This is a Quality Assurance Surveillance Plan (QASP) for a contract providing Facilities Environmental Compliance, Planning, and Resiliency Technical Support, effective April 20, 2026.

The QASP establishes procedures for the Contracting Officer's Representatives (CORs) to monitor contractor performance against standards defined in the Performance Work Statement (PWS). The Contracting Officer (KO) maintains overall contract compliance responsibility and designates one primary COR for performance management, with additional task order-specific CORs serving as technical inspectors. CORs are responsible for continuous technical oversight, maintaining Quality Assurance files, documenting actual performance, reporting performance problems to the KO, and providing annual performance assessments for past performance documentation. The plan requires simplified surveillance methods including routine inspection of all deliverables, review of deliverables with no required re-performance or re-work at least 80% of the time, and random monitoring by designated inspectors. Performance standards are documented using a monitoring form that captures surveillance method, surveillance level (monthly, quarterly, or as needed), percentage of items sampled, observed performance measurement rates, and narrative assessments.

Five primary performance requirements are specified: (1) provision of trained, professional staff filled 95% of the time with vacancies not exceeding one month; (2) 100% compliance with environmental permits through data collection and recordkeeping; (3) response with qualified personnel within four hours for environmental releases or CBRN incidents; (4) support for resiliency programs through data collection and analysis; and (5) support for planning initiatives through data collection and recordkeeping. If contractor performance fails to meet minimum requirements, the contractor may be required to develop a corrective action plan demonstrating how and when performance will be brought to required levels.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Quality Assurance Surveillance Plan (QASP)

Facilities Environmental Compliance, Planning, and Resiliency Technical Support

April 20, 2026

1 Introduction

1.1 Purpose

2 Roles and Responsibilities

2.1 Contracting Officer (KO)

2.2 Contracting Officer's Representative (COR)

3 Identification of Performance Standards/Quality Levels

4 Methods and Monitoring Performance

4.1 Surveillance Techniques

5 Quality Assurance Documentation

5.1 Monitoring Form

6 Anaysis of Quality Assurance Assessment

Attachment 1 - Performance Requirement Summary

Attachment 2 - Sample Quality Assurance Monitoring Form

Quality Assurance Surveillance Plan (QASP)

1 Introduction

This Quality Assurance Surveillance Plan (QASP) is pursuant to the requirements listed in the

Performance Work Statement (PWS) entitled Facilities Environmental Compliance, Planning, and Resiliency Technical Support. This plan sets forth the procedures and guidelines the

Contracting Officer’s Representatives (CORs) for each task order will use in ensuring the required performance standards or services levels are achieved by the contractor.

1.1 Purpose

The purpose of the QASP is to describe the systematic methods used to monitor performance and to identify the required documentation and the resources to be employed. The QASP provides a means for evaluating whether the contractor is meeting the performance standards/quality levels identified in the PWS and the contractor’s quality control plan (QCP), and to ensure that the government pays only for the level of services received. The government may provide a copy of the QASP to the contractor to facilitate open communication. In addition, the QASP should recognize that unforeseen or uncontrollable circumstances might occur that are outside the control of the contractor. Bottom line, the QASP should ensure early identification and resolution of performance issues to minimize impact on mission performance.

2 Roles and Responsibilities

2.1 Contracting Officer (KO)

The KO is responsible for monitoring contract compliance, contract administration, and cost control; and for resolving any differences between the observations documented by the task order COR and the contractor. The KO will designate one COR for the overall contract who will serve as the government authority for performance management. Additional task order specific

CORs will serve as technical inspectors to evaluate the contractor’s performance, and must be identified and designated by the KO.

2.2 Contracting Officer's Representative (COR)

The COR is responsible for providing continuous technical oversight of the contractor's performance. The COR uses the QASP to conduct the oversight/surveillance process. The COR shall keep a Quality Assurance file that accurately documents the contractor's actual performance. The purpose is to ensure that the contractor meets the performance standards contained in the contract. The COR is responsible for reporting early identification of performance problems to the KO. The COR is required to provide an annual performance assessment to the KO which will be used in documenting past performance. The QASP is the primary tool for documenting contractor performance. The COR is not empowered to make any contractual commitments or to authorize any contractual change on the Government's behalf.

3 Identification of Performance Standards and Quality Levels

The required performance standards and/or quality levels are included in the PWS and in

Technical Exhibit 1, “Performance Requirements Summary.”

4 Methods and Monitoring Performance

4.1 Surveillance Techniques

In an effort to minimize the performance management burden, simplified surveillance methods shall be used by the government to evaluate contractor performance when appropriate. The primary methods of surveillance:

• Routine Inspection – COR and/or the COR’s designee will inspect all deliverables.

• Routine Inspection – COR shall review deliverables/performance with no required re-performance or re-work at least 80% of the time.

• Random monitoring, which shall be performed by the COR designated inspector.

5 Quality Assurance Documentation

5.1 Monitoring Forms

The Government’s QA surveillance, accomplished by the COR, will be reported using the monitoring form in Attachments 2 of this document. The form, when completed, will document the Government’s assessment of the contractor’s performance under the contract to ensure that the required results quality levels are being achieved.

5.1.1 The COR will retain a copy of all completed QA surveillance forms.

6 ANALYSIS OF QUALITY ASSURANCE ASSESSMENT

6.1 Determining Performance

The Government shall use the monitoring methods cited to determine whether the performance standards and service levels have been met. If the contractor has not met the minimum requirements, it may be asked to develop a corrective action plan to show how and by what date it intends to bring performance up to the required levels.

Attachment 1 – Performance Requirement Summary

Performance Objective Standard Performance

Threshold

Method of

Surveillance

PRS # 1

The Contractor shall provide trained, professional staff in accordance with contract requirements.

As defined in the PWS under 1.13.3

Personnel

Matters.

Staff position is filled by an acceptable specialist 95% of the time or greater. Time not to exceed 1 month of vacancy at any time.

Vacant positions will be notified to the

COR immediately

PRS # 2

As specified within task order requirements, the

Contractor shall meet the technical requirements for compliance with environmental permits.

Compliance requirement specified within permits issued by state and local authorities

Data collection, analysis, and recordkeeping are performed to ensure

100% compliance with permits

100% of the time meet permit requirements

PRS # 3

As specified within task order requirements, the

Contractor shall support

WHS readiness to respond to an environmental release or

CBRN incident.

CBRN

Response and

Recovery

Plans; Spill

Prevention and

Response

Plans

Response with qualified personnel within

4 hours of incident occurring

Direct observation by

WHS response personnel

PRS # 4

As specified within task order requirements, the

Contractor shall support resiliency programs for

WHS

As defined in the

PWS under 1.13.3

– Personnel

Matters

Data collection, analysis, and recordkeeping are performed as needed

Direct observation by

WHS response personnel

PRS # 5

As specified within task order requirements, the

Contractor shall support planning initiatives for WHS

As defined in the PWS under

1.13.3 –

Personnel

Matters

Data collection, analysis, and recordkeeping are performed as needed

Direct observation by

WHS response personnel

ATTACHMENT 2 – SAMPLE

QUALITY ASSURANCE MONITORING FORM

SERVICE or STANDARD: _________________________________________________________________

SURVEY PERIOD:

SURVEILLANCE METHOD (Check):

Random Sampling 100% Inspection Periodic Inspection

LEVEL OF SURVEILLANCE (Check):

Monthly Quarterly As needed

PERCENTAGE OF ITEMS SAMPLED DURING SURVEY PERIOD: ______ %

ANALYSIS OF RESULTS:

Observed Service Provider Performance Measurement Rate: ______%

Service Provider’s Performance (Check): Meets Standards

Does Not Meet Standards

Narrative of Performance During Survey Period: ______________________________________________