A2 Thule AB Fuel Hoses SOW (23 Oct 20).pdf
PDF 476 KB Posted
- Solicitation number
- FA2523-21-Q-0001
About this file
This statement of work and related solicitation seek two new floating fuel hose and reel assemblies for delivery to Thule Air Base in Greenland. The statement of work provides specifications for 600-foot long floating hoses rated for 250 psi working pressure and compatible with the base's existing fittings. It also specifies reel drums and drive frames capable of accommodating the 600-foot hoses with hydraulic motor drives and power units. The solicitation requires delivery of the assembled hoses and reels to the Port of Fredericia, Denmark no later than May 15, 2021 and includes freight costs. Questions regarding the solicitation are due by December 18, 2020 with responses required by December 30, 2020. The solicitation is issued by the Department of the Air Force Space Command.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work for: Procure Two Long Length Floating Hoses and Reels for Facility 990, Thule Air Base, Greenland
STATEMENT OF WORK
FOR
PROCURE TWO LONG LENGTH FLOATING HOSES
AND REELS FOR FACILITY 990,
THULE AIR BASE, GREENLAND
Prepared By:
DLA ENERGY EUROPE & AFRICA
with extracts and input from Thule AB, Greenland 821 SPT/CE
PREPARATION DATE: 23 October 2020
REVISION NUMBER: 1.4
1 SCOPE
This effort shall furnish all materials, equipment, labor and personnel necessary to plan, design, manage, procure deliver and receive two (2) sets of new floating hoses, including all necessary fittings, and with their associated hose reels and accessories identified.
The hoses are required to be compatible with the existing hoses and connections that are at the waterfront offloading facility near the Thule Air Base (AB) pier.
All work is to be accomplished IAW the present code requirements, as stated below. A complete and usable product shall be furnished to Government and delivered per the guidance below.
The hose and reel replacements are at/associated with the following facility/Real Property asset: Facility 990 -
Liquid Fuel Off-Shore Unloading Facility
1.1 BACKGROUND
The site uses four (4) tanker offloading hoses to execute the offloading of the annual fuel delivery. The older pair of these hoses (funded for purchase in January 2002) are well beyond their life expectancy and are showing signs of delamination and bulging. Also, the associated hose reels, property that has been in use even prior to the older pair of hoses, no longer have functioning hydraulics and braking, putting the operators in an unsafe situation, and no repair parts are produced for these reels any longer. Two (2) new sets of hoses and reels, with all the necessary fittings, are required to be procured and delivered to Thule AB prior to the next tanker offload in the summer of
2021.
2 REQUIREMENTS
2.1 GENERAL
This effort shall procure and have delivered, to the Port of Fredericia, Denmark, two (2) sets of new floating hoses, including all necessary fittings, with their associated hose reels and accessories. The effort shall provide all materials, labor, equipment, and supervision necessary to deliver, receive and inspect the two (2) new hose and reel assemblies.
Specifications: The hose and reel assemblies capable of delivery JP-8 fuel from tanker ship to the pipeline manifold in an arctic environment of Thule, Air Base and of will consist of the following items:
1. Quantity of 2 each – Fuel Oil Reeling System containing:
• 8 inch x 600 foot (8” x 600’) Long length floater hose.
o Electrically: Discontinuous. ANSI 150 WN RF. Textile Long Length Hose.
o Soft wall. Inside dia. 205 mm, outside dia. 233 mm, weight in air empty 12.3kg/m, weight in air full of water 46.1kg/m.
o Working pressure of 250 psi or higher, test pressure 450 psi, burst pressure 1200 psi.
o Aromatic resistance up to 50%.
o Flow velocity up to 21 m/s.
o Each assembly includes all necessary fittings, 8" towing slit clamps, 8" couplings, ball valves, 8" towing clamps, 8" seal O-rings, 8" seal back-up rings, 8" camlock adaptors w/valves and
8" towing clamp handling harness.
• Reel drum and drive frame o Refueling hose drum & support frame capable of accommodating 8-inch x 600’ bunker hose o Hydraulic motor drive unit c/w failsafe brake o Electro/hydraulic power unit (7.5 kW - 10 HP) o Direct-on-line electric starter unit (7.5 kW - 10 HP) o Electrical Supply Main 208 volts 3 phase 60 Hz o Hydraulic Piping: 316L Stainless Steel – Metric o Hydraulic Fittings 316L Stainless Steel – Double Ferrule – Metric
• 208 volt, 3-phase, 60 Hz Hydraulic Power Unit (HPU) should be integrated onto reel with a 10 HP
(7.5 kW) capacity electric motor
• Standard Documentation Pack, Manufacturing Data Book and Factory Pressure Testing Certifications
2. Freight costs must be included to Port of Fredericia, Denmark. All materials must be delivered as one shipment NLT 15 MAY 2021.
The hoses must be assembled onto the associated reels prior to shipping from the manufacturer’s facility to the Port of Fredericia, Denmark. Proper coordination and advance communication must be provided with the government representatives to allow for Factory Acceptance Testing (FAT) and to witness the final assembly/spooling of the hoses onto the reels before they are shipped. Government points of contact will be provided upon contract award. FAT to include as a minimum:
• Reel system light run functional test
• Hydraulic system, hydraulic pressure tested - 1.5 x Max Working Pressure
• Hydraulic system cleaned & flushed to ISO 17/15/12
• Hydraulic system sealed/capped after flushing
• Hose Pressure testing at 1.5 x max working pressure
3. Acceptance is contingent Government representative witnessing satisfactory FAT and equipment arrival at
Port of Fredericia, Denmark certified for ocean transportation in accordance with commercial shipping regulations.
2.2 PROGRAM PLANNING and MANAGEMENT
2.2.1 Permits - The manufacturer shall obtain all applicable work permits and customs forms necessary to deliver the final hose and reel assemblies to the Port of Fredericia, Denmark. The equipment shall be certified for ocean transportation in accordance with commercial shipping regulations. Ocean transportation points of contact will be provided at contract award.
2.3 DELIVERABLES
2.3.1 Language and Measurements - All literature, measurements, and received measurements shall be in
English, and utilize where possible Society of Automotive Engineers (SAE) units of measure. Unit of measure exceptions shall only be accepted for filtering measurements, water chemistry, and equipment literature that was originally written with metric measurements.
2.3.2 Final government acceptance will take place at Port of Fredericia, Demark
2.3.3 Final Records, Warranty and O&M Documentation - No later than 3 weeks after final inspection, deliver final documentation shall be 2 each digital copy in PDF format. These shall be sent to following: 21
CONS/Detachment 1, 821 SPTS/CEP. The manufacturer shall deliver 2 sets of documentation for both hose and reel assemblies to include specification documents and manuals. These shall include as a minimum, but not limited to:
• Hose specifications and technical acceptance documents
• Hose Factory Pressure Testing Certifications
• Hose reel operations and maintenance manuals
• Warranty documents
• O & M manuals:
o O&M manuals shall include:
✓ Major components with manufacturer’s datasheets and information
✓ Manufacturers recommended maintenance actions and schedule/cycle
✓ Manufacturers anticipated life expectancy of the hoses
✓ List of manufacturers recommended spare parts
✓ Test Certificates IAW reference documents
DRAWINGS/PHOTOS:
Old Hose and Reel Sets – Hoses Funded for Purchase in 2002, Reels Predate Hoses
Old Hose Delamination and Bulges – July 2019
Old Hose Delamination and Bulges – July 2019
Statement of Work for: Procure Two Long Length Floating Hoses and Reels for Facility 990, Thule Air Base, Greenland
Statement of Work for: Procure Two Long Length Floating Hoses and Reels for Facility 990, Thule Air Base, Greenland
File details come from the government source that posted it. Updated .