This document outlines the requirements for a contractor-provided work order processing system for the Defense Commissary Agency (DeCA) Supply Directorate locations. The contractor shall provide a computerized work order reception platform capable of receiving, storing, and processing DeCA-generated work repair requests within response times specified in the Performance Work Statement. The system must utilize commercial software to manage work orders, identify and annotate on-site inconsistencies, and maintain an updated database. The contractor is required to deliver monthly reports summarizing all completed work orders with each month's invoice.
The work order system must incorporate strict access controls, with only named individuals from each site, the Contracting Officer's Representative (COR), and contracting staff granted access. Actions estimated at EUR 2,000 or less are input at the site level, while all other work tasks require engineering input. The system must capture nine specific data points on every work order, including DeCA inventory number, nature of the problem, location, service type (PM/EM/UM), proposed solution with technical and cost details, schedule tracking, work completion documentation with photos, third-party inspection requirements, and site staff acceptance signatures. The Government requires an electronic or digital solution capable of capturing physical signatures from site staff and initials from technicians, with completed work order forms serving as supporting documents that are uploaded into the work order reception system.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A.15.01.03.07 Annex G delivery matrix.xlsx | XLSX spreadsheet | |
| A.15.01.03.04 Annex D Inventory Label Instructions.pdf | ||
| A.15.01.03.01 Annex A Items that may require repair.xlsx | XLSX spreadsheet | |
| A.15.01.03.06 Annex F Inventory Change Criteria.pdf | ||
| A.15.01.03.05 Annex E Emergency Criteria.pdf | ||
| A.15.01.03.08 Annex H Perfromance Requirement Summary.xlsx | XLSX spreadsheet | |
| A.15.01.03.03 Annex C current inventory SPA.xlsx | XLSX spreadsheet | |
| A.15.01.03.02 Annex B Items Excluded from Contract.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTOR PROVIDED WORK ORDER SYSTEM
If requested by the COR or KO, the Contractor shall provide a work order processing system. This system shall have the following features.
1. Work Order Reception Service For the Supply Directorate locations, the contractor shall provide computerized work order reception services. Access to an online computer work order reception platform shall be provided. DeCA generated work repair requests shall be received, stored, dates recorded, proposals issued, and work completion stored to each request within the response times outlined in the PWS.
2. The contractor shall have and maintain a commercial type of software program that uses the given information for work orders. The contractor shall identify on-site inconsistencies, annotate all inconsistencies on the work order, and update the database with the correct information.
3. A monthly report of all work orders completed shall be provided as a summary wrap up with each month’s invoice.
4. Work Control: Work order control log. The contractor shall only accept service requests which were created in the computerized work reception platform only, other formats shall not be accepted by the contractor. Content of the work orders shall be an agreed to format by the contractor and COR prior to access being granted to the Supply Chain Directorate staff. Only named individuals from each site, the COR, and contracting staff will be given access to the system and input access. Any action estimated at EUR 2000 or less will be input at the site level, all other work task must be input by engineering.
5. Basic Outline of Work Order Form:
The following data points shall be checked, verified, initialed, and signed for completion (digitally on the work order) by the Supply Chain Directorate Staff on every work order:
1. DeCA Inventory number
2. Nature of the problem
3. Location of the Inventory
4. Nature of services being requested (PM/EM/UM) (TECHNICAL/SCHEDULE and any unique site constraints)
5. Solution/Proposal Proposed (TECHNICAL/SCHEDULE/COSTS)
6. Schedule Tracking
7. Work Completion (Documentation and Photo)
8. Third Party Commissioning/Inspection Services Required (Y/N). COR/Site Staff to Determine.
9. Site Staff Signature of Acceptance of Operability
All information shall be recorded, entered, and verified in the contractor’s computer system accurately for each Work Order.
6. The Government will only accept an electronic or digital solution in order to achieve the work order form as outlined. The electronic or digital solution must be capable of capturing a physical signature from the site staff and initials from the technician. The work order form will act as a supporting document to all service/maintenance records and will be uploaded into the work order reception system.