Abate Central Chase - 1- SOW.pdf

PDF 269 KB Posted

Attached to
Z1DA--667-26-111 CON Abate Central Chase & Replace Fire Main
Solicitation number
36C25626R0047
Issued by

About this file

Summary: Statement of Work – Abate Central Chase/Replace Fire Main

This Statement of Work describes the scope, requirements, and phasing for asbestos abatement and fire main replacement at Overton Brooks VAMC (Project No. 667-26-111). The contractor must remove all asbestos-containing material (ACM) from the central pipe chase spanning the sub-basement through the 12th floor of Building 1, and replace the existing 6-inch fire sprinkler standpipe system from the 1st to 12th floor with new control valves at each floor, approved fire-rated cabinet enclosures or access panels, and fire-rated chase access doors. All chase penetrations must be sealed per NFPA requirements, and abandoned systems must be identified, removed, capped, or terminated. The work includes re-insulation of all pipes following asbestos abatement. The contractor must complete all work within 200 days from the Notice to Proceed and is responsible for attending a mandatory Pre-Bid Site visit to verify existing conditions and take measurements and photographs.

Critical operational requirements include maintaining negative air pressure of -0.02 inches of water for the entire chase throughout the contract duration, strict infection control compliance with the Infection Control Risk Assessment (ICRA), and comprehensive dust control during demolition, construction, and hauling. Work must be phased across seven phases, processing two floors at a time from top to bottom. Noise-intensive or odorous work must occur after hours or on weekends, and utility outages require two-week advance written notification to the Contracting Officer's Representative (COR). The contractor bears sole responsibility for protecting adjacent hospital areas and repairing any damage at no additional cost. All material deliveries and waste removal must be coordinated with the COR; dumpsters must be emptied immediately when full with no debris piling above container edges. Final deliverables include pre-final and final inspections, clearance air monitoring results following asbestos abatement, and electronic submittals with completed VA transmittal sheets. C&A requirements and a Security Accreditation Package are not required for this project.

View the file

Other files

File Type Posted
36C25626R0047 0003.pdf PDF
36C25626R0047 0002.docx DOCX document
Attachment No. 1 Piping Asbestos Survey.pdf PDF
Attachment No. 2 Pre-bid Conference Sign-in Sheet.pdf PDF
Attachment No. 3 WD LA20260031.pdf PDF
36C25626R0047 0002.pdf PDF
36C25626R0047 0001.pdf PDF
Abate Central Chase - 13 - ICRA.pdf PDF
36C25626R0047 EXHIBIT B.docx DOCX document
36C25626R0047 EXHIBIT D.docx DOCX document
36C25626R0047 EXHIBIT C.docx DOCX document
36C25626R0047.pdf PDF
Abate Central Chase - 8 - CRA.pdf PDF
WD LA20260031 01022026.pdf PDF
Abate Chase - FY26 - Final Drawings.pdf PDF
Abate Chase - FY26 - IFC Specs - Updated.pdf PDF
Abate Central Chase - 14 - Class II Precautions.pdf PDF
36C25626R0047 EXHIBIT A.docx DOCX document
36C25626R0047 EXHIBIT E.docx DOCX document
36C25626R0047 EXHIBIT F.docx DOCX document
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Abate Central Chase/Replace Fire Main Project No. 667-26-111

SCOPE OF WORK (SOW):

Overton Brooks VAMC has a requirement to remove all the asbestos in the central pipe chase and to replace the fire main riser in the main hospital, Building 1. The central pipe chase and fire main traverse through all floors of the hospital. This project will remove friable asbestos-containing material within the main central chase of the hospital. Asbestos-containing material (ACM) is being removed to allow for the facilities primary fire main risers to be replaced. New fire main risers will be installed.

Piping in the central chase will be re insulated. Project will require a multi-phase process to prevent asbestos related exposure and to allow for sampling and asbestos abatement. New fire main risers will need to be installed prior to removal of existing ones.

The C&A requirements do not apply, and that a Security Accreditation Package is not required.

PERIOD OF PERFORMANCE:

The Contractor shall complete the work 200 Days from the issuance of Notice to Proceed.

CONTRACTOR SITE VISIT AND FIELD VERIFICATION PRIOR TO BIDDING:

Contractor shall be responsible for attending the Pre-Bid Site visit prior to bidding to verify all existing conditions and take any necessary measurements and photos required to adequately bid the project. If the contractor chooses not to attend the Pre-Bid Site visit, the contractor may submit their bid at their own risk.

INFECTION CONTROL DURING CONSTRUCTION:

Contractor shall follow and comply with the established Infection Control Risk Assessment (ICRA) specific for numerous project sites. Contractor is responsible for dust control during demolition, during construction, and during hauling operations. Contractor shall always maintain negative air pressure of -0.02 for the entire chase for the duration of the contract. The chase is a continuous space spanning the length of the hospital vertically (sub-basement through the 12th floor).

DEMOLITION:

Contractor shall protect all adjacent areas of the hospital, especially windows and doors during all operations. Repairing any damage shall be the sole responsibility of the contractor at no additional cost to the government. If any damage is noticed prior to starting work, which may be misconstrued as damage caused by the contractor, the COR shall be notified immediately, and the damage shall be documented as existing conditions.

NEW WORK:

New work includes, but is not limited to:

1. All asbestos-containing material in this scope of work shall be abated and pipes re-insulated.

2. Existing 6” Fire Sprinkler Standpipe system shall be replaced from the 1st floor to the 12th floor and to the control valves for each floor.

3. New system shall include, but not limited to, new control valves at each floor, approved fire cabinet enclosure or with an access panel at each floor (fire rated).

4. All chase penetrations or existing breeches are to be sealed per NFPA requirements.

5. New Fire rated chase access doors are to be installed at each floor.

6. Any items or systems determined to be abandoned or no longer required shall be identified to be removed and capped or terminated. PHASING, NOISE, SMELLS, AND AFTER-HOURS WORK:

PHASING IS LIMITED TO TWO FLOORS AT A TIME, WORKING FROM THE TOP FLOOR DOWN

PHASE 1: TWELFTH AND ELEVENTH FLOORS

PHASE 2: TENTH AND NINTH FLOORS

PHASE 3: EIGHTH AND SEVENTH FLOORS

PHASE 4: SIXTH AND FIFTH FLOORS

PHASE 5: FOURTH AND THIRD FLOORS

PHASE 6: SECOND AND FIRST FLOORS

PHASE 7: BASEMENT AND SUB-BASEMENT FLOORS

The areas to be renovated will likely be occupied during construction; therefore, adequate scheduling shall be coordinated with the COR. Work resulting in extensive noise or odor, shall be performed after hours or on weekends. Any required utility outages shall be scheduled at the convenience of the hospital and potentially require after-hours work or on weekends. Any required outages shall also require a written two-week notification to the COR prior to any outages.

DELIVERIES:

Contractor shall coordinate all materials and equipment deliveries, storage, and handling requirements with the COR and use only approved drop-off locations. Contractor shall coordinate all activities with the COR and include clearance air monitoring results following asbestos abatement.

FINAL CLEAN, PRE-FINAL AND FINAL INSPECTIONS:

Once all work has been completed, the Contractor shall adequately clean the project sites prior to a Pre-Final Inspection. Upon completion of the Pre-Final punch list items, the contractor shall request a Final Inspection. Each of these inspections will be scheduled at the convenience of the hospital.

SUBMITTALS:

Submit an electronic copy to the COR and each copy shall have a completed VA transmittal sheet attached.

Contractor shall provide submittal as detailed in the specifications and samples of all finishes showing the full range of available colors and options to be selected by the VA-ID and COR.

ADDITIONAL GUIDANCE:

• Contractor shall remove and dispose of waste daily in accordance with all legal and VA requirements. Dumpsters shall be emptied immediately once full. No debris shall be placed around the dumpster or piled/stacked above the top edge of the dumpster walls.

AREA OF WORK

CENTRAL CHASE

SCOPE OF WORK (SOW):
The C&A requirements do not apply, and that a Security Accreditation Package is not required.
CONTRACTOR SITE VISIT AND FIELD VERIFICATION PRIOR TO BIDDING:
INFECTION CONTROL DURING CONSTRUCTION:
DEMOLITION:
NEW WORK:
DELIVERIES:
FINAL CLEAN, PRE-FINAL AND FINAL INSPECTIONS:
SUBMITTALS: