Project Utility Coordination Form Summary
This is a Project Utility Coordination (PUC) Form prepared by the Massachusetts Department of Transportation (MassDOT) Highway Division for Proposal No. 610544-135966, the Multi-Use Path Construction of Independence Greenway at Route 1 and Interstate 95 in Peabody, Massachusetts (FAP No. CMQ/STP/TAP-0034(034)X). The project involves comprehensive utility relocation and coordination across multiple utility providers including Peabody Municipal Light Plant, First Light, Astound/RCN, Comcast, Verizon, National Grid Gas, MBTA, Keolis, and various municipal departments. The scope encompasses the underground and relocation of electric transmission and distribution lines, fiber optic cables, telecommunications infrastructure, fire alarm systems, gas mains, and water/sewer facilities. The project includes installation of approximately 47-71 utility poles (12 proposed new poles, 8 removals), with detailed staging across multiple phases and tasks requiring coordination of exclusive and concurrent utility operations. The document indicates a revision date of 2/3/2026 and includes detailed specifications for contractor responsibilities regarding enabling work, access preparation, and coordination protocols.
The PUC Form details estimated durations for utility work phases ranging from 2 to 169 work days depending on the task, with advance notification requirements of 7 calendar days for the contractor to provide progress validation and 30 days advance notice-to-proceed for each utility relocation. Key constraints include MBTA access licensing requirements (allowing 9 months for acquisition), seasonal restrictions on gas line installations from November 15 to March 15, and environmental considerations such as avoiding placement of heavy equipment on sewer lines. The contractor is responsible for providing safe and unimpeded access to utilities, including tree removal, clearing, grading, and removal of existing infrastructure. The document notes a betterment on Lowell Street involving 650 feet of gas main relocation with no Force Account reimbursement, and specifies that all costs associated with enabling work are deemed incidental to the project. Critical contacts include the consulting engineer (BSC Group) and multiple MassDOT representatives, with cost sharing and reimbursement provisions established between the contractor and individual utility companies.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A00801-610544.pdf | ||
| 610544 - Plan Holders List 8-18-2026.pdf | ||
| PEABODY-610544-135966-A-1.pdf | ||
| PEABODY-610544-135966-A-4.pdf | ||
| A00860-610544.pdf | ||
| A00830-610544.pdf | ||
| A00811-610544.pdf | ||
| A00881-610544.pdf | ||
| A00844-610544.pdf | ||
| 610544 - Notice to Contractors.pdf | ||
| A00851-610544.pdf | ||
| A00875-610544.pdf | ||
| 610544 Bid Items List.txt | TXT text file | |
| A00802-610544.pdf | ||
| PEABODY-610544-135966-A-3.pdf | ||
| A00861-610544.pdf | ||
| A00810-610544.pdf | ||
| A00864-610544.pdf | ||
| PEABODY-610544-135966-A-2.pdf | ||
| 610544 - Plan Holders List 8-31-2026.pdf | ||
| A00831-610544.pdf | ||
| A00850-610544.pdf | ||
| A00863-610544.pdf | ||
| A00820-610544.pdf |
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Massachusetts Department Of Transportation Highway Division Proposal No. 610544-135966
A00808 - 1
DOCUMENT A00808
PROJECT UTILITY COORDINATION FORM
Massachusetts Department Of Transportation Highway Division Proposal No. 610544-135966
A00808 - 2
THIS PAGE IS INTENTIONALLY LEFT BLANK
2/3/2026
Revision Date:
Mass DOT PM: Total Poles Relocated: 2/4/2026
PRINTED
Yes No Agreement YES NO YES NO UG OH Peabody Municipal Light Plant
Brian Abcunas William Cardello Roy Simoes
(978) 573-1234 x230
(978) 573-1233
(978) 587-4489 babcunas@pmlp.com WCardello@pmlp.com rsimoes@pmlp.com x x x x x x
Cobra Head Lighting on poles R&R
PMLP to R&R with force account William Cadello
(978) 573-1233 (978) 587-4489 wcardello@pmlp.com x x x x
Peabody Fire Alarm Joseph Dasilva (978) 531-3444 joe.dasilva@peabody-ma.gov x x x x x
First Light Heather Araujo Scott Johns
(207) 432-2045
(978) 302-9334
FirstLight_MA@firstlight.net (haraujo@firstlight.net) sjohns@firstlight.net x x x x x x
Astound - RCN Jenn O'Neill (781) 316-8890 (617) 756-9881 jennifer.oneill@astound.com x x x x x x
Comcast Michael Cook Jason Delgado
Michael_Cook7@comcast.com Jason_Delgado@comcast.com x x x x x x
Verizon Paul Diamantopoulos Stacey Manseau
(978) 382-2855
(978) 339-5812
(508) 245-5522
(978) 501-3967
Paul.E.Diamantopoulos@verizon.com smanseau@pike.com x x x x x x
National Grid Gas Melissa Owens Ryan Cormier
(781) 907-2845
(617) 592-7850
(781) 392-4782
Melissa.Owens@nationalgrid.com Ryan.Cormier@nationalgrid.com x x x x
Utilities Underground (UG)
/Aerial (OH)
Potential for District Initiated Early Relocation *
Email x
PMLP to R&R cobra heads as part of Force Account - PMLP owns and maintains the street lighting on wood poles and underground street lighting where lights the public way. The city pays the bill for these lights.
Cell #
Utilities On Bridge/Structure
Richard.DeSantis@dot.state.ma.us 857 368 4074
23Kv Primaries - Undergrounding everything on Rte. 1 next to bridge only
William Paille Kathryn Eagan Sam Saba-Farmer Samuel Offei-Addo Conrado Fajarillo - Keville CTD
617-896-4312 617-896-4315 617-896-4300 617-896-4300 wpaille@bscgroup.com keagan@bscgroup.com ssabafarmer@bscgroup.com soffeiaddo@bscgroup.com cfajarillo@keville.com
Fire alarm circuit on SB RT1, to be undergrounded using Contract Items - Including conduit, providing and pulling cables, riser, weather head. Peabody Fire to splice only w/no reimbursement.
Scope, Budget, Duration Submitted Reimbursement
Non-Reimb'le Notes
Kristine.l.Chestna@dot.state.ma.us 08/01/2026 x 603-249-6736
Route/Street: Scheduled Ad Date: Asst. Dist Const /Dist Utility Reimb. Eng
Office # Cell # Email
Underground Aerial 288f cable on Rt 1 SB.- Contract Items for one EHH and 2-4" Sched 40 with sweeps SB, and 1 -4" PVC NB. Contractor to provide Conduit-Encased, Sweeps, Pull ropes and Caps only.
Consultant:
Amanda.Klemm@dot.state.ma.us/781-570-1154
Contact: Office # Municipality Consultant - BSC Group
MULTI-USE PATH CONSTRUCTION OF INDEPENDENCE
GREENWAY AT I-95 AND ROUTE 1
Utility Company Contact
Project File #: Utility Pole Set:
CONTACTS AND GENERAL UTILITY INFORMATION
Project Utilities Coordination (PUC) Form
Peabody 610544 Jose.A.Jimenez@dot.state.ma.us Peabody Mun/Verizon
City/Town: PUC Completed by:
2 fiber lines SB and 1 NB - Contract or install conduit 2-4" SB and 1 -4" NB - Astound to coord with Comcast for owner Duct (also to rise with Crowncastle)
Comcast has OH Services on Rte. 1. 1 OH Cable SB, & 2 NB - Contractor installs conduit 1-4" SB and 2-4" NB. Coord Comcast service outage with massDOT CCTV on Bourbon. Contractor installed 2-4". Place Comcast Frame and Cover on CMH Sta 102+50 Lt
OHW at Rte. 1 - JO Pole Owner, OHWires on NB and SB, RET SAC box on NB. Contractor install conduit 2-4" w/Sweeps, Sched 40 Conc Encased for both sides. and EMH/EHH - Will share duct with FirstLight and Fire but No Shared EHH/EMH.
Early test pits at 4" PL at RR and Conduit crossing on Rte. 1 SB. Prop Gas Relay on Lowell St. from Rte. 1 Bridge to Burbon Street.
Coordinate Prop. signal loop detector and Conduit and drainage work with Prop Gas work.
x
Prposal No. 610544 - 135966
A00808 - 3 https://hwyapps.massdot.trans.internal/ProjectInfoNET/(S(mzqaqmwl3wmhde3kbb0zmxp1))/ProjectSummary.aspx?ProjectNumber=610544 mailto:Jose.A.Jimenez@dot.state.ma.us mailto:Richard.DeSantis@dot.state.ma.us%20857%20368%204074 mailto:Kristine.l.Chestna@dot.state.ma.us mailto:Amanda.Klemm@dot.state.ma.us/781-570-1154 mailto:babcunas@pmlp.com mailto:babcunas@pmlp.com mailto:babcunas@pmlp.com mailto:wcardello@pmlp.com mailto:joe.dasilva@peabody-ma.gov mailto:haraujo@firstlight.net mailto:haraujo@firstlight.net mailto:haraujo@firstlight.net mailto:haraujo@firstlight.net mailto:jennifer.oneill@astound.com mailto:wendy_brown@cable.comcast.com mailto:wendy_brown@cable.comcast.com mailto:Paul.E.Diamantopoulos@verizon.com mailto:Paul.E.Diamantopoulos@verizon.com mailto:Richard.DeSantis@dot.state.ma.us%20857%20368%204074 mailto:Kristine.l.Chestna@dot.state.ma.us mailto:Amanda.Klemm@dot.state.ma.us/781-570-1154 https://hwyapps.massdot.trans.internal/ProjectInfoNET/(S(mzqaqmwl3wmhde3kbb0zmxp1))/ProjectSummary.aspx?ProjectNumber=610544 mailto:Jose.A.Jimenez@dot.state.ma.us
MassDOT ITS Tone Wade Abraham E. Hagoss Louis Lamoureux Jack Weathers William Adams
781 431-5168
(857) 368-6473
(781) 431-5166
(617) 835-6922
(617) 708-4254
(774) 286-6486
(857) 368-6473
(617) 447-0913 tony.wade@dot.state.ma.us Abraham.E.Hagoss@dot.state.ma.us Louis.Lamoureux@dot.state.ma.us Jack.Weathers@dot.state.ma.us williams.adams@dot.state.ma.us x x x x
MBTA PM liaison Christine Bresnahan (617) 222-3361 (617) 455-7087 CBresnahan@mbta.com x x x x
MBTA - RR Ops Robert Proulx (RR Ops) (617) 222-8364 (857) 330-2813 rproulx@mbta.com x x x x
Keolis Track Will Wallace william.wallace@keoliscs.com x x x x
Peabody City Eng William Paulitz (978) 536-7126 William.Paulitz@Peabody-ma.gov
Peabody Water Michael Velez (978) 536-7126 Michael.Velez@peabody-ma.gov
Peabody Sewer Kevin Guzofski (978) 536-7137 Kevin.Guzofski@peabody-ma.gov
Peabody Police Capt. Scott Richards Traffic/SOPS Commander
(978) 538-6359 srichards@peabodypolice.org
Peabody Comm.
Devlmt- Director
Curt Bellavance (978) 538-5770 Curt.Bellavance@peabody-ma.gov
Crown Castle Mark Vegnani (508) 208-9117 Mark.Vegnani@crowncastle.com
CSX Michael Sliper (518) 767-6081 Michael_Sliper@csx.com
Verizon Wireless Liz Glidden (508) 245-8832 elizabeth.glidden@vzw.com
NGrid Casey Silva (617) 429-7797 Casey.Silva@nationalgrid.com
South Essex Sewer Peter Pommersheim (978) 744-4550 x221 ppommersheim@sesd.com
Tenn. Gas David Wood (860) 763-6005 (413) 530-7117 KMEncroachmentsNorth@kindermorgan.com
Enbridge Kathleen Aruda (508) 938-7728 (617) 921-4910 Kathleen.Aruda@enbridge.com
MWRA Water Ralph Francesconi (617) 305-5827 (617) 461-3573 Ralph.Francesconi@mwra.com
MBTA - Bus Robert Guptill (617) 222-4434 (617) 820-7394 rguptill@mbta.com
Suggested Sequence of Relocation ( Based on Consultant proposed construction staging) x Contractor to coordinate with RR OPS and Keolis to stack existing rails and OTM at convenient Location for Easy pick up. Keep
99 Year lease. 2.) Ttrack & Rail Salvage. 3.)
Access License req by Cotnractor, PMLD, Vz, Astound x Contractor to Coord with MBTA to stack rails and signal poles for scrap pick up.
The sequence as detailed on the following pages is based on the consultants proposed staging plan. This information was compiled through meetings that included all of the utilities listed below along with the designer and the City of Peabody. The information provided is the best available information prior to project advertisement.
Keep Informed of all Work
PROJECT Lead from Town
Late night closure/ 01 12 2023 No MBTA Bus Service in this location
The Contractor is not to place heavy equipment for extended periods of time or material stockpiles on top of the sewer. Such as, requesting that the crane for the Proctor Brook bridge not be on top of the sewer line. NOTE - Contractor shall avoid placing the crane on top of the sewer line. Similarly, Contractor shall be cautious of heavy equipment at Prop. culvert near Lt. Ross Park and the Route 1 bridge work.
Review recent CCTV for some portions of the sewer within project limits. City shall request post construction CCTV inspection of the sewer main to confirm that no damage occurred due to construction activities.
Utility Relocation Notes for MassDOT Contractor Unless otherwise noted by Contract, the MassDOT Contractor is to provide the District Construction Office with 7 Calendar Days advance notification in order to validate the current progress and provide the required 30 Days advance notice-to-proceed for the first Utility - and each subsequent Utility. These advance notifications are to be identified in the Contractor's Schedules (Pre-Con preparation, Baseline, Subnets, and Updated/Monthly Schedules) as specified in Subsection 8.02 (for DBB Contracts) and/or Section 9 (of DB Contracts). Note: The durations included below do not include these lead-times. See Additional 'Important Basis notes for Contractor' - on last PUC Form page.
Additional notes:
2024 07 03 - No Facilities
No Facilities 3-16-23 - Water at Rte. 1 SB W Bridge Abut
Former CSX converted to Town Ownership sewer shown on Rte. 1 SB at East Abut?
water shown on Rte. 1 SB at East Abut?
No Facilities - RCS
No Facilities - RCS
No Facilities or No Conflicts
No Facilities - RCS Guy has this as N/C
For Information Only
No Facilities at Rte. 1
2023 2 9 No facilities x
CCTV on Lowell Street - Comcast to replace Comm Service to Camera from UP#153-1 on Burbon Street to Camera at Sta. 106+00.
Comm is disrupted due to Wood Pole being removed. Contractor to install riser, sweeps, 2- 4" conduit, and EHH and Comcast to run a
Prposal No. 610544 - 135966
A00808 - 4 mailto:CBresnahan@mbta.com mailto:rproulx@mbta.com mailto:william.wallace@keoliscs.com mailto:William.Paulitz@Peabody-ma.gov mailto:Michael.Velez@peabody-ma.gov mailto:Kevin.Guzofski@peabody-ma.gov mailto:srichards@peabodypolice.org mailto:Curt.Bellavance@peabody-ma.gov mailto:Mark.Vegnani@crowncastle.com mailto:elizabeth.glidden@vzw.com mailto:Casey.Silva@nationalgrid.com mailto:ppommersheim@sesd.com mailto:KMEncroachmentsNorth@kindermorgan.com mailto:Kathleen.Aruda@enbridge.com mailto:Ralph.Francesconi@mwra.com mailto:rguptill@mbta.com
Yes No 2/4/2026 x PRINTED
Yes No x
Exclusive Utility on site
Concurrent Utilities
Contractor Off-Site
Contractor Concurrent
C
Co nt ra ct or U
U til ity
C o.
U til ity w or ki ng w ith n o ot he r U til iti es in v ic in ity
U til ity w or o th er iti es o n sit e
N o
Co nt ra ct or ph ys ic al co ns tr uc tio n op er at io ns o n-sit e
(w hi le U
Co nt ra ct or a nd ity re ki ng o n-sit e bu t N
O T in th e sa m e vi ci ni ty
Stage : 1 Phase : A
Task: 1 C x x y No work on RR without
C x x y
No work on RR without License
Task: 2 U X x y No work on RR without U X x y No work on RR without U X x y No work on RR without
RE
SP
O N
SI
BL
E
PA
RT
Y
MBTA Access license: PMLP allow 9 months for access licenses to be obtained for any work on 99 year lease property MBTA Access license: Verizon allow 9 months for access licenses to be obtained for any work on 99 year lease property MBTA Access license: Astound allow 9 months for access licenses to be obtained for any work on 99 year lease property
Re as on /N ot e
(o pt io na l)
Sub-Total 0
Utility Co. Utilities
Is 'enabling' (prep) work, by the Contractor, necessary prior to the start of the first series of utility relocations:
Has any of the Utility work been identified to work concurrently
Concurrent / Exclusive Utility Work Contractor note: In planning and executing the work, the Access Restraints listed in the Special Provisions, takes precedence over the checklist in these 4 columns.
Access Restraint & Limitations of Operations Notes
Should an AR be considered for the Contractor ?
Es tim at ed
D ur at io n (W or k
Da ys
) b y
U til iti es
(L ea d tim e no t i nc lu de d)
PUC FORM - CONTINUED
DESCRIPTION - Utility Relocation Phases, Tasks and Activities
Po te nt ia l A cc es s R es tr ai
(Y es /N o)
Enabling' work by the Contractor - Get Access License with MBTA, Coordiante to verify Utilities have Access. *Construction starting location/ order of operations (Rt.1 NB + SB, Lowell Street, Bourbon Street) to be determined by contractor when coordination with each utility happens* PMLP has expressed that the switch gear will have long lead time for material acquisition during the design process.
Contractor shall build/Install all Underground Conduit and Manhole, HH, & Pull boxes - Contractor shall adjust Structurs until they contain wires installed by Utilities. Contractor shall be responsible for Tree Removal/trimming necessary for Utility pole, Guy wire and OHW placement, Contractor shall dig safe job, coordinate the staking of poles and guys and layout curb and back of sidewalk by survey in preparation for a field walk with DE, RE, and DURE in advance of Utility notice to proceed. Verify guy wire anchors in PUE locations with property owners, test pit for pole locations for possible ug conflicts, apply for WR#s from Peabody Muni Light for street lighting, Disconnect/Reconnects. Review Water and Drainage work next to Prop Poles to verify if some work should be done in advance (i.e. Hydrants/CBs). Utilities to acquire MBTA access license for work on trail. Project trail property on a 99 year ATC lease from MBTA.
Contractor to coordinate with Keolis/MBTA RR ops as they want to salvage all rail and OTM within the project. OHW SUB-transmission wires parallel to Rt. 1 to remain during construction - Contractor to coordinate with PMLP to install switches off-site to de-energize OHW. These de-energize times are not guaranteed(Extream Heat, High Winds). NGRID Gas may elect to replace existing gas mains during construction if encroachment and damages happen or leaks are discoverd on pipe that are uncovered. Coordinate with NGRID Gas to relay any existing mains deemed in poor condition during construction. There is one Betterment proposed on Lowell Street Approx 650'.
Project File #: 610544 Peabody
MULTI-USE PATH CONSTRUCTION OF INDEPENDENC
City/Town:
Route/Street:
UTILITY OPERATIONS - Preconstruction Notifications Prime Contractor Access license from MBTA Contractor to clarify the rails and OTM and location and method of stacking. Coordinate a drop site and arrange for traffic control etc. for Keolis to send over a trailer to pick up Steel/Iron. MBTA/ Keolis to salvage all steel rails and OTM on site. No 3rd party agreement for Material Salvage required. MassDOT contractor to remove all RR ties, stack steel rails, and OTM for Keolis in an accessible location for salvage contractor to pick up. Contractor to coordinate locations with Keolis to determine removing/ stacking existing rail/ OTM when project starts.
A00808 - 5
Exclusive Utility on site
Concurrent Utilities
Contractor Off-Site
Contractor Concurrent
C
Co nt ra ct or U
U til ity
C o.
U til ity w or n o ot he r U til iti es in v ic ity w or o iti es o n sit e
N o
Co nt ra tr uc tio n op er at io ns o n-sit e
(w hi le U ra ct or ity ki ng o n-sit e bu t N
O T in th e sa m e vi ci
O N
SI
BL
E
PA
RT
Y
Re as on /N ot e
(o pt io na l)
Concurrent / Exclusive Utility Work Contractor note: In planning and executing the work, the Access Restraints listed in the Special Provisions, takes precedence over the checklist in these 4 columns.
Access Restraint & Limitations of Operations Notes
Should an AR be considered for the Contractor ?
Es tim at ed
D ur at io n (W or k
Da ys
) b y
U til iti es
(L ea d tim e no t i nc lu de d)
DESCRIPTION - Utility Relocation Phases, Tasks and Activities
Po te nt ia l A cc es s R es tr
Task: 3
C - X x n
C - X x n C - X x n C X x n C
U 1 X x n U 2 X x n U 1 X x n U 1 X x n U 1 X x n U 1 X x n U 1 X x n U 1 X x n U 1 X x n U 1 X x n U 1 X x n U 1 X x n U 1 X x n U 1 X x n U 1 X x n U 1 X x n U 2 X x n U 5 X x n U 1 X x n U 1 X x n U 1 X x n
Task: 4
C x n C x n
U X x n * DUCE Estimate
Task: 5 C x x n
U 1 x x n U 2 x x n U 1 x x n U 2 x x n U 1 x x n U 1 x x n U X x n *DUCE
Task: 6 U X x n
C X x n U X x n U X x n
Task: 7
C X x n
U X x n U X x n U X x n
C x x n U X x n * DUCE Estimate
C U x x n U X x n * DUCE Estimate
C x x n
Burbon Street - Install underground conduit, sweeps, riser, and EHH at Bourbon Street for Comcast - Not in Force Account
Advanced permitting for pole rights -
Sub-Total 9
Utility Co. Astound
Install underground Conduit, Pull ropes and Sweeps and Caps on NB and SB Rt. 1( Provide As-Built GIS Plans to RCN) Pull cable, and installs Wire Guard/riser fixtures on UPL's 20
Phase 1 Tree crew to clear railroad bed of vegetation for access
During overnight road shutdown, run new overhead crossing between pole 76.5 (UPL-4) and 318.
Install new pole 317.75 (UPL-2) and prep for riser
Rte. 1 Relocate Coax plant off poles to new underground, install wire guard/risers and remove old plant off poles
Utility Co. Comcast
Rte. 1 Move fiber from poles to new underground and splice 7 Rte. 1 Prep fiber for relocation off poles to new underground plant 5
Sub-Total
Install Conduit, Elect MH with COMCAST F&C, Pull ropes and Sweeps and Caps on NB and SB Rt. 1- ( Provide As-Built GIS Plans to Comcast)
Replace pole 54 on railroad a few feet behind, transfer and remove pole to pole guy and guy stub pole 54S Install new pole 76.5 (UPL-4) near Bosun Marine sign and prep for street crossing
Splice and plan outages 38
R&D old UP Sta 107+22 (Unclassified Exc. and Disposal of Treated Wood)
Coordinate with massDOT ITS for the Communication outage 2 hrs.
CCTV Replace new Comm service from UP#153-1 to CCTV underground
Splicing by fire department when poles are dressed and wire is pulled
Utility Co. Peabody Fire Alarm Install underground conduit, Sweeps and Risers on the north side of Rt.1 SB only (Provide As-Built GIS Plans to Fire)
Comcast Splices in new service cable, and abandons old pole and removes OHW. 1
Place and Lash new cable btween Slack Loops through approx 269' new Conduit to be placed by DOT
Sub-Total Utility Co. First Light Install underground conduit, Pull ropes and Sweeps and Caps on NB and SB Rt.1(Provide As-Built GIS Plans to Firstlight)
Install wire guard/riser, and grounding
Delash fiber between existing slack loops at Pole 315/315 to 324/324 Newbury Street
Prep Slack loops for new splice cases at each location Overnight cutover- splice active services in old cable to new cable at each splice location - may need 30 day lead time Complete remaining non service affecting Splicing Wreck out old strand and fiber
Set 2 new poles 55-1-1 and 55-1-2 in 216 Newbury Street property to re-feed service, new xfmr's, drop cables across railroad, remove old xfmr's Install new anchor and remove old guy stub pole at station 216 off UPL 57.
Install in-line disconnects on open wire circuit for future de-energization during bridge setting
After street crossing is energized, remove cables between 76.5 (UPL-4) and 80 and remove poles in between
Phase 3 After contractor installs 4" conduits on NB side of Rt. 1, pull in new underground cables and re-feed services and lights After contractor installs 6" conduits & manhole, pull in new underground cables and set switchgear. Make up all terminations.
After new underground is energized, remove overhead lines between pole 318 & 320.
Phase 2
Utility Co. Peabody Muni Light
Contractor Coordinatate with PMLP & installs Conduit Sweeps and Cap from Pole to Pole and EHH/EMH
Contractor to review lead time with PMLP for Outage when Crane Pick Bridge on Rte. 1 Order prop switch gear, wire, and necessary materials to underground OHW's in project
Perform switching procedure, drop cables between pole 53 and 319, prep pole 53 for riser
UTILITY OPERATIONS - OHW relocations to UG Conduit
Contractor R&R service to Signal on Lowell Street Sta 512 Rt before old pole can be removed Provide As-Built GIS Plans to PMLP
Sub-Total
Pull cable, and install all appropriate fixtures on UPL's
Replace pole 320 and prep for riser (Plans say RET) Install new pole 320.5 (UPL-3) near 216 Newbury St. lot exit
Disconnect - PMLP will install a Disconnect and scheduled outage for the 23kV lines at the site for a short duration for Crane Activity.
MassDOT contractor to coordinate with PMLP for any schedule regarding temp outages.
Replace pole 318 (PlanS say RET) and prep for street crossing
Install new pole 317.5 (UPL-1)
Set new pole 79 (UPL-5) near pole 80 - future secondary riser Replace pole 79-1 (Plans say RET) Run secondary cables to re-feed lights for Bosun Marine Install 2 new poles on Lowell Street and transfer secondary cables, remove old.
Sub-Total 19
A00808 - 6
Exclusive Utility on site
Concurrent Utilities
Contractor Off-Site
Contractor Concurrent
C
Co nt ra ct or U
U til ity
C o.
U til ity w or n o ot he r U til iti es in v ic ity w or o iti es o n sit e
N o
Co nt ra tr uc tio n op er at io ns o n-sit e
(w hi le U ra ct or ity ki ng o n-sit e bu t N
O T in th e sa m e vi ci
O N
SI
BL
E
PA
RT
Y
Re as on /N ot e
(o pt io na l)
Concurrent / Exclusive Utility Work Contractor note: In planning and executing the work, the Access Restraints listed in the Special Provisions, takes precedence over the checklist in these 4 columns.
Access Restraint & Limitations of Operations Notes
Should an AR be considered for the Contractor ?
Es tim at ed
D ur at io n (W or k
Da ys
) b y
U til iti es
(L ea d tim e no t i nc lu de d)
DESCRIPTION - Utility Relocation Phases, Tasks and Activities
Po te nt ia l A cc es s R es tr
Task: 8 x x n
C x x n U 5 x x n U 4 x x n U 13 x x n U 15 x x n U 4 x x n
Task: 9 U 10 x x n * DUCE Estimate
Utility Pole Relocations
Stage : 1 Phase : A
Task: 10 C
U 25 x x n * DUCE Est
Stage : 1 Phase : A
Task: 11 U 4 x * DUCE Est U 4 x * DUCE Est U 4 x * DUCE Est
C x
Sta. 101+ 80, 102+50, 103 Proposed Conduit must not encroach within 12" of Existing Gas
ADJ PMLP EMH
ADJ NG Gas Gates SMH, Drainage, Signal HH, WG's, etc.
Unless otherwise specified in the MassDOT Construction Contract, or unless specifically noted within this PUC Form, these durations (herein) are based upon the Contractor providing unimpeded access to the Utility company to perform Utility relocations (see Note 5 - Access).
Enabling' work by the Contractor - Test pit any crossings or encroachments. Coordinate with gas with any excavations within proximity to their gas main.
Coordiante for the Signal Loop detector - so gas can cut through and Contractor can replace loops without much down time.
"Concurrent Utilities" operations noted herein, are to signify those Utility Company operations that can be worked concurrently (e.g. Utility A and Utility B work on-site together) - MassDOT and the Contractor are to prepare NTPs to Utilities accordingly.
Access - Unless otherwise noted in the Contract, and in addition to the 'enabling' notes above, the Contractor must provide safe and unimpeded access (for trucks, lifts, cranes, etc.) to the Utilities, to allow for the proposed relocation(s) -including but not limited to snow removal, clearing and grubbing, guard rail removal, barrier removal, tree removal, and grading. Any costs associated with these tasks are deemed to be incidental to the project.
For all MassDOT construction contracts issued after January 2014, the new Utility Coordination/documentation specification is required. This is Section 8.14 in Design-Bid-Build Contracts (see Design-Build index reference for applicable section #).
Prior to starting any and all enabling work for Utilities, the Contractor is to plan in advance with submittals and approved durations.
* Potential District Initiated Early Utility Relocation - if noted herein, the District reserves the right to initiate early utility relocation in advance of the Contract NTP. In submitting a bid price and in the development/basis of the Baseline Schedule, the Contractor shall not plan the Work with the potential benefit of any form of 'early utility relocation.' As a requirement of the Baseline submission, unless otherwise noted in this Specification, the earliest that the first Utility company is to receive the 30 days advance notification to mobilize to the site, will be 7 calendar days after the pre-construction meeting and never sooner than 7 days after the Contract NTP.
Utility non-work periods - For planning purposes, the durations above contain some non work days (contingency) for New England conditions (precipitation, high temperatures, low temperatures, snow, ice). Gas line work however, typically has a seasonal restriction and can NOT be installed from 15-November to 15-March. Municipally Owned Electric and Gas Utilities are also restricted from proceeding from 15-November to 15-March. The Contractor shall (and the CTD plan) reflect this calendar restriction within the schedule (unless otherwise note).
IMPORTANT BASIS NOTES - FOR CONTRACTOR
Sub-Total Enabling' work by the Contractor - coordinate to provide grades to utilities at every structure - additional work may be required at full depth areas as well as on intermediate set for work curtailed during winter season.
Utility Co. All Private and Public Utilities ADJ Verizon TMH
UTILITY OPERATIONS - Structure adjustment for paving/ sidewalk
Sub-Total
Lowell St. Relay 650' 6" BS 60# w/650' 6" PL 60# Sta. 508+50 to 513+00 and Sta 514+70 to 517+70 Betterment - No Force Account
"Potential Access Restraints" noted within this PUC Form are for planning purposes. See MassDOT Contract for Contractual Access Restraints (refer to Subsections 8.02, 8.03, and/or 8.06 for Design Bid Build Contracts and Volume II Section 9 for Design Build Contracts).
Utility Co. National Grid Gas UTILITY OPERATIONS - Trenching and Underground activities
Sub-Total 10
Utility Co. Peabody Muni Light PMLP to remove old poles
Sub-Total 41
Utility Co. Verizon Peabody Muni to install poles and anchors Install underground conduit, and risers on NB and SB Rt. 1 ( Provide As-Built GIS Plans to Vz) Vz Contractor to Install HH over existing conduit Vz to Install Strand and Guying Vz to rod and rope conduit and place cables Vz to splice over cables and terminals Vz line crews to remove cables
A00808 - 7
2/4/2026 POLE RELOCATION SUMMARY SHEET Page 6 of 7
Project Name: Peabody Independence Greenway
Project File No.: 610544 Respon. for Design:
Prepared By: BSC Group
Revision Date: 7/17/25 Design Stage: 75% ROW takings to be done by : Municipality
Notes: 1) Offsets are measured to center of pole unless otherwise noted. 3) Occupant: P = Power; T = Telephone; C = Cable TV; F = Fire Alarm; JO = Joint Owned, SO= Sole owned
MassDOT / Utility Company Comments
Risers Cut Fill Risers "X" if Yes
F" if Floodlight by Power co.
R&R Cobra
Head PLLP F C T list by owner (Total) Qty - by owner Northing Easting
1 UPL-5 X 2+23.59 17.38 LT RET >18" -
2 UPL-6 X NONE NONE - RET N 3023619.4499 E 792517.7861 >18" -
3 UPL-6S X 0+81.56 90.96 RT RET >18" -
4 6B X NONE NONE - RET N 3023631.3471 E 792517.8077 >18" -
5 UPL 4 X 4+11.91 29.99 LT RET >18" -
6 UPL 18-4 X 6+36.35 75.50 RT RET >18"
7 UPL 62 X 6+58.18 60.67 RT RET >18"
8 UPL 4-1 X 5+44.99 32.27 LT RET >18"
9 UPL 61 X 7+15.89 23.44 LT RET >18" -
10 UPL 18-5 X 7+28.92 19.17 LT RET >18" -
11 UPL 88 X 9+29.76 27.63 LT RET >18" -
12 UPL 62 X 9+69.67 12.48 LT 1.2 RET >18" -
13 UPL 62S X 6+96.90 17.06 LT RET >18" -
14 UPL 61 X 11+13.92 12.91 LT 0.6 RET >18" -
15 UPL 60 X 12+41.00 13.29 LT RET >18" -
16 UPL 59 X 14+18.43 13.81 LT RET >18" -
17 UPL 58 X 15+99.73 14.17 LT RET >18" -
18 UPL 57 X 17+78.94 14.53 LT RET >18" -
19 UPL 56 X 19+81.67 13.01 LT RET >18" -
20 UPL 55 X 21+24.21 13.89 LT RET >18" -
21 GPL 55PB 21+26.83 37.38 LT RET >18" -
22 UPL 55-1 X 21+29.05 69.39 LT RET >18" -
23 UPL 55-1-1 X 1 PROP 22+20.80 43.92 LT N 3024135.0996 E 794566.3782 >18" N
24 UPL 55-1-2 X 1 PROP 23+67.20 39.27 LT N 3024190.1717 E 794701.8445 >18" N
25 UPL 53-1 X 24+59.33 78.96 LT RET >18" -
26 UPDL 54 2F X 22+62.14 14.31 LT 1 PROP KEEP IN LINE & ELIMINATE NEED
FOR GUY SYSTEM
22+61.97 18.93 LT N 3024128.9567 E 794614.1507 >18" N
27 UPL 54S X 22+61.07 14.73 LT REM KEEP UPL 54 IN LINE & ELIMINATE
NEED FOR GUY SYSTEM
>18" -
28 UPL 1/P318-1 X X 24+52.67 26.02 RT RET >18" -
29 UPL 1/P318-A1 X X 25+70.91 34.55 RT RET >18" -
30 EX GPL (FOR
UPDL 53)
24+92.90 20.53 LT RET >18" -
31 UPDL 53 2F X 24+96.88 19.85 LT RET (2)
2 - PMLP
>18" -
32 UPL 1/P318-A1 X X 25+70.91 34.55 RT RET >18" -
33 UPL 1/320 X X 26+33.03 27.57 LT RET >18" -
34 LPL 1X 509+17.52 33.958 LT RET 11' -
35 UPL 4160-1 1X X X X X 509+29.25 34.369 RT RET 7.7' -
36 LPL 1F PMLP 510+35.51 32.241 LT RET 10' -
37 UPL 85-1 1X X X 510+37.96 43.911 RT RET 4.8' -
38 LPL 2F 511+04.67 31.77 LT RET 8.6' -
39 LPDL 2F 511+83.84 33.28 LT RET 10' -
40 ULT-159 1F X X PMLP 511+97.30 51.071 RT REM IN PATHWAY 7.3' -
41 UP-8 1X X X 1 PROP IN PATHWAY 512+22.46 52.67 RT N 3024857.6619 E 795605.6472 27' N UP-6 on 75% Plans, revised to be UP-8 after the submission
42 ULT 158 1X X X 513+04.94 29.2 RT REM IN PATHWAY 14' -
43 UP-9 1X X X 1 PROP IN PATHWAY 513+08.69 36.78 RT N 3024787.2300 E 795657.8435 21' N UP-7 on 75% Plans, revised to be UP-9 after the submission
44 ULT 1X X 516+27.07 30.25 RT RET 15' -
45 LPL 1X X 517+28.91 21.844 RT RET 4.9' -
46 UPL MASSDOT X MassDOT 517+34.30 28.44 RT REM IN PATHWAY 11' - Removed, no relocation as service will be undergrounded 7
47 ULT 153-1 1X X X X PMLP 517+34.30 28.44 RT RET (1)
1 - COMCAST
13' -
ALIGNMENT - INDEPENDENCE WEST
ALIGNMENT - LOWELL ST.
Offset Total of new PL's
Retain/ Relocate Reason Station6 Inch + Changes
ONLY
Offset GPS Coordinates
(MA State Plane NAD 83) Min. Offset (ft)
Face of Curb to face of Pole (Existing or Proposed)
Design Exception Req. (Horizontal
Offset) Designer Comments Station
MassDOT
4) Locations shall not be changed without approval of MassDOT and/or the Utility Companies
Existing Pole Information Proposed by Designer
Line No.
Sheet No.
Pole No.
Streetlight Interests
A00808 - 8
2/4/2026 POLE RELOCATION SUMMARY SHEET Page 7 of 7
Project Name: Peabody Independence Greenway
Project File No.: 610544 Respon. for Design:
Prepared By: BSC Group
Revision Date: 7/17/25 Design Stage: 75% ROW takings to be done by : Municipality
Notes: 1) Offsets are measured to center of pole unless otherwise noted. 3) Occupant: P = Power; T = Telephone; C = Cable TV; F = Fire Alarm; JO = Joint Owned, SO= Sole owned
MassDOT / Utility Company Comments
Risers Cut Fill Risers "X" if Yes
F" if Floodlight by Power co.
R&R Cobra
Head PLLP F C T list by owner (Total) Qty - by owner Northing Easting
Offset Total of new PL's
Retain/ Relocate Reason Station6 Inch + Changes
ONLY
Offset GPS Coordinates
(MA State Plane NAD 83) Min. Offset (ft)
Face of Curb to face of Pole (Existing or Proposed)
Design Exception Req. (Horizontal
Offset) Designer Comments Station
MassDOT
4) Locations shall not be changed without approval of MassDOT and/or the Utility Companies
Existing Pole Information Proposed by Designer
Line No.
Sheet No.
Pole No.
Streetlight Interests
48 GPL 216+02.83 2.71 LT REM IN PATHWAY >18" -
49 UPL 56 218+47.03 24.5 RT RET >18" -
50 GPL 7 223+99.16 11.76 LT RET >18" -
51 UPL 317 1F X X X X PMLP 100+92.75 55.39 LT RET 29' -
52 UPL-1
PMLP(217.5)
X X X X 1 PROP UNDERGROUNDING
(2)
1 - COMCAST
1 - ASTOUND
101+56.15 55.21 LT N 3024090.0334 E 794915.9210 29' N
53 UPL-2
PMLP(217.75)
X X X X 1 PROP UNDERGROUNDING (2)
2 - PMLP
102+16.97 54.98 LT N 3024147.4111 E 794936.0816 29' N
54 UPL 1318
PMLP(318)
X X X X 102+37.10 54.92 LT RET
(3)
1 - VERIZON
1 - FIRSTLIGHT
1 - FIRE
29' -
55 UPL-6 1F (PROP) X X X 1 PROP UNDERGROUNDING 102+40.22 149.74 RT N 3024102.2169 E 795137.1069 53' N 56 UPL-4 1F (PROP) X X X 1 PROP UNDERGROUNDING COMCAST1 - ASTOU 102+74.56 120.97 RT N 3024144.1028 E 795121.1925 27' N
57 UPDL 77 2F X X X 102+91.64 118.92 RT RET (1)
1 - VERIZON
25' -
58 UPL 319 X X X X 103+72.95 26.95 LT REM UNDERGROUNDING 9.7' -
59 UPDL 78 2F X X X 103+97.87 105.17 RT REM UNDERGROUNDING 15' -
60 UPL-76 1F (PROP) X X X 101+55.45 135.22 RT RET
61 UPL-7 X X X 1 PROP UNDERGROUNDING 104+02.66 150.45 RT N 3024256.6331 E 795191.4224 62' N
62 UPL 320 2F X X X X 104+68.92 25.41 LT RET (2)
2 - PMLP
8.9' -
63 UPL-3
PMLP(320.5)
X X X X 1 PROP UNDERGROUNDING
(3)
1 - VERIZON
1 - FIRSTLIGHT
1 - FIRE
104+83.78 25.37 LT N 3024389.7784 E 795050.8280 10' N
64 UPL 79 X X X 104+87.81 95.66 RT REM UNDERGROUNDING 4.8' -
65 UPL 1F X 105+65.26 149.66 LT RET (2)
2 - PMLP
60'
66 UPL 321 2F X X X X 105+98.37 25.62 LT RET
(2)
1 - COMCAST
1 - ASTOUND
3.7' -
67 UPL-5
PMLP(79)
X X X 1 PROP UNDERGROUNDING (2)
2 - PMLP
106+33.29 94.62 RT N 3024493.0052 E 795212.3719 4.3' N
68 UPL 80 X X X PMLP 106+39.62 94.66 RT RET
(2)
1 - COMCAST
1 - ASTOUND
4.4' -
69 GPL 106+40.00 98.21 RT RET 8.0' -
70 GPL 106+43.67 110.63 RT RET 21' -
71 UPL 2F X X 106+55.39 218.6 RT RET 128' -
Proposed 12 - Remove 8 -
ALIGNMENT - INDEPENDENCE EAST
ALIGNMENT - ROUTE 1
Totals
A00808 - 9
THIS PAGE IS INTENTIONALLY LEFT BLANK
A00808 - 10
| A00808-1 Project Utility Coordination Form 1 |
| A00808-1 Project Utility Coordination Form 2 |
| Page 1Contacts & General Info |
| Page 2&3 - PUC detail |
| UPRSS20250717 DUCE |
File details come from the government source that posted it. Updated .