About this file

This document outlines requirements for a construction permit and related federal contract opportunity. The construction permit application requests approval for above ceiling and wall penetration work at the VA Long Beach Healthcare System. It specifies requirements for sealing penetrations, safety precautions, and includes a job safety analysis. The related federal contract opportunity is a 100% SDVOSB set-aside solicitation to prepare the construction site for a pharmacy sterile compounding trailer at the VA Long Beach facility. The requirement includes all labor, materials, and utilities necessary for site preparation. The solicitation number is 36C25820B0014 and responses were due on the attached issue date. The Department of Veterans Affairs Veterans Health Administration VISN 22 is the contracting agency.

View the file

Other files

File Type Posted
11. DBA Wage Determination CA20200022 - 08-07-2020 .pdf PDF
15. 600-19-117 (Pharmacy Trailer)_Specs_Addendum 1.pdf PDF
17. Cable Instal Label Test SOP 07-013 Ver. 2.pdf PDF
13. 000110 - Specs TOC_Addendum 1 .pdf PDF
19. 600-19-117 (Trailer Site Prep) RFI Log Trailer_2020818.docx DOCX document
14. 600-19-117 (Pharmacy Trailer)_Plans_Addendum 1.pdf PDF
16. Hirsch_TS_ScramblePad_Reader_Family_DS.pdf PDF
36C25820B0014 0002.docx DOCX document
18. Site Visit Sign-In Sheet - 600-19-117 - 36C25820B0014 - Trailer Prep Site.pdf PDF
36C25820B0014 0001.docx DOCX document
IFB - 36C25820B0014 - Trailer Prep Site .docx DOCX document
10 - Meeting Minutes Fillable.pdf PDF
36C25820B0014_1.docx DOCX document
12 - VHA STANDARDIZED VENDOR FILE PROCEDURE.docx DOCX document
7. IMS SOP 07-013 Cable Installation Labeling and Testing Ver. 2.pdf PDF
8. Excavation Permit.pdf PDF
2. 600-19-117 Plans & Designs.pdf PDF
1. 600-19-117 Specs.pdf PDF
9. Utility and Service Impact Permit Form (USIP 600-148-R2)-07.10.2020.pdf PDF
11 - DBA Wage Determination CA20200022 - 07-10-2020 .pdf PDF
6. VALBMC Hot Work Permit.pdf PDF
4. VA Energized Work Permit.pdf PDF
3. Mobile Crane Permit 08-2017.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

VA Long Beach Healthcare System (VALBHS)

Above the Ceiling & Penetration Permit This permit requests must be submitted through the Fire & Life Safety PM, or Safety designee; 48 working hours in advance, before the start of any work. For emergency permit requests, call (562)826-8000 or ext. 3153.

Contact: VALBMC FLS PM Page 1 of 2 Form – FLS 5 (562)676-2236 or Ext. 3153 Rev: Sept. 2019 By: MB

Penetration - Life Safety Deficiency / ILSM Considerations

Horizontal or vertical penetrations, in: 1.) existing structure 2.) New construction

Smoke Barriers: YES NO Fire Barriers: YES NO

Will fire sprinklers, fire alarm system/devices be affected?................. YES NO

Will work have PACM (potentially asbestos containing material) exposure? …. YES NO

Other: ___________________________________________________________________________________

Acknowledgments/Approvals (print, sign, date):

General Contractor: ______________________________________________________ Date: __________________

*Acknowledges and is responsible for compliance with OSHA, IBR CONCENSUS STANDARDS and VHA requirement, for all work processes performed at VALBMC; and has read and understood reverse page information this permit.

1. Approved/Disapproved: _______________________________________________ Date: __________________

(Project Engineer: RE/COR)

2. Approved/Disapproved: _______________________________________________ Date: __________________

(Section Chief/Shop Supervisor)

3. Concur/Non-concur: __________________________________________________ Date: __________________

3.a Permit Expiration Date: _______________________________________________________________________

(Life Safety Officer)

Final, completion of work Inspection: ____________________________________________ Date: __________________

(COR)

Requestor: Date of Request: Date of Request:

COR/Requester’s HCG/Shop: Phone#:

Est. start of work – Date: Time: Est. Compl. of work -Date: Time:

Affected Working Area Building(s) #: HCG/Service/Clinic:

Floor(s): Room(s)#: Other:

Immediate Area Affected:

Scope/Description of work to Be performed:

Actual Start, Date/Time of work: / Actual Compl., Date/Time of work: /

Responsible Party for Sealing Penetrations Supervisor’s Name: Company:

Supervisors’ Phone#: 24-HR Emergency Phone#:

Type of penetration sealant or fire stop:

(submit/attach: SDS and/or applicable fire stop manufacture specification)

Type of penetration sealant or fire stop:

(submit/attach: SDS and/or applicable fire stop manufacture specification)

UL/ASTM Approved for use? Yes No (ex: ASTM E814, UL1479, etc.)

VA Long Beach Healthcare System (VALBHS)

Above the Ceiling & Penetration Permit This permit requests must be submitted through the Fire & Life Safety PM, or Safety designee; 48 working hours in advance, before the start of any work. For emergency permit requests, call (562)826-8000 or ext. 3153.

Contact: VALBMC FLS PM Page 2 of 2 Form – FLS 5 (562)676-2236 or Ext. 3153 Rev: Sept. 2019 By: MB

The VALBMC expectation is full cooperation in complying with our efforts to maintain our fire/smoke barriers, throughout our facility; and providing a safe environment for: our patients, staff, students, and visitors.

A. General contractors, vendors and VA staff performing short/long term work, that requires aspects of permit, at the VA Long Beach Healthcare System shall:

1) Obtain fully approved Above-Ceiling-Work/Fire/Wall Penetration Permit; prior to the commencement of any work.

2) Requests must be submitted 48 working hours prior to the start of any work. Permits are valid for 24 hours. On a case-by-case basis, the maximum length of any permit is 1 working week.

3) Must specifically include all work areas affected and thorough scope of work, for operation.

4) Ensure a copy of valid permits, are conspicuously posted at work location; and readily available for inspection/verification, upon request.

5) Permit must be accompanied by a completed and signed Infection Control Risk Assessment (ICRA) Form.

6) Upon completion of work and after COR’s final inspection. Permit is to be returned to the Safety Service’s

Fire and Life Safety PM to be filed: 1.). Permit, 2. JSA 3. SDS/MFG. Specifications.).

B. Permits shall be used to: 1.) Control, maintain and assure permanent record of any penetrations and/or drywall openings made in fire/smoke barriers. 2.) Ensure general safety precautions are addressed. Such as, but not limited to:

1) Secure the Area - placement of barricades or cones around work areas to prevent inadvertent access or exposure to all potential hazards associated with the scope of work to employees, patients, and visitors.

2) Not leave work area unattended - If work areas are left unattended for breaks or lunch, etc., ladders are stored safely, ceiling tiles are replaced, no wires, etc. are left in public access areas.

3) Securing the work tools and equipment so as not to create any hazard or be used as weapons.

C. General contractor scope of work shall include job specific Job Safety Analysis (JSA), to mitigate and address identified risk (ex: PACM, ILSM, Fall Protection, Electrical Safety, etc.). Attach JSA to permit request for VALBMC Fire & Life Safety Program Managers review.

D. General contractors, vendors are responsible for their employees, its agents or subcontractors; to be properly trained and knowledgeable on: 1.) The application of fire stopping materials. 2.) Scope of work. 3.) Applicable general safety, local policy & federal standards; and related environmental responsibility.

E. Within 24 hours or less, any penetrations made in a fire rated wall, ceiling, or floor; must be sealed.

Penetration seal work must be performed IAW applicable: manufacture specification, NFPA, consensus standard, and VA policy. The competed work must be visually inspected by the VA COR representative to verify integrity.

Under no circumstances will penetrations remain unsealed or open.

F. Please direct your questions to: Corresponding Engineering Contracting Officer Representative (COR), Project Engineer/designated representative, Unit Supervisor in charge of this project or the VA Life Safety Program Manger.

Requestor Date of Request:
Date of Request:
Phone:
Affected Working Area:
Buildings:
Floors:
Rooms:
Other:
Immediate Area Affected:
ScopeDescription of work to Be performed:
Other_2:
Responsible Party for Sealing Penetrations:
Supervisors Name:
Company:
Supervisors Phone:
24HR Emergency Phone:
General Contractor:
ConcurNonconcur:
3a Permit Expiration Date:
Final completion of work Inspection:
Date_5:
Vertical: Off
Horizontal: Off
Existing: Off
New: Off
CORRequesters HCGShop:
HCG/Service/Clinic:
UL/ASTM Approved for use?:
Type of penetration sealant or fire stop:
Approved/Disapproved:
Approved/Disapproved_2:
YES4: Off
YES3: Off
YES2: Off
YES1: Off
YES5: Off
NO5: Off
NO_2: Off
NO_1: Off
NO_4: Off
NO_3: Off
Date_Approved:
Date_GC:
Date_Approved2:
Date_Concur:
Time_EST START:
Date_EST START:
Date_EST COMPLETE:
Time_EST COMPLETE:
Date_ACTUAL START:
Time_ACTUAL START:
Date_ACTUAL COMPLETE:
Time_ACTUAL COMPLETE:

File details come from the government source that posted it. Updated .