IFB - 36C25820B0014 - Trailer Prep Site .docx

DOCX document 591 KB Posted

Attached to
Construction - Trailer Site Preparation for Pharmacy Sterile Compounding - BLDG 164 Project #600-19-117 See Continuation Page
Solicitation number
36C25820B0014
Issued by

About this file

This solicitation is for construction services to prepare the site and install required utilities for a pharmacy sterile compounding trailer at the VA Long Beach Healthcare System facility in Long Beach, California. The contractor will provide all labor, equipment, and materials to perform work in accordance with attached specifications, drawings, and other supporting documents. The estimated cost range is $500,000. The contract type is firm-fixed-price. The period of performance is 90 calendar days from notice to proceed. This requirement is 100% set aside for service-disabled veteran-owned small businesses. The solicitation includes instructions for site visits, questions, bid contents and due date, evaluation criteria, and other terms. The contracting agency is the Department of Veterans Affairs.

View the file

Other files

Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER

2. TYPE OF SOLICITATION

3. DATE ISSUED

PAGE OF PAGES

4. CONTRACT NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

6. PROJECT NUMBER

7. ISSUED BY

CODE

8. ADDRESS OFFER TO

a. NAME

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014)

STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION

SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES

NO

a.

Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b.

An offer guarantee is, is not required.

c.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d.

Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C25820B0014 X

TBD

600-20-2-5140-0040

600-19-117 Y

Department of Veterans Affairs NCO22-Gilbert Network Contracting 777 E. Missouri, Suite 300 Phoenix AZ 85014 Y

Department of Veterans Affairs Phoenix VA Healthcare System 777 E. Missouri, Suite 300 Phoenix AZ 85014 Dena Hallaren 602-795-4527 Construction - Project #600-19-117 – Trailer Site Preparation for Pharmacy Sterile at the Long Beach VAMC, in Long Beach, CA.

Reference the Following Interested Items along with all Clauses, Provisions and Instructions.

Section A: Price/Cost Schedule Section B: SOW Section D: Design, Specs and All Other Attachments for Bid content.

Section E: Instructions, Conditions and Other Statements to Bidders - To include the following:

- Details for Site Visit, RFI's, Bid Contents, Bid Due Date, Bid Opening, Bonding, NAICS, Magnitude, etc.

Bid amount shall list at a minimum Material cost, Labor cost, Overhead, Profit and list in a separate line a Grand Total. This information is required and will be used for possible future modifications.

The bids will be evaluated based on the Grand Total amount only.

Awardee shall perform work in strict accordance with General Specifications, Statement of Work, Attachments, Schedule, Site Drawings, and terms and Conditions set forth in the contract.

This requirement is 100% set aside for SDVOSB concerns.

x X

52.211-10 X

1pm 08-13-2020 X

14. NAME AND ADDRESS OF OFFEROR

15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE

FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (

26. ADMINISTERED BY

27. PAYMENT WILL BE MADE BY

PHONE:

FAX:

28. NEGOTIATED AGREEMENT

29. AWARD

Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code) (Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror) (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

600-3600162-5923-854200-3223 23NRNR000

777 E. Missouri, Suite 300 Phoenix AZ 85014

This is accomplished through the Tungsten Network located at:

http://www.fsc.va.gov/einvoice.asp This is mandatory and the sole method for submitting invoices.

Table of Contents

PART I - THE SCHEDULE1
SECTION A - SOLICITATION/CONTRACT FORM1
A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)1
A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION, ALTERATION, OR REPAIR)– BACK2
A.3 PRICE/COST SCHEDULE6
ITEM INFORMATION6
A.4 DELIVERY SCHEDULE6
SECTION B - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK7
B. STATEMENT OF WORK7
B.1 INTRODUCTION:7
B.2 BACKGROUND / DESCRIPTION OF WORK:7
B.3 CONSTRUCTION DOCUMENT:7
B.4 SPECIFICATIONS:7
B.5 SPECIFIC REQUIREMENTS:8
B.6 CONFORMANCE STANDARDS:10
B.7 HOURS OF COVERAGE:10
B.8 IDENTIFICATION, PARKING, NO SMOKING, AND VA REGULATIONS:11
B.9 INFORMATION SECURITY:11
B.10 POINTS OF CONTACT AND PHYSICAL LOCATION:11
B.11 PERIOD OF PERFORMANCE:11
B.12 SUBMITTALS:12
B.13 COMMENCEMENT, COMPLETION, AND PAYMENT FOR WORK:12
B.14 MODIFICATIONS:13
B.15 ACRONYMS:13
SECTION C - CONTRACT CLAUSES15
C.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984)15
C.2 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAR 2020)15
C.3 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)18
C.4 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) ALTERNATE II (APR 1984)21
C.5 SUPPLEMENTAL INSURANCE REQUIREMENTS22
C.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)23
C.7 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)26
C.8 VAAR 852.219-10 VA NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE (JUL 2019) (DEVIATION)26
C.9 VAAR 852.219-74 LIMITATIONS ON SUBCONTRACTING—MONITORING AND COMPLIANCE (JUL 2018)28
C.10 VAAR 852.223-71 SAFETY AND HEALTH (SEP 2019)29
C.11 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)30
C.12 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)30
C.13 VAAR 852.232-71 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS (INCLUDING NAS– CPM) (NOV 2018)30
C.14 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV 2018)33
C.15 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (APR 2019)34
C.16 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)35
C.17 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)36
C.18 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT ADMINISTRATION (APR 2019)36
C.19 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT (SEP 2019)37
C.20 VAAR 852.270-1 REPRESENTATIVES OF CONTRACTING OFFICERS (JAN 2008)38
SECTION D - CONTRACT DOCUMENTS, EXHIBITS, OR ATTACHMENTS40
D.1 LIST OF ATTACHMENTS40
SECTION E - SOLICITATION PROVISIONS42
E.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2020)42
E.2 52.209-13 VIOLATION OF ARMS CONTROLS TREATIES OR AGREEMENTS—CERTIFICATION (JUN 2018)46
E.3 52.216-1 TYPE OF CONTRACT (APR 1984)47
E.4 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (MAY 2014)48
E.5 52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)48
E.6 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)49
E.7 52.228-1 BID GUARANTEE (SEP 1996)50
E.8 52.233-2 SERVICE OF PROTEST (SEP 2006)51
E.9 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB 1995)51
E.10 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)52
E.11 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)52
E.25 INSTRUCTIONS, CONDITIONS, AND OTHER STATEMENTS TO BIDDERS53
1. PROJECT DESCRIPTION:53
2. PROJECT LOCATION:53
3. CONTRACTING OFFICER:53
4. CONTRACT SPECIALIST:53
5. TYPE OF CONTRACT:53
6. ESTIMATED COST RANGE:53
7. DESIGN:53
8. ESTIMATED COMPLETION TIME:53
9. PRE-BID CONFERENCE AND SITE VISIT:53
10. REQUEST FOR INFORMATION:54
11. BID CONTENTS:55
12. BID DUE DATE:55
13. PUBLIC BID OPENING:55
14. OFFER GUARANTEE (BID BOND):56
15. PAYMENT AND PERFORMANCE BONDS:56
16. DAVIS BACON WAGE RATE56
17. NORTH AMERICAN INDUSTRY CLASSIFICATION SYSTEM (NAICS)56
18. BUY AMERICAN ACT:56
19. AMENDMENTS:56
20. REPRESENTATIONS AND CERTIFICATIONS:56
21. SAFETY OR ENVIRONMENTAL VIOLATIONS AND EMR57
22. RESPONSIBILITY DETERMINATION57
23. PAYMENT VENDOR FILE58

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM NUMBER
DESCRIPTION OF SUPPLIES/SERVICES
QUANTITY
UNIT
UNIT PRICE
AMOUNT
1.00
JB
__________________
__________________

CONSTRUCTION SERVICES FOR PROJECT #600-19-117 TRAILER SITE PREPARATION FOR PHARMACY STERILE COMPOUNDING - BUILDING 164 AT THE VA LONG BEACH HCS.

PER ATTACHED STATEMENT OF WORK, DESIGN, SPECS AND ALL OTHER DOCUMENTS INCLUDED.

******Bid amount SHALL list Material cost, Labor cost, Overhead, Profit and in a separate line the Grand Total.*** Material Cost: $_______________ Labor Cost: $__________________ Overhead: $___________________ Profit: $________________________

GRAND TOTAL
__________________

A.4 DELIVERY SCHEDULE

ITEM NUMBER
QUANTITY
DELIVERY DATE
0001
SHIP TO:
Long Beach VA Healthcare System

5901 E. 7th Street

BLDG 164

Long Beach, CA 90822 5201

USA

1.00
90 Calendar Days after NTP
MARK FOR:
COR - TBA

Office: 562-826-8000 ext

Page 1 of

SECTION B - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

36C25820B0014

Page 1 of Page 1 of

B. STATEMENT OF WORK

Statement of Work Trailer Site Preparation for Pharmacy Sterile Compounding - Building 164 - Construction Services Project Number 600-19-117 VA Long Beach Health Care System (VALBHCS - 600)

B.1 INTRODUCTION:

This requirement is for construction services to provide all labor and materials necessary to prepare the site including all required utilities for the pharmacy sterile compounding trailer at Building 164 at VA Long Beach Healthcare System. (VALBHCS). This requirement is classified under construction as it calls for the alteration of real property.

B.2 BACKGROUND / DESCRIPTION OF WORK:

A. The Veterans Affairs Healthcare System located in Long Beach, California (600) requires construction services to perform site preparation for pharmacy trailer. This project was designed by MA Architects, Inc.

B.3 CONSTRUCTION DOCUMENT:

A. Contractor shall furnish all labor, equipment, certification, supervision, and materials necessary to perform all operations in connections with this order. Contractor shall perform work in strict accordance with the General Specifications, Statement of Work, schedule, and all other supporting documents for this contract to include, but not limited to the following documents:

1. Refer to SECTION D of Solicitation for attachments.

B.4 SPECIFICATIONS:

A. The VA Master Construction Specifications contain work procedures and material requirements designed to meet regulatory compliance requirements. Whenever possible, the Master Construction Specifications shall be used as the basis for project designs.

1. Refer to SECTION D of Solicitation for attachments.

B. A complete list of these specifications can be viewed at the following website: http://www.cfm.va.gov. Specifications which address CEOSH requirements include, but are not limited to, the following:

1. SECTION 00 01 15 – List of Drawing Sheets

2. SECTION 01 00 00 – General Requirements

3. SECTION 01 33 23 – Shop Drawings, Product Data, and Samples

4. SECTION 01 35 26 – Safety Requirements

5. SECTION 01 74 19 – Construction Waste Management

6. SECTION 01 91 00 – General Commissioning Requirements

7. SECTION 01 45 29 – Testing Laboratory Service

8. SECTION 02 41 00 - Demolition

9. SECTION 03 30 53 – (Short-Form) Cast-in-Place Concrete

10. SECTION 05 12 34 – Structural Steel For Fencing

11. SECTION 22 05 11 – Common Work Results for Plumbing

12. SECTION 26 05 11 – Requirements for Electrical Installations

13. SECTION 26 05 19 – Low Voltage Electrical Power Conductors and Cables

14. SECTION 26 05 26 – Grounding and Bonding for Electrical Systems

15. SECTION 26 05 33 – Raceway and Boxes for Electrical Systems

16. SECTION 26 05 73 – Overcurrent Protective Device Coordination Study

17. SECTION 26 08 00 – Commissioning of Electrical Systems

18. SECTION 26 22 00 – Low Voltage Transformers

19. SECTION 26 27 26 – Wiring Devices

20. SECTION 28 13 16 – Physical Access Control System and Database Management

21. SECTION 31 20 00 – Earthwork

22. SECTION 32 05 23 – Cement and Concrete for Exterior Improvements

23. SECTION 32 12 16 – Asphalt Paving

24. VA Long Beach Healthcare System Infection Control Risk Assessment

25. VA Long Beach Healthcare System Interim Life Safety Measures

B.5 SPECIFIC REQUIREMENTS:

A. Contractor shall review and adhere to the attached design and specification documents along with inspecting existing site conditions prior to starting construction.

B. All testing and commissioning for this project shall be done and paid for by contractor.

C. The contractor shall hire a subcontractor, whose supervisory archeological personnel will coordinate with native American tribes to ensure that no excavation deeper than 4 inches below the current surface will occur without the presence of a Native American monitor.

D. Shall install eight feet (8’) high construction chain link fence with green fabric and safety signs around excavated areas and staging areas.

E. LBVAHCS cannot guarantee but will make every effort to provide staging area for materials storage.

F. Contractor shall comply with OSHA Regulations and LBVAHCS policy and regulations including the following but not limited to Infection Control Risk Assessment (ICRA), Interim Life Safety Measures (ILSM), excavation permit, above ceiling work permit, hot work permit, energized work permit, crane permit, utility system maintenance advisory, etc…Refer to SECTION D of Solicitation for attachments.

G. Majority of work performed will be outside the facility. But due to installation of communication and utility lines, some work will be performed inside the Pharmacy and Emergency Department area to join the lines. Contractor’s shall NOT touch, move or shift any LBVAHCS documents and/or Government equipment. Coordinate with COR if Government property is impeding on contractor work. Contractors shall stay inside designated project area. Refer to Design Attachment in Section D.

H. Contractor shall cleanup all project areas at the end of every workday.

I. Contractor shall submit valid TB test results within 90 calendar days prior to start of work for all workers, valid 10-hour OSHA safety training for all workers and 30 hours OSHA safety training for Superintendent and project manager for VA approval, prior to starting construction work. Contractor personnel shall attend VA provided 30-minute safety orientation training and obtain security badges before starting construction work.

J. All shutdowns shall be carried out after hours or on weekends to minimize disruptions to the VA operations.

K. All shutdowns requests shall be submitted to COR at least two weeks in advance of the shutdown date for proper preparation and approval.

L. Contractor shall submit, Invoices to Contracting Officer Representative (COR) on VA forms prior to submitting to Tungsten.

M. Contractor shall verify that Sub-Contractor’s technical submittals, manufacturers’ cut sheets and shop drawings comply with VA construction documents, before submitting for VA and COR review and approval.

N. All workers shall be required to follow CDC guidance and social distancing guidelines with regard to COVID-19 prevention. Workers shall be required to wear masks (except for medical reasons and must obtain prior approval) at the contractor’s own expense while on campus. Workers are also required to obtain the daily wristband from one of VALBHCS screening stations on campus before start of work.

B.6 CONFORMANCE STANDARDS:

A. All design and construction accomplished pursuant to this contract shall comply with the latest edition of the following documents unless the contractor is directed otherwise by the Contracting Officer. Any exceptions shall be approved in writing by the Contracting Officer prior to construction startup.

1. VA Master Construction Specifications – VA Technical Information Library link: https://www.cfm.va.gov/til/spec.asp#01

2. VA Construction Standards

3. VA Seismic Design Handbook

4. VA Space Planning Criteria

5. VA Design Manuals

6. VA CADD Standards

7. NFPA 101, Life Safety Code

8. NFPA 70, National Electric Code

9. NFPA 99, Health Care Facilities

10. NFPA 12, Installation of Sprinkler Systems

11. Accessibility Standards (ADAAG, ABAAS, Barrier Free Design Guide)

12. AIA Guidelines for Construction and Equipment of Hospital and Medical Facilities

13. International Building Codes

14. State and Local codes and guidelines (as applicable)

B.7 HOURS OF COVERAGE:

A. Normal hours of operation are Monday through Friday from 6:00 am to 4:00 pm PST time. Most work is expected to be performed generally during normal hours of coverage unless requested or approved by the COR or his/her designee.

B. Before commencement of work, the Contractor shall confer with the VA COR and Contracting Office to agree on a sequence of procedures; means of access to premises and building. All work performed, to include delivery of materials and equipment, shall be made with minimal interference to Government operations and personnel.

C. Work performed outside the normal hours of coverage shall be approved by the COR or his/her designee.

D. Federal Holidays observed by Veterans Health Administration are:

1. Federal Holidays are as follows:

New Years' DayLabor Day
Martin Luther King DayColumbus Day
Presidents' DayVeterans' Day
Memorial DayThanksgiving Day
Independence DayChristmas Day

2. For actual dates observed, see the following link:

https://www.opm.gov/policy-data-oversight/pay-leave/federal-holidays/

B.8 IDENTIFICATION, PARKING, NO SMOKING, AND VA REGULATIONS:

A. The Contractor's FSEs shall wear visible identification issued by VAHCS Police Section at all times while on the premises of VAHCS. It is the responsibility of the Contractor to park in the appropriate designated parking areas. Information on parking is available from the VA Police Section. VAHCS shall not invalidate or make reimbursement for parking violations of the Contractor under any conditions. Smoking is strictly prohibited anywhere on the Veterans Affairs Health Care Facilities, to include main facility, and any other buildings at or on the premises. Possession of weapons is prohibited. Enclosed containers, including tool kits, shall be subject to search. Violations of VA regulations may result in citation answerable in the United States (Federal) District Court, not a local district, state, or municipal court.

B.9 INFORMATION SECURITY:

A. In accordance with Appendix A, Handbook 6500.6 Checklist blocks 7, the C&A requirements do not apply to this requirement, and Security Accreditation Package is not required. The nature of this requirement is technical; however, there is no information to be protected.

B.10 POINTS OF CONTACT AND PHYSICAL LOCATION:

A. Access to worksite shall be coordinated through:

1. Point of Contact – COR TBD

2. LONG BEACH VA HEALTH CARE SYSTEM (LBVAHCS):

5901 East 7th Street, Long Beach, CA 90822 Bldg 164

B.11 PERIOD OF PERFORMANCE:

A. Commencement of work shall begin within 10 days after receipt of written Notice to Proceed (NTP), and should last no longer than a duration of 90 continuous calendar days after date NTP is issued.

B.12 SUBMITTALS:

A. Contractor shall submit all required material/shop drawing submittals to the Contracting Officer within 10 calendar days of award, or as agreed to by the Contracting Officer for approval. No materials shall be installed prior to approval.

B. All material submittals and shop drawings shall contain, and have the Project Title, Project Number, and Contract number clearly indicated.

C. Material submittals and shop drawings shall be checked and signed by the Contractors Quality Control Manager prior to submission to the Government. Shop drawings shall be stamped and approved by the appropriate Architect/Engineer who are licensed/registered in the state of California.

D. Submittals shall be legible and shall include all technical data needed to verify that the item meets requirements of listed specifications, and applicable codes.

E. Contractors shall utilize Material Approval Submittal for use as cover sheet when submitting to Government for approval. Forms shall be provided to contractor at post-award, pre-construction conference

B.13 COMMENCEMENT, COMPLETION, AND PAYMENT FOR WORK:

A. The Contractor shall be required to commence work required at the time specified on the Notice to Proceed (NTP), execute the work, and complete the entire work not later than the completion time specified on the NTP. The time stated for completion shall include final cleanup of the premises. At the government’s option, it may choose to specify a two-stage performance period. For example, separating material lead-time from construction days can considerably decrease the length of time occupied buildings are inconvenienced by construction.

B. Before commencement of work, the Contractor shall confer with the VA COR and Contracting Office to agree on a sequence of procedures; means of access to premises and building; space for storage of materials and equipment; delivery of materials and use of approaches; use of corridors, stairways, elevators, and similar means of communications; location of partitions, eating spaces, and restrooms for the Contractor employees; and the like. Delivery of materials and equipment shall be made with minimal interference to Government operations and personnel.

C. The Contractor shall be paid upon submission of proper invoices for work completed. If the performance period exceeds 30 days and a progress schedule (approved by the Government) has been submitted, partial payment(s) may be authorized. Final payment shall be withheld until all discrepancies are corrected and as-built drawings are approved by the Government.

D. The contractor shall attend weekly progress meetings with the COR and/or Contracting Officer to discuss at a minimum; progression of work, projected progress versus actual progress, action items due from the contractor, action items due from the government, and any other significant issues that require attention. The contractor also shall document the meeting minutes and forward a signed copy to the COR for concurrence of the documentation. Copies of all minutes shall be forwarded to the Contracting Officer. In the event of any discrepancies the Contracting Officer shall be notified immediately for clarification. Contractor shall use the Meeting Minutes form provided for use at the post-award, pre-construction conference.

B.14 MODIFICATIONS:

A. Modifications for this project shall be submitted to the assigned COR who shall then submit a formal request to the Contracting Officer (CO). Work, time, cost or scope changes are not allowed to commence prior to Contracting Officer’s signed and written approval via fully executed Standard Form (SF) 30 modification.

B.15 ACRONYMS:

A. ABAAS - Architectural Barriers Act Accessibility Standard B. ADAAG - Americans with Disabilities Act Accessibility Guidelines.

C. AIA - American Institute of Architects' AIA D. CAC - Certified Asbestos Consultant E. CADD - Computer Aided Design and Drawing F. CDC – Center for Disease Controls and Prevention G. CO - Contracting Officer. The Federal employee who is warranted by the Government to enter into contracts on behalf of the Government and is the only person authorized to make changes to those contracts H. COR - Contracting Officer's Representative. Individual designated by the CO to place orders, furnish technical guidance, advice, certify invoices, and provide general supervision of the work performed under the executed contract I. COVID-19 – Coronavirus Disease-2019 J. EOSH - Environmental and Occupational Safety and Health K. EPA - Environmental Protection Agency L. FSE - Field Service Engineer M. HIPAA - Health Insurance Portability and Accountability Act of 1996 N. ICRA - Infection Control Risk Assessment O. IPRM - Information Protection Risk Management P. ILSM - Interim Life Safety Measures Q. ISO - International Standards Organization R. LBVAHCS - Long Beach VA Health Care System S. MOU - Memorandum of Understanding T. NFPA - National Fire Protection Association U. NTP - Notice to Proceed V. OEM - Original Equipment Manufacturer W. OSHA - Occupational Safety and Health Administration X. SF - Standard Form Y. SME - Subject Matter Expert Z. SOW – Statement of Work AA. TIL – Technical Information Library AB. TWA - Time-Weighted Average AC. AB. VA – Veterans Affairs AD. AC. VAHCS – Veteran Affairs Health Care System AE. AD. VHA - Veterans Health Administration

(END OF SOW)

SECTION C - CONTRACT CLAUSES

C.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) ALTERNATE I (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 days after receipt of notice to proceed. The time stated for completion shall include final cleanup of the premises.

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 10. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

(End of Clause)

C.2 52.219-28 POST-AWARD SMALL BUSINESS PROGRAM REREPRESENTATION (MAR 2020)

(a) Definitions. As used in this clause— Long-term contract means a contract of more than five years in duration, including options. However, the term does not include contracts that exceed five years in duration because the period of performance has been extended for a cumulative period not to exceed six months under the clause at 52.217-8, Option to Extend Services, or other appropriate authority.

Small business concern means a concern, including its affiliates, that is independently owned and operated, not dominant in the field of operation in which it is bidding on Government contracts, and qualified as a small business under the criteria in 13 CFR part 121 and the size standard in paragraph (d) of this clause. Such a concern is "not dominant in its field of operation" when it does not exercise a controlling or major influence on a national basis in a kind of business activity in which a number of business concerns are primarily engaged. In determining whether dominance exists, consideration shall be given to all appropriate factors, including volume of business, number of employees, financial resources, competitive status or position, ownership or control of materials, processes, patents, license agreements, facilities, sales territory, and nature of business activity.

(b) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (f) of this clause or, if applicable, paragraph (h) of this clause, upon occurrence of any of the following:

(1) Within 30 days after execution of a novation agreement or within 30 days after modification of the contract to include this clause, if the novation agreement was executed prior to inclusion of this clause in the contract.

(2) Within 30 days after a merger or acquisition that does not require a novation or within 30 days after modification of the contract to include this clause, if the merger or acquisition occurred prior to inclusion of this clause in the contract.

(3) For long-term contracts—

(i) Within 60 to 120 days prior to the end of the fifth year of the contract; and

(ii) Within 60 to 120 days prior to the date specified in the contract for exercising any option thereafter.

(c) If the Contractor represented that it was any of the small business concerns identified in 19.000(a)(3) prior to award of this contract, the Contractor shall rerepresent its size and socioeconomic status according to paragraph (f) of this clause or, if applicable, paragraph (h) of this clause, when the Contracting Officer explicitly requires it for an order issued under a multiple-award contract.

(d) The Contractor shall rerepresent its size status in accordance with the size standard in effect at the time of this rerepresentation that corresponds to the North American Industry Classification System (NAICS) code(s) assigned to this contract. The small business size standard corresponding to this NAICS code(s) can be found at http://www.sba.gov/content/table-small-business-size-standards.

(e) The small business size standard for a Contractor providing a product which it does not manufacture itself, for a contract other than a construction or service contract, is 500 employees.

(f) Except as provided in paragraph (h) of this clause, the Contractor shall make the representation(s) required by paragraph (b) and (c) of this clause by validating or updating all its representations in the Representations and Certifications section of the System for Award Management (SAM) and its other data in SAM, as necessary, to ensure that they reflect the Contractor's current status. The Contractor shall notify the contracting office in writing within the timeframes specified in paragraph (b) of this clause, or with its offer for an order (see paragraph (c) of this clause), that the data have been validated or updated, and provide the date of the validation or update.

(g) If the Contractor represented that it was other than a small business concern prior to award of this contract, the Contractor may, but is not required to, take the actions required by paragraphs (f) or (h) of this clause.

(h) If the Contractor does not have representations and certifications in SAM, or does not have a representation in SAM for the NAICS code applicable to this contract, the Contractor is required to complete the following rerepresentation and submit it to the contracting office, along with the contract number and the date on which the rerepresentation was completed:

(1) The Contractor represents that it [ ] is, [ ] is not a small business concern under NAICS Code 236220 assigned to contract number TBD.

(2) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not, a small disadvantaged business concern as defined in 13 CFR 124.1002.

(3) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not a women-owned small business concern.

(4) Women-owned small business (WOSB) concern eligible under the WOSB Program. [Complete only if the Contractor represented itself as a women-owned small business concern in paragraph (h)(3) of this clause.] The Contractor represents that—

(i) It [ ] is, [ ] is not a WOSB concern eligible under the WOSB Program, has provided all the required documents to the WOSB Repository, and no change in circumstances or adverse decisions have been issued that affects its eligibility; and

(ii) It [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR part 127, and the representation in paragraph (h)(4)(i) of this clause is accurate for each WOSB concern eligible under the WOSB Program participating in the joint venture. [The Contractor shall enter the name or names of the WOSB concern eligible under the WOSB Program and other small businesses that are participating in the joint venture: _____.] Each WOSB concern eligible under the WOSB Program participating in the joint venture shall submit a separate signed copy of the WOSB representation.

(5) Economically disadvantaged women-owned small business (EDWOSB) concern. [Complete only if the Contractor represented itself as a women-owned small business concern eligible under the WOSB Program in (h)(4) of this clause.] The Contractor represents that—

(i) It [ ] is, [ ] is not an EDWOSB concern eligible under the WOSB Program, has provided all the required documents to the WOSB Repository, and no change in circumstances or adverse decisions have been issued that affects its eligibility; and

(ii) It [ ] is, [ ] is not a joint venture that complies with the requirements of 13 CFR part 127, and the representation in paragraph (h)(5)(i) of this clause is accurate for each EDWOSB concern participating in the joint venture. [The Contractor shall enter the name or names of the EDWOSB concern and other small businesses that are participating in the joint venture: _____.] Each EDWOSB concern participating in the joint venture shall submit a separate signed copy of the EDWOSB representation.

(6) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that it [ ] is, [ ] is not a veteran-owned small business concern.

(7) [Complete only if the Contractor represented itself as a veteran-owned small business concern in paragraph (h)(6) of this clause.] The Contractor represents that it [ ] is, [ ] is not a service-disabled veteran-owned small business concern.

(8) [Complete only if the Contractor represented itself as a small business concern in paragraph (h)(1) of this clause.] The Contractor represents that—

(i) It [ ] is, [ ] is not a HUBZone small business concern listed, on the date of this representation, on the List of Qualified HUBZone Small Business Concerns maintained by the Small Business Administration, and no material changes in ownership and control, principal office, or HUBZone employee percentage have occurred since it was certified in accordance with 13 CFR part 126; and

(ii) It [ ] is, [ ] is not a HUBZone joint venture that complies with the requirements of 13 CFR part 126, and the representation in paragraph (h)(8)(i) of this clause is accurate for each HUBZone small business concern participating in the HUBZone joint venture. [The Contractor shall enter the names of each of the HUBZone small business concerns participating in the HUBZone joint venture: _____.] Each HUBZone small business concern participating in the HUBZone joint venture shall submit a separate signed copy of the HUBZone representation.

[Contractor to sign and date and insert authorized signer's name and title.] (End of Clause)

C.3 52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)

(a) Definitions. As used in this clause— "Commercially available off-the-shelf (COTS) item"—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

"Component" means any article, material, or supply incorporated directly into construction material.

"Construction material" means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

"Cost of components" means—

(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the end product (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

"Domestic construction material" means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

"Foreign construction material" means a construction material other than a domestic construction material.

"United States" means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:

N/A

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

FOREIGN AND DOMESTIC CONSTRUCTION MATERIALS PRICE COMPARISON

Construction Material Description
Unit of Measure
Quantity
Price (Dollars)*

Item 1:

Foreign Construction Material

Domestic Construction Material

Item 2:

Foreign Construction Material

Domestic Construction Material

[List name, address, telephone number, and contact for suppliers surveyed Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] [*Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).] (End of Clause) C.4 52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997) ALTERNATE II (APR 1984)

(a) The Contractor shall keep on the work site a copy of the drawings and specifications and shall at all times give the Contracting Officer access thereto. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern. In case of discrepancy in figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at its own risk and expense. The Contracting Officer shall furnish from time to time such detailed drawings and other information as considered necessary, unless otherwise provided.

(b) Wherever in the specifications or upon the drawings the words "directed," "required," "ordered," "designated," "prescribed," or words of like import are used, it shall be understood that the "direction," "requirement," "order," "designation," or "prescription," of the Contracting Officer is intended and similarly the words "approved," "acceptable," "satisfactory," or words of like import shall mean "approved by," or "acceptable to," or "satisfactory to" the Contracting Officer, unless otherwise expressly stated.

(c) Where "as shown," "as indicated," "as detailed," or words of similar import are used, it shall be understood that the reference is made to the drawings accompanying this contract unless stated otherwise. The word "provided" as used herein shall be understood to mean "provide complete in place," that is "furnished and installed."

(d) Shop drawings means drawings, submitted to the Government by the Contractor, subcontractor, or any lower tier subcontractor pursuant to a construction contract, showing in detail (1) the proposed fabrication and assembly of structural elements and (2) the installation (i.e., form, fit, and attachment details) of materials of equipment. It includes drawings, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance and test data, and similar materials furnished by the contractor to explain in detail specific portions of the work required by the contract. The Government may duplicate, use, and disclose in any manner and for any purpose shop drawings delivered under this contract.

(e) If this contract requires shop drawings, the Contractor shall coordinate all such drawings, and review them for accuracy, completeness, and compliance with contract requirements and shall indicate its approval thereon as evidence of such coordination and review. Shop drawings submitted to the Contracting Officer without evidence of the Contractor's approval may be returned for resubmission. The Contracting Officer will indicate an approval or disapproval of the shop drawings and if not approved as submitted shall indicate the Government's reasons therefor. Any work done before such approval shall be at the Contractor's risk. Approval by the Contracting Officer shall not relieve the Contractor from responsibility for any errors or omissions in such drawings, nor from responsibility for complying with the requirements of this contract, except with respect to variations described and approved in accordance with (f) below.

(f) If shop drawings show variations from the contract requirements, the Contractor shall describe such variations in writing, separate from the drawings, at the time of submission. If the Contracting Officer approves any such variation, the Contracting Officer shall issue an appropriate contract modification, except that, if the variation is minor or does not involve a change in price or in time of performance, a modification need not be issued.

(g) The Contractor shall submit to the Contracting Officer for approval four copies (unless otherwise indicated) of all shop drawings as called for under the various headings of these specifications. Three sets (unless otherwise indicated) of all shop drawings, will be retained by the Contracting Officer and one set will be returned to the Contractor. Upon completing the work under this contract, the Contractor shall furnish 2 sets of prints of all shop drawings as finally approved. These drawings shall show changes and revisions made up to the time the equipment is completed and accepted.

(End of Clause)

C.5 SUPPLEMENTAL INSURANCE REQUIREMENTS

In accordance with FAR 28.307-2 and FAR 52.228-5, the following minimum coverage shall apply to this contract:

(a) Workers' compensation and employers liability: Contractors are required to comply with applicable Federal and State workers' compensation and occupational disease statutes. If occupational diseases are not compensable under those statutes, they shall be covered under the employer's liability section of the insurance policy, except when contract operations are so commingled with a Contractor's commercial operations that it would not be practical to require this coverage. Employer's liability coverage of at least $100,000 is required, except in States with exclusive or monopolistic funds that do not permit workers' compensation to be written by private carriers.

(b) General Liability: $500,000.00 per occurrences.

(c) Automobile liability: $200,000.00 per person; $500,000.00 per occurrence and $20,000.00 property damage.

(d) The successful bidder must present to the Contracting Officer, prior to award, evidence of general liability insurance without any exclusionary clauses for asbestos that would void the general liability coverage.

(End of Clause)

C.6 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far/index.html http://www.va.gov/oal/library/vaar/

(End of Clause)

FAR Number