Construction - Trailer Site Preparation for Pharmacy Sterile Compounding - BLDG 164 Project #600-19-117 See Continuation Page
Solicitation number
36C25820B0014
Issued by

About this file

This document contains a federal construction solicitation for trailer site preparation services at a Veterans Affairs medical center. The solicitation calls for construction services including all labor and materials necessary to prepare the site and required utilities for a pharmacy sterile compounding trailer at Building 164 of the VA Long Beach Healthcare System in California. The requirement is classified as construction as it involves alteration of real property. The solicitation sets aside this opportunity exclusively for service-disabled veteran-owned small businesses and indicates the contracting agency is the Veterans Health Administration within the Department of Veterans Affairs.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Long Beach Healthcare System Tibor Rubin Medical Center

Form USIP 600-138-R2

Date:

GC Safety Manager:

Phone:

Start Date: Start Time:

End Date: End Time:

Oxygen Nitrous Oxide Air Vacuum

Feeder Panel (#_____) Riser Circuit (#_____)

Air Handler Exhaust Fan

Water Steam Natural Gas

Hot Water Cold Water Heating Sewer

Device Type: Device Identifier:

Sprinkler Fire Pump Jockey Pump

Smoke Heat Pull AV

Date:

Phone:

Narrative to include sequence to make utility safe and then bring back on line; SOP may be attached in lieu of a description.

Section C - Shutdown Process

Work order(s) placed. WO #'s_______________________________________________________

UTILITY AND SERVICE IMPACT PERMIT

Fire Suppression:

Initiating Device:

Other:

Prime Contractor:

Contractor POC:

HVAC:

PART I (Filled out by Contractor or Requestor)

Section A - Requestor Information

Section A - COR/PM Information

Medical Gas:

Electrical:

Section C - Systems

Plumbing:

Fire Alarm:

Section D - Purpose of Shutdown

PART II (Filled out by COR, Supervisor, or PM in coordination with Engineering M&O and Safety)

Section B - Areas Effected by Shutdown

List the rooms effected by the shutdown (Highlight rooms that contain Critical Mission equipment or functions)

Section B - Date and Time of Impact (21 day notice required)

Describe the purpose of the utility and/or system impact.

VA COR/PM:

When impacting fire alarm system utilize Worksheet A if shutdown effects only an individual device or system reset to restore to normal. Complete Parts II and III of this form if multiple devices or entire fire zone is affected.

Project #

Plant:

Map of impacted areas and control shutoff points included with this form

Utility and Service Impact Permit 1 of 2

Form USIP 600-138-R2

UTILITY AND SERVICE IMPACT PERMIT

Lockout: Simple Complex Form Attached (Complex Only) _____N/A

Electric "Live Work": Yes No Form Attached

Hot Taps:

Hot Work Permit: Yes No Form Attached

Hazard Assessment: Yes No Form Attached

ILSM: Yes No Form Attached

VISN Notification: Yes No Form Attached

ICRA: Yes No Form Attached

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

Service POC :__________________________ Title: ________________ Signature:____________________________

COR/Supervisor/PM : Signature: Date:

Shop Requiring Shutdown: __________________. Supervisor approval below:

Print name: Signature: Date:

Shop Requiring Shutdown: __________________. Supervisor approval below:

Print name: Signature: Date:

Shop Requiring Shutdown: __________________. Supervisor approval below:

Print name: Signature: Date:

OSEMS Safety Manager: Signature: Date:

General Foreman: Signature: Date:

Owning Section Chief: Recommendation: Approval Disapproval

Signature: Date:

Chief, Engineering Service: Date:

Section D - Special Issues Required (Forms highlighted below need to be posted in the jobsite)

NOT AUTHORIZED

Section B - Notification of Employees

Section A - Approvals

PART III (Routed to Signatures per Section A)

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Date: ______________

PART II Cont'd (Filled out by COR, Supervisor, or PM in coordination with Engineering M&O and Safety)

Affected employees shall be notified both before the onset of and after completion of the outage.

Construction Safety Committee Notified - Email: VHALONCSCNotifications@va.gov

General Notification (3 Days Out) - On schedule -Email: VHALONENGINEERINGACTIONITEM@va.gov

Section E - Service representative concurrence (Service POC will print name, job title, sign, and date)

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Date: ______________

Utility and Service Impact Permit 2 of 2

Form USIP 600-138-R2 Worksheet A

General Notes:

2. VA Facilitates all programing.

What type of device Fire Alarm: Device Type: Device Identifier:

Fire Suppression: Sprinkler Fire Pump Jockey Pump

Initiating Device: Smoke Heat Pull/AV

Electronics Contractor

Safety Office Other: .

Has Safety Service been informed? YES NO N/A

Describe the work that is being conducted:

Describe how this work will impact the fire alarm system:

Describe how long the fire alarm system will be affected- Time/date(s):

Additional Comments:

FIRE ALARM EQUIPMENT STATUS

REPORT OF ACTIONS

Who is putting the fire system into a trouble condition? (Name and Department/Section)

1. Fill out form to ensure an accurate account of the fire system is kept.

3. If fire alarm system is affected for more than 4 hours, ILSM and Fire Watch forms are needed. Final copies must be sent to the VA Electric Shop.

List the areas that will be affected - Building(s), Area(s), Floor(s)+1, etc.:

Worksheet A 1 of 1

Prime Contractor:
Contractor POC:
Start Date:
End Date:
Circuit:
Panel:
Device Identifier:
Smoke:
undefined:
Work orders placed WO s:
Service POC:
Service POC_2:
Service POC_3:
Service POC_4:
Service POC_5:
Service POC_6:
Service POC_7:
Service POC_8:
Service POC_9:
Service POC_10:
Service POC_11:
Service POC_12:
Service POC_13:
Title:
Title_2:
Title_3:
Title_4:
Title_5:
Title_6:
Title_7:
Title_8:
Title_9:
Title_10:
Title_11:
Title_12:
Title_13:
Text2:
Text3:
Text4:
Text5:
Text6:
Text7:
Text8:
Check Box9: Off
Check Box10: Off
Text11:
Check Box12: Off
Check Box13: Off
Check Box14: Off
Check Box15: Off
Check Box18: Off
Check Box19: Off
Check Box20: Off
Check Box21: Off
Check Box17: Off
Check Box23: Off
Check Box24: Off
Check Box25: Off
Check Box22: Off
Check Box26: Off
Check Box27: Off
Check Box28: Off
Check Box16: Off
Check Box29: Off
Check Box30: Off
Check Box32: Off
Text18:
Check Box31: Off
Check Box33: Off
Check Box34: Off
Check Box35: Off
Text19:
Text20:
Text21:
Shop Requiring Shutdown_3:
Shop Requiring Shutdown_2:
Shop Requiring Shutdown:
name3:
name4:
name5:
name2:
name1:
name:
Check Box2: Off
Check Box4: Off
Check Box3: Off
Check BoxFA: Off
Check BoxFA1: Off
Check BoxFA2: Off
Check BoxFA3: Off
Check BoxFA4: Off
Check BoxFA5: Off
Check Box5: Off
Check Box6: Off
Check Box7: Off
Check Box8: Off
Check Box11: Off
Text1:
Text9:
Check Box36: Off
Check Box37: Off
Check Box38: Off
Check Box39: Off
Check Box40: Off
Check Box41: Off
Check Box42: Off
Check Box43: Off
Check Box44: Off
Check Box45: Off
Text46:
Check Box47: Off
Text50:
Text51:
Text52:
Text53:
Text54:
Text56:

File details come from the government source that posted it. Updated .