.doc DOC document
Wage_Determination.pdf PDF
Jim_Brown_100-38_0_Mar-13.pdf PDF
OwnerPastPerformanceSurvey 1 .docx DOCX document
sf24_bid_bond.pdf PDF
Supplemental_Specs_Mar-13.docx DOCX document
JimBrown_PreSol_Map.pdf PDF
Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

AG-02RC-S-13-0019

2. TYPE OF SOLICITATION

FORMCHECKBOX

SEALED BID (IFB)

FORMCHECKBOX

NEGOTIATED (RFP)

3. DATE ISSUED

05/24/2013

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

641711

6. PROJECT NO.

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

USDA, Forest Service

Idaho Montana Acquisition Team

Clearwater National Forest

12730 HWY 12

Orofino, ID 83544

USFS Idaho Montana Acquisition Team

Attn: AG-02RC-S-13-0055 (Matthew Markovich)

12730 HWY 12

9. FOR INFORMATION

CALL:

A. NAME

Matthew Markovich, CO B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(208) 476-8379

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

Jim Brown Culvert Replacement Nez Perce-Clearwater National Forests Lochsa Ranger District, Idaho County, Idaho

The Government's estimate is:

between $100,000 and $250,000.

11. The Contractor shall begin performance within 10 calendar days and complete it by September 15, 2013 after receiving

FORMCHECKBOX

award, FORMCHECKBOX notice to proceed. This performance period is FORMCHECKBOX mandatory, FORMCHECKBOX negotiable. (See Section F, Clause 52.211-10.)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

FORMCHECKBOX

YES

FORMCHECKBOX

NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A.

Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8 by 2:30 pm local time June 24, 2013. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B.

An offer guarantee

FORMCHECKBOX

is, FORMCHECKBOX is not required.

C.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D.

Offers providing less than 30 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212

1442-101

STANDARD FORM 1442 (REV. 4-85)

Computer Generated

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

DUNS No:__________________________

TIN:_________________________

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE

FACILITY CODE

17.

The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.
DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

FORMCHECKBOX

10 U.S.C. 2304(c)( )

FORMCHECKBOX

41 U.S.C. 253(c)( )

26. ADMINISTERED BY

CODE

27. PAYMENT WILL BE MADE BY

USDA, Forest Service

Idaho Montana Acquisition Team

Clearwater National Forest

12730 HWY 12

USDA, OCFO, COD, APB

PO Box 60075

New Orleans, LA 70160

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

FORMCHECKBOX

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.

FORMCHECKBOX

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

Computer Generated

STANDARD FORM 1442 BACK (REV. 4-85)

PART I – SCHEDULE OF ITEMS

SECTION B – SUPPLIES OR SERVICES & PRICES/COSTS

JIM BROWN CREEK CULVERT REPLACEMENT

ROAD NO. 100 MP-38.0

LOCHSA RANGER DISTRICT

NEZPERCE-CLEARWATER NATIONAL FORESTS

CLEARWATER COUNTY, IDAHO

B-1 SCHEDULE OF ITEMS

ITEM NO.
DESCRIPTION
METHOD
PAY UNIT
EST. QTY.
UNIT PRICE
TOTAL PRICE
15101
Mobilization
LSQ
Lump Sum
1
$________
$________
15221
Construction Survey and Staking
LSQ
Lump Sum
1
$________
$________
15722
Straw wattle
CQ
Linear Foot
720
$________
$________
20301A
Removal of existing 87"x63" pipe-arch culvert
AQ
Each
1
$________
$________
20301B
Removal of existing 36" corrugated steel pipe
AQ
Each
1
$________
$________
20434
Channel excavation
LSQ
Lump Sum
1
$________
$________
20435
Ground protection mats, 4'x8' sheets
AQ
Each
12
$________
$________
20806
Structure excavation
LSQ
Lump Sum
1
$________
$________
25101
Placed riprap, Class 3 machine placed (contractor furnished)
CQ
Cubic Yard
80
$________
$________
27201
Geocell
CQ
Square Yard
85
$________
$________
30809
Crushed aggregate, surfacing, method 2 (government furnished)
CQ
Cubic Yard
145
$________
$________
553A01
Precast concrete bridge (including wingwalls, footings & curbs) design, fabricate, transport & install
LSQ
Lump Sum
1
$________
$________
60202
28" span, 20" rise corrugated steel pipe-arch, 0.064" thickness
CQ
Linear Foot
92
$________
$________
61701
Guardrail system, type 1, class A
CQ
Linear Foot
212.5
$________
$________
62201
Equipment rental, hydraulic excavator with thumb
AQ
Hour
XX
$________
$________
62503
Seeding, Dry Method (Government Furnished Seed)
LSQ
Lump Sum
1
$________
$________
62509
Mulching, Dry Method
LSQ
Lump Sum
1
$________
$________
62602
Clump planted vegetation
LSQ
Lump Sum
1
$________
$________
64803
Placed streambed simulation rock, bed class 4 (government furnished)
CQ
Cubic Yard
200
$________
$________
64808
Channel rock size 1 (government furnished)
CQ
Cubic Yard
5
$________
$________
SUM TOTAL PRICE
$________

*** IMPORTANT: This acquisition has been set-aside for Small Business Concerns (see FAR 52.219-3, Notice of Total Small Business Set-Aside in Section I). Quoter must be a certified Small Business Concern with the U.S. Small Business Administration. For information regarding the on-line application process, go to the following website at https://eweb1.gov/hubzone/Internet/. This process can take 30-45 days to complete.

NOTE: Prices must be entered for all Items.

CQ = Contract Quantity; AQ = Actual Quantity; LSQ = Lump Sum Quantity See Section 109.10 of the Forest Service Supplemental Specifications for METHOD definitions.

B-2 NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under 151.01 Mobilization. The above pay items are contract quantities unless noted.

B-3 - Written Acceptance : Any contract resulting from this solicitation will require written acceptance within 10 days of receipt by the Contractor.

B-4 - Basis of Award: One award will be made. Offer of award will be made to the Quoter whose quote, as determined by the Contracting Officer, provides the best value to the Government, considering but not limited to, such factors as price, past performance, and capability to accomplish this type of work. The Experience Questionnaire will be used as part of this evaluation.

B-5 - BASIS OF AWARD: As you offer, submit a completed and signed Standard Form 1442, a completed Schedule of Items (Section B), a Technical Proposal, an original bid bond, and a completed Section K. Technical and price proposals are required for evaluation of offers. See Section L for proposal instructions and Section M for evaluation/award information.

B-6 - Amendments: It is incumbent upon the offeror to monitor www.fbo.gov for Amendments to this solicitation and to review and submit a signed copy of each Standard Form 30 (Amendment to Solicitation).

Fascimile proposals are NOT acceptable.

B-7 - Idaho Use Tax: Under clause 52.236-7, Permits and Responsibilities, Contractors shall be responsible for complying with any Federal, State, and municipal laws, codes and regulation applicable to the performance of the work. Questions regarding the applicability of the Idaho Use Tax to the performance of this contract should be directed to the Idaho State Tax Commission at (208) 799-3491.

SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C-1 - PROJECT DESCRIPTION AND LOCATION

a. Description of Work. This project consists of the removal of an existing 87" x 63" steel pipe arch and construction of a new 25'-0" span x 7'-0" rise 32' long precast concrete bridge including footings, wingwalls, and curb. Other bridge work includes structural excavation, placement of riprap, excavation and embankment of the roadway approaches for installation of guardrail and aggregate road surfacing. Project will also include the installation of two 28” span x 20” rise pipe arches. Final roadway will be two lanes. Improvements consist of relocating 200' of the existing stream that is adjacent to the road to an old meander that can be seen on the ground and is 400' long. This work includes excavation for the new streambed which will be placed as fill in the existing channel. Ground protection mats are required for the stream channel restoration work described above. Streamside stabilization will be accomplished with some riprap, mostly wattles, clump plantings, and seeding and mulching.

b. Project Location.

From Orofino go east on highway 12 for 8 miles to the junction with state highway 11. Follow Highway 11 for 18 miles to Weippe. From Weippe follow the Musselshell road east for 8.2 miles to Peterson Corners and FS Road 100. Follow FS Road 100 for approximately 2.0 miles north toward Pierce, Idaho to Mile Post 33.8 and the project. (There is a discrepancy in Mile Posts and the plans are incorrect).

c. Price Range. ($100,000 - $250,000)

d. Pre-Bid Tour. A pre-bid tour will be held on June 7, 2013 at 11:00am at the project site.. For more information phone Travis Mechling 208-476-8210.

e. Start Work. It is estimated that work will begin on August 1, 2013. The contractor shall give 14 days notice prior to starting any work and closing the road.

f. Period of Performance. (See Part I, Section F, Clause 52.211-10).

g. Construction Timing. All in-stream work for contract shall not start until August 1, 2013 and must be completed by September 30, 2013. Contractor shall give 2 days notice before dewatering the channel. Dewatering shall be done slowly to encourage movement of fish out of the construction area and support successful salvage of fish and other aquatic organisms. The contractor can expect up to a 6 hour delays as the FS salvages fish and other aquatic organism. Dewatering shall take place between the hours of 6:00 am and 12:00pm. Re-watering of the channel will be done slowly, up to a 3 day period, to minimize sediment movement and meet state turbidity standards for water quality as monitored by the C.O.

C-2 - GOVERNMENT FURNISHED MATERIAL

Crushed Aggregate, Item 30809 and Bedding Material– This source is the government stockpile at the Section 6 Pit located in Section 6, T34N, R06E, B.M. at M.P. 0.7 of Road 5150.

Streambed Simulation Material – Item 64803 and Channel Rock – Item 64808 from the same source.

Grass Seed.

C-3 - STANDARD SPECIFICATIONS

Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03, U.S. Customary Units are included in this solicitation by reference only. The requirements contained in these Specifications are hereby made a part of this solicitation and any resultant contract. Copies of these Specifications are available on the internet at www.wfl.fha.dot.gov/design/specs/fp03.htm

C-4 - FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS

Forest Service supplementary specifications are included as a separate APPENDIX of this solicitation.

The supplementary specifications applicable to this project are listed in Appendix A.

C-5 – DRAWINGS (Entitled “JIM BROWN CREEK CULVERT REPLACEMENT”)

The following drawings are a part of this solicitation and any resulting contract:

Title
Page of Pages
Title Sheet
1 of 12
Summary of Quantities and General Notes
2 of 12
Road Typical Sections & Point Tables
3 of 12
Road Plan and Profile
4 of 12
General Layout
5 of 12
Precast Bridge Details
6 of 12
Stream Details
7-8 of 12
Guardrail Details
9-11 of 12
Stream Diversion Plan
12 of 12
Roadway Cross Sections
XS1-XS2

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

SECTION E--INSPECTION AND ACCEPTANCE

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

E-1 52.246-12 Inspection of Construction (AUG 1996)

E-2

AGAR 452.246-70

Inspection and Acceptance (FEB 1988)

(a) The Contracting Officer or the Contracting Officer's duly authorized representative will inspect and accept the supplies and/or services to be provided under this contract.

(b) Inspection and acceptance will be performed at* the project site.

(End of clause)

SECTION F--DELIVERIES OR PERFORMANCE

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

F-1 52.242-14 Suspension of Work (APR 1984)

F-2 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) After the payment and performance bonds are received and approved by the Contracting Officer, the Contractor shall be required to (a) commence work in accordance with the accepted work plan (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than October 31, 2013. The time stated for completion shall include final cleanup of the premises.

Any in-stream work cannot start before August 1st.

SECTION G--CONTRACT ADMINISTRATION DATA

G-1 - CONTRACTING OFFICER'S REPRESENTATIVE

The Contracting Officer will designate a representative, hereinafter referred to as the Contracting Officer's Representative (COR) or, alternatively, as the Engineer, who will provide on-the-ground administration for the Government. The COR will be designated in writing and a copy of the designation will be furnished to the Contractor before or at the prework conference. The Contractor is cautioned to read the COR designation because certain authority under the contract is reserved solely for the Contracting Officer. The term "Contracting Officer" as used throughout the Specifications, shall be interpreted to include the Contracting Officer's designated representative(s) acting within the limits of their delegation of authority.

G-2 – CONTRACT RELEASE

When submitting final payment, Contractor shall provide a signed and dated contract release that includes the following information: "In consideration of receipt of final payment in the amount of $__________ Contractor hereby releases the United States of America from any and all obligations arising under this contract and any modifications thereof except as reserved herein. Reservations:______________"

SECTION H – SPECIAL CONTRACT REQUIREMENTS

H-1

FAR 52.236-4

Physical Data (APR 1984)

Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

(a) The indications of physical conditions on the plans and in the specifications are the result of site investigations by Forest Service specialists making physical determination based on surface observations.

(b) Weather Conditions. Normal snow conditions indicate a work season from approximately June 15 to October 31.

(c) Transportation Facilities. The project is located at MP- 33.8 on Jim Brown Creek Road, USFS RD 100. From Weippe, Idaho take the Musselshell Road, east to the intersection of Jim Brown Creek Road, approximately 8 miles at Petersons Corner. Turn left (North) on Jim Brown Creek Road. Travel approximately 2.0 miles to the site. All roads are graveled, 2 lane and usually open year round.

(d) Material Sources.

The material source for Government Furnished Materials is the Section 6 pit and stockpile located in Section 6, T34N, R06E, B.M. at M.P. 0.7 of Road 5150.

H-2

BARRICADES, WARNING SIGNS, AND OTHER DEVICES

The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.

…As a minimum, it is anticipated that the following type and number of signs will be required:

Location
Designation
Quantity
Junction with Road 100 and Road 250
ROAD CLOSED 8.0 MILES AHEAD
Junction with Road 100 and Musselshell Road at Peterson Corners
ROAD CLOSED 2.0 MILES AHEAD
Road 100 approximately 500’ each side of construction site.
ROAD CLOSED

H-3

LANDSCAPE PRESERVATION

(a) Do not remove, deface, injure, or destroy trees, shrubs, lawn, or natural features not designated for treatment. This does not include access roads. Confine operations to within the clearing limits or other areas designated in the contract documents, and prevent the depositing of rocks, excavated materials, stumps, or other debris outside of these limits. Retrieve material which falls outside of these limits and dispose of, or incorporate in the work.

Preserve the scenic and natural environment along this construction project.

(b) Do not allow objectionable material to enter any stream, river, lake, or other body of water. Retrieve material which falls in these areas and dispose of, or incorporate in the work, and repair damage to vegetation or structures outside the project limits.

(c) Do not operate equipment or otherwise disturb the natural vegetation and soil beyond the construction limits.

H-4

ENVIRONMENTAL PROTECTION

Prevention of Oil Spills.

The contractor is required to have a spill plan. The plan will contain a description of the specific hazardous materials, procedures, and spill containment that will be used, including inventory, storage, and handling.

All vehicles carrying fuel will have specific equipment and materials needed to contain or clean up any incidental spills at the project site.

All pumps and generators used in or near streams will have appropriate spill containment structures and/or absorbent pads in place during use.

When storage facilities for oil or oil products are on site, appropriate preventive measures shall be taken to insure that any spill of such oil or oil products does not enter any stream or any other body of water. If a spill of petroleum product should occur in water, immediately notify the Contracting Officer and appropriate state agencies.

Fuel and service all equipment only in the areas approved by the Contracting Officer. If the total oil or oil products storage exceeds 1320 gallons or if any single container exceeds a capacity of 660 gallons, prepare a Spill Prevention Control and Countermeasures (SPCC) Plan. Meet all applicable EPA requirements (40 CFR 112) including certification by a registered professional engineer.

Contractor shall ensure that all personnel involved in handling and packaging the hazardous waste are trained for the level of expertise required for the proper performance of the task and, in particular, in the areas of chemical incompatibility, general first aid procedures, and spills. Provide handling and personal protective equipment appropriate to ensure safe handling of the hazardous waste according to 29 CFR 1910.120). Notify the Forest Service of all hazardous material that may be brought onto the National Forest.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. The contractor must clean up spills or leaks in a manner that complies with Federal, state, and local laws and regulations and to the satisfaction of the CO. Any spills resulting in a detectable sheen on water shall be reported to the EPA National Response Center (1-800-424-8802). Any spills over 25 gallons will be reported to the Idaho Division of Environmental Quality and cleanup will be initiated within 24 hours of the spill. When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

Equipment Fuel/Oil Leakage.

All equipment used for instream work will be cleaned of external oil, grease, dirt and mud; and leaks repaired; prior to arriving at the project site. All equipment will be inspected by the Contracting Officer’s Representative before unloading at site. Any leaks or accumulations of grease will be corrected before entering streams or areas that drain directly to streams or wetlands.

Equipment used for in-stream or riparian work (including chainsaws and other hand power tools) will be fueled and serviced in an area approved by the CO. When not in use, vehicles will be stored in the designated staging area. The staging area should be in an area that will not deliver fuel, oil, etc. to streams.

Contractor is required to have a Spill Kit or equivalent that contains oil-absorbing floating booms, and other equipment such as pads and absorbent “peanuts” appropriate for the size of the stream, available on-site during all phases of construction. For small streams with few pools or slack water, booms may not be effective. Use pads and straw bales to anchor booms if necessary. Booms will be placed in a location that facilitates an immediate response to potential petroleum leakage.

H-5

NOXIOUS WEED CONTROL

In order to prevent the potential spread of noxious weeds into work areas, Contractor shall be required to use weed-free equipment.

The following is considered proof of weed-free equipment:

The Contractor will be required to clean all construction equipment prior to entry on to national forest land. This cleaning shall remove all dirt and plant parts and material that could carry noxious weed seeds into the work area. Only clean construction equipment inspected by the Forest Service will be allowed to operate within the work area. All subsequent move-ins of construction equipment shall be treated in the same manner as initial move-in. "Construction equipment" does not include pickup trucks and personal vehicles.

H-6

FIRE CONTROL (FS 236-1)

(a) Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.

(b) Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or his employees, the Contractor when requested by the Contracting Officer shall place his employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.

Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area. An equitable adjustment in contract time may be made for this period.

(c) Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to his operation under the contract.

(1) Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.

(2) Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:

One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with a 4 BC or higher rating.

One - shovel, round point #0 lady or equal.

One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.

One - water container (at least 1-gallon capacity), not required with stationary equipment.

(3) Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.

(4) Powersaws. For each powersaw used in connection with this contract, the following will be provided:

One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.

One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.

Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.

(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.

(6) Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.

(7) Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site when all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.

(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.

(9) Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.

All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.

(10) Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.

(11) Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.

When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:

(i) All high fire risk operations could be terminated at 1300 local time.

(ii) All burning could be stopped, including debris burning fires.

(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.

(12) Pump and Trailer. NOT USED

(13) Burning. Before starting any open burning, the Contractor shall comply with the following:

(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.

(ii) Submit a burning permit from the District Ranger.

(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.

(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.

(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.

(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his discretion, prohibit all open burning for definite periods within specific areas of the National Forest.

PART II--CONTRACT CLAUSES

SECTION I – CONTRACT CLAUSES

FAR 52.211-18 Variation in Estimated Quantity (APR 1984)

Add the following:

Adjustment of contract prices as described in this section shall not apply to Section 622, Rental Equipment, Item 62201 Hydraulic Excavator with Thumb. The Government reserves the right to reduce or eliminate entirely the work under this item with no adjustment in contract unit price.

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.203-3 Gratuities (APR 1984)

52.203-5 Covenant Against Contingent Fees (APR 1984)

52.203-7 Anti-Kickback Procedures (OCT 2010)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (JAN 1997)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010)

52.204-4 Printed or Copied Double-Sided on Recycled Paper (AUG 2000)

52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (DEC 2010)

52.211-18 Variation in Estimated Quantity (APR 1984)

52.215-2 Audit and Records -- Negotiation (OCT 2010)

52.219-6 Notice of Total Small Business Set-Aside (NOV 2011)

52.219-8 Utilization of Small Business Concerns (JAN 2011) 52.219-14 Limitations on Subcontracting (DEC 1996)

52.219-16 Liquidated Damages --Subcontracting Plan (JAN 1999) (Applicable if > $1.5 Million) 52.222-3 Convict Labor (JUN 2003)

52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation (JUL 2005)

52.222-6 Davis-Bacon Act (JUL 2005)

52.222-7 Withholding of Funds (FEB 1988)

52.222-8 Payrolls and Basic Records (JUN 2010)

52.222-9 Apprentices and Trainees (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements (FEB 1988)

52.222-11 Subcontracts (Labor Standards) (JUL 2005) 52.222-12 Contract Termination - Debarment (FEB 1988)

52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988)

52.222-14 Disputes Concerning Labor Standards (FEB 1988)

52.222-15 Certification of Eligibility (FEB 1988)

52.222-21 Prohibition of Segregated Facilities (FEB 1999)

52.222-26 Equal Opportunity (MAR 2007)

52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999)

52.222-35 Equal Opportunity for Veterans (SEP 2010)

52.222-36 Affirmative Action for Workers with Disabilities (OCT 2010)

52.222-37 Employment Reports for Veterans (SEP 2010)

52.222-50 Combating Trafficking in Persons (FEB 2009)

52.223-2 Affirmative Procurement of Biobased Products Under Service and Construction Contracts (DEC 2007)

52.223-6 Drug-Free Workplace (MAY 2001)

52.223-14 Toxic Chemical Release Reporting (AUG 2003)

52.223-15 Energy Efficiency in Energy-Consuming Products (DEC 2007)

52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving (AUG 2011)

52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008)

52.225-25 Prohibition on Contracting with Entities Engaging in Sanctioned Activities Relating to Iran-Certification (NOV 2010)

52.227-1 Authorization and Consent (DEC 2007)

52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007)

52.228-2 Additional Bond Security (OCT 1997)

52.228-11 Pledges of Assets (SEP 2009)

52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995)

52.228-14 Irrevocable Letter of Credit (DEC 1999)

52.228-15 Performance and Payment Bonds – Construction (OCT 2010)

52.229-3 Federal, State, and Local Taxes (APR 2003)

52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002)

52.232-17 Interest (OCT 2010)

52.232-18 Availability of Funds (APR 1984)

52.232-23 Assignment of Claims (JAN 1986)

52.232-27 Prompt Payment for Construction Contracts (OCT 2008)

52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (OCT 2003)

52.233-1 Disputes (JULY 2002)

52.233-3 Protest after Award (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)

52.236-2 Differing Site Conditions (APR 1984)

52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)

52.236-5 Material and Workmanship (APR 1984)

52.236-6 Superintendence by the Contractor (APR 1984)

52.236-7 Permits and Responsibilities (NOV 1991)

52.236-8 Other Contracts (APR 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (APR 1984)

52.236-10 Operations and Storage Areas (APR 1984)

52.236-11 Use and Possession Prior to Completion (APR 1984)

52.236-12 Cleaning Up (APR 1984)

52.236-13 Accident Prevention (NOV 1991) 52.236-14 Availability and Use of Utility Services (APR 1984) 52.236-15 Schedules for Construction Contracts (APR 1984)

52.236-17 Layout of Work (APR 1984)

52.236-21 Specifications and Drawings for Construction (FEB 1997)

52.236-26 Preconstruction Conference (FEB 1995)

52.242-13 Bankruptcy (JUL 1995)

52.243-4 Changes (JUN 2007)

52.244-6 Subcontracts for Commercial Items (DEC 2010)

52.246-21 Warranty of Construction (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2010)

52.249-2 Termination for Convenience of the Government (Fixed-Price) (MAY 2004)--Alternate I (SEP 1996)

52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)

452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996)

452.236-72 Use of Premises (NOV 1996)

452.236-73 Archeological or Historic Sites (FEB 1988)

452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)

452.236-76 Samples and Certificates (FEB 1988)

452.236-77 Emergency Response (NOV 1996)

AGAR 452.228-70 Alternative Forms of Security (NOV 1996)

If furnished as security, money orders, drafts, cashier's checks, or certified checks shall be drawn payable to: USDA Forest Service.

FAR 52.204-7 Central Contractor Registration (DEC 2012)

(a) Definitions. As used in this provision—

“Central Contractor Registration (CCR) database” means the primary Government repository for Contractor information required for the conduct of business with the Government.

“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and Bradstreet, Inc. (D&B) to identify unique business entities.

“Data Universal Numbering System+4 (DUNS+4) number” means the DUNS number means the number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same concern.

“Registered in the CCR database” means that—

(1) The Offeror has entered all mandatory information, including the DUNS number or the DUNS+4 number, as well as data required by the Federal Funding Accountability and Transparency Act of 2006 (see subpart 4.14), into the CCR database; and

(2) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record “Active”. The Offeror will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.

(b)

(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS+4” followed by the DUNS or DUNS+4 number that identifies the offeror’s name and address exactly as stated in the offer. The DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.

(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.

(1) An offeror may obtain a DUNS number—

(i) Via the internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or

(ii) If located outside the United States, by contacting the local Dun and Bradstreet office. The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.

(2) The offeror should be prepared to provide the following information:

(i) Company legal business name.

(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(iii) Company physical street address, city, state and Zip Code.

(iv) Company mailing address, city, state and Zip Code (if separate from physical).

(v) Company telephone number.

(vi) Date the company was started.

(vii) Number of employees at your location.

(viii) Chief executive officer/key manager.

(ix) Line of business (industry).

(x) Company Headquarters name and address (reporting relationship within your entity).

(d) If the Offeror does not become registered in the CCR database in the time prescribed by the Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.

(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.

(f) Offerors may obtain information on registration at https://www.acquisition.gov .

(End of Provision) 52.217-7 Option for Increased Quantity -- Separately Priced Line Item (MAR 1989) The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written notice to the Contractor within 10 days. Delivery of added items shall continue at the same rate that like items are called for under the contract, unless the parties otherwise agree.

(End of Clause)

52.219-28 Post-Award Small Business Program Representation (APR 2012)

(a) Definitions. As used in this clause--

Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (c) of this clause. Such a concern is “not dominant in its field of operation” when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was a small business concern prior to award of this contract, the Contractor shall rerepresent its size status according to paragraph (e) of this clause or, if applicable, paragraph (g) of this clause, upon the occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts—

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code assigned to this contract. The small business size standard corresponding to this NAICS code can be found at http://www.sba.gov/content/table-small-business-size-standards .

(d) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(e) Except as provided in paragraph (g) of this clause, the Contractor shall make the rerepresentation required by paragraph (b) of this clause by validating or updating all its representations in the Online Representations and Certifications Application and its data in the Central Contractor Registration, as necessary, to ensure they reflect the Contractor’s current status. The Contractor shall notify the contracting officer in writing within the timeframes specified in paragraph (b) of this clause that the data have been validated or updated, and provide the date of the validation or update.

(f) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (e) or (g) of this clause.

(g) If the Contractor does not have representations and certifications in ORCA, or does not have a representation in ORCA for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

The Contractor represents that it [ ] is, [ ] is not a small business concern under NAICS Code ______________ assigned to contract number ______________.[Contractor to sign and date and insert authorized signer's name and title].

(End of clause) 52.225-9 Buy American Act–Construction Materials (Sep 2010)

(a) Definitions. As used in this clause--

“Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (46 U.S.C. App. 1702), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means--

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in…

This is the start of the file's text. The full file is on GovTribe.