This is a Construction Risk Assessment and Exposure Control Checklist for Project 667-26-111 Abate Central Chase, dated September 26, 2025. The document identifies hazards, required control measures, and inspection responsibilities for abatement construction work at a VA facility. Key hazards with required controls include asbestos abatement with negative air exhaust to outside, maintenance of Safety Data Sheets for chemicals, negative air machine operation with filters exhausted outside, respiratory protection (P100 respirator) as needed, and daily waste removal in covered carts using freight elevators without placement in VA dumpsters. Security requirements mandate contractor ID badges at all times, off-site or Stoner parking, and material storage in assigned rooms. Work is restricted to normal business hours on weekdays and daytime weekend hours, with night work requiring Contracting Officer Representative (COR) coordination.
Additional control measures address infection control through dust suppression via cover carts, walk-off mats, routine corridor and elevator lobby mopping during demolition, fire protection via fire caulking of penetrations and contractor-supplied fire extinguishers, electrical safety through lockout-tagout procedures coordinated with VA electrical staff, and hot work requiring daily permit opening and closing with COR coordination. Fall protection requires tie-offs when working in the chase with coordinated tie-off points. Inspection responsibility assignments specify daily (D), weekly (W), and as-needed (AN) frequencies for Construction Safety Officer, Infection Control, Safety Specialist, GEMS, and Safety Officer roles. The checklist was approved by Project Manager/M&O/COR/CSO Thomas Comb, digitally signed on September 26, 2025.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25626R0047 0003.pdf | ||
| 36C25626R0047 0002.docx | DOCX document | |
| Attachment No. 1 Piping Asbestos Survey.pdf | ||
| Attachment No. 2 Pre-bid Conference Sign-in Sheet.pdf | ||
| Attachment No. 3 WD LA20260031.pdf | ||
| 36C25626R0047 0002.pdf | ||
| 36C25626R0047 0001.pdf | ||
| 36C25626R0047 EXHIBIT C.docx | DOCX document | |
| Abate Central Chase - 13 - ICRA.pdf | ||
| 36C25626R0047 EXHIBIT B.docx | DOCX document | |
| 36C25626R0047 EXHIBIT D.docx | DOCX document | |
| 36C25626R0047.pdf | ||
| Abate Central Chase - 1- SOW.pdf | ||
| WD LA20260031 01022026.pdf | ||
| Abate Chase - FY26 - Final Drawings.pdf | ||
| Abate Chase - FY26 - IFC Specs - Updated.pdf | ||
| Abate Central Chase - 14 - Class II Precautions.pdf | ||
| 36C25626R0047 EXHIBIT A.docx | DOCX document | |
| 36C25626R0047 EXHIBIT E.docx | DOCX document | |
| 36C25626R0047 EXHIBIT F.docx | DOCX document |
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Construction Risk Assessment and Exposure Control Checklist
Project: 667-26-111 Abate Central Chase Date: 09/26/2025
Hazard Concern (Y/N?)
Control Measure Remarks
Security Issues Site Security Y Contractor to keep work area secure Identification of Contractors Y Every contractor to obtain ID and wear ID at all times Appropriate parking Y Off Site or utilize parking at Stoner Storage of Materials Y Contractor to secure material in assigned room Change of locks? Access to site Y Traffic Control N Hours of Work Y Normal business hours during weekday and daytime weekend hours for majority of work. Coordinate night work with COR.
IH Issues/GEMS/NEPA Asbestos Y Per contract Neg Air exhaust to outside Haz Com: Chemicals used/SDS Required Y Contractor to maintain SDS Sheets Spills N Monitor, seal any floor penetrations Air Pressure Relationships-Vapors/Fumes Y Contractor to maintain negative pressure within construction area.
Contractor required to install an appropriate magnehelic gauge to identify pressure within construction area. Gauge must be visible outside of construction area
Lead Paint N Respiratory Protection Y If a specific activity requires it. P100
Respirator - Abatement Waste disposal Y Must remove daily in clean covered carts. Use freight elevators as needed. Report waste diversion monthly.
Do not put in VA dumpster at Back Dock.
Recycling Y As appropriate.
NEPA (See NEPA Compliance Checklist) N
Infection Control Issues (see ICRA) Dust Y Maintain cover carts, walk-off mats, and negative air. Routinely mop corridor and elevator lobby during demolition phase Proximity of air intakes N Proximity of patients Y Water leaks/Mold/Mildew N Negative Air Y Negative air machines with filter Exhaust to outside, replace filters when dirty Risk of TB transmission to contractors N Will not be working in a high-risk patient area.
Potential for potable water contamination N
Patient Safety Issues
Hazard Concern (Y/N?)
Control Measure Remarks
Access to construction site by patients Y Contractor to keep work area secure. Storeroom door lock w/ door closer
Engineering Issues Utility Interruption Y Coordinate w/ COR and VA staffing Vibration / Noise Y Intermittent & minor Will monitor Electrical Safety Y Contractor to utilize lockout tagout controls. Coordinate w/ VA Electrical Staff Welding/Cutting – Hot Work Y Coordinate all HOT work with the COR. Open/Close permits daily.
Frequency of Inspections Y Superintendent present at all times during work. 30hr
OSHA
Construction Safety Team Weekly Rounds.
Critical Barriers N Coordination with staff in vicinity Y All employee notification and department leaders notifications Contractor to notify COR weeks in advance
Fire Protection Issues Penetrations Y Fire Caulk Smoking N Absolutely not allowed.
ILSM (see ILSM Evaluation) Y Ref to ILSM. Contractor to provide fire extinguisher inside construction areas.
Fire watch Y Actions taken by hospital to facilitate HOT Work Burn
Permit
Disruption to fire protection systems Y Deactivate smoke detectors, tape and bag during dust producing work elements
Coordinate w/ VA fire safety
Safety Issues Trenching/Shoring N Scaffolding N Tool safety Y Follow manufacture guidance on proposed tool usage Contractor to secure PPE Y As work activity requires. Cloth mask or face covering requires in all
VA occupied spaces during COVID epidemic
Cranes N Fall Protection Y Tie off when in chase Coordinate Tie-off points with safety Confined space N Hand and Power tools Y As required. Follow manufacture guidance on proposed tool usage.
Emergency Response to/from site Y Educate staff on access to & from site.
Signage Y Identify “Construction Area” and ensure all required signs are displayed
LOTO Y Electrical work, coordinate with COR. Must meet requirements of OSHA standards.
EMS Issues Pest control within construction areas N No food in work area, remove debris daily.
Dust Control Y Walk off mats as required. Mop corridor/elevator lobby when needed Waste Disposal Y Remove daily in covered carts.
Specialized Training Requirements
Team Members to Conduct Inspections: D=Daily W=Weekly AN=As needed O=Other
Construction Safety Officer D W AN Infection Control D W AN Safety Spec D W AN GEMS D W AN Safety Officer D W AN
Approval Signatures:
Project Mgr./M&O/COR/CSO
Patient Safety
Chief Engineer/Facility Safety Officer
GEM’s (if applicable)
Infection Prevention (if no ICRA)
Safety Manager
VHASHRCombT Highlight
| 2025-09-26T09:41:30-0500 | |
| THOMAS COMB |
File details come from the government source that posted it. Updated .