A04_RPFO_NCA_Vault_Toilet_SOW_Spec_s_revised_4_23_26.pdf
PDF 479 KB Posted
- Attached to
- RPFO-NCA VAULT TOILET AND REMOVAL
- Solicitation number
- 140L1726Q0018
About this file
This is a Statement of Work and Specifications for the Bureau of Land Management (BLM) Albuquerque District Office - Rio Puerco Field Office to procure and install one precast concrete vault toilet building at the NCA Joe Skeen Campground near Grants, New Mexico (coordinates 34.943164°, -107.820487°).
The new single vault toilet building must be 6' 6" x 14' 8" with BARNWOOD wall texture in OATMEAL BUFF color and CEDAR SHAKE roof texture in RICH EARTH color. The structure shall be ADA compliant and include a gabel roof, standard 3068 steel door, wall vent, solar light kit, and solar fan kit. The contractor is responsible for one-way transportation, site preparation, installation, backfill, and recontouring of the new building at the designated location. The contractor must provide all site prep equipment, lifting equipment, and rigging necessary for installation and shall submit detailed offload configuration options at least four weeks prior to delivery. The contractor must also remove and properly dispose of the existing Gunnison model CXT vault toilet building, backfill and recontour that site, and comply with all state and federal laws. The BLM will provide road access for standard semi-trailers and cranes, clear 16 feet of height from tree limbs and power lines, and pump out the existing vault prior to removal. Payment is structured as a single line item covering delivery, site preparation, installation of the new structure, removal and proper disposal of the existing vault, and backfill and recontouring of both sites.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BLM ADO-RPFO Precast Vault Toilet Replacement
Bureau of Land Management
Rio Puerco Field Office
Precast Concrete Vault Toilet Replacement
Statement of Work and Specifications
Bureau of Land Management
Albuquerque District Office - Rio Puerco Field Office
1. Project Information
A. Intent of Project
The Bureau of Land Management (BLM) Albuquerque District Office (ADO) - Rio Puerco Field
Office (RFPO), intends to purchase and install one single-vault precast concrete toilet building. The new building shall match or exceed the size, materials, durability, and functional characteristics of the existing vault toilet buildings currently installed at the NCA recreation site.
This project also includes removal of one existing single-vault toilet building. The Contractor shall transport and install the new building and remove and properly dispose of the existing building in accordance with applicable regulations.
Please refer to the pictures and maps for details. The NCA Joe Skeen Campground can be accessed from Interstate 40 at Exit 89, go south on NM Hwy 117 approximately 11.5 Miles to the campground entrance. BLM ADO-RPFO NCA Vault Toilet Installation and Removal coordinates, near Grants, NM: 34.943164°, -107.820487°
2. New Single Vault Toilet Precast Building
A. Building Specifications
1. 6’ 6” x 14’ 8”, single vault toilet precast building.
2. The building wall texture shall be BARNWOOD, and the roof texture shall be the
CEDAR SHAKE. The building wall color shall be OATMEAL BUFF & roof Color shall be RICH EARTH.
3. ADA compliant
4. One way transportation - installation and set up by contractor.
5. Site Prep and Installation by Contractor
6. Paint touch-up kit, two tone color OATMEAL BUFF & RICH EARTH
7. Gabel Roof
8. Standard 3068 Steel Door
9. Wall Vent
10. Solar Light Kit
11. Solar Fan Kit
B. Requirements
1. The new single vault toilet precast building shall be located within the NCA Joe
Skeen Campground recreation site.
2. The Contractor shall be responsible for site prep, installation, backfill and recontour of the new Single Vault Toilet Precast Building at the designated location set forth by the BLM. (See Map for Details) The contractor shall comply with all State and
Federal Laws during the performance of work.
3. The Contractor shall provide all site prep equipment, all lifting equipment and rigging needed for the installation of the new Single Vault Toilet Precast Building.
4. A minimum of four (4) weeks prior to the delivery of the Single Vault Toilet Precast
Building, the contractor shall provide the BLM with detailed offload configuration options. Work shall consist of providing and installing One (1) Single Vault Toilet
Precast Building and the removal and disposal of one (1) Gunnison model CXT by the contractor.
3. Removal of Existing Single Vault Gunnison Model CXT Building
A. Existing Gunnison Model CXT Building
1. The Contractor shall be responsible for the removal and proper disposal of the existing Gunnison model CXT building as designated by the BLM, as pictured on page 1. (See Map for Details)
2. The Contractor shall backfill and recontour the existing vault.
3. The contractor shall comply with all State and Federal Laws during the performance of work.
4. The Contractor shall provide all excavation, lifting and rigging equipment needed for the removal and disposal of the existing Gunnison model CXT building.
4. Work Provided by Government
A. Description
1. The BLM will provide access/roadway to site so that standard over the road semi and trailer and crane can navigate and park within 2’ of pad.
2. The BLM will clear height of 16’ free from tree limbs and power lines.
3. Existing Gunnison CXT vault will be pumped out by the BLM prior to removal and disposal by contractor.
5. Payment
A. Basis of Payment
Pay Item
Delivery, Site Prep and Installation of
Structure. Removal, proper disposal, and backfill and recontour of existing vault.
B. Work included in Payment
The Bureau of Land Management will consider the following work as paid:
1. Transportation, delivery, site prep, and installation of new single vault toilet to the specified location.
2. Proper removal and disposal of existing Gunnison single vault toilet.
3. Backfill and recontour of removal and installation sites.
Vault to Remove
New Vault toilet location to be determined within campground loop.
File details come from the government source that posted it. Updated .