Addendum 1 25054.pdf

PDF 3 MB Posted

Attached to
751/25054. RLO; Straits SP - Solar PV & EV Charging Stations
Solicitation number
RFQ 171 250000000183 3
Issued by
Clare County, Michigan

About this file

This Addendum No. 1 document issued by the Michigan Department of Technology, Management and Budget (DTMB) on February 5, 2025, provides clarifications and modifications to the Request for Proposal for the Straits State Park Solar PV and EV Charging Stations project (File Number 751/25054.RLO). The project, administered by DTMB's State Facilities Administration Design and Construction Division in partnership with the Michigan Department of Natural Resources (DNR), involves the design and construction of a solar photovoltaic array, publicly accessible electric vehicle charging infrastructure, and associated control systems. The scope includes installation of one Level 2 charger with two ports (80A dual port, pedestal mount, 15 kW rated capacity) with J1772 and NACS connectors, support for EMV contactless payment, and cellular connectivity for remote monitoring. The solar array will be sized at approximately 149.5 kW-dc (17.5 kW-dc for the Headquarters Meter and 132 kW-dc for the North Campground Meter) to offset electricity consumption for two utility meters at Straits State Park (720 Church Street, Saint Ignace, Michigan). The mandatory pre-bid meeting was held on February 3, 2025, at the project site. Questions must be submitted via email to osgar@michigan.gov no later than 2:00 p.m. on February 12, 2025. Proposals are due on February 19, 2025, at 2:00 p.m. EST to both the issuing office and the SIGMA VSS system. Contract award is anticipated by mid-March 2025, with substantial completion scheduled for December 1, 2025, and work to be completed outside the normal camping season (May 15–September 15) between 8:00 a.m. and 6:00 p.m. Monday through Friday.

The base bid must include the specified Level 2 charger with design-build services encompassing Phase 500 final documents, Phase 600/700 construction administration, LARA plan review permit applications, and all necessary permits and approvals. Design-build proposals must include a $50,000 DTMB provisional allowance under the bid schedule, plan review fees, consultant and testing expenses, all as reimbursable expenses, along with completed and signed bid summary, bid schedule, QDV form if applicable, Certification of a Michigan Based Business, and bond forms. An alternate bid option includes installation of a DNR-provided Ford Pro charging station. The project will be evaluated by an Ad Hoc Advisory Committee. Pricing and funding information from the RFP indicates the utility is Cloverland Electric Cooperative under the General Service 1 (GEN1) rate plan with full net metering provisions, and the project sizing is constrained to a 110% annual electricity offset under 150 kW-ac to qualify for Investment Tax Credit incentives (IRA 30% credit). The bidder must provide domestic content percentage estimates and explain feasibility assessments for complex technical elements including medium voltage equipment integration for the North Campground meter, underground utility coordination, and long-term data acquisition monitoring systems. The contractor is responsible for obtaining and paying for all permits and coordination with LARA and the utility company and must maintain 100% on-site supervision during construction.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0414 RFP (Rev 2/22)

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration Design and Construction Division

REQUEST FOR PROPOSAL

ADDENDUM NO. 01

This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals.

Addenda will be numbered by the Project Director and distributed through SIGMA Vendor VSS as an attachment.

TO:

ALL PROPOSERS

DATE ISSUED

2-5-2025

PROJECT NAME

Straits State Park / Solar PV & EV Charging Stations

FILE NUMBER

751/25054.RLO

PROJECT DIRECTOR

Ronda Osga

PROPOSAL DUE DATE:

February 19th, 2:00 PM EST

ADDENDUM ITEMS: (attach additional sheets and drawings if required)

Attached please find:

1. Attendance / Sign-in Sheet

2. Meeting Agenda – Revised items in Bold Purple

3. Attachment 1 - DNR Straits PV_EV Report – Revised

4. Attachment 2 – Rescinded

RFI questions / responses below:

Q1- Does the scope of the services include supplying the Level 2 chargers for the North Campground (2 units at 19kW max charge rate)

R1- Per the walk through on February 3, 2025, the scope of work includes suppling a level two charger with two charging ports – see revised Attachment 1 for the charger specifications.

Q2- What about an Energy Storage unit - as solar is intermittent.

R2- Energy storage is not a part of this project; the park will still be connected to the utility company.

Q3- Could you also share with us which rate plan you are on?

R3- The rate plan is General Service 1 (note 10 in Attachment 1).

APPROVED BY:

PROJECT DIRECTOR Ronda Osga DATE 2-5-2025

Revisions are in Bold Purple

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration

Design and Construction Division Mailing Address: P.O. Box 30026, Lansing, MI 48909

Street Address: 3111 W. St. Joseph Street, Lansing, MI 48917

PRE-BID MEETING AGENDA

Project: Department of Natural Resources / Parks & Recreation Division

Straits State Park - Straits Solar PV and EV Charging Stations

File Number: 751/25054.RLO

Meeting Date and Time: Monday, February 3, 2025, at 1:00 pm local time

Meeting Place: Straits State Park, 720 Church Street, Saint Ignace, MI 49781

Agenda Items:

1. Introductions / Sign-In Sheet.

This is a Mandatory Pre-Bid Meeting. Confirm your attendance is recorded on the sign-in sheet to ensure your bid is considered.

Project Representatives

--Ronda Osga / DTMB Project Director

--Brian Guigue / DTMB Field Rep

-- Julia Cogger / DNR Planner

--Michelle Crook / DNR Senior Project Engineer

--Chuck Allen / DNR Departmental Specialist

-- Eric Cowing / DNR District Supervisor

-- Charlie Maltby / DNR State Park Supervisor

--Other DNR Divisions Staff

2. Request for Proposals – Standard Design-Build Not-to-Exceed RFP

a. Qualification format: Includes General Design-Build entity Information;

Understanding of the Project and how the Design-Build entity will accomplish the project, including any unique conditions or issues; Personnel and resumes;

Provide experience with similar projects; How is the Design-Build entity the best suited for the project.

b. Include plan review fees, consultants and testing expenses.

c. Include $50,000 for DTMB provisionary allowance in bid (under line 2 of the Bid

Schedule – Construction, Trade Labor and Subcontractors).

d. Include consultants and testing as reimbursable expenses.

e. Include filled out and signed Bid Summary, Bid Schedule, QDV form (if applicable), Certification of a Michigan Based Business and Bond forms.

f. Proposals will be evaluated by an Ad Hoc Advisory Committee.

3. Project Scope

a. The Michigan Department of Natural Resources, Parks and Recreational Division, is requesting development of design documents and installation of a new solar array, publicly accessible EV chargers and control systems. The array will offset electricity for two utility meters one serving the Headquarters Building and the other serving the North Campground at Straits State Park. Reference the

Design-Build Project Advertisement and attachments for detailed scope of work and energy goals for the project.

b. Base bid to include new charging station as specified in the revised DNR Straits

PV_EV Report- Attachment 1. Alternate bid to include the installation of a DNR provided Ford Pro charging station (see attachment 2).

c. Design-Build entity is responsible for design and construction of the project.

Design services to include Phase 500 Final Documents, Phase 600/700

Construction Administration.

d. Design-Build services shall include, but are not limited to:

• Document existing conditions in order to provide the required design documents.

• Include LARA Plan Review Permit application and Construction Code approval, and all permits and standards required to be met by this project.

• Submittal of 50% and 90% Phase 500 documents and cost estimates for

Owner review.

e. Provide a biweekly progress summary email to the project team, briefly documenting the prior 2-week’s progress by the Design-Build entity and display the initial project schedule and current schedule status.

f. The Contractor responsible for managing and supervising the work and must be on site 100% of time while work is taking place.

g. Contractor is responsible for obtaining and paying for all permits and coordination required by LARA, utility company or any other agency as required.

4. Site Visits

a. Accessibility to the site: Collect all information needed today. If additional information is needed contact me.

5. Schedule

a. E-mail questions to osgar@michigan.gov no later than 2:00 p.m., Wednesday, February 12, 2025. DO NOT send questions in through SIGMA as they do not get to the project directors from SIGMA.

b. If necessary, an addendum will be posted on the SIGMA VSS website no later than COB, February 14, 2025.

c. Proposals are due on Wednesday, February 19, 2025, no later than 2:00 p.m.

EST to issuing office and on SIGMA VSS.

• If you experience issues or have questions regarding your electronic submission, you must contact the SIGMA Help Desk for assistance prior to the 2:00 p.m. deadline. You may contact the SIGMA Help Desk by telephone at 517.284.0540 or toll-free at 888.734.9749.

• Please email the Design and Construction Contract Specialists if you are having SIGMA VSS issues. Please include your SIGMA ticket number and any supporting documentation (i.e., screenshots) to Anne Watros

(WatrosA@michigan.gov) and Don Klein (KleinD4@michigan.gov).

d. Ad Hoc Advisory Committee will review proposals and award contract by Mid-

March.

e. Work to be completed outside of normal camping season (May 15-Sept 15).

Work within normal camping season allowed outside of campground area, timing and hours of operation to be coordinated with Park Supervisor.

f. All work to take place between the hours of 8:00 am and 6:00 pm Monday through Friday.

g. Substantial Completion scheduled for December 1, 2025.

6. Substantial Completion Requirements: Section 5.8 Substantial Completion Prerequisites

(d) Signed agreement with Utility for Interconnect

(e) Copy of Complete Interconnect Contract

(f) Price Breakdown with costs for panels, racking, inverters, wiring, EV chargers, engineering, construction, and other related costs.

(g) Equipment model numbers and quantities of equipment use

7. Questions

DNR.MEO – Straits PV and EV Page 1 of 7

Straits State Park:

720 Church Street, St. Ignace, MI 49781

The Michigan DNR intends to own and operate behind-the-meter solar PV systems at Straits State Park. This scope of work includes the design and build of PV arrays to offset electricity for two utility meters and for the installation of publicly accessible EV chargers. Available site data including drawings, photos, and load profiles are provided as additional exhibits.

An overall design concept is shown in Figure 1. Cloverland Electric Cooperative, the regional electric utility provider, has communicated one area of PV arrays may offset two utility meters. This is conditional upon each utility meter connecting to independent AC power generators (inverters). Additionally, DNR plans for a Level 2 charger with two ports to be installed within the North Campground electrical circuit.

Figure 1: Overall PV and EV design.

OsgaR Text Box Attachment 1 revised 02-03-2025

DNR.MEO – Straits PV and EV Page 2 of 7

Overall PV Design

The PV design details are applicable for both utility meters except when specifically defined per meter.

Figure 2: PV Array area.

Project details and assumptions:

1. Array Layout: 30 degree fixed-tilt, 2-high modules in portrait, min 3’ from ground.

2. Major Equipment:

a. Modules: Bifacial modules are Tier 1 or equivalent.

i. Total Project Size Estimate: 149.5 kW-dc.

ii. HQ Meter Size: 17.5 kW-dc

iii. N Campground Meter Size: 132 kW-dc

b. Inverters: May be microinverters or string inverters. Multiple inverters are preferred per meter.

i. HQ Meter Voltage: Single phase, 120/240V.

ii. HQ Meter Inverter Size Estimate: Variable pending microinverters or strings. Assume inverter loading ratio in the range of 1.2 – 1.3.

iii. N Campground Meter Voltage: Three phase, 13.2 kV

DNR.MEO – Straits PV and EV Page 3 of 7

iv. N Campground Inverter Size Estimate: DC:AC ratio of 1.2 – 1.3. Variable pending bidder proposal and explanation of 1,000V or 1,500V string inverters.

c. MV Equipment:

i. N Campground Meter: The 13.2 kV interconnect will require a step-up transformer and need to integrate with the existing DNR owned MV cable between the utility meter and the N Campground electrical infrastructure. The Bidder should explain their proposal of new DNR-owned medium voltage equipment.

d. Balance of System:

i. HQ Meter: The Bidder should provide a brief explanation describing the feasibility of modules sharing a rack for two different meters and inverters, and any potential grounding implications with the systems sharing electrically conductive equipment.

ii. N Campground Meter: The two key areas for PV electrical design are near the PV array and near the interconnect. The Bidder may propose a direct bore solution in conduit for the PV power as DC or as medium voltage AC, low voltage AC is assumed impractical.

Note, the area near the utility’s meter is land constrained.

3. Land Constraints:

a. For the PV Array: Road to West, trees to North and South, property boundary and ditch to East.

Setbacks from the road, north tree line and southern trees should be communicated in Bidders explanation.

b. The area near the N Campground Meter is also relatively constrained due to the wooded surroundings.

4. Shade Details: Tree trimming and vegetation removal is expected to be performed by DNR, Bidder should provide an explanation of their preliminary assessment of tree trimming in proposal.

5. Fence Requirements: DNR prefers no permanent fence around the PV array but will defer final requirements to comply with applicable codes. For example, it is assumed the National Electrical Code requires fencing around systems greater than 1,000V. If fencing is not proposed nor required, Bidder should include a solution for minimizing the quantity of exposed wire as risk mitigation from the general public.

6. Underground Conditions:

a. Utilities: Known underground utilities include DNR owned sewer and water lines in the PV array area. There is a survey drawing showing the utilities, though the dimensions of the drawing appear inaccurate. For example, the entrance road has been measured to 16’ while the survey drawing states 20’. Bidders should include an explanation of how to manage construction when existing underground conduits are assumed to not include traceability.

b. DNR requires all underground wires be installed in conduit.

7. Data Acquisition System: In the bid provide the bidder’s recommendation for long-term data monitoring inclusive of any necessary long-term costs such as cellular plans or a method to connect to site communications.

8. Load Data: Annual electricity usage including EV charging projections are as an attachment to the RFP.

9. Interconnection: Areas of interest are provided in diagrams here and additional photos in the exhibits.

a. HQ Meter: Recommended line side POCC prior to HQ panelboard, such as adjacent to utility meter, or the most feasible location between the utility ownership and DNR ownership.

DNR.MEO – Straits PV and EV Page 4 of 7

b. N Campground Meter: Recommended line side POCC near meter.

10. Utility and Rate Case: Cloverland Electric Co-Op. General Service, GEN1. Full Net Metering rate.

11. Utility sizing constraints: 110% annual electricity offset. Size is under 150 kW-ac full net metering cap.

12. Financial Incentive Potential Qualifications: IRA: Under 1 MW (30%), Bidder to provide estimate for domestic content percentage expectations.

Figure 3: Grassy area adjacent to N Campground meter (measured at medium voltage).

DNR.MEO – Straits PV and EV Page 5 of 7

Overall EV Design

The charger(s) will be installed near the entrance to Straits State Park to ensure convenient access for visitors

(see Figure 4). The installation will include mounting the charger on a pedestal, with provisions for cable management to keep the charging cables organized and easily reachable.

1. Public Chargers:

a. Number of Chargers 1

b. Number of Ports per Charger: 2

c. Connector(s): J1772 and NACS

d. Charger Type: 80 A Dual port, pedestal mount, 15ft cable or longer

e. Rated Capacity (DC power): Not to exceed 80A (19.2 kW)

f. AC Grid Voltage; Input Voltage: 120 / 240 V ; 120 / 240 V

g. Communications: Cellular connection

h. Payment Options: Must support EMV contactless credit/debit reader

i. Charger Order/Model code: Bidder to provide specific charger model with all features

j. ADA Compliance Requirements: See EV Parking Design example.

k. Must follow site design requirements as described by ChargePoint for installation.

2. Site preparation may include trenching, mounted concrete pads, and restriping parking stalls. The charger(s) will be configured for network communication to support remote monitoring and payment options. Placement will prioritize ADA accessibility and ease of use for the public (see Figure 5, EV

Parking Design example). Bidder will be responsible for providing final parking design. The installation will follow the charger’s specific guidelines for proper setup and compliance with all requirements.

Figure 4: Straits Park Entrance Charger Location

DNR.MEO – Straits PV and EV Page 6 of 7

Figure 5: Example Parking Detail

DNR.MEO – Straits PV and EV Page 7 of 7

Compliance and Standards

All installations will adhere to regulatory standards, including National Electrical Code (NEC) requirements, ADA compliance for accessible parking spaces, and DNR Guidelines.

Installation Process and Timelines

The project will proceed in several phases:

1. Site Assessment and Design: Evaluating site conditions, electrical capacity, and finalizing charger placements.

2. Permitting and Procurement: Securing necessary permits, including LARA permitting, and procuring equipment.

3. Installation: Charger installation, electrical upgrades, testing and parking striping.

4. Commissioning: Final inspections, operational tests, and training for DNR staff.

The anticipated project timeline from the start of the site assessment to final commissioning should be proposed to DNR.

Operational Requirements

Chargers will be connected to a network for monitoring and payment processing. Public chargers will support contactless payment via credit/debit cards. DNR will manage long-term operations but may consider a routine maintenance proposal from the winning Contractor.

Acceptance Criteria

• All chargers are installed and operational according to the specifications.

• Final inspections are passed, and necessary permits are closed.

• DNR staff receive training on charger operation and maintenance procedures.

• Any punch list items identified during commissioning are resolved.