9-UCA Geyser Peak Evaluation ScoreSheet v1.xlsx
XLSX spreadsheet 29 KB Posted
- Solicitation number
- GJ26-149
- Issued by
- Tooele County, Utah
About this file
This is an evaluation scoresheet for the Utah Communications Authority ("UCA") Geyser Peak New Site Build Project RFP, a state procurement for construction and equipment installation services at a remote communications site in Sevier County, Utah (GPS coordinates 38.511960, -111.460180). The project encompasses a multi-discipline off-grid communications tower and shelter installation requiring site preparation, tower foundation and erection (Sabre S3TL with 45-foot northeast leg ice shield and four ground bus bars), modular shelter installation (~12,000 pounds), propane tank and fuel line installation, solar photovoltaic systems (three sectors with twelve panels each), microwave and radio antenna and transmission line systems, ice bridge installation, facility grounding, and comprehensive testing and closeout documentation. Questions are due by May 19, 2026, at noon MT, with proposals due by May 22, 2026, at 10:00 AM MT via the U3P portal. Materials for the project will be picked up from the UCA Warehouse and UDOT Road Shed near Fish Lake (GPS coordinates 38.473200, -111.832516). The substantial completion date is July 31, 2026, requiring contractors to coordinate mobilization, foundation curing, equipment delivery and installation, testing, demobilization, and closeout within the specified timeframe while accounting for USFS coordination, weather conditions, road access limitations, and UCA material procurement dependencies.
The evaluation scoresheet uses a 1,000-point total scoring framework with cost integrated into the technical evaluation pursuant to a written waiver executed under Utah Code 63G-6a-707(7)(b). The technical scoring allocation is 750 points across five criteria: Contractor Experience and Past Performance (200 points), Project Team and Subcontractor Qualifications (100 points), Technical Approach and Work Plan (200 points), Project Schedule achievement (150 points), and Safety and Quality Assurance Program (100 points). Cost constitutes 250 formulaic points calculated by the procurement officer using the statutory formula: Cost Points = 250 × (Lowest Grand Total ÷ Offeror's Grand Total), with cost line items derived from 16 scope-area lump-sum prices submitted in each proposal's Appendix C. Three independent evaluators score technical criteria and provide written justifications; the procurement officer calculates cost points without subjective scoring. The final ranking averages the three evaluators' technical scores, adds calculated cost points, and flags which responsive offerors meet the 800-point minimum threshold required by RFP Section 12, with the highest-ranked offeror meeting the threshold receiving the award recommendation.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Instructions
| UCA Geyser Peak New Site Build Project — Evaluation Score Sheet | ||
| Overview | ||
| This workbook captures committee evaluation of proposals submitted under the UCA Geyser Peak New Site Build Project RFP. The scoring framework is 1,000 points total, with cost integrated into the technical evaluation under the waiver authority of Utah Code § 63G-6a-707(7)(b). The Procurement Official has executed a written waiver, which is on file with the UCA Procurement Unit and is reproduced in Section 9 of the RFP. | ||
| Scoring Framework — 1,000 Points Total | ||
| Component | Max Points | Scored By |
| 1. Contractor Experience and Past Performance | 200 | Each evaluator |
| 2. Project Team and Subcontractor Qualifications | 100 | Each evaluator |
| 3. Technical Approach and Work Plan | 200 | Each evaluator |
| 4. Project Schedule — July 31, 2026 Completion | 150 | Each evaluator |
| 5. Safety and Quality Assurance Program | 100 | Each evaluator |
| Cost Proposal (formulaic, integrated) | 250 | Procurement Officer (Cost_Calculation tab) |
| TOTAL POSSIBLE | 1000 | |
| Workflow | ||
| 1. The procurement officer fills in the Offerors tab with the names of each responsive offeror. | ||
| 2. Each evaluator opens their dedicated tab (Evaluator_1, Evaluator_2, Evaluator_3) and scores each offeror against the five technical criteria (Criteria 1–5, total 750 points possible per offeror). Evaluators provide written justification for each score. | ||
| 3. Cost is NOT scored subjectively. The procurement officer enters each offeror's 16 line-item lump sums into the Cost_Calculation tab (one column per offeror). The workbook auto-sums the line items into a Grand Total and applies the statutory formula: Cost Points = 250 × (Lowest Grand Total ÷ Offeror's Grand Total). The tab also captures the offeror's stated Grand Total from the bottom row of Appendix C and flags any inconsistency with the computed sum for procurement-officer attention. | ||
| 4. The Summary tab averages the technical scores across all three evaluators, adds the calculated cost points, totals out of 1,000, flags whether each offeror meets the 800-point threshold, and assigns a Rank. | ||
| 5. Each evaluator must sign and date their tab. All tabs together comprise the evaluation record retained under UCA's records-retention obligations. | ||
| Color Conventions | ||
| Blue text | Hardcoded inputs (evaluator scores, cost line-item prices entered by procurement officer) | |
| Black text | Formulas and calculations | |
| Green text | Cross-sheet references | |
| Yellow fill | Cells requiring input | |
| Statutory Authority | ||
| Utah Code § 63G-6a-707(7)(a) ordinarily requires that evaluation committee members not have access to cost information until after technical scoring is recommended. Subsection (7)(b) permits a procurement official to waive that prohibition by signing a written statement of best interest. The UCA Procurement Official has executed that waiver for this procurement; the waiver is on file with the UCA Procurement Unit and is set forth in Section 9 of the RFP. Accordingly, cost is integrated into the overall evaluation as the 250-point Cost component. |
Offerors
| Offeror Roster | ||
| The Procurement Officer fills in the responsive offerors below. Evaluator and Cost_Calculation tabs pull offeror names from this sheet automatically. Add or remove rows as needed; if you change the number of offerors, update the references in the other tabs. | ||
| Offeror # | Offeror Name (Firm) | Notes |
| Offeror 1 | [Enter Offeror 1 Firm Name] | |
| Offeror 2 | [Enter Offeror 2 Firm Name] | |
| Offeror 3 | [Enter Offeror 3 Firm Name] | |
| Offeror 4 | [Enter Offeror 4 Firm Name] | |
| Offeror 5 | [Enter Offeror 5 Firm Name] |
Evaluator_1
| Evaluator 1 — Technical Scoring (Geyser Peak) | |||||||
| Evaluator Name: | [Enter evaluator name] | ||||||
| Evaluator Role / Title: | |||||||
| Date of Evaluation: | |||||||
| Signature: | |||||||
| Instructions: Score each offeror against each criterion in the range 0 to the Max for that criterion. Provide written justification in the row immediately below each score row. Yellow cells require your input. The Subtotal row at the bottom auto-calculates. Do not score cost — cost is calculated separately by the procurement officer in the Cost_Calculation tab. | |||||||
| Criterion | Max | [Enter Offeror 1 Firm Name] | [Enter Offeror 2 Firm Name] | [Enter Offeror 3 Firm Name] | [Enter Offeror 4 Firm Name] | [Enter Offeror 5 Firm Name] | |
| 1. Contractor Experience and Past Performance — Multi-Discipline Site Builds | |||||||
| Unknown Author: Comparable off-grid or solar-powered communications site builds; new tower erection, modular shelter set, solar PV, propane, A&L, sweep/PIM, L3 Harris-compliant grounding; 5+ projects in past 5 years; USFS land experience helpful. | 200 | ||||||
| Justification / Notes | |||||||
| 2. Project Team and Subcontractor Qualifications | |||||||
| Unknown Author: Org chart with project manager, on-site superintendent, lead tower-erection foreman, sweep/PIM technician, Utah-licensed LP gas plumber (with license number), concrete subcontractor (if used), and electrical/PV lead. Climber/rescue, RF awareness, OSHA 10/30, first aid/CPR. | 100 | ||||||
| Justification / Notes | |||||||
| 3. Technical Approach and Work Plan | |||||||
| Unknown Author: Approach to each scope area: site prep, tower foundation (ACI 318-14, 4,500 psi, cylinder test), tower erection (Sabre S3TL with ice shield at 45' on NE leg and 4 ground bus bars), shelter foundation and set, propane plumbing, solar sectors, ice bridge, A&L (MW + radio with TTA, polyphasers, tape coding), sweep/PIM methodology, L3 Harris-compliant grounding. | 200 | ||||||
| Justification / Notes | |||||||
| 4. Project Schedule — July 31, 2026 Substantial Completion | |||||||
| Unknown Author: Schedule showing mobilization, foundation cure, tower erection, shelter delivery/offload, solar, propane, A&L, grounding, sweep/PIM, alignment, demob, closeout. USFS coordination, weather, road conditions, and UCA material pickup dependencies. | 150 | ||||||
| Justification / Notes | |||||||
| 5. Safety and Quality Assurance Program |
Unknown Author: Written safety plan, daily JHA/JSA, climber rescue plan, remote-site communications protocol; 3-yr EMR; 3-yr OSHA 300 recordables; QA for multi-discipline construction including grounding QC and L3 Harris manual protocol.
Unknown Author: Comparable off-grid or solar-powered communications site builds; new tower erection, modular shelter set, solar PV, propane, A&L, sweep/PIM, L3 Harris-compliant grounding; 5+ projects in past 5 years; USFS land experience helpful.
Unknown Author: Org chart with project manager, on-site superintendent, lead tower-erection foreman, sweep/PIM technician, Utah-licensed LP gas plumber (with license number), concrete subcontractor (if used), and electrical/PV lead. Climber/rescue, RF awareness, OSHA 10/30, first aid/CPR.
| Unknown Author: Approach to each scope area: site prep, tower foundation (ACI 318-14, 4,500 psi, cylinder test), tower erection (Sabre S3TL with ice shield at 45' on NE leg and 4 ground bus bars), shelter foundation and set, propane plumbing, solar sectors, ice bridge, A&L (MW + radio with TTA, polyphasers, tape coding), sweep/PIM methodology, L3 Harris-compliant grounding. | 100 | ||||||
| Justification / Notes | |||||||
| TECHNICAL SUBTOTAL (max 750) | 750 | 0 | 0 | 0 | 0 | 0 |
Evaluator_2
| Evaluator 2 — Technical Scoring (Geyser Peak) | |||||||
| Evaluator Name: | [Enter evaluator name] | ||||||
| Evaluator Role / Title: | |||||||
| Date of Evaluation: | |||||||
| Signature: | |||||||
| Instructions: Score each offeror against each criterion in the range 0 to the Max for that criterion. Provide written justification in the row immediately below each score row. Yellow cells require your input. The Subtotal row at the bottom auto-calculates. Do not score cost — cost is calculated separately by the procurement officer in the Cost_Calculation tab. | |||||||
| Criterion | Max | [Enter Offeror 1 Firm Name] | [Enter Offeror 2 Firm Name] | [Enter Offeror 3 Firm Name] | [Enter Offeror 4 Firm Name] | [Enter Offeror 5 Firm Name] | |
| 1. Contractor Experience and Past Performance — Multi-Discipline Site Builds | |||||||
| Unknown Author: Comparable off-grid or solar-powered communications site builds; new tower erection, modular shelter set, solar PV, propane, A&L, sweep/PIM, L3 Harris-compliant grounding; 5+ projects in past 5 years; USFS land experience helpful. | 200 | ||||||
| Justification / Notes | |||||||
| 2. Project Team and Subcontractor Qualifications | |||||||
| Unknown Author: Org chart with project manager, on-site superintendent, lead tower-erection foreman, sweep/PIM technician, Utah-licensed LP gas plumber (with license number), concrete subcontractor (if used), and electrical/PV lead. Climber/rescue, RF awareness, OSHA 10/30, first aid/CPR. | 100 | ||||||
| Justification / Notes | |||||||
| 3. Technical Approach and Work Plan | |||||||
| Unknown Author: Approach to each scope area: site prep, tower foundation (ACI 318-14, 4,500 psi, cylinder test), tower erection (Sabre S3TL with ice shield at 45' on NE leg and 4 ground bus bars), shelter foundation and set, propane plumbing, solar sectors, ice bridge, A&L (MW + radio with TTA, polyphasers, tape coding), sweep/PIM methodology, L3 Harris-compliant grounding. | 200 | ||||||
| Justification / Notes | |||||||
| 4. Project Schedule — July 31, 2026 Substantial Completion | |||||||
| Unknown Author: Schedule showing mobilization, foundation cure, tower erection, shelter delivery/offload, solar, propane, A&L, grounding, sweep/PIM, alignment, demob, closeout. USFS coordination, weather, road conditions, and UCA material pickup dependencies. | 150 | ||||||
| Justification / Notes | |||||||
| 5. Safety and Quality Assurance Program |
Unknown Author: Written safety plan, daily JHA/JSA, climber rescue plan, remote-site communications protocol; 3-yr EMR; 3-yr OSHA 300 recordables; QA for multi-discipline construction including grounding QC and L3 Harris manual protocol.
Unknown Author: Comparable off-grid or solar-powered communications site builds; new tower erection, modular shelter set, solar PV, propane, A&L, sweep/PIM, L3 Harris-compliant grounding; 5+ projects in past 5 years; USFS land experience helpful.
Unknown Author: Org chart with project manager, on-site superintendent, lead tower-erection foreman, sweep/PIM technician, Utah-licensed LP gas plumber (with license number), concrete subcontractor (if used), and electrical/PV lead. Climber/rescue, RF awareness, OSHA 10/30, first aid/CPR.
| Unknown Author: Approach to each scope area: site prep, tower foundation (ACI 318-14, 4,500 psi, cylinder test), tower erection (Sabre S3TL with ice shield at 45' on NE leg and 4 ground bus bars), shelter foundation and set, propane plumbing, solar sectors, ice bridge, A&L (MW + radio with TTA, polyphasers, tape coding), sweep/PIM methodology, L3 Harris-compliant grounding. | 100 | ||||||
| Justification / Notes | |||||||
| TECHNICAL SUBTOTAL (max 750) | 750 | 0 | 0 | 0 | 0 | 0 |
Evaluator_3
| Evaluator 3 — Technical Scoring (Geyser Peak) | |||||||
| Evaluator Name: | [Enter evaluator name] | ||||||
| Evaluator Role / Title: | |||||||
| Date of Evaluation: | |||||||
| Signature: | |||||||
| Instructions: Score each offeror against each criterion in the range 0 to the Max for that criterion. Provide written justification in the row immediately below each score row. Yellow cells require your input. The Subtotal row at the bottom auto-calculates. Do not score cost — cost is calculated separately by the procurement officer in the Cost_Calculation tab. | |||||||
| Criterion | Max | [Enter Offeror 1 Firm Name] | [Enter Offeror 2 Firm Name] | [Enter Offeror 3 Firm Name] | [Enter Offeror 4 Firm Name] | [Enter Offeror 5 Firm Name] | |
| 1. Contractor Experience and Past Performance — Multi-Discipline Site Builds | |||||||
| Unknown Author: Comparable off-grid or solar-powered communications site builds; new tower erection, modular shelter set, solar PV, propane, A&L, sweep/PIM, L3 Harris-compliant grounding; 5+ projects in past 5 years; USFS land experience helpful. | 200 | ||||||
| Justification / Notes | |||||||
| 2. Project Team and Subcontractor Qualifications | |||||||
| Unknown Author: Org chart with project manager, on-site superintendent, lead tower-erection foreman, sweep/PIM technician, Utah-licensed LP gas plumber (with license number), concrete subcontractor (if used), and electrical/PV lead. Climber/rescue, RF awareness, OSHA 10/30, first aid/CPR. | 100 | ||||||
| Justification / Notes | |||||||
| 3. Technical Approach and Work Plan | |||||||
| Unknown Author: Approach to each scope area: site prep, tower foundation (ACI 318-14, 4,500 psi, cylinder test), tower erection (Sabre S3TL with ice shield at 45' on NE leg and 4 ground bus bars), shelter foundation and set, propane plumbing, solar sectors, ice bridge, A&L (MW + radio with TTA, polyphasers, tape coding), sweep/PIM methodology, L3 Harris-compliant grounding. | 200 | ||||||
| Justification / Notes | |||||||
| 4. Project Schedule — July 31, 2026 Substantial Completion | |||||||
| Unknown Author: Schedule showing mobilization, foundation cure, tower erection, shelter delivery/offload, solar, propane, A&L, grounding, sweep/PIM, alignment, demob, closeout. USFS coordination, weather, road conditions, and UCA material pickup dependencies. | 150 | ||||||
| Justification / Notes | |||||||
| 5. Safety and Quality Assurance Program |
Unknown Author: Written safety plan, daily JHA/JSA, climber rescue plan, remote-site communications protocol; 3-yr EMR; 3-yr OSHA 300 recordables; QA for multi-discipline construction including grounding QC and L3 Harris manual protocol.
Unknown Author: Comparable off-grid or solar-powered communications site builds; new tower erection, modular shelter set, solar PV, propane, A&L, sweep/PIM, L3 Harris-compliant grounding; 5+ projects in past 5 years; USFS land experience helpful.
Unknown Author: Org chart with project manager, on-site superintendent, lead tower-erection foreman, sweep/PIM technician, Utah-licensed LP gas plumber (with license number), concrete subcontractor (if used), and electrical/PV lead. Climber/rescue, RF awareness, OSHA 10/30, first aid/CPR.
| Unknown Author: Approach to each scope area: site prep, tower foundation (ACI 318-14, 4,500 psi, cylinder test), tower erection (Sabre S3TL with ice shield at 45' on NE leg and 4 ground bus bars), shelter foundation and set, propane plumbing, solar sectors, ice bridge, A&L (MW + radio with TTA, polyphasers, tape coding), sweep/PIM methodology, L3 Harris-compliant grounding. | 100 | ||||||
| Justification / Notes | |||||||
| TECHNICAL SUBTOTAL (max 750) | 750 | 0 | 0 | 0 | 0 | 0 |
Cost_Calculation
| Cost Calculation — Line-Itemized (Procurement Officer Only) | ||||||
| Per the § 63G-6a-707(7)(b) waiver, cost is integrated into the evaluation at 250 points. Cost is not scored subjectively. Enter each offeror's Lump Sum Price for each of the 16 scope-area line items from Appendix C of their proposal (one column per offeror). The workbook auto-sums the line items into the COMPUTED GRAND TOTAL row. Also enter each offeror's STATED GRAND TOTAL (the figure they wrote on the bottom row of Appendix C); the consistency check row will flag any mismatch for your attention per RFP Section 9. The COST POINTS row applies the formula: Cost Points = 250 × (Lowest Computed Grand Total ÷ Offeror's Computed Grand Total). If you elect to score an offeror at zero cost points due to a material inconsistency (RFP Section 9), overwrite their COST POINTS cell with 0 and add a note. | ||||||
| Item | Scope Area | [Enter Offeror 1 Firm Name] | [Enter Offeror 2 Firm Name] | [Enter Offeror 3 Firm Name] | [Enter Offeror 4 Firm Name] | [Enter Offeror 5 Firm Name] |
| 1 | Site Preparation and Minor Grading | |||||
| 2 | Tower Foundation (ACI 318-14, 4,500 psi, cylinder testing) | |||||
| 3 | Tower Erection (Sabre S3TL, ice shield at 45' on NE leg, 4 tower ground bus bars) | |||||
| 4 | Shelter Foundation (23'-3" x 14' x 6" pad with footing and grounding conduit) | |||||
| 5 | Shelter Pickup, Transport, and Installation (~12,000 lb modular shelter) | |||||
| 6 | Propane Tank Installation (1,000-gal tank on 2x 4'x4' pads) | |||||
| 7 | Propane Fuel Line and Sensor Line (qualified Utah LP gas plumber) | |||||
| 8 | Ice Bridge Installation (24" x 10' section) | |||||
| 9 | Solar Installation (3 sectors x 12 panels; conduit and wiring) | |||||
| 10 | A&L — Microwave (6' dish at 40' centerline, LMR-400, ground kits) | |||||
| 11 | A&L — Radio System (RX/TX panels, TTA, polyphasers, coax, tape coding) | |||||
| 12 | Sweep Testing — All Coaxial Lines | |||||
| 13 | PIM Testing — TX Line | |||||
| 14 | Site Grounding — Exterior (L3 Harris T4618 Rev F) | |||||
| 15 | Mobilization, Demobilization, Travel, Lodging, Per Diem | |||||
| 16 | Closeout Package (Attachment H photos, sweep/PIM, cylinder test, as-builts) | |||||
| COMPUTED GRAND TOTAL (sum of items 1–16) | ||||||
| OFFEROR'S STATED GRAND TOTAL (from Appendix C bottom row) | ||||||
| Internal Consistency Check (Computed vs Stated, within $1) | ||||||
| COST POINTS (Max 250) | ||||||
| Notes (consistency exceptions, scoring overrides, etc.) | ||||||
| Procurement Officer: | ||||||
| Signature: | ||||||
| Date: |
Summary
| Evaluation Summary and Final Ranking — Geyser Peak | |||||||||
| Final scores: average of the three evaluators' technical subtotals (out of 750), plus the calculated cost score (out of 250), for a total out of 1,000. The 'Meets Threshold?' column flags whether the offeror cleared the 800-point minimum required by RFP Section 9. The Rank column auto-assigns rank by Total score (1 = highest). The recommended award per RFP Section 12 is the responsive offeror with Rank 1, subject to meeting the 800-point threshold. | |||||||||
| Offeror # | Offeror Name | Evaluator 1 Tech (750) | Evaluator 2 Tech (750) | Evaluator 3 Tech (750) | Average Tech (750) | Cost Points (250) | TOTAL (1000) | Meets Threshold (≥800)? | Rank |
| Offeror 1 | [Enter Offeror 1 Firm Name] | 0.0 | 0.0 | 0.0 | 0.00 | ||||
| Offeror 2 | [Enter Offeror 2 Firm Name] | 0.0 | 0.0 | 0.0 | 0.00 | ||||
| Offeror 3 | [Enter Offeror 3 Firm Name] | 0.0 | 0.0 | 0.0 | 0.00 | ||||
| Offeror 4 | [Enter Offeror 4 Firm Name] | 0.0 | 0.0 | 0.0 | 0.00 | ||||
| Offeror 5 | [Enter Offeror 5 Firm Name] | 0.0 | 0.0 | 0.0 | 0.00 | ||||
| Note: To view offerors in rank order, click on the Rank column header (J) and use Excel's Sort & Filter → Sort Smallest to Largest. The Rank column auto-assigns rank by Total score (1 = highest). The recommended award per RFP Section 12 is the responsive offeror with Rank 1, subject to meeting the 800-point threshold. |