This document is a technical specification section for Traffic Regulations (Section 01570) that provides comprehensive requirements for managing traffic safety and control during construction projects. The specification details requirements for traffic control, including the mandatory submission of a Traffic Control Plan that must specify signage locations, types of signs, and compliance with the Manual on Uniform Traffic Control Devices (MUTCD) and Colorado Department of Transportation (CDOT) standards. Material requirements include reflectorized signs meeting MUTCD standards and orange safety cones at least 18 inches high that are highly visible in day and night conditions.

The document outlines key execution requirements for public safety, mandating that contractors provide, erect, and maintain all necessary traffic control devices as approved in the Traffic Control Plan and by local authorities. Contractors must maintain traffic flow with minimal obstruction, keep all traffic control devices clean and readable, and remove temporary devices when no longer needed. Notably, there will be no direct payment for these traffic regulation activities, with associated costs expected to be incorporated into the overall contract bid price. The specification applies specifically to work in Fremont County, Colorado, and emphasizes the importance of safe and expeditious movement of traffic through construction zones.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TRAFFIC REGULATIONS

01570-1

PART 1: GENERAL

1.1 SUMMARY

A. Section Includes: Requirements to provide safe and expeditious movement of traffic through constructions zones.

1.2 SUBMITTALS

A. General: Submittals shall be according to Section 01009 - General

Information and Requirements.

B. Traffic Control Plan: Submit one copy for approval. Plan shall include at a minimum the following topics:

1. Specific signage to be used and locations for signs on each side of the entrance to the work location. Signs shall inform the public of the type of work ahead. Signage shall be placed to inform the public of trucks and/or equipment accessing and leaving the work location and onto the county road. Signage to be used shall comply with current MUTCD, and CDOT.

2. Traffic Control requirements, if applicable, for working adjacent to county roads within Fremont County, CO.

PART 2: PRODUCTS

2.1 MATERIALS

A. Signs: Shall have reflectorized sheeting and meet the standards of the current Manual on Uniform Traffic Control Devices for Streets and Highways (MUTCD) for colors, sizes, and shapes.

B. Cones: Cones shall be a minimum of 18 inches high and shall be orange colored and highly visible both in daylight and darkness. Reflectorized material shall have a smooth, sealed outer surface, which will display the same approximate color day and night. Cones shall be capable of remaining upright during normal traffic flow and wind conditions.

PART 3: EXECUTION

3.1 PUBLIC SAFETY

A. Preparation: Provide, erect, and maintain all necessary traffic control devices as on the approved Traffic Control Plan and as required by the State and local authorities having jurisdiction. Mobilization or construction shall not begin until all traffic control persons or devices as approved are in place. Traffic control devices shall remain in place until completion of project or as approved by the Contracting Officer.

3.2 VEHICLE TRAFFIC CONTROL

TRAFFIC REGULATIONS

01570-2

A. Application: Maintain flow of public traffic and conduct operations, to offer the least possible obstruction and inconvenience to public traffic.

1. Maintain the condition, operation, and effectiveness of all traffic control devices throughout their period of use. Remove all temporary traffic control devices when no longer needed.

3.3 ROADWAYS, TEMPORARY AND PERMANENT

A. Maintenance of Traffic Control Devices: Signs and other devices shall be kept clean and readable.

PART 4: MEASUREMENT AND PAYMENT

4.1 METHOD OF MEASUREMENT

A. Units: The work described in this section will not be measured for payment.

4.2 BASIS OF PAYMENT

A. Payment: No direct payment for the work described under this section will be made. Consideration for this item shall be included in the bid price for other items of the Contract.

END OF SECTION