A5- SOW BKTZ192002 Sustain Steel Structures Basewide.pdf
PDF 86 KB Posted
- Attached to
- Repair Restrooms and Sustain Steel Structures
- Solicitation number
- W50S97-24-B-0004
- Issued by
-
Department of the Army National Guard
About this file
This document is a Statement of Work (SOW) for a federal construction contract to sustain steel structures at the 118th Wing in Nashville, Tennessee. The work includes replacing fasteners and preparing, cleaning, priming, and painting approximately 13,400 square feet of steel structures. The performance period is 90 calendar days. The contractor will be responsible for obtaining necessary permits, verifying measurements, submitting project submittals, performing material testing, and site cleanup and debris removal.
The related federal contract opportunity is a solicitation to award a single firm fixed-price contract for services to repair steel support structures and restrooms at Berry Field Air National Guard Base in Nashville, Tennessee. The contract duration is 180 days after notice to proceed. The contract is set aside for small businesses, with a NAICS code of 236220 and a size standard of $45,000,000. A pre-bid conference is scheduled for August 30, 2024, and the bid opening date is September 15, 2024. The solicitation includes a base bid to repair steel structures and an option to sustain steel structures basewide.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
118th Wing SECTION 01000
Nashville, Tennessee Statement of Work
BKTZ 192002 6 September 2023
STATEMENT OF WORK
SUSTAIN STEEL STRUCTURES
BERRY FIELD, NASHVILLE, TENNESSEE
1) GENERAL
a) The work covered by this Statement of Work (SOW) consists of furnishing all labor, equipment, and materials to replace fasteners (for example: nuts, etc.) and prepare, clean, prime, paint steel structures in accordance with this written statement of work, all construction plans, specifications, and the building codes. The work location is the 118th
Wing, Nashville, Tennessee. Contractor will be fully responsible for compliance with all base, local, state, and federal laws and regulations that apply to include environmental and occupational safety.
2) PERFORMANCE PERIOD
a) The performance period for this project is 90 calendar days.
3) SCOPE OF WORK
a) Contractor will perform all work as described herein and as shown on drawings for project BKTZ192002, Sustain Steel Structures Basewide. Work includes but is not limited to the following items.
1. CLIN 0001 – Base Bid: Replace fasteners and prepare, clean, prime, and paint approximately 13,400 square feet steel structures
a. Replace fasteners per specifications.
b. Paint fasteners prior to installation
c. Prepare, clean, prime, and paint steel structures per specifications
d. Two coats of primer and one coat epoxy paint finish on all surfaces
e. Paint color to match existing.
f. See plans and specifications for full description of work.
g. Surface square footage for BKTZ192002: approximately 13,400 square feet.
Provided measurements should not be used to order materials. Contractor must perform own measurements to fulfill requirements as listed in this SOW, project specifications, and drawings.
b) Contract Requirements
1. The contractor will adhere to all contract requirements in the solicitation and subsequent contract or delivery order.
BKTZ 192002 6 September 2023
2. In addition to those items in the solicitation/contract, the contractor will also be responsible to:
a. Obtain all dig permits, crane permits, or any other permits prior to starting construction.
b. Verify all field and plan measurements and notify the contracting officer’s representative (COR) of any discrepancies.
c. Prepare project site for construction by placing adequate signage and other devices indicating construction zone for vehicular traffic and pedestrians.
d. Submit all project submittals to the COR for approval prior to the manufacture or placement of any construction materials.
e. Perform all material testing as required by specifications and building code.
f. Perform site finishing and cleanup to include submit dust/debris plan and cleaning plan that describes measures to prevent the entrance of dust/debris in the areas where work is to be performed.
g. Remove all work related debris and dispose of it off the base property upon completion of project.
3. Contractor Manpower Reporting
a. The contractor will report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for
Air Force collection site. The contractor is required to completely fill in all required data fields using the following web address:
https://afcmra.hqda.pentagon.mil/
b. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through
September 30. While inputs may be reported any time during the FY, all data must be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk at http://www.ecmra.mil/.
c. Unit Identification Code (UIC) for the Requiring Activity: L41CFTRM
d. Issuing Office DoDAAC: W50S97
4) REFERENCES
In general, all technical specifications are provided within the Construction Documents. In the event any project element is not covered in the specifications provided, the contractor will refer to the Specification Hierarchy for direction related to the element.
5) SPECIFICATION HIERARCHY
a) The specification hierarchy is the collection of technical specifications to be used for all projects. The contractor should refer to the specifications provided in the Construction
Documents first before moving to the next technical specification listed in the https://afcmra.hqda.pentagon.mil/ http://www.ecmra.mil/
BKTZ 192002 6 September 2023 specification hierarchy. The hierarchy is listed in the order of precedence (i.e. “1” supersedes “2”). The hierarchy is as follows:
1. Specifications provided with Construction Documents
a. Technical Specifications
b. Construction Drawings
2. For MATOC contracts, the 118th Base Design Standards
3. UFC 3-190-06 Protective Coatings and Paints dated 1 March 2021. Unified Facility
Criteria available on www.wbdg.org.
4.
6) SECURITY REQUIREMENTS
Access and General Protection/Security Policy and Procedures. Contractor to complete
Antiterrorism Level 1 Training and provide documentation of completion upon request. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor will comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local
Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection
Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
'End of Statement of Work’ http://www.wbdg.org/