This document is a Site Demolition technical specification (Section 02223) detailing requirements for removing an existing cattleguard and associated infrastructure. The scope of work includes excavating and disposing of the existing cattleguard, including its wings and base, with the option to salvage bases that are in good condition. The Bureau of Land Management (BLM) will transport any salvaged bases away from the site.
Contractor responsibilities include performing a one-call utility notification before digging, placing salvageable materials at a designated onsite location, and supplying equipment and labor to load salvaged items onto a government trailer. Any items not designated for salvage will become the contractor's property and must be legally disposed of. Payment for the demolition work will be made on a lump sum basis, specifically under the pay item "02223(1) Day Use Demolition" with a lump sum payment unit.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SITE DEMOLITION
02223- 1
SECTION 02223
PART 1: GENERAL
1.1 SUMMARY
A. Section Includes: The removal and disposal, and salvage of identified items. Work includes removal of existing Cattleguard including wings and base. Items will be disposed of by contractor. Bases may be salvaged if they are in good condition and will be transported by the BLM away from the site.
PART 2: PRODUCTS
(No products are required in this section.)
PART 3: EXECUTION
3.1 PREPARATION
A. Materials designated for salvage shall be placed onsite at a location designated by the Contracting Officer until removed from the site by the Government. The Contractor shall supply equipment and labor to load the salvaged items onto a Government trailer. The Government shall be responsible for securing the items once loaded.
3.2 DEMOLITION
A. Excavate and dispose of existing cattleguard, wings, and base unless it is determined by the COR that the base is in salvageable condition. The contractor is responsible to do a one-call notification for utilities before digging.
3.3 SALVAGE
A. Placement After Removal: Store items removed as salvage at a location onsite as determined by the Contracting Officer. Place items in a manner that will not cause damage and will allow access for future loading and removal from the worksite by the Government.
3.4 DISPOSAL OF DEBRIS
A. Requirements: Items or debris not designated as salvage for the Government shall become the property of the Contractor. Remove such materials from the site and dispose of in a legal manner.
PART 4: MEASUREMENT AND PAYMENT
4.1 METHOD OF MEASUREMENT
A. Units: Demolition will be measured and paid for on a lump sum basis.
4.2 BASIS OF PAYMENT
A. Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:
02223- 2
Pay Item Pay Unit
02223(1) Day Use Demolition . . . . . . . . . . . . . . . Lump Sum