This is an Infection Prevention & Control Construction Risk Assessment (ICRA) form for the Overton Brooks Veterans Affairs Medical Center (VAMC) for the project "Abate Central Chase Replace Fire Main 667-18-111," dated September 25, 2025, and signed by Carol Phillips, Infection Prevention Officer.

The assessment determines infection control precautions required for construction activities based on two primary factors: construction project type and affected patient risk groups. The project has been classified as TYPE B (small scale, short duration activities creating minimal dust), specifically noting that cutting through plaster walls in hallway is required. The affected patient risk group is identified as HIGH Risk, which includes areas such as Emergency Rooms, Laboratories, Medical Units, Outpatient Surgery, Pharmacy, Surgical Units, and Sterile Supply storage/distribution. Using the IC Matrix that correlates construction type with patient risk, the assessment determines that Class II/II infection control precautions are required. This classification indicates the need for moderate infection control measures appropriate for a small-scale construction project in a high-risk patient care area, ensuring that dust migration can be controlled and patient safety is maintained during the fire main replacement work in the central chase space.

View the file

Other files

File Type Posted
36C25626R0047 0003.pdf PDF
36C25626R0047 0002.docx DOCX document
Attachment No. 1 Piping Asbestos Survey.pdf PDF
Attachment No. 2 Pre-bid Conference Sign-in Sheet.pdf PDF
Attachment No. 3 WD LA20260031.pdf PDF
36C25626R0047 0002.pdf PDF
36C25626R0047 0001.pdf PDF
36C25626R0047 EXHIBIT B.docx DOCX document
36C25626R0047 EXHIBIT D.docx DOCX document
36C25626R0047 EXHIBIT C.docx DOCX document
36C25626R0047.pdf PDF
Abate Central Chase - 1- SOW.pdf PDF
Abate Central Chase - 8 - CRA.pdf PDF
WD LA20260031 01022026.pdf PDF
Abate Chase - FY26 - Final Drawings.pdf PDF
Abate Chase - FY26 - IFC Specs - Updated.pdf PDF
Abate Central Chase - 14 - Class II Precautions.pdf PDF
36C25626R0047 EXHIBIT A.docx DOCX document
36C25626R0047 EXHIBIT E.docx DOCX document
36C25626R0047 EXHIBIT F.docx DOCX document
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overton Brooks VAMC

Infection Prevention & Control Construction Risk Assessment (ICRA)

Project: Abate Central Chase Replace Fire Main 667-18-111 Date: 09/25/2025

STEP ONE: CIRCLE the Type of Construction Project based on scope and expected activity (Type A-D)

TYPE

A

Inspection and Non-Invasive Activities. Includes, but is not limited to:

▪ removal of ceiling tiles for visual inspection only, e.g., limited to 1 tile per 50 square feet

▪ painting (but not sanding)

▪ wallcovering, electrical trim work, minor plumbing, activities which do not generate dust or require cutting of walls or access to ceilings other than for visual inspection.

TYPE

B

Small scale, short duration activities which create minimal dust Includes, but is not limited to:

▪ installation of telephone and computer cabling

▪ access to chase spaces

▪ cutting of walls or ceiling where dust migration can be controlled.

▪ Project Specific: cutting through plaster walls in hallway required

TYPE

C

Work generates a moderate/high level of dust or requires demolition/removal of any fixed building components or assemblies Includes, but is not limited to:

▪ sanding of walls for painting or wall covering

▪ removal of floorcoverings, ceiling tiles and casework; new wall construction

▪ minor duct work or electrical work above ceilings

▪ major cabling activities

▪ any activity which cannot be completed within a single work shift.

TYPE

D

Major demolition and construction projects Includes, but is not limited to:

▪ activities which require consecutive work shifts

▪ requires heavy demolition, removal of a complete cabling system, or excavation

▪ new construction.

STEP TWO: CIRCLE the affected Patient Risk Groups. If more than one risk group will be affected, select the higher risk group.

Low Risk Medium Risk High Risk Highest Risk

▪ Office areas

▪ Kitchen storage area

▪ Public access, hallways, elevator

Lobby

▪ Non-clinical vacated engineering space

▪ Cardiology

▪ Echocardiography

▪ Endoscopy

▪ Nuclear Medicine

▪ Physical Therapy

▪ Radiology/MRI

▪ Respiratory

Therapy

▪ Kitchen – food preparation area

▪ Step Down Unit

▪ Emergency Room

▪ Laboratories (specimen)

▪ Medical Units

▪ Outpatient Surgery

▪ Pharmacy

▪ Post Anesthesia Care Unit

▪ Surgical Units

▪ Minor Procedure Rooms

▪ Sterile Supply storage/distribution

▪ Immunocompromised patient care areas

▪ Cardiac Cath Lab

▪ Sterile Processing Service

▪ Preparation Area

▪ Decontamination Area

▪ Intensive Care Unit

▪ Negative pressure isolation rooms

▪ Oncology

▪ Operating rooms

STEP THREE: Using the IC Matrix CIRCLE the Class of Precautions as determined by Construction Type and Patient Risk

Construction Project Type

Patient Risk Group TYPE A TYPE B TYPE C TYPE D

IC

M a tr ix LOW Risk Group I II II III/IV

MEDIUM Risk Group I II III IV

HIGH Risk Group I II III/IV IV

HIGHEST Risk Group II III/IV III/IV IV