Addendum 2 22-069-PW Pole Replacement~1.pdf

PDF 135 KB Posted

Attached to
EWEB ITB 22-069-PW Oak Grove Lake Harriet Pole Replacement
Solicitation number
S-P00140-00002782
Issued by
Clackamas County, Oregon

About this file

This document is an Addendum to ITB #22-069-PW for the Oak Grove Lake Harriet Pole Replacement project issued by the Eugene Water & Electric Board (EWEB) in Oregon. The addendum provides clarification on the pricing structure, indicating that the lump sum bid price must include the cost of poles and materials. Additionally, the document revises the project timeline, noting that the work must be completed within a three-week period during a scheduled transmission line outage from September 12 through September 30, 2022. EWEB may adjust the start date by up to three weeks to accommodate the contractor's receipt of long lead-time equipment or materials, but the overall duration will remain unchanged.

The addendum also clarifies that there will be some scheduled work at the power plant and substations that will be performed concurrently with the contractor's work, which will require coordination but should not affect the project timeline. The bid submission deadline remains unchanged at May 10, 2022, at 2:00 pm.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

April 27, 2022

ADDENDUM # 2

Title: Oak Gove Lake Harriet Pole Replacement

ITB #22-069-PW

This addendum adds additional information to the original ITB document.

A. QUESTION AND ANSWER:

Q1. Are we to include the price for poles and materials in our lump sum bid price or are these to be a pass-through cost?

A1. Yes, lump sum price and all-inclusive of materials.

B. CHANGES TO ITB DOCUMENT:

Section – Specification 01014, paragraph 1.5(F)

Paragraph is revised from:

To the following:

The required timing of Contractor work will be dictated by the need to coordinate with work performed by Owner and others. Contractor’s performance of the work shall conform to Owner’s established planned transmission line outage that is currently scheduled for September 12th through September 30th, 2022. Owner may adjust the start date for the project timeline by up to three weeks if necessary to accommodate Contractor’s receipt of long lead time equipment or materials. The allowed duration for the work of three work weeks shall remain unchanged. as needed for Owner’s sole benefit. Such adjustments shall be at no additional cost to Owner. Anticipated timing is as follows:

There is some scheduled work at the power plant and substations that will be performed in parallel to Contractor’s work which will require a clearance on the transmission line. This work will be completed within the normal workday schedule and should have no effect on this project outside of coordination.

CLOSING DATE AND TIME

May 10, 2022, 2:00 pm. Remains unchanged.

This addendum constitutes a MATERIAL CHANGE to the Request for Proposals.

Addendum prepared by:

Sandra Hahn Purchasing Analyst

File details come from the government source that posted it. Updated .