This is a Scope of Work or Purchase Description document for a County procurement of an air compressor system installation project. The County seeks a vendor-furnished and installed compressor system with all labor, tools, rigging, and incidental materials required for mechanical assembly, connection to existing compressed air distribution infrastructure, and condensate drain line installation. The installation must be completed by August 17, 2026, and the project includes factory-authorized startup and commissioning with documentation submitted within five business days of completion. Vendor responsibilities encompass delivery via lift-gate equipped truck with offloading and staging at the installation site, operator and maintenance training of minimum two hours duration conducted by the vendor's factory-authorized technician, and provision of operation and maintenance manuals. The vendor must ensure all components and sub-assemblies can pass through a 46-inch wide doorframe without structural building modification and must coordinate delivery access with the County at least five business days in advance.
The pricing structure requires vendors to submit a total all-inclusive cost for the system, installation, training, and warranty as a single line item. The vendor is responsible for all required permits, licenses, and calibration certificates at vendor expense. The package includes a 24-month warranty on the compressor pump and a 12-month warranty covering parts and labor on the entire system, with an optional extended warranty coverage available on an annual basis for years one through five. The County is responsible for completing electrical rough-in (conduit, disconnect switch, and branch circuit wiring), providing a level reinforced concrete floor adequate for unit weight, and completing compressed air distribution piping beyond the system outlet connection point prior to startup and commissioning.
View the file
Other files
Show 40 more
Latest 50 of 143 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Item Quantity Units Description Cost
1 1 Each
Installation by August 17, 2026 (Must be installed by date.) Vendor shall furnish all labor, tools, rigging, and incidental materials required to set, assemble, level, anchor, and connect the compressor system at the designated installation location. Installation shall include: mechanical assembly and re-connection of any components disassembled for transport; connection to the existing compressed air distribution header at the point of connection identified by the County; connection of condensate drain lines to the nearest available floor drain; and verification that all safety devices, gauges, and controls are properly mounted and functional. Electrical rough-in (conduit, disconnect, and branch circuit wiring to the single power connection point on the unit) is the responsibility of the County and shall be completed prior to the Vendor’s installation visit.
Installation to be completed by:
Included
2 1 System
Model Type and Number:
BRAND NAME(s) OR EQUAL PURCHASE
DESCRIPTION:
3 1 System
SITE READINESS: The County shall provide a level, reinforced concrete or structural floor adequate for the unit weight prior to the scheduled installation date. Vendor shall provide certified weight data to the County not less than ten
(10) business days in advance of delivery to allow floor-loading verification. Included
ELECTRICAL ROUGH-IN (COUNTY-FURNISHED):
Electrical conduit, disconnect switch, and branch circuit wiring from the County facility panel to the single power connection point on the compressor unit is the responsibility of the County and shall be completed and inspected before the Vendor’s startup visit. County
COMPRESSED AIR DISTRIBUTION PIPING
(COUNTY-FURNISHED): Compressed air distribution piping beyond the system outlet connection point to the laboratory header is the responsibility of the County and shall be completed prior to the startup and commissioning visit. County
FACTORY-AUTHORIZED STARTUP AND
COMMISSIONING: Documentation of all commissioning data on a startup report to be submitted to the County within five (5) business days of completion. Included
6 1 System Training
OPERATOR AND MAINTENANCE TRAINING: The Vendor’s factory-authorized technician shall conduct on-site operator and maintenance training at the time of startup and commissioning. O&M manual is provided. Training shall be a minimum of two (2) hours in duration.
Included
7 24 Months Warranty – compressor pump ≥ 24 months from acceptance
Included
8 12 Months Warranty – system ≥ 12 months parts and labor
Included
CRITICAL:
All components and sub-assemblies of the air compressor package, whether shipped assembled or knocked down, must be capable of passing through a 46-inch (46") wide doorframe without structural modification to the building.
Included
DELIVERY:
F.O.B. – Destination: System shall be delivered via lift-gate equipped truck to the designated delivery point at the County facility. The Vendor shall offload and stage the equipment at the installation site. Any disassembly required for transport through the 46-inch doorframe shall be documented, and re-assembly instructions shall be provided. Vendor shall coordinate delivery access with the County not less than five
(5) business days before the scheduled delivery date.
Any required permits or licenses are the responsibility and cost of Vendor. Any calibration will have a certificate provided to the County at the responsibility and cost of Vendor. Included
12 All Costs Included
Total Costs with System, Installation, Training, and Warranty $
13 1-5 Annual Rate Optional Extended Warranty Coverage $
Vendor Name
Completed By
Date