A#1 Bobcat LaPorte Uravan NRD Special Conditions.pdf

PDF 221 KB Posted

Attached to
PKAA, Bobcat LaPorte Uravan NRD Project
Solicitation number
DQ1 PKAA 2026000430 2
Issued by
Morgan County, Colorado

About this file

This is Amendment No. 01 to the special conditions for the Bobcat LaPorte Uravan Natural Resource Damage Project issued by the State of Colorado Department of Natural Resources, Division of Reclamation, Mining and Safety. The amendment clarifies and modifies bid requirements for environmental remediation work at a legacy uranium mine site in Montrose County, approximately 18 miles north of Naturita. Key modifications include updated specifications for Bid Item 7.0 (revegetation materials), with organic fertilizer application increased from 300 to 600 pounds per acre and mulch changed to HH WF Black Diamond Soil Stabilizer pelletized mulch at 2,500 pounds per acre; the addition of a new optional Bid Item 9.0 for geosynthetic clay liner installation (60 linear feet of CETCO Bentomat CL or approved equivalent) along the LaPorte diversion channel; and clarification that backfill from feature 2959 Subs 1 may be used as berm material for Bid Item 4.0. Bid submissions are due by 4:00 p.m. on Tuesday, May 12, 2026, with bid opening on Wednesday, May 13, 2026. The amendment incorporates the Uranium Work Safety Procedures plan into project requirements and mandates daily checks of Montrose County fire restrictions throughout the project duration.

The amendment requires bidders to acknowledge receipt and acceptance by submitting the revised bid schedule and include the newly added List of Equipment Offered Form as a mandatory submission document. Contact information is provided for Brent Hardy at QIS Supply and Kevin Lewellen at Ferguson Waterworks for amendments and material clarifications. The Model Construction Agreement with Federal Provisions has been added for informational purposes only. All other terms and conditions of the original Documented Quote remain in effect except as modified by this amendment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Special Conditions

Bobcat LaPorte Uravan NRDProject

Amendment No. # 01 DQ1 PKAA 2026-0430

May 5, 2026

Thank you for your attendance at the Pre-Bid Meeting. The following clarifications and amendments should be noted and incorporated into the bid documents:

1. The Bid Submittal will be onTuesday May 12by 4:00p.m. The Bid Opening will be onWednesday May 13, 2026.

2. The Uranium Work Safety Procedures plan is included with this amendment to this project and has been added to the Google drive link:

Bobcat_LaPorte_Uravan_NRD_Project

3. All Montrose County fire restrictions must be checked daily and will apply during the project.

4. The backfill source for feature 2959 Subs 1 can be used as berm material if needed for Bid Item 4.0 Hydrologic Controls Bobcat.

5. Clarification for Bid Item 7.0: Choice of organic fertilizer and application rate change from 300 pounds to 600 pounds per acre:

Richlawn Organic fertilizer 3-6-3 or QIS Supply 3-4-3

Mulch changed from weed-free straw mulch to HH WF - Black Diamond Soil Stabilizer pelletized mulch applied at a rate of 2,500 lb per acre.

Contacts for amendments:

https://drive.google.com/drive/folders/1cdeAPtPNKNdyYTwkAr_ucKn1j28AIoR0?usp=sharing

Brent Hardy QIS Supply T: 970.442.6100 M: 208-863-7529 brent.hardy@qissupply.com -www.qissupply.com

Kevin Lewellen - Grand Junction & Western Slope Ferguson Waterworks 970-985-2984 Kevin.Lewellen@ferguson.com www.FergusonWaterworks.com

6. The Bid Schedule attached to the original bid has been replaced with a Revised Bid Schedule attachment named “A#1 Revised Bid Schedule” and includes the changes below:

a. Additional Bid Item 9.0: Geosynthetic Clay LinerNOT GUARANTEED Sixty feet of 15’ wide CETCO Bentomat CL Geosynthetic Clay Liner (GCL) or approved equivalent will be applied as discussed at Prebid and directed by the Project Manager along the LaPorte diversion channel described in Bid Item 5.0.

The liner will be cut into 4 feet wide strips and placed in the channel, with overlap in the direction of water flow. Fifteen feet will be laid over the in-channel subsidence feature and forty-five feet placed adjacent to the end of channel subsidence feature.

7. The List of Equipment Offered Form has been added to this amendment and is attached. This list of equipment is a required document to be included with bid submission.

8. The Model Construction Agreement with Federal Provisions has been added to this amendment for informational use only and is attached.

All terms and conditions of the Documented Quote other than as changed by this amendment remain the same.

Page2of3 http://www.qissupply.com/ mailto:Kevin.Lewellen@ferguson.com https://urldefense.com/v3/__http://www.fergusonwaterworks.com/__;!!PUG2raq7KiCZwBk!bjw-jy7tDhB18pKRmu50eVVAavjkwp7SI7F9B5cgxRQt2jl5TFDKU4t2Qcoxxp23mQgd7uVVJXH1oR9LMJsCAKClc1X0EzXW$

Receipt and acceptance of this amendment shall be acknowledged on the bid schedule and by submitting therevised Bid Schedule.

Page3of3