This is Addendum No. 04 to RFP 00002649 issued by the City of Portland, Oregon Procurement Services for Streetcar Vehicles, Parts and Tools. The addendum modifies specifications and requirements for the solicitation, with proposal responses due by 4:00 pm on January 30, 2026. The document updates the proposal page limit from 100 to 250 pages, with certain sections excluded from the page count including resumes, subcontractor relevant experience, delivery and production schedules, and detailed system supplier information. The addendum also revises Package 3 - Corporate Responsibility requirements, changing the Sustainable Business Practices section to request the top five actions to reduce environmental impacts rather than the original top three employment opportunity actions.

The addendum includes comprehensive updates to Attachment D - Sample Contract, including revised definitions of "Milestone," clarification of contract unit terminology, and a complete reordering of the order of precedence to establish which contract documents take priority in case of conflicts. The order of precedence now ranks amendments highest, followed by federal requirements, master terms and conditions, contractor pricing, change orders, statement of work, technical specifications, and other exhibits and sample documents. Additionally, the addendum addresses a question regarding warranty service locations, confirming that warranty service for new streetcars will be performed at the current Operations and Maintenance Facilities (OMFs) rather than at new facilities. Respondents are directed to contact Kristina Kolata, Senior Procurement Specialist, at 971-509-0713 for questions and concerns.

View the file

Other files

File Type Posted
Anticlimber drawing 0000471 Rev A.pdf PDF
USC layout drawings.pdf PDF
Addendum 05 RFP00002649 - Note to File (number skipped in sequence).txt TXT text file
Addendum 07 RFP00002649 Question and Answer (2).pdf PDF
00002742 Exhibit D - GS RFP 00002649 Streetcar Vehicles Parts and Tools.pdf PDF
South Bldg - Selected As-Built Drawings.pdf PDF
MontgomeryParkStreetcarExtension-alignment.pdf PDF
Addendum 03 Attachment 1 Dimensional Consistency Drawings.pdf PDF
Addendum 08 RFP00002649 Question and Answer (2).pdf PDF
Addendum 03 RFP00002649 Question and Answer (2).pdf PDF
Thurman Floorplan.pdf PDF
Portland Stcar Loop IFB Vol 1 shts 10-115.pdf PDF
USC Vehicle Dynamic Envelope.pdf PDF
Inekon TRIO Vehicle dynamic envelope.pdf PDF
Addendum 09 RFP00002649 Extend Close Date (2).pdf PDF
Addendum 06 RFP00002649 Question and Answer (2).pdf PDF
Streetcar Facility Site Plan -May 2012.pdf PDF
Yard track entry and transfer.pdf PDF
Pages from 15B Tilikum Crossing - Volume 1.pdf PDF
Gibbs extension track profiles.pdf PDF
Original 2001 track profiles.pdf PDF
00002742 QBS-RFP Streetcar Replacement Project Support.pdf PDF
Coupler SP1520157VEN-02.pdf PDF
Addendum 02 RFP00002649 RFP Clarifications (2).pdf PDF
Addendum 01 RFP00002649 Update Pre-Proposal Information (2).pdf PDF
North Bldg - Selected As-Built Drawings.pdf PDF
Riverplace extension track profiles.pdf PDF
Eastside expansion - trackwork.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 1

Procurement Services City Operations City of Portland, Oregon

@PortlandGov portlandgov

PortlandORGov

November 26, 2025

ADDENDUM NO. 04

RFP 00002649

FOR

Streetcar Vehicles, Parts and Tools Responses Due: January 30, 2026

By: 4:00 pm

This Addendum provides changes to the specifications for the above-entitled project to be considered by each respondent. Any changes made by this Addendum to said specifications offset only the portion of the words or paragraphs specifically mentioned herein, and the balance of the specifications remain in full force. It is the responsibility of all respondents to conform to this addendum.

This Addendum shall:

1. Add/delete the following language from the solicitation document RFP00002649 Proposal Response Packet Streetcar Vehicles Parts and Tools. New language is in bold and underline and deleted language is in strikethrough.

Proposal Page Limit is 100 Pages Proposals must be clear, succinct, and not exceed 100 250 pages. Not all parts of the proposal are included in the page limit. The Proposal Checklist in Section 8 of this document lists which parts are included in the page limit.

The following items from Package 2 – Technical Proposal are excluded from the page count. All other requirements within each section will be applied to the overall page count:

i. Resumes - required within Section d. Qualifications, Requirement 3.

Staffing Plan and Resumes

ii. Subcontractor Relevant Experience - required within Section d.

Qualifications, Requirement 4. Subcontractors

iii. Section e. Delivery and Production Schedule

Sylvester Donelson, Jr. Tracy Warren Michael Jordan Chief Procurement Officer Deputy City Administrator Chief Administrative Officer https://twitter.com/PortlandGov https://www.instagram.com/PortlandGov/ https://www.facebook.com/PortlandORGov

Page | 2

iv. Section h. Detailed Information Requirement 1. System Suppliers

2. Add/delete the following language from the solicitation document RFP00002649 Proposal Response Packet Streetcar Vehicles Parts and Tools. New language is in bold and underline and deleted language is in strikethrough.

Package 3 – Corporate Responsibility

c. Sustainable Business Practices

1. List the top three actions/ongoing practices your firm has implemented to ensure you provide opportunities for, and remove barriers to, employment in your workforce for everyone, including women and people of color, at all levels of your firm (e.g., upper management, middle management and lower-level management).

1. List the top five actions/ongoing practices your firm has implemented to reduce the environmental impacts of your operations (for example, energy efficiency, use of recycled content or non-toxic products, use of public transit or alternative fuel vehicles, waste prevention and recycling, water conservation, green building practices, etc.).

3. Delete Attachment D – Sample Contract in its entirety and replace it with Updated Attachment D – Sample Contract.

Items to note that were updated:

a. References to the term “Unit” within the Contract were updated to “unit” as a definition is not provided.

b. For the following, new language is in bold and underline and deleted language is in strikethrough.

SECTION 1: DEFINITIONS

“Milestone”(*) means a specified milestone date in the Contract by which the Contractor is required to complete a designated portion or segment of the Work. “Milestone” includes but is not limited to dates established for S substantial C completion of all or a designated portion or segment of the Work.

c. For the following, new language is in bold and underline and deleted

SECTION 2 ORDER OF PRECENDENCE

Order of Precedence.

In the event there is a conflict or ambiguity between the terms and conditions of one portion of this Contract with another portion of this Contract, the

Page | 3 conflict or ambiguity will be resolved in accordance with the order of precedence below. This order of precedence designates which portion of the Contract takes precedence over the other for purposes of interpretation.

Contractor’s hyperlinks contained herein will not supersede or alter the Master Terms and Conditions. For the avoidance of doubt, no other terms and conditions will override the Parties’ obligations in the Confidentiality, Indemnification, or Choice of Law provisions in these Master Terms and Conditions. In this Contract the order of precedence shall be:

1. Amendments

2. Exhibit E, Federal Requirements

3. Master Terms and Conditions

4. Exhibit A, Contractor’s Price

5. Change Orders

6. Exhibit B, Statement of Work

7. Exhibit C, Technical Specification

8. Exhibit D, City RFP/Bid # ________

9. Exhibit F, Contractor’s Proposal

10. Exhibit G - Sample Documents:

a. G-2 Certificate of Acceptance,

b. G-3 Change Order

c. Attachment S, Sample Software Escrow Agreement, see

5.15, Software Escrow Account

d. Shipping Release referenced as part of the Sample SCV

Forms?, see 8.4.2 Shipment Authorization

e. Certificate of Title form referenced as part of the Sample

SCV Forms?, see 8.4.7.1 Conditional Acceptance of SCV

f. Notice of Non-Acceptance, see 8.4.7.3 Non-Acceptance

d. For the following, new language is in bold and underline and deleted

Section 3.3.1. Amendment of the Contract

Any changes to the provisions of this Contract shall be in the form of an Amendment. No provision of this Contract may be amended unless such Amendment is approved as to form by the City Attorney and executed in writing by authorized representatives of the Parties. If the requirements for Amendment of this Contract as described in this section are not satisfied in full, then such Amendments automatically will be deemed null, void, invalid, non-binding, and of no legal force or effect. The City reserves the right to make administrative changes to the Contract unilaterally, such as extending option years and increasing compensation. An administrative change means a written Contract change that does not affect the substantive rights of the Parties.

Page | 4

4. Respond to questions received up to November 25, 2025 for this RFP in the table below.

No. QUESTION AND ANSWER

QUESTION:

Currently there are two OMFs that serve Portland Streetcar Inc current operations. Please confirm if the warranty service for the Streetcars will be performed in these OMFs. Are there any plans to build any new OMF, in addition to those two, for the warranty & maintenance activities of the new Streetcars to be procured?

Reference: Attachment D – Sample Contract pg 37 of 56 Section 7. Warranty

ANSWER:

Warranty service will be performed in the current OMF

Please direct all questions and concerns to Kristina Kolata, Senior Procurement Specialist at 971-509-0713.

End of Addendum bt :kmk