Addendum No. 1~9.pdf
PDF 298 KB Posted
- Attached to
- CSA 20 Joshua Tree Community Center Roof Coating
- Solicitation number
- SPD126-SPDAD-6394
- Issued by
- San Bernardino County, California
About this file
This Addendum No. 1 modifies the bidding requirements for the CSA 20 Joshua Tree Community Center Roof Coating project issued by the San Bernardino County Department of Public Works - Special Districts Division. The project, located at 6171 Sunburst Avenue, Joshua Tree, California, involves the rehabilitation and life-extension of an existing low-slope roof system through application of a fluid-applied roof coating system suitable for modified bitumen roofing. The scope includes surface preparation, localized repairs, base coat and finish coat applications, and manufacturer inspection to achieve a minimum 20-year No Dollar Limit manufacturer warranty. The primary change in this addendum is the rescheduling of the bid opening date from May 21, 2026 at 10:00 AM to June 4, 2026 at 1:30 PM, with the bid opening to be conducted via Microsoft Teams meeting. The project must be completed within 30 calendar days following issuance of the Notice to Proceed, with liquidated damages assessed at $1,500 per calendar day for delays.
Bidders must hold a valid California Class C-39 (Roofing) or Class B (General Building) contractor's license, register with the Department of Industrial Relations, list at least three similar projects completed within the last five years, and comply with prevailing wage requirements under California Labor Code sections 1770 et seq. Bid security equal to 10 percent of the total base bid plus additive bid price is required, and bids must remain valid for 60 calendar days after the bid opening date. The successful bidder will be required to furnish performance and payment bonds each equal to 100 percent of the contract sum and maintain comprehensive insurance coverage including workers' compensation, general liability ($1,000,000 combined single limit), automobile liability ($1,000,000 combined single limit), and builder's risk coverage. Progress payments will not exceed 95 percent of the total contract price, with final payment processed 60 calendar days after filing of the Notice of Completion. The specific contract award value or budget range is not disclosed in the available bid documents.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SAN BERNARDINO COUNTY
DEPARTMENT OF PUBLIC WORKS
SPECIAL DISTRICTS
ADDENDUM NO. 1
TO THE BIDDING REQUIREMENTS, CONTRACT DOCUMENTS, GENERAL CONDITIONS,
SPECIAL CONDITIONS, AND TECHNICAL SPECIFICATIONS FOR THE
CSA 20 JOSHUA TREE COMMUNITY CENTER ROOF COATING
PROJECT NO.: 30.30.0204
MAY 19, 2026
The Contract Documents for the above referenced project are hereby amended as set forth below. All provisions of Addendum No. 1 are hereby incorporated into the Contract Documents, and Bidders shall account for all provisions pursuant to this Addendum No.1 in submitting their bid proposals. Each Bidder shall include a dated and signed copy of this Addendum with their sealed bid proposal.
1. SECTION A: BIDDING REQUIREMENTS
Contractors are advised of the following changes to the bid opening date as it appears within Section A: BIDDING REQUIREMENTS
A. All references to the bid opening date for CSA 20 JOSHUA TREE COMMUNITY ROOF
COATING PROJECT SHALL BE REPLACED FROM:
MAY 21, 2026 at 10:00AM
To
JUNE 4, 2026 at 1:30PM
Microsoft Teams meeting Join: https://teams.microsoft.com/meet/215827859124729?p=axQ5WLvabzRK9lwoAW Meeting ID: 215 827 859 124 729 Passcode: D3v6uS6e
Need help? | System reference Dial in by phone +1 661-568-6806,,592473370# United States, Santa Clara Find a local number Phone conference ID: 592 473 370# For organizers: Meeting options | Reset dial-in PIN
All other terms, conditions, and requirements of the Contract Documents remain unchanged unless specifically modified by this Addendum.
ISSUE DATE: MAY 2026 Date Acknowledged by Bidder:
By:
By:
Nicholas Torres, Project Manager Bidders Company Name Department of Public Works - Special Districts Project Management Division
Bidders Signature
File details come from the government source that posted it. Updated .