Addendum 2 to ITB 14564 modifies the Invitation to Bid for the Smith Rock State Park Visitor Improvement Project issued by the Oregon Parks and Recreation Department. The addendum deletes the pay station (OFCI) from the scope of work, including removal from Section 011000 Summary of Work and Section 012200 Measurement and Payment in the Technical Specifications. Additionally, Addendum 2 revises multiple landscape material plan sheets (L3.00, L3.11, L3.12, L3.16, L7.04) and civil erosion control details (C4.05) to correct detail keynotes, callouts, and remove pay station references. The revised deadline for all ITB closing submissions has been extended to November 19, 2026, at 2:00 PM (PT), with prospective bidders required to submit written questions, requests for changes, or protests by 5:00 PM on November 16, 2026. Receipt of this material addendum must be acknowledged on Attachment A, Form A-1 of the original ITB.
The addendum includes clarifications addressing bidder questions regarding landscape material notes, manufacturer installation information for owner-provided items (benches, removable bollards, kiosks, gates, and trash receptacles), archaeological monitoring (to be provided by the owner), ADA compliance requirements (Architectural Barriers Act for park work and ODOT/Deschutes County standards for right-of-way work), erosion control specifications, and acceptable materials for underdrains. Project 4 (Restroom Plaza) remains a bid alternate subject to owner determination after bidding but prior to contract execution. Rock hammering for split rail fence installation is considered incidental to fence work rather than charged against the rock excavation allowance, and the contractor is responsible for installing and adjusting Best Management Practices during construction to control sediment in accordance with technical specifications and the 1200-CA permit.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #2
OregonBuys # S-63400-00018081
ITB # 14654
Smith Rock Visitor Improvement Project
This Addendum 2 modifies the Invitation to Bid (“ITB”) only to the extent indicated herein. All other areas not specifically mentioned or affected by this Addendum 2 shall remain in full force and effect. This Addendum shall be added as a part of the original ITB document(s) and shall become part of the work required.
ADDENDUM
1. ATTACHMENT A FORM A-2 PRICING FORM is amended to delete and replace with Addendum 2, Attachment A Form A-2 Pricing Form which is found as a separate file in OregonBuys.
2. ATTACHMENT B TECHNICAL SPECIFICATIONS is amended as follows:
A. Section 011000 SUMMARY OF WORK, Part 1 GENERAL, paragraph 1.01, C., 3., ee. C31. Pay Station (OFCI) is deleted.
B. Section 012200 MEASUREMENT AND PAYMENT, Part 1 GENERAL, paragraph 1.02, C., 31., C31. Pay Station (OFCI) is deleted.
3. ATTACHMENT C – PLANS AND DRAWINGS is amended to delete and replace the following Plans and Drawings. Replacement sheets are provided in Addendum 2, Attachment C - Revised Drawings which is found as a separate file in OregonBuys:
· L3.00 LANDSCAPE MATERIALS NOTES AND LEGENDS – Detail/Sheet callouts have been revised.
· L3.11 LANDSCAPE MATERIALS PLAN – Detail keynote has been revised.
· L3.12 LANDSCAPE MATERIALS PLAN – Detail keynote has been revised.
· L3.16 LANDSCAPE MATERIALS PLAN – Detail keynote has been revised, pay station has been deleted.
· L7.04 LANDSCAPE SITE DETALS IV – Detail has been added.
· C4.05 CIVIL EROSION CONTROL DETAILS II – Detail has been revised.
All references to the ITB CLOSING DATE are changed to:
November 19, 2026, at 2:00PM (PT)
Addendum prepared by:
Bryant Hayes Sr. Contracts Specialist Bryant.hayes@oprd.regon.gov
Prospective Bidders have until 5:00 PM on November 16, 2026 to submit written questions, requests for change, or protests regarding this Addendum.
1.
2.
3.
4.
5.
6.
1.
2.
3.
4.
5.
6.
This Addendum constitutes a MATERIAL change to the solicitation document. Its receipt by the Offeror shall be acknowledged per Attachment A, Form A-1 of the ITB.
7.
8.
9.
10.
11.
12.
7.
8.
9.
10.
11.
12.
End of Addendum 2
CLARIFICATIONS AND RESPONSE(S) TO QUESTIONS
The following provides OPRD’s answers to questions received from potential Bidders. The information provided below is for clarification purposes only and does NOT constitute a change to the solicitation documents or requirements.
QUESTION: Sheet L3.12 shows a circled note 1.5 typ, that note is not shown in the table on sheet L3.00. will this note be added?
OPRD RESPONSE: See Addendum 2 Attachment C Revised drawings.
QUESTION: Several notes from sheet L3.00 to L3.18 show detail information on the wrong sheets, will a cleaned-up bid set be provided for this pricing request?
OPRD RESPONSE: See Addendum 2 Attachment C Revised drawings.
QUESTION: Can we get the manufacturers installation information for items provided by the owner?
OPRD RESPONSE: Bench, Removable Bollard, Kiosk, and Gate details are included on L7.05. See Addendum 2 Attachment C Revised Drawings for trash receptacle detail.
QUESTION: Will the archeological monitor be provided by the owner?
OPRD RESPONSE: Yes. The archaeology monitor will be provided by the owner. The contractor is responsible to provide an accurate schedule and coordinate monitoring needs in advance per the Contract Documents.
QUESTION: Detail 2/C4.05 references further information on sheets C3.4 & C3.5. These sheets are not in the current bid set, will these plan sheets or the information referenced from these plan sheets be made available?
OPRD RESPONSE: See Addendum 2 Attachment C Revised drawings.
QUESTION: What type of pedestrian control do we think we need, chain link or orange fence?
OPRD RESPONSE:
QUESTION: Is there any particular sequencing?
OPRD RESPONSE: Sequencing is described in Section 011019 CONTRACT CONSIDERATIONS.
QUESTION: What does monitoring look like if we need to jackhammer?
OPRD RESPONSE: Park staff or consultant monitor will need to be on site to observe eagle behavior for stress indicators. Monitoring needs must be coordinated in advance per Section 011019.
QUESTION: Which ADA are we complying with?
OPRD RESPONSE: Work on site within the park must comply with the Architectural Barriers Act (ABA). Work in the right-of-way must comply with ODOT and Deschutes County.
QUESTION: What about Project 4?
OPRD RESPONSE: Project 4 is a bid alternate. Owner will determine whether or not to include the work after bidding, prior to contract execution.
QUESTION: Erosion Control, plans show the installation of sediment fence and wattle along the down hill side of all trails. Can we plan on installing the sediment fence and wattle along the trails on the down hill side throughout LX.11- LX.17? If not, how will it be determined where the erosion control sediment fencing and wattle will be installed?
OPRD RESPONSE: Per the Technical Specifications, Plans and 1200-CA permit, the Contractor is responsible to install and adjust BMP’s as needed during construction to control sediment and sediment laden water on site. Detail 2, C4.05 depicts several options for trail erosion control QUESTION: If rock hammering is necessary for installation of new split rail fence, does the rock hammering fall under rock excavation allowance? Or should the rock hammering be assumed and included within the split rail fencing line item?
OPRD RESPONSE: Rock hammering for installation of split rail fence is incidental to the fence installation work. The Rock Excavation allowance is for significant rock encountered during General Excavation and Earthwork.
QUESTION: Is 4” slotted 30-34 acceptable to use for the slotted under drain piping?
OPRD RESPONSE: Yes, perforated ASTM D 3034 PVC is acceptable.