This is a Special Provisions document issued by the Massachusetts Department of Transportation Highway Division for a bridge replacement project in Raynham and Taunton, Massachusetts. The project, Federal Aid Project No. HPP/STP-0035(073)X, involves the replacement of Bridge No. R-02-003=T-01-004 (South Street East/Old Colony Avenue) over the Taunton River. The scope of work includes removal and disposal of the existing bridge superstructure; removal of portions of existing abutments, wingwalls, and piers; installation of abutment, pier, and wall caps; installation of continuous steel beam and reinforced concrete deck superstructure; installation of approach slabs, guardrail transitions, and metal bridge rail; temporary water control; excavation; riprap channel protection; sidewalk construction; full-depth roadway construction; fine milling and overlay; pavement markings; utility relocations; and safety controls and signing. Work is restricted to one 8-hour shift per day, five days a week, Monday through Friday, between 7:00 AM and 3:30 PM, unless otherwise approved by the Town. Labor participation goals are established at 15.3% for minorities and 6.9% for women for each job category, applicable to both the contractor and subcontractors' on-site construction workforce.
The contract is subject to federal Build America, Buy America requirements mandating that all iron, steel, manufactured products, and construction materials be produced in the United States, with limited exceptions. Comprehensive insurance requirements are specified, including Railroad Protective Liability Insurance of not less than $5,000,000 per occurrence and $10,000,000 aggregate, Umbrella Liability Coverage of not less than $10,000,000 per occurrence, and Automobile Liability Insurance with limits of not less than $1,000,000 combined single limit. The project involves significant environmental permitting and coordination requirements, including compliance with Section 401/404 of the Clean Water Act, the Taunton Wetlands Protection Ordinance, the Raynham Wetlands Protection Bylaw, and Endangered Species Act protections for the northern long-eared bat and tricolored bat. In-water work is restricted from March 1 to July 15 and September 1 to November 15. The project requires coordination with the MBTA and Keolis Commuter Services regarding railroad operations, with substitute bus transportation required for weekend rail shutdowns. Holiday work restrictions are imposed on major arterial roadways during specified periods including New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving, and Christmas. The contractor must comply with truck safety device requirements per Massachusetts regulations, manage utility coordination through detailed scheduling and documentation procedures, and implement an Invasive Plant Management Strategy for controlling invasive plant species on-site.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A00802-613642.pdf | ||
| A00810-613642.pdf | ||
| A00875-613642.pdf | ||
| A00882-613642.pdf | ||
| A00841-613642.pdf | ||
| A00831-613642.pdf | ||
| A00813-613642.pdf | ||
| A00881-613642.pdf | ||
| A00812-613642.pdf | ||
| A00844-613642.pdf | ||
| A00811-613642.pdf | ||
| A00820-613642.pdf | ||
| A00842-613642.pdf | ||
| A00808-613642.pdf | ||
| A00840-613642.pdf | ||
| A00860-613642.pdf | ||
| A00815-613642.pdf | ||
| A00814-613642.pdf | ||
| A00861-613642.pdf | ||
| 613642 - Notice to Contractors.pdf | ||
| 613642 Bid Items List.txt | TXT text file |
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Massachusetts Department Of Transportation Highway Division Proposal No. 613642-136413
A00801 - 1
DOCUMENT A00801
SPECIAL PROVISIONS
RAYNHAM- TAUNTON
Federal Aid Project No. HPP/STP-0035(073)X
Bridge Replacement, R-02-003=T-01-004 (3M4), South Street East Over the Taunton River
Labor participation goals for this Project shall be 15.3% for minorities and 6.9% for women for each job category. The goals are applicable to both Contractor’s and Subcontractor’s on-site construction workforce. Refer to Document 00820 for details.
SCOPE OF WORK
All work under this Contract shall be done in conformance with the 2026 Standard Specifications for Highways and Bridges, the Supplemental Specifications contained in this book, the Construction Standard Details in effect as of July 2026, the 1990 Standard Drawings for Signs and Supports, the 2015 Overhead Signal Structure and Foundation Standard Drawings, the 11th Edition of the Manual on Uniform Traffic Control Devices (MUTCD) and the January 2026 Massachusetts Amendments to the MUTCD, the 1968 Standard Drawings for Traffic Signals and Highway Lighting, the latest edition of The American Standard for Nursery Stock, the Plans and these Special Provisions.
The work under this Contract includes the superstructure replacement of Bridge No. R-02-003=T- 01-004 South Street East/Old Colony Avenue over Taunton River. The work includes removing and disposing of the existing bridge superstructure; removing and disposing of portions of the existing bridge abutments, wingwalls, and piers; installing abutment, pier, and wall caps; installing continuous steel beam and reinforced concrete deck superstructure; installing approach slabs, highway guardrail transitions, and metal bridge rail. The work also includes temporary water control, excavation, riprap channel protection, sidewalks, full depth roadway construction, fine milling and overlay, pavement markings, utility relocations, the provisions of safety controls and signing for construction operations, and other incidental work included in the contract documents.
SUBSECTION 7.05 INSURANCE REQUIREMENTS
The insurance requirements set forth in this subsection are in addition to the requirements of the Standard Specifications.
7.05.B: Public Liability Insurance 4.
Asbestos Liability Insurance shall be obtained for this project.
A00801 - 2
INSURANCE REQUIREMENTS
The insurance requirements set forth in this section are in addition to the requirements of the Standard Specifications.
Railroad Operations Directorate: Section F:
. The Contractor shall furnish, with respect to the operations of the Contractor or any of the Contractor's Subcontractors performing within the Railroad right-of-way, broad form Railroad Protective Liability Insurance covering all work performed under this Contract in the amount of not less than $5,000,000 per occurrence, $10,000,000 aggregate combined bodily injury and property damage. The Contractor shall carry Worker's Compensation Insurance, including Employers Liability Insurance as provided by Massachusetts General Laws, Chapter 152, as amended, covering all work performed by him under the Contract. The Contractor shall carry Umbrella Liability Coverage with limits of not less than $10,000,000 per occurrence, covering all work performed by him under this Contract. Automobile Liability Insurance: The Contractor shall provide Automobile Liability Insurance to include the use of all vehicles; owned, leased, hired and non-owned, with limits not less than $1,000,000 combined single limit covering all work performed under the Contract.
2. Such insurance shall be written on an occurrence basis.
3. The MBTA and applicable railroads shall be the named insureds on such insurance. Additional named insured are listed below. Original policies and certificates shall be made out to the MBTA and applicable railroads and mailed to:
MBTA: Treasurer-Controller
Massachusetts Bay Transportation Authority 10 Park Plaza Boston, MA 02116 Tel. (617) 222-3064
Keolis: General Counsel
Keolis Commuter Services, LLC 470 Atlantic Avenue Boston, MA 02210
AMTRAK: General Superintendent
230 Congress Street Boston, MA 02110 Tel. (617) 654-2020
CSX: General Manager
CSX
1 Bell Crossing Road RD. #2, Box 145 Selkirk, NY 12158-9618 Tel. (518) 767-6111
A00801 - 3
INSURANCE REQUIREMENTS (Continued)
4. The Contractor shall furnish to the MBTA and railroad companies a signed original of the Railroad Protective Liability Policy prior to entry upon the railroad right-of-way.
5. Such policies shall provide 30 days notice to each named insured by the insurance company before any change or cancellation of the policies.
6. Such Railroad Protective Insurance policies may be provided in forms commonly referred to as AAR/AASHTO or ISO/RIMA but not Oregon.
Questions regarding insurance should be directed to the MBTA’s Risk Manager at 617-222- 3064.
The contractor shall be aware of the latest MBTA insurance limits / requirements. See the following link for more information:
https://www.mbtarealty.com/licenses.html
CONTRACTOR QUESTIONS AND ADDENDUM ACKNOWLEDGEMENTS
Prospective bidders are required to submit all questions to the Construction Contracts Engineer by 3:00 P.M. on the Tuesday of the previous week before the scheduled bid opening date. Any questions received after this time will not be considered for review by the Department.
Contractors should email questions and addendum acknowledgements to the following email address massdotspecifications@dot.state.ma.us The MassDOT proposal number and municipality is to be placed in the subject line.
NONCONFORMING COMPRESSIVE STRENGTH OF CEMENT CONCRETE
Concrete with compressive strength test results failing to attain the limits specified in Table 901.64-3 of 901.64.B: Acceptance Testing shall be evaluated for structural adequacy and serviceability at the Contractors’ expense. The Department will review all production records, the concrete test records, petrographic analysis report, field notes, and the placement records for the concrete in question. If the Engineer determines the material is found to be adequate to remain in place, payment shall be adjusted in accordance with the following formula:
𝑃𝑃 =
2(𝑓𝑓𝑓𝑓 − 𝑓𝑓′𝑐𝑐)(𝑈𝑈𝑈𝑈)(𝑄𝑄)
𝑓𝑓′𝑐𝑐
Where:
𝑃𝑃 = 𝑝𝑝𝑝𝑝𝑝𝑝 𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑓𝑓𝑓𝑓𝑓𝑓 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐
𝑓𝑓′𝑐𝑐 = 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠ℎ 𝑎𝑎𝑎𝑎 28 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑓𝑓𝑓𝑓 = 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠ℎ 𝑎𝑎𝑎𝑎 56 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 𝑄𝑄 = 𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞𝑞 𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟 𝑏𝑏𝑏𝑏 𝑡𝑡ℎ𝑒𝑒 𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 𝑈𝑈𝑈𝑈 = 𝑢𝑢𝑢𝑢𝑢𝑢𝑢𝑢 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑜𝑜𝑜𝑜 𝑡𝑡ℎ𝑒𝑒 𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 𝑠𝑠𝑠𝑠𝑠𝑠 𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏𝑏 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑝𝑝𝑝𝑝𝑝𝑝 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦 𝑓𝑓𝑓𝑓𝑓𝑓 𝑡𝑡ℎ𝑒𝑒 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑜𝑜𝑜𝑜 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐 𝑖𝑖𝑖𝑖 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 https://www.mbtarealty.com/licenses.html mailto:MassDOTSpecifications@dot.state.ma.us
A00801 - 4
BUILD AMERICA BUY AMERICA PREFERENCE
On Federally-aid projects the Buy America (23.CFR § 635.410) and Build America, Buy America Act. requires the following,
(1) all iron and steel used in the project are produced in the United States--this means all manufacturing processes, from the initial melting stage through the application of coatings, must occur in the United States. Foreign steel and iron can be used if the cost of the materials does not exceed 0.1% of the total Contract cost or $2,500, whichever is greater.
The action of applying a coating to a covered material (i.e., steel and iron) is deemed a manufacturing process subject to Buy America. Coating includes epoxy coating, galvanizing, painting and any other coating that protects or enhances the value of a material subject to requirements of Build America, Buy America. Steel used for temporary support of excavation, including H piles, soldier piles, and sheeting when the steel is required to be left in place is subject to requirements of Build America, Buy America. Temporary steel, shall remain in place when it falls within the influence zone of the soil supporting any structure or railroad tracks.
(2) all manufactured products used in the project are produced in the United States—this means the manufactured product was manufactured in the United States and
(3) all construction materials are manufactured in the United States—this means that all manufacturing processes for the construction material occurred in the United States.
“Construction materials” includes an article, material, or supply—other than an item of primarily iron or steel; a manufactured product; cement and cementitious materials;
aggregates such as stone, sand, or gravel; or aggregate binding agents or additives—that is or consists primarily of:
• non-ferrous metals,
• plastic and polymer-based products (including polyvinylchloride, composite building materials, and polymers used in fiber optic cables),
• glass (including optic glass),
• lumber; or
• drywall.
The Buy America preference only applies to articles, materials, and supplies that are consumed in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools, equipment, and supplies, such as temporary scaffolding, brought to the construction site and removed at or before the completion of the infrastructure project. Nor does a Buy America preference apply to equipment and furnishings, such as movable chairs, desks, and portable computer equipment, that are used at or within the finished infrastructure project but are not an integral part of the structure or permanently affixed to the infrastructure project.
All articles, materials, and supplies should be classified as an iron or steel product, a manufactured product, or another product as specified by law or in 2 CFR part 184 (such other products specified by law or in 2 CFR part 184 include “excluded materials” and “construction materials”); an article, material, or supply must not be considered to fall into multiple categories.
A00801 - 5
HOLIDAY WORK RESTRICTIONS
(Supplementing Subsection 7.09)
The District Highway Director (DHD) may authorize work to continue during these specified time periods if it is determined by the District that the work will not negatively impact the traveling public. DHD may allow work in those areas on a case by case basis and where work is behind barrier and will not impact traffic
Below are the holiday work restrictions:
New Years Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day. No work on local roadways on the holiday without permission by the DHD and the local police chief.
Martin Luther King's Birthday (Federal Holiday) No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.
President's Day (Federal Holiday) No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.
Evacuation Day (Suffolk County State Holiday) No work restrictions due to traffic concerns.
Patriot's Day (State Holiday) Work restrictions will be in place for Districts 3 and 6 along the entire Boston Marathon route and any other locations that the DHD in those districts determine are warranted so as to not to impact the marathon. All other districts work restrictions will be as per DHD.
Mother’s Day No work on Western Turnpike and Metropolitan Highway System from 5:00 AM on the Friday before, until the normal start of business on the following day.
Memorial Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the Friday before, until the normal start of business on the following day.
Bunker Hill Day (Suffolk County State Holiday) No work restrictions due to traffic concerns.
Juneteenth No work restrictions due to traffic concerns, however work on local roadways requires permission by the DHD and local police chief.
A00801 - 6
HOLIDAY WORK RESTRICTIONS (Continued)
Independence Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day. No work on local roadways on the holiday without permission by the DHD and the local police chief.
Labor Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the Friday before, until the normal start of business on the following day.
Columbus Day (Federal Holiday) No work on major arterials from 5:00 AM on the Friday before, until the normal start of business on the following day
Veterans' Day (Federal Holiday) No work restrictions due to traffic concerns.
Thanksgiving Day (Federal Holiday) No work on major arterials from 5:00 AM two days before until the normal start of business on the following Monday.
Christmas Day (Federal Holiday) No work on major arterial roadways from 5:00 AM on the day before until the normal start of business on the next subsequent business day.
SOIL STOCKPILING DIRECTIVE P-22-001
Any stockpiling of soil must be performed in compliance with Policy Directive P-22-001, Off- Site Stockpiling of Soil from MassDOT Construction Projects. This directive limits the allowable locations for off-site stockpiling of soil generated during MassDOT projects and includes various requirements that must be satisfied by the contractor prior to off-site stockpiling. The Contractor is responsible for identifying a suitable stockpile location.
BIDDERS LIST
Pursuant to the provisions of 49 CFR Part 26.11 all official bidders will be required to report the names, addresses and telephone numbers of all firms that submitted bids or quotes in connection with this project. Failure to comply with a written request for this information within 15 business days may result in a recommendation to the Prequalification Committee that prequalification status be suspended until the information is received.
The Department will survey all firms that have submitted bids or quotes during the previous year prior to setting the annual goal and shall request that each firm report its age and gross receipts for the year.
A00801 - 7
SUBSECTION 8.02 SCHEDULE OF OPERATIONS
Replace this subsection with the following:
An integrated cost and schedule controls program shall be implemented by the Contractor to track and document the progress of the Work from Notice to Proceed (NTP) through the Contractor Field Completion (CFC) Milestone. The Contractor’s schedules will be used by the Engineer to monitor project progress, plan the level-of-effort required by the Department’s work force and consultants and as a critical decision-making tool. Accordingly, the Contractor shall ensure that it complies fully with the requirements specified herein and that its schedules are both accurate and updated as required by the specification throughout the life of the project. Detailed requirements are provided in Division II, Section 722 Construction Scheduling.
Work on this project is restricted to (1) 8-hour shift per day, 5 days a week, Monday through Friday, between the hours of 7:00 AM and 3:30 PM, with the Prime Contractor and all Subcontractors working on the same shift, unless otherwise approved by the Town
TRUCK SAFETY DEVICES
(Supplementing Subsection 7.04: Motor Vehicles)
All motor vehicles subject to Section 7 of Chapter 90 to be operated under this Contract shall be equipped with safety devices as provided therein and in 540 CMR 4.00.
The Contractor shall certify to the Registry of Motor Vehicles, in a manner prescribed by the Registrar, that all applicable vehicles are equipped with Lateral Protective Devices, Convex Mirrors, Cross Over Mirror(s) and Back Up Cameras in accordance with the requirements of 540
CMR 4.00.
The Contractor shall provide evidence satisfactory to the Department to demonstrate compliance with the above certification requirement for all applicable vehicles operated under this Contract by the Contractor and its subcontractors and vendors in a manner set forth by the Department.
Thereafter, the Contractor shall have an affirmative obligation to continue to provide such evidence of compliance on an ongoing basis and no later than 7 days after certification with the Registry of Motor Vehicles of any additional vehicles operated under this Contract by the Contractor and its subcontractors and vendors.
Non-compliance with respect to a vehicle that is subject to 540 CMR 4.00 may subject the Contractor to statutory fines as established in M.G.L. c. 90, § 7 and/or contractual remedies up to and including termination of the Contract.
A00801 - 8
SUBSECTION 8.14 UTILITY COORDINATION, DOCUMENTATION, AND
MONITORING RESPONSIBILITIES
A. GENERAL
In accordance with the provisions of Section 8.00 Prosecution and Progress, utility coordination is a critical aspect to this Contract. This section defines the responsibility of the Contractor and MassDOT, with regard to the initial utility relocation plan and changes that occur as the prosecution of the Work progresses. The Engineer, with assistance from the Contractor shall coordinate with Utility companies that are impacted by the Contractor’s operations. To support this effort, the Contractor shall provide routine and accurate schedule updates, provide notification of delays, and provide documentation of the steps taken to resolve any conflicts for the temporary and/or permanent relocations of the impacted utilities. The Contractor shall provide copies to the Engineer of the Contractor communication with the Utility companies, including but not limited to:
• Providing advanced notice, for all utility-related meetings initiated by the Contractor.
• Providing meeting minutes for all utility-related meetings that the Contractor attends.
• Providing all test pit records.
• Request for Early Utility work requirements of this section (see below).
• Notification letters for any proposed changes to Utility start dates and/or sequencing.
• Written notification to the Engineer of all apparent utility delays within seven (7) Calendar
Days after a recognized delay to actual work in the field – either caused by a Utility or the Contractor.
• Any communication, initiated by the Contractor, associated with additional Right-of-Way needs in support of utility work.
• Submission of completed Utility Completion Forms.
B. PROJECT UTILITY COORDINATION (PUC) FORM
The utility schedule and sequence information provided in the Project Utility Coordination Form (if applicable) is the best available information at the time of the bid and has been considered in setting the contract duration. The Contractor shall use all of this information in developing the bid price and the Baseline Schedule Submission, inclusive of the individual utility durations sequencing requirements, and any work that has been noted as potentially concurrent utility installations.
C. INITIATION OF UTILITY WORK
The Engineer will issue all initial notice-to-proceed dates to each Utility company based on either the:
1) Contractor’s accepted Baseline Schedule
2) An approved Early Utility Request in the form of an Early Utility sub-net schedule (in accordance with the requirements of this Subsection)
3) An approved Proposal Schedule
C.1 - BASELINE SCHEDULE – UTILITY BASIS
The Contractor shall provide a Baseline Schedule submission in accordance with the requirements of Subsection 8.02 and inclusive of all of the information provided in the PUC Form that has been issued in the Contract documents. This is to include the utility durations, sequencing of work, allowable concurrent work, and all applicable considerations that have been depicted on the PUC Form.
A00801 - 9
SUBSECTION 8.14 (Continued)
C.2 – EARLY UTILITY REQUEST – (aka SUBNET SCHEDULE) PRIOR TO THE BASELINE All early utility work is defined as any anticipated/required utility relocations that need to occur prior to the Baseline Schedule acceptance. In all cases of proposed early utility relocation, the Contractor shall present all known information at the pre-construction conference in the form of a ‘sub-net’ schedule showing when each early utility activity needs to be issued a notice-to-proceed. The Contractor shall provide advance notification of this intent to request early utility work in writing at or prior to the Pre-Construction meeting. Prior to officially requesting approval for early utility work, the Contractor shall also coordinate with MassDOT and all utility companies (private, state or municipal) which may be impacted by the Contract. If this request is acceptable to the Utilities and to MassDOT, the Engineer will issue a notice-to-proceed to the affected Utilities, based on these accepted dates.
C.3 – PROPOSAL SCHEDULE - CHANGES TO THE PUC FORM
If the Contractor intends to submit a schedule (in accordance with MassDOT Standard Specifications, Division I, Subsection 8.02) that contains durations or sequencing that vary from those provided in the Project Utility Coordination (PUC) Form, the Contactor must submit this as an intended change, in the form of a Proposal Schedule and in accordance with MassDOT Standard Specifications, Division I, Subsection 8.02. These proposed changes are subject to the approval of the Engineer and the impacted utilities, in the form of this Proposal Schedule and a proposed revision to the PUC form. The Contractor shall not proceed with any changes of this type without written authorization from the Engineer, that references the approved Proposal Schedule and PUC form changes. The submission of the Baseline Schedule should not include any of these types of proposed utility changes and should not delay the submission of the Baseline Schedule. As a prerequisite to the Proposal Schedule submission, and in advance of the utility notification(s) period, the Contractor shall coordinate the proposed utility changes with the Engineer and the utility companies, to develop a mutually agreed upon schedule, prior to the start of construction.
D. UTILITY DELAYS
The Contractor shall notify the Engineer upon becoming aware that a Utility owner is not advancing the work in accordance with the approved utility schedule. Such notice shall be provided to the Engineer no later than seven (7) calendar days after the occurrence of the event that the Contractor believes to be a utility delay. After such notice, the Engineer and the Contractor shall continue to diligently seek the Utility Owner’s cooperation in performing their scope of Work.
In order to demonstrate that a critical path delay has been caused by a third-party Utility, the Contractor must demonstrate, through the requirements of the monthly Progress Schedule submissions and the supporting contract records associated with Subsection 8.02, 8.10 and 8.14, that the delays were beyond the control of the Contractor.
A00801 - 10
SUBSECTION 8.14 (Continued)
All documentation provided in this section is subject to the review and verification of the Engineer and, if required, the Utility Owner. In accordance with MassDOT Specifications, Division I, Subsection 8.10, a Time Extension will be granted for a delay caused by a Utility, only if the actual duration of the utility work is in excess of that shown on the Project Utility Coordination Form, and only if;
1) proper Notification of Delay was provided to MassDOT in accordance with the time requirements that are specified in this Section
2) the utility delay is a critical path impact to the Baseline Schedule (or most recently approved Progress Schedule)
E. LOCATION OF UTILITIES
The locations of existing utilities are shown on the Contract drawings as an approximation only.
The Contractor shall perform a pre-construction utility survey, including any required test pits, to determine the location of all known utilities no later than thirty (30) calendar days before commencing physical site work in the affected area.
F. POST UTILITY SURVEY – NOTIFICATION
Following completion of a utility survey of existing locations, the Contractor will be responsible to notify the Engineer of any known conflicts associated with the actual location of utilities prior to the start of the work. The Engineer and the Contractor will coordinate with any utility whose assets are to be affected by the Work of this Contract. A partial list of utility contact information is provided in the Project Utility Coordination Form.
G. MEETINGS AND COOPERATION WITH UTILITY OWNERS
The Contractor shall notify the Engineer in advance of any meeting they initiate with a Utility Owner’s representative to allow MassDOT to participate in the meeting if needed.
Prior to the Pre-Construction Meeting, the Contractor should meet with all Utility Owners who will be required to perform utility relocations within the first 6 months of the project, to update the affected utilities of the Project Utility Coordination Form and all other applicable Contract requirements that impact the Utilities. The Contractor shall copy the Engineer on any correspondence between the Utility Owner and the Contractor.
H. FORCE ACCOUNT / UTILITY MONITORING REQUIREMENTS
The Engineer will be responsible for recording daily Utility work force reports. The start, suspension, re-start, and completion dates of each of the Utilities, within each phase of the utility relocation work, will be monitored and agreed to by the Engineer and the Contractor as the work progresses.
I. ACCESS AND INSPECTION
The Contractor shall be responsible for allowing Utility owners access to their own utilities to perform the relocations and/or inspections. The Contractor shall schedule their work accordingly so as not to delay or prevent each utility from maintaining their relocation schedule.
A00801 - 11
COMPLIANCE WITH THE NATIONAL DEFENSE AUTHORIZATION ACT
(Supplementing Subsection 7.01)
On all projects, the “Prohibition on Certain Telecommunications and Video Surveillance Services or Equipment” Regulation (2 CFR 200.216) prohibits the Contractor from using or furnishing the following telecommunications equipment or services:
• Telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities).
• For the purpose of public safety, security of government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities).
• Telecommunications or video surveillance services provided by such entities or using such equipment.
• Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of the National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.
This prohibition applies to all products manufactured by the aforementioned companies, including any individual components or parts.
By submitting a bid on a project, the Contractor certifies that all work will be in compliance with the terms of 2 CFR 200.216. The Contractor shall submit a COC indicating compliance with the above provisions for all telecommunications equipment or services included in the Contract.
Payment for the item in which the materials are incorporated may be withheld until these COCs are received. Any cost involved in furnishing the certificate(s) shall be borne by the Contractor.
A00801 - 12
EMERALD ASH BORER ADVISORY
To the extent possible, all trees and brush shall be disposed on site, typically chipped and spread in place. When trees or brush must be removed, such as in urban, or otherwise populated areas, Contractor shall identify proposed location for disposal, and provide written notification to the Engineer for approval. Disposal shall be in city or town of project, or at minimum, within county, of construction operations.
ENVIRONMENTAL PERMITTING
The proposed work occurs in jurisdictional wetland resources subject to Section 401/404 of the Clean Water Act as well as the Taunton Wetlands Protection Ordinance and the Raynham Wetlands Protection Bylaw; therefore, a Water Quality Certification from the Massachusetts Department of Environmental Protection; a Nationwide Permit authorization from the US Army Corps of Engineers; and Orders of Conditions from both municipalities (under the local Ordinance/Bylaw only) have been obtained. The Contractor is advised that all terms and conditions within said permits shall be strictly adhered to. The proposed work qualifies for the bridge exemption authorized in the Transportation Bond Bill and is therefore not subject to the Massachusetts Wetlands Protection Act, the Massachusetts Public Waterfront Act (Chapter 91), or the Massachusetts Environmental Policy Act. The proposed work, however, is subject to the Raynham and Taunton wetlands bylaws.
If Contractor erection, demolition, storage, or other procedures not originally allowed by existing environmental permits require work to occur in or otherwise impact water or wetland resource areas, the Contractor is advised that no associated work can occur until all required environmental permits have been either amended or obtained allowing such work. The Contractor must notify the MassDOT Highway Division District 5 Highway Director and Resident Engineer in writing at least 60 days prior to commencement of the proposed activity. All environmental submittals, including any contact with Local, State, or Federal environmental agencies, must be coordinated through the MassDOT Highway Division District 5 Environmental Engineer. The Contractor is expected to fully cooperate with requests for information and provide same in a timely manner.
The Contractor is further advised that the Department will not entertain a delay claim due to the time required to modify or obtain the environmental permits.
Army Corps of Engineers – Section 404 General Permit Coverage Work under this project is subject to Section 404 of the Federal Clean Water Act, 33 U.S.C. 1251 et seq and is authorized under the Department of the Army Nationwide Permits (NWPs). Activities are eligible for coverage under the NWPs provided that 1) the activity meets the terms and conditions of applicable NWPs and General Conditions (GCs), and 2) the activity is demonstrated to qualify as non-reporting or a Pre-Construction Notification (PCN) is submitted to the Corps. A PCN was submitted at a point in time where the Massachusetts General Permits were still in effect, and the PCN therefore listed the applicable GPs (23 & 24) for the work proposed under this project.
The verification letter from the Corps indicates that the project is authorized under NWP 14: Linear Transportation Projects. The NWP is considered part of this contract and a copy of the entire NWP document, PCN authorization and all associated plans/attachments shall be maintained on-site while activities regulated by the NWP are being performed.
A00801 - 13
ENVIRONMENTAL PERMITTING (Continued)
The Contractor is hereby notified that he/she will be responsible and held accountable for performing any/all work necessary to satisfy and comply with the entire NWP document.
The Contractor is advised that no additional compensation will be allowed for work required to establish, achieve, and maintain compliance with the NWP, as payment for the work shall be included in the various bid items, unless specified elsewhere. This work may include, but is not limited to, the following: the hiring and paying for the services of a Professional Biologist, Botanist, Wetland Scientist, Engineer, Landscape Architect, etc.; preparation and submission of as-built plans; wetland flagging; wetland replication monitoring reports, etc.
MassDEP – Section 401 Water Quality Certification This project is subject to Section 401 of the Federal Clean Water Act and has been issued a Water Quality Certification (“WQC”) by the Department of Environmental Protection. The WQC and Application are to be considered part of this contract and a copy of the WQC and all plans/attachments shall be on-site while activities regulated by the WQC are being performed. The Contractor’s attention is directed to the fact that special conditions and other requirements are associated with this WQC and Application. It is the Contractor’s responsibility to be aware of and comply with these conditions and requirements and plan his/her work and schedule accordingly.
The Contractor is hereby notified that he/she will be responsible and held accountable for performing any/all work necessary to satisfy and comply with the entire WQC and Application. The Contractor is advised that no additional compensation will be allowed for work required to establish, achieve, and maintain compliance with the WQC and Application, as payment for the work shall be included in the various bid items, unless otherwise specified. This work may include, but is not limited to, the following: preparation and submission of as-built plans;
wetland flagging; wetland replication monitoring reports; preparation of the construction period erosion, sedimentation, and pollution prevention plan (CP/PP); etc.
Orders of Conditions Orders of Conditions have been obtained from the Raynham and Taunton Conservation Commissions for work in and around the onsite resource areas. Payment for work required by the Orders of Conditions and any Special Conditions, unless otherwise provided for, shall be considered incidental to other items, and no additional payment shall be made for this work.
Wetlands Protection Signage This project is subject to Taunton Wetlands Protection Ordinance and the Raynham Wetlands Protection Bylaw, refer Document A00861. Signs shall be in accordance with the latest MassDOT Construction Standards. All costs for the manufacture, erection, maintenance, moving, and removal of the signs shall be absorbed by the Contractor with no additional compensation other than the contract unit prices.
For this project, one (1) sign will be required in each municipality. The sign in Taunton shall read "Taunton ConCom N1394" and the sign in Raynham shall read "Approved by Town of Raynham Wetlands Protection Bylaw Ch. 336 on date: 4-27-2026”.
Demolition Plan A work plan describing the means of methods of demolition and associated measures for protecting the Taunton River from discharge of debris shall be provided in narrative format for review and approval by MassDEP as required by the 401 WQC.
A00801 - 14
ENVIRONMENTAL PERMITTING (Continued)
Dredged Material Dewatering Plan A Dredged Material Dewatering Plan shall be prepared and submitted to MassDEP for review and approval as required by the 401 WQC. At a minimum, the Plan shall include but not be limited to the type of containment, method of dewatering (i.e. mechanical or by gravity), method of collecting the dewatered effluent and method of disposal.
Certification of Erosion and Sedimentation Control Measures As required by the Order of Conditions issued by the Raynham Conservation Commission(Document A00861), a Massachusetts registered professional engineer must submit written certification to the Conservation Commission that all erosion control measures are properly installed before the beginning of any work. The location of the erosion control measures shall be certified by a Massachusetts registered land surveyor prior to start of any site work. The Contractor is responsible for retaining the required licensed professional to complete this task.
Wildlife Shelf Dumped riprap shall be placed in a manner to create a wildlife shelf at the top of the streambank along the southern abutment as shown on the project plans. This shelf must be leveled out with chinked-in stones as required by the 401 WQC.
Recreational Boating Access As required by the Corps NWP authorization letter, boating (canoe/kayak or other) shall be safely maintained throughout the duration of the project either through the existing river channel or through a temporary portage trail. If this boating cannot be safely maintained, signage must be posted at the upstream and downstream boating access sites to inform the public of the river closure.
Resource Area Flagging All flagging demarcating boundaries of Resource Areas at the site shall be reestablished prior to construction as required by the 401 WQC and the Orders of Conditions.
Test Pits As required by the 401 WQC, the Contractor shall complete test pits to confirm the elevations of Estimated Seasonal High Groundwater. The Engineer shall be contacted to witness test pit excavation.
TIME-OF-YEAR (TOY) RESTRICTIONS
As required by the environmental approvals obtained for the project, no in-water work shall take place during the spring TOY restriction from March 1 to July 15 or the fall TOY restriction from September 1 to November 15 of any year(s).
A00801 - 15
GENERAL REQUIREMENTS FOR DEMOLITION AND
WORK INVOLVING PAINTED STEEL
(02/06/2020)
Demolition and work involving painted steel shall conform to the requirements of Document 00961.
Work Involving Painted Steel.
Hazardous materials shall be removed in the immediate area of any intended welding, heating, saw cutting or burning of steel. Hazardous material removal is required to allow the demolition of structural steel, railings, drainage systems, utility supports, steel lamp posts, etc.
The contractor shall assume that the coatings on the steel contain lead (Pb), unless otherwise determined by testing. The contractor shall certify in writing to the Engineer the results of all testing, and shall also certify that any lead (Pb) coated steel removed from the project was not reused or buried, but was sent to a scrap metal recycling facility.
Implement and maintain programs and procedures, which comply with the requirements of this specification and all applicable standards and regulations. Comply with all applicable regulations even if the regulation is not specifically referenced herein. If a state or local regulation is more restrictive than the regulation of this specification, follow the more restrictive requirements.
This requirement is intended only for the demolition and preparation prior to repair and does not include provisions for recoating of steel.
Environmental
All applicable portions of Subsections 961.65 “Worker Protection” and 961.66 “Environmental Protection and Monitoring” shall be followed when performing this work.
During chemical stripping a hand washing facility may be used in lieu of a decontamination/changing facility.
Hazardous material shall be collected during the disassembly and disposed of as outlined in Subsection 961.68 “Handling of Hazardous Waste and Reporting Release Programs”.
The applicable submittals shall be according to Subsection 961.69 “Submittals”.
A00801 - 16
GENERAL REQUIREMENTS FOR DEMOLITION AND
WORK INVOLVING PAINTED STEEL (Continued)
Cleaning/Removal
Cutting Or Burning Of Steel
All surfaces to be welded, heated, saw cut or burned shall be cleaned so as to remove all contaminants and/or hazardous materials, which could be discharged to the environment as a function of the subsequent operations.
Lead paint shall be removed in its entirety in an area prescribed by a 6 inch (15 cm) minimum offset from the required work. The paint removal operation may be dry abrasive blasting, wet abrasive blasting or chemical stripping.
Proper level of containment shall be used when performing this work in accordance with Subsection 961.67 “Containment”. Full containment is not required during chemical stripping operation however; the Contractor shall install proper shielding and/or tarpaulins under the chemical stripping operations in order to catch all debris generated during this procedure. A cleaned area must be inspected and approved before the demolition operations are started.
During cleaning operations the Contractor shall be required to furnish and erect temporary floodlights illuminating the steel surface at a minimum of 30-foot candles. This lighting shall be used in areas where there is insufficient lighting for proper cleaning operations and inspection.
The Contractor shall supply electrical power.
The Contractor shall provide support for interim and final inspection of the bridge during cleaning operations. This support shall include the necessary traffic controls and safe access to the work.
Mechanical Disassembly Of Steel
All surfaces to be mechanically disassembled by shear cutting or removing bolts or rivets shall not require deleading. When shear cutting or removing bolts or rivets, the Contractor shall not use any method that will cause dust and/or particles to be emitted and/or dispersed into the environment to an extent that would expose the workers above the Action Levels of 30µg/m3.
For purposes of limiting the lead (Pb) dust, the Contractor will be required to dampen the lead paint work areas.
The contractor shall install a proper shielding and/or tarpaulins under all lead-paint-coated surfaces to be shear cut or bolts or rivets ordered removed in order to catch any loose lead paint chips, dust or particles.
A00801 - 17
NORTHERN LONG-EARED BAT AND TRICOLORED BAT PROTECTION
The northern long-eared bat (Myotis septentrionalis; NLEB) and tricolored bat (Perimyotis subflavus; TCB) are listed as federally endangered or proposed endangered, respectfully, under the Endangered Species Act (ESA). The U.S. Fish and Wildlife Service (USFWS) developed this guidance to address ESA compliance and promote conservation of NLEB and TCB. This project has been consulted with the USFWS through the Federal Highway Administration (FHWA), Federal Railroad Administration (FRA), and Federal Transit Administration (FTA) Programmatic Biological Opinion/Conference Opinion for Transportation Projects in the Range of the Indiana bat, northern long-eared bat, and tricolored bat, dated December 13, 2024. and generated a May Affect, Not Likely to Adversely Affect (NLAA) determination (see Document A00844). Subsequently, the project has completed Section 7 consultation under the ESA.
In advance of the uplisting of the TCB to endangered under the ESA, the following Avoidance and Minimization Measures (AMMs) must be strictly adhered to in order to protect NLEB and TCB and to be in compliance with the ESA. Contact MassDOT Environmental Services - Wildlife Unit Supervisor for questions about project limits, restrictions, or conservation measures.
General AMM
• The Contractor shall ensure all personnel working in on the project site are aware of all environmental commitments related to NLEB and TCB, including all applicable AMMs. NLEB and TCB information (https://www.fws.gov/midwest/endangered/mammals/nleb/ and https://www.fws.gov/species/tricolored-bat-perimyotis-subflavus) shall be made available to all personnel.
• On June 2, 2025, MassDOT Highway Division Environmental Services conducted a northern long-eared bat summer presence/absence survey, in accordance with the 2025 survey guidelines.
The survey did not confirm the presence of NLEB and/or TCB. If work is proposed by the Contractor past June 2, 2030 additional review is required by the MassDOT Highway Division’s Environmental Services Section, and additional review and restrictions may be required by the USFWS.
Bridge AMM
• On June 2, 2025, MassDOT Highway Division Environmental Services, conducted a northern long-eared bat bridge/structure bat assessment, in accordance with the USFWS guidelines. The assessment did not find presence of, or evidence of use by bats, and as stated within the guidelines, the assessment is valid for two years. If bridge work is not complete before June 2, 2027 assessment of the bridge for the presence of, or evidence of use by, bats shall be completed by the MassDOT Wildlife Unit prior to continuing bridge work. The Contractor shall notify the MassDOT Wildlife Unit no later than fourteen (14) days prior to June 2, 2027 to provide adequate time for inspection. If bats are found to be present, or, if there is evidence of bat usage, work at the bridge shall not commence until after the MassDOT Wildlife Unit has completed coordination with the US Fish and Wildlife Service to determine the appropriate follow up or mitigation actions.
https://www.fws.gov/midwest/endangered/mammals/nleb/
A00801 - 18
PIGEON WASTE
The Contractor shall remove and dispose of the pigeon waste and any other debris accumulated on the steel members and bridge seats in areas where work is being performed. Pigeon waste and debris material contaminants will require special handling and disposal in accordance with all Federal, state, and local requirements. No separate payment will be made for removal and disposal of pigeon waste. Cost shall be incidental to the contract pay items.
NOTIFICATION OF FUNDING SOURCES FOR WORK TO BE PAID BY OTHERS
This contract has an agreement with the City of Taunton; whereas when the construction costs for the contract scope exceed the total participating contract bid price by more than ten percent (10%), the City of Taunton shall be responsible for the amount over 110% of the total participating contract bid price.
ASBESTOS CONDUIT
Utility conduits are considered suspect materials for asbestos. Please determine whether asbestos is present in existing drainage pipe and utility conduits to be removed throughout the project corridor. Item 182.1 – Inspection and Testing for Asbestos (if needed) and Item 182.2 – Removal and Disposal of Asbestos is included in the contract.
CONTAMINATED SOIL
Soil to be removed from the project area shall not be assumed to be uncontaminated and must be evaluated prior to off-site management for potential contamination with hazardous materials. No soil may be disposed of off-site without proper assessment by the contractor and approval from the Resident Engineer (RE), District Environmental Engineer (DEE), or the project designee.
A00801 - 19
NOTICE TO OWNERS OF UTILITIES
(Supplementing Subsection 7.13)
Written notice shall be given by the Contractor to all public service corporations or municipal and State officials owning or having charge of publicly or privately owned utilities of his intention to commence operations affecting such utilities at least one (1) week in advance of the commencement of such operations. Privately owned utility companies (ex: Eversource-Gas) require 30 days written notice before the start of any work. The Contractor shall, at the same time, file a copy of such notice with the Engineer. The Contractor shall ensure that all affected utilities / agencies are notified.
The following website lists the names and addresses of the utilities may be affected, but the completeness of the list is not guaranteed:
https://www.mass.gov/info-details/utility-contacts-by-district-and-municipality
Select District 5 Select the Raynham Town and Taunton City, and then locate the utility
Town/City officials are shown at website https://www.mass.gov/lists/massachusetts-cities-and-towns and select the required City/Town website.
State Police are shown at website https://www.mass.gov/info-details/massachusetts-state-police-troop-boundaries. Select the area of jurisdiction to find the local station.
The following is the name and addresses of the agency which may be affected and must be notified. Completeness is not guaranteed by the Department. The Contractor shall assure that all affected agencies are notified.
https://www.mass.gov/info-details/utility-contacts-by-district-and-municipality https://www.mass.gov/lists/massachusetts-cities-and-towns https://www.mass.gov/lists/massachusetts-cities-and-towns https://www.mass.gov/info-details/massachusetts-state-police-troop-boundaries https://www.mass.gov/info-details/massachusetts-state-police-troop-boundaries
A00801 - 20
NOTICE TO OWNERS OF UTILITIES (Continued)
RAYNHAM - Pole Data
Municipality Pole Set Responsibility Updated RAYNHAM & TAUNTON Taunton Municipal Light/Verizon 1/11/2018
District Utility/Constructability Engineer
County District Contact Phone Email Bristol 5 Christopher Lockett 857-368-5073 Christopher.lockett@state.ma.us
Utility Data
Electric
Company Address City State Zip Updated Taunton Municipal Lighting Plant
P.O. Box 870 Taunton MA 02780 7/8/2009
Contact Office Extension Email
Joe Fernandes 508-824-5844 3179 josephfernandes@tmlp.com 9/4/2012
Gas
Company Address City State Zip Updated Eversource Gas 995 Belmont St. Brockton MA 02301 1/8/2021
Brendan Pitts 508-895-4818 brendan.pitts@Eversource.com 12/4/2023
A00801 - 21
Telephone
Verizon 385 Myles Standish Blvd. Taunton MA 02780 11/8/2013
Evan McSorley 774-409-3184 evan.mcsorley@verizon.com 9/29/2025
Water Raynham
Raynham Center Water District
P.O. Box 160 Raynham MA 02767
William Ward 508-824-0020
4/24/2013
Water - Taunton
Taunton DPW-Water Division
90 Ingell Street Taunton MA 02780 7/28/2010
Mike Arruda 508-823-3582 marruda@taunton-ma.gov
4/5/2022
Sewer – Raynham
Raynham Sewer Dept. 416 Titicut Rd. Raynham MA 02767
Carly Brady 508-824-2749 cbrady@raynhamsewer.com 7/29/2026
A00801 - 22
Sewer – Taunton
Veolia Water (Municipal)
825 West Water St Taunton MA 02780 3/24/2010
Mike Arruda 508-823-3582 marruda@taunton-
Cable
Comcast Cable Corporation PO Box 6505, 5 Omni Way Chelmsford MA 01824 8/8/2018
Michael Cook
Michael_Cook7@comcast.com 12/24/2025
DPW – Raynham
Raynham Hwy. Dept. 1555 King Phillip Street Raynham MA 02767
Norm Sturtevant 508-824-2718 nsturtevant@town.raynham.ma.us 5/6/2025
Elizabeth Glidden elizabeth.glidden@vzw.com 3/25/2025
A00801 - 23
DPW – Taunton
City State Taunton MA
Michael Patneaude 508-821-1027 mpatneaude@taunton-
Railroad
MBTA Archives & Digital Asset Preservation
10 Park Plaza Boston MA 02116 8/1/2024
Sylvia Welsh archives@mbta.com 8/1/2024
Mass Coastal Railroad
12 Harding Street, Unit 202
Lakeville MA 02347 6/18/2019
Chris Podgurski 508-291-2116 cpodgurski@capetrain.com 3/11/2015
CSX Transportation 2000 West Cabot
Blvd - Suite 130 Langhorne PA 19047 2/13/2023
Michael Sliper 518-767-6081
Michael_Sliper@csx.com…