Summary of Jackson Township Municipal Center Construction Documents
This is a comprehensive civil site construction specification document for the Jackson Township Municipal Center renovation and addition project located at 439 Roth's Church Road, Spring Grove, Pennsylvania 17362. The project encompasses renovation of an existing township building, construction of a new storage garage, and a new salt storage building, with sealed bids received online via PennBid until 1:00 PM EST on Tuesday, December 8, 2026. The contract includes four separate bid packages: General Construction, Plumbing Construction, Mechanical Construction, and Electrical Construction. The site work scope includes selective demolition, site clearing and grubbing, temporary erosion and sediment controls, bulk earthwork and rough grading, underground utility piping for sanitary sewer and roof drainage, stormwater management facilities (SCM-001 and SCM-002), asphalt paving with multiple course layers, concrete sidewalks and driveway aprons, ADA parking area paving, concrete curbing, parking bumpers, pavement markings, finish grading and seeding, and ADA accessible parking sign assemblies. Bidding documents became available online at no cost via PennBid on November 4, 2026. A pre-bid conference is scheduled for Tuesday, November 10, 2026, at 10:00 AM EST on-site, with attendance highly recommended but not mandatory. The contract award is scheduled for a regularly scheduled Jackson Township meeting on January 4, 2027. The contract time is four hundred (400) calendar days from the Notice to Proceed.
A bid bond or certified check equal to 10% of the maximum bid is required from each bidder, made payable to Jackson Township and submitted via PennBid. The project is subject to Pennsylvania Prevailing Wage Act provisions (Act 442, P.L. 987, as amended). Civil work payment items are established on a combination of unit-price and lump-sum basis through the Bid Form, with unit prices applying to pipe items, curb, concrete work, aggregate base, asphalt courses, parking bumpers, and pavement markings, while lump-sum items cover mobilization, site demolition and removals, bulk earthwork and rough grading, erosion and sediment control, finish grading and seeding, stormwater facilities, trench drains, riprap, clearing and grubbing, and pavement markings. The contract incorporates the 2021 International Building Code as adopted by Pennsylvania, with accessibility requirements per 2018 IBC and the 2010 ADA Standards for Accessible Design. Jackson Township reserves the right to accept any bid, waive informalities, or reject any or all bids. All work must be coordinated with approved Erosion and Sediment Control Plans and requires compliance with York County Conservation District permit conditions and NPDES requirements.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 01 10 00.00 SITEWORK SCOPE OF WORK AND COORDINATION
JACKSON TOWNSHIP SITEWORK SCOPE OF WORK AND COORDINATION SECTION 01 10 00.00
SECTION 01 10 00.00
SITEWORK SCOPE OF WORK AND COORDINATION
PART 1 GENERAL
1.1 SUMMARY
A. This Section defines the Site/Civil scope and its interfaces for JACKSON TOWNSHIP MUNICIPAL CENTER. The Architect's overall Project Summary, procurement documents, Agreement, and Division 01 govern project-wide administration, schedule, occupancy, access, work hours, and coordination. This Section supplements those documents and does not establish separate contracts or work packages.
1.2 PROJECT AND SITEWORK COORDINATION
A. Project: JACKSON TOWNSHIP MUNICIPAL CENTER, 439 Roth's Church Road, Spring Grove, Pennsylvania 17362.
Owner: Jackson Township. No architectural project number is assigned.
B. Owner's Representative for on-site coordination: Shane Shaffer. Coordinate site access, operational impacts, notices, and proposed service interruptions through the Contract administration procedures. This designation does not change the Architect's Contract administration role or authorize changes to the Work.
C. Architect, design consultants, and project-wide coordinators are identified in the overall Project Summary. Do not duplicate their contact schedules, owner-furnished product schedules or project-wide restrictions in this Section. No separate phased-completion requirements are established for sitework.
1.3 SITEWORK SCOPE
A. Provide the sitework indicated on the Civil Drawings and required by the applicable technical specifications, including selective site demolition and removals; clearing and grubbing; temporary erosion and sediment controls; bulk earthwork and rough grading; exterior gravity sanitary sewer, sanitary force main, manhole, cleanouts and connections assigned to civil; underground roof drainage, storm sewer, subdrainage and stormwater facilities; aggregate base and asphalt paving; concrete curb, sidewalks, driveway aprons and ADA parking-area paving; concrete parking bumpers; ADA accessible-parking sign assemblies; pavement markings;
and permanent finish grading and seeding. Perform work within the scope and connection limits established by the Contract Documents.
B. Building demolition, structural modifications, interior building systems, and planned propane-tank work are covered by the Architectural, Structural, and applicable building-system documents. Coordinate civil interfaces without duplicating or omitting the assigned work. Permanent irrigation is not part of this project.
C. Suspected contaminated soil or water and unexpected tanks encountered during civil work are governed by Section 024119.00, coordinated with Section 312000.00. Stop affected work, secure the area, and notify the Owner, Architect and Site Engineer. Obtain direction regarding investigation, testing, handling and disposal before disturbing or removing suspected contaminated materials. Obtain written authorization before resuming affected work. Administer authorized additional work under Section 012200.00 and the Contract change procedures. Do not delay emergency protective action or legally required reporting.
1.4 COORDINATION OF SITEWORK
A. Coordinate utility disconnections, building sanitary and roof-drain connections, thresholds, foundations, equipment supports, site accessories, and finished grades with the responsible trades before installation. Verify existing connection sizes, materials, and elevations; report discrepancies before affected work.
B. Sequence sitework consistently with the approved E&S/PCSM plans and permit. Coordinate District preconstruction meetings, licensed-professional observations, and critical SCM stages under Sections 015723.00 and 312000.00. Protect permanent drainage facilities from construction sediment and loads.
C. Maintain protection of retained improvements and utilities and comply with the overall Project Summary access, occupancy, notification and interruption requirements. Obtain required approvals before interruptions; do not infer unrestricted site access from this Section.
D. Submit coordinated product/shop information and inspection requests sufficiently in advance of affected work.
Resolve conflicting dimensions, elevations, and scope interfaces through the Contract procedures; product approval does not authorize a design change.
E. Limit site disturbance to the limits of disturbance shown on the approved NPDES/E&S plans approved by York County Conservation District. Do not expand disturbance or use off-site areas without required authorization and permit approvals.
1.5 CODES AND ACCESSIBILITY
A. Comply with the 2021 International Building Code as adopted and amended by Pennsylvania under the Uniform Construction Code. Accessibility requirements include the applicable 2018 IBC accessibility provisions and ICC A117.1-2009, together with the 2010 ADA Standards for Accessible Design. Coordinate site routes, parking, ramps, landings, signage, and building interfaces with the approved accessibility design; report conflicting requirements before affected construction.
1.6 CIVIL SCOPE EXCLUSIONS
A. Civil signage is limited to the proposed ADA accessible-parking identification signs, including supplemental van-accessible signs only where indicated, and their indicated sign-support assemblies. General traffic-control, directional, building-identification, interior, and other new signs are outside the civil signage scope.
B. New bollards, including fixed or removable units, pipe fill, sleeves, hardware, reinforcement, anchorage and foundations, are part of the Structural scope and are excluded from civil construction and payment items.
Removal of existing bollards is included in civil demolition only where expressly assigned on the Civil Drawings.
Concrete parking bumpers are part of the civil scope and are distinct from bollards. Coordinate bollard locations and installation with paving, utilities and accessible routes.
C. Additional civil scope exclusions and trade interfaces are established in Article 1.7 and Section 012200.00.
Coordinate excluded work with the responsible trades without duplicating or omitting work at civil interfaces.
1.7 PAYMENT AND DOCUMENT INTERFACES
A. Measurement and Payment: Measure and pay for civil work under Section 012200.00 and the Civil Schedule of Bid Items and Quantities in the Architect’s GC01 Bid Form. The Bid Form and Agreement establish payable items and the payment basis. Technical specification requirements do not create additional payment items. Include incidental work in the corresponding scheduled item as specified in Section 012200.00. Do not include the same work in more than one payment item.
B. Signage and Parking Bumpers: New signage within the civil scope is limited to the proposed ADA accessible-parking sign assemblies, including van-accessible identification where indicated. Parking bumpers are included in the civil scope where shown. Relocation of existing signs shall follow the assignments on the civil demolition drawings.
C. Bollards and Gates: New bollards and their foundations are part of the Structural scope. Gates, hardware, posts, supports and gate foundations are part of the Architectural scope. Coordinate civil grades, pavement, drainage and utility locations with these improvements. Include civil grading and surface improvements at these interfaces under the corresponding civil items. Removal of existing bollards is included in civil demolition only where expressly assigned on the Civil Drawings.
D. Waterlines: All new waterlines and associated appurtenances, including exterior water-service work, are covered by the MEP plans, specifications, and scope and shall be furnished and installed by the MEP Contractor.
Coordinate alignments, elevations, crossings, construction sequence, and restoration limits with the civil work.
No separate civil waterline payment item is included.
E. Sanitary System: Provide exterior gravity sanitary sewer piping, SAN MH-2, the connection to the existing sanitary/septic system, the 1-1/2-inch sanitary force main and sanitary cleanouts assigned to civil under Section
333115.00 and Items 410 through 450 of Section 012200.00. The MEP Contractor shall provide SAN MH- 1/dosing tank, pumping and dosing equipment, oil/water separator, associated equipment piping and valves, power, controls and alarms. Include excavation, foundation preparation, backfill and compaction associated with the MEP tank and equipment assemblies in the MEP scope. The Civil Contractor shall provide exterior sanitary piping and complete connections to MEP-installed assemblies at the interface points indicated on the Contract Drawings. Coordinate connection sizes, locations, elevations, installation sequence and testing before construction. Do not duplicate tank, equipment, excavation, backfill or connection work between civil and MEP scopes.
F. Building Roof Drainage: The MEP Contractor shall furnish and install building roof drainage, aboveground downspouts, downspout boots and associated transition adapters. The Civil Contractor shall provide the 6-inch and 8-inch underground roof drainage piping and complete connections to the MEP-installed boots or adapters at the interface points indicated on the Contract Drawings. Include civil underground fittings and cleanouts with the corresponding pipe item. Coordinate connection locations, sizes, inverts and installation sequence to provide complete connections without duplication or gaps between trade scopes.
G. Building and Mechanical Work: Planned propane-tank disconnection and removal are part of the Mechanical scope. Coordinate completion before civil excavation and restoration in the affected area. Building demolition and structural equipment pads are covered by the applicable Architectural and Structural documents.
H. Erosion and Sediment Control Plans: The approved Erosion and Sediment Control Plans are provided as a separate plan set accompanying the Contract Drawings and are part of the Contract Documents. E&S measures are not duplicated on the civil construction plans. Provide, install, inspect, maintain and remove temporary E&S measures as required by the approved plans, applicable permit conditions and Section 015723.00. Establish required controls before associated earth disturbance and coordinate the E&S construction sequence with the civil improvements. Temporary E&S work is included under Item 150; permanent finish grading and seeding are included under Item 160; and permanent stormwater facilities are included under Items 280 and 290, as specified in Section 012200.00. Report conflicts between the approved E&S plans and other Contract Documents to the Architect and Site Engineer before proceeding with affected work.
I. Stormwater Facilities: Provide SCM-001 and SCM-002 complete in accordance with the Contract Drawings and applicable technical specifications. SCM-001 includes SMH-2 and OS-1 under Item 280. SCM-002 includes SMH-3, SMH-4 and OS-2 under Item 290. Include internal connecting piping and appurtenances within the respective facility payment limits. SMH-1 and MTD-1 are separately paid under Items 260 and 270. Other separately scheduled storm sewer pipe, inlet, trench drain, riprap and surface improvements remain payable under their corresponding items. Apply the detailed payment inclusions and exclusions in Section 012200.00.
J. Concrete and Pavement Interfaces: Provide sidewalks and driveway aprons with 6-inch-thick concrete over 6 inches of compacted AASHTO No. 57 aggregate base. Provide ADA parking-area paving with 6-inch-thick reinforced concrete over 8 inches of compacted PennDOT 2A aggregate base. Provide reinforcement as detailed on the Contract Drawings. Include aggregate base beneath concrete in the corresponding concrete item.
Aggregate base beneath asphalt pavement is separately paid under Item 550. Coordinate concrete, curb and asphalt pavement limits to avoid overlapping quantities or omitted work.
PART 2 PRODUCTS (NOT USED)
PART 3 EXECUTION (NOT USED)
END OF SECTION 01 10 00.00 - SITEWORK SCOPE OF WORK AND COORDINATION
SECTION 01 22 00.00 UNIT PRICES
JACKSON TOWNSHIP UNIT PRICES SECTION 01 22 00.00
SECTION 01 22 00.00
UNIT PRICES
PART 1 GENERAL
1.1 SUMMARY
A. This Section establishes civil unit-price and lump-sum payment items, measurement methods, included work, and procedures for authorized quantity adjustments. Provide complete work shown on the Contract Drawings and required by the applicable technical specifications.
B. Related Requirements: Bid Form and Agreement for scheduled items, quantities, prices and adjustment provisions; General and Supplementary Conditions for payment and changes; Section 011000.00 for civil scope and coordination; and the applicable Division 02, 10, 31, 32 and 33 technical sections.
C. The Bid Form establishes the payable items. Descriptions in this Section define the scope of corresponding scheduled items and do not create additional payment items or authorize work beyond the Contract Documents.
No work shall be paid under more than one item.
1.2 DEFINITIONS
A. Unit Price: Amount entered in the Bid Form for a stated unit of completed and accepted work. Extend the unit price by the scheduled bid quantity for bid comparison and by the accepted measured quantity for payment, subject to the Agreement.
B. Lump Sum: Fixed amount entered for the complete defined work of an item, subject to authorized changes.
Partial payments shall reflect accepted progress under an approved schedule of values; a lump-sum item is not converted to unit-price payment by listing component quantities.
C. Units: LF means linear foot; EA means each; SF means square foot; SY means square yard; CY means cubic yard;
LS means lump sum.
D. Site Engineer: The civil design professional identified in the Contract Documents. Quantity review and technical acceptance by the Site Engineer do not change the Architect's or Owner's contract-administration authority.
1.3 BID QUANTITIES AND DRAWING COORDINATION
A. Use the item numbers, descriptions, quantities and units established in the Bid Form for preparation of bids. The Contract Drawings and technical specifications establish construction requirements and payment limits.
Scheduled quantities for unit-price items are estimated bid quantities; final payment shall be based on completed and accepted quantities measured in accordance with this Section, unless the Agreement expressly establishes another payment basis. Report discrepancies among the Bid Form, drawing quantities and construction limits in accordance with Paragraph D. Do not substitute bidder-developed quantities for the scheduled bid quantities.
B. Submit prices for the separate items established in the Bid Form. Do not combine separately scheduled pipe diameters, materials, structure types, pavement courses or concrete sections under a single price. Submit apparent omissions or discrepancies for clarification in accordance with Paragraph D; do not add or modify Bid Form items without an issued addendum.
C. Provide two separate stormwater facility items: SCM-001, quantity one LS, and SCM-002, quantity one LS. Use the facility limits and component designations on the Contract Drawings.
D. Compare drawing quantity schedules, plan limits, details and the Bid Form before bidding. Submit discrepancies, omitted items and unclear payment boundaries for clarification under the Instructions to Bidders. Obtain clarification before proceeding with affected work when a discrepancy is discovered after award.
E. A difference between an estimated bid quantity and an accepted measured quantity does not itself authorize a change in scope or unit price. Administer quantity adjustments and changes under the Agreement and General Conditions.
1.4 COSTS INCLUDED IN PRICES
A. Include labor, materials, equipment, delivery, handling, installation, ordinary waste, supervision, overhead and profit necessary for complete accepted work of each item.
B. Include associated excavation, ordinary trench support and dewatering, bedding, specified backfill, compaction, fittings, joints, connections, protection, Contractor-required testing, cleanup and incidental work in the corresponding item unless specifically assigned to another scheduled item.
C. Include general civil construction layout, administrative startup and closeout, and compilation of civil record-drawing information under Item 110, Mobilization. Include item-specific Contractor testing, product submittals, field measurements, quantity records, and installation documentation in the corresponding work item. Do not duplicate these costs among payment items. Owner-retained professional services are governed by the Agreement.
D. Pay separately scheduled pavement, curb, concrete and landscape restoration under their corresponding items.
Include incidental restoration for which no separate item is scheduled in the item causing the disturbance. Do not include the same restoration in multiple items.
E. Corrections of defective work, unauthorized over excavation, excess waste, damage caused by Contractor operations, and work outside authorized limits are not separately payable.
1.5 QUANTITY RECORDS AND PAYMENT APPLICATIONS
A. Notify the Architect and Site Engineer before covering work that requires measurement. Provide reasonable opportunity to observe dimensions and material limits.
B. Submit itemized quantity calculations with each application for payment. Identify the Bid Form item, drawing location, size/type, current-period quantity, cumulative quantity, previous payments and supporting field measurements.
C. Record authorized unsuitable-soil excavation limits and elevations before removal, and replacement-fill limits before concealment. Supplement surveys with photographs, delivery/disposal records and daily reports; truck counts or loose truck volumes alone do not establish in-place or compacted CY quantities.
D. Submit an initial schedule of values for each LS item with identifiable components and progress values. Use this breakdown for progress evaluation without creating additional pay items or changing the LS obligation.
E. Payment review does not constitute acceptance of defective work or waive testing, maintenance, restoration or closeout requirements.
1.6 UNSUITABLE SOIL AND ENVIRONMENTAL CONDITIONS
A. No separate unsuitable-soil removal or replacement-fill bid items are established. Include ordinary excavation and fill required for the defined work in the applicable scheduled items. Evaluate authorized additional work under the Contract change procedures and Section 312000.00.
B. Suspected contaminated soil, water and unexpected tanks are governed by Section 024119.00. Stop affected work, secure the area, and notify the Owner, Architect and Site Engineer. Obtain direction regarding investigation, testing, handling and disposal before disturbing or removing suspected contaminated materials.
Obtain written authorization before resuming affected work.
C. Document authorized environmental response separately and administer compensation under the Contract change procedures. Do not delay emergency protective action or legally required reporting.
1.7 CIVIL BID SCHEDULE
A. The civil bid schedule is included in the Bid Form. Use the item numbers, descriptions, quantities and units established therein. Part 3 of this Section establishes measurement and payment requirements for the corresponding civil bid items. Provide complete work for each item in accordance with the Contract Drawings and applicable technical specifications.
B. Scheduled quantities for unit-price items are estimated quantities for bidding. Measurement and payment shall comply with this Section and the Agreement. Each lump-sum item has a bid quantity of one.
C. Item descriptions do not establish additional payment for components included in another scheduled item.
Assign each component to one payment item only.
1.8 WORK OUTSIDE CIVIL PAYMENT ITEMS
A. Gates, gate hardware, posts, supports and gate foundations are part of the Architectural scope and are excluded from civil payment items. Civil grading, pavement, drainage and utility work at gate interfaces remain included in their corresponding civil items.
B. All new waterlines and associated appurtenances, including exterior water service, are covered by the MEP plans, specifications and scope. Exclude waterline installation and associated trench work from civil payment items. Include only restoration expressly assigned to civil under the corresponding scheduled civil item.
C. New bollards, including foundations and anchorage, are part of the Structural scope and are excluded from civil payment items. Concrete parking bumpers are included under Item 520 and are distinct from bollards. Removal of existing bollards is included under Item 130 only where assigned to civil demolition on the Contract Drawings.
D. Civil signage is limited to the proposed ADA accessible-parking sign assemblies under Item 590. Other new signage is excluded from civil payment items. Existing-sign removal or relocation is included under Item 130 only where expressly assigned to civil.
E. Building roof drainage, aboveground downspouts, downspout boots and transition adapters assigned to MEP are excluded from civil payment items. Items 210 and 220 begin at the civil connection points indicated on the Contract Drawings. Coordinate connection sizes, elevations and installation responsibilities with MEP.
F. Sanitary pumping and dosing equipment, controls, alarms, electrical connections and other components assigned to MEP are excluded from civil payment items. Include SAN MH-1/dosing-tank construction and associated excavation and backfill in the MEP scope where designated on the Contract Drawings. Civil sanitary work is limited to Items 410 through 450 and their indicated connection limits. Do not duplicate equipment, structure, excavation, backfill or connection costs between civil and MEP work.
PART 2 PRODUCTS
A. Not used. Materials and products are specified in the applicable technical sections and Contract Drawings.
PART 3 EXECUTION
3.1 GENERAL MEASUREMENT RULES
A. Measure only completed and accepted work within authorized drawing limits or written change limits. Measure LF along the installed alignment; SF and SY by horizontal plan area; and EA by the number of complete accepted assemblies. Apply the item-specific rules below.
B. Do not increase measured quantities for laps, joints, waste, irregular excavation, working room, temporary work, repeated installation, or repairs required because of Contractor operations.
C. For CY items, use jointly documented field dimensions, survey records or other accepted measurements to calculate the specified in-place or compacted volume. Do not apply an assumed swell or shrinkage factor as a substitute for measurement.
D. An item designated below as separate is separately payable only when scheduled in the Bid Form. Otherwise, include that work in the expressly identified associated item; obtain clarification where the Contract Documents do not identify an association.
3.2 STORM SEWER PIPE
A. Items 230 and 240: Unit LF, separately scheduled by diameter and material. Measure along the installed pipe centerline between inside faces of structures and to terminal pipe ends or designated connection points. Exclude pipe within structure footprints and pipe assigned to Items 280 or 290.
B. Include pipe, fittings, adapters, joints, excavation, bedding, specified backfill, compaction, ordinary trench support and dewatering, connections, required testing and cleaning. Do not deduct incidental fittings from measured pipe length.
C. Exclude separately paid structures, trench drains, riprap and surface restoration. Facility underdrains, risers, cleanouts, manifolds and internal connecting pipe are included in the corresponding stormwater facility lump-sum item.
3.3 STORMWATER INLETS, MANHOLES AND HYDRODYNAMIC SEPARATOR
A. Item 250 — Type C Inlet: Unit EA per complete 2-foot by 4-foot inlet shown. Include excavation, foundation preparation, structure, risers, frame and grate, pipe penetrations and seals, internal shaping, backfill, compaction and final adjustment to grade.
B. Item 260 — Stormwater Diversion Manhole SMH-1: Unit EA per complete assembly shown. Include excavation, foundation preparation, structure, internal diversion components, risers, frame and cover, pipe penetrations and seals, backfill, compaction and final adjustment to grade.
C. Item 270 — Hydrodynamic Separator MTD-1: Unit EA per complete ADS Arcadia AR6PC assembly shown. Include excavation, foundation preparation, structure, proprietary treatment components, access assemblies, pipe penetrations and seals, backfill, compaction and manufacturer-required installation coordination.
D. Include required testing, cleaning and installation documentation in each assembly price. Exclude external connecting pipe paid under a separate pipe item.
E. Structures assigned to Items 280 or 290 are included in the corresponding facility lump sum and are not separately payable under this article. SMH-1 and MTD-1 are excluded from the facility lump-sum items.
3.4 STORMWATER FACILITIES
A. Item 280 — Stormwater Facility SCM-001: Unit LS for the complete facility within the payment limits shown on the Contract Drawings.
B. Item 290 — Stormwater Facility SCM-002: Unit LS for the complete facility within the payment limits shown on the Contract Drawings.
C. Include facility excavation, subgrade preparation, specified stone and media, geotextiles, liners where detailed, proprietary storage and treatment components, manifolds, internal pipe, underdrains, cleanouts, access assemblies, outlet-control components, backfill and compaction.
D. Include facility structures under the payment assignments established in Paragraphs F and G. Include each structure and connecting pipe under one payment item only. External pipe separately measured under another scheduled item is excluded from the facility lump sum.
E. Include construction-stage protection, protection of infiltration surfaces, coordination of required observation stages, Contractor-required testing and documentation, cleaning, sediment removal and restoration of facility performance before acceptance.
F. Item 280 — Stormwater Facility SCM-001 includes SMH-2 and OS-1, complete with excavation, foundation preparation, structures, internal components, access frames and covers, pipe penetrations and seals, backfill, compaction, testing and cleaning. Include connecting piping within the SCM-001 payment limits shown on the Contract Drawings. SMH-2 and OS-1 are not separately payable under other bid items.
G. Item 290 — Stormwater Facility SCM-002 includes SMH-3, SMH-4 and OS-2, complete with excavation, foundation preparation, structures, internal components, access frames and covers, pipe penetrations and seals, backfill, compaction, testing and cleaning. Include connecting piping within the SCM-002 payment limits shown on the Contract Drawings. SMH-3, SMH-4 and OS-2 are not separately payable under other bid items.
H. The specific products and configurations identified in Section 334200.00 and the Contract Drawings form the basis of the facility design and demonstration of compliance with applicable PCSM and NPDES permit requirements. Contractor-proposed substitutions shall comply with Section 334200.00.
I. Include Contractor-funded re-engineering, additional professional review, required permit revisions and fees, coordination and associated construction changes resulting from Contractor-proposed substitutions. No additional payment is due solely because the Contractor proposes an alternative product. Obtain required written approvals before procurement or installation. Owner-directed changes remain subject to the Contract change provisions.
J. Exclude separately scheduled Stormwater Diversion Manhole SMH-1, Hydrodynamic Separator MTD-1, Type C inlet, external connecting storm sewer pipe, Trench Drain TD-1, R-3 riprap, pavement, curb, concrete paving and permanent finish grading and seeding. Pay these components under their corresponding scheduled items. Do not include the same work in a facility lump-sum price and another scheduled item.
3.5 CURB
A. Item 510 — Vertical Concrete Curb: Unit LF measured along the curb face in horizontal plan, including curved segments. Exclude openings without curb.
B. Include excavation, subgrade preparation, the detailed 4-inch No. 57 aggregate foundation, forms, concrete, reinforcement where shown, transitions, joints, curing, backfill, compaction, and incidental restoration.
C. Aggregate foundation beneath curb is included in Item 510 and is not payable under Item 550. Do not also measure curb area as sidewalk, concrete paving, or asphalt pavement.
3.6 CONCRETE SIDEWALKS, DRIVEWAY APRONS AND ADA PARKING AREA
A. Item 530 — 6-inch Concrete Sidewalks and Driveway Aprons: Unit SY measured by horizontal plan area of completed and accepted concrete within the indicated limits. Include 6-inch-thick concrete over 6 inches of compacted AASHTO No. 57 aggregate base. Provide reinforcement where detailed.
B. Item 540 — 6-inch Reinforced Concrete Paving, ADA Parking Area: Unit SY measured by horizontal plan area of completed and accepted concrete within the indicated limits. Include 6-inch-thick reinforced concrete over 8 inches of compacted PennDOT 2A aggregate base. Provide reinforcement as detailed.
C. Include excavation to the required section, subgrade preparation, aggregate base, forms, concrete, reinforcement where detailed, integral thickened edges, joints, joint fillers and sealants, finishing, curing, testing, protection, ramp shaping and transitions shown.
D. Aggregate base beneath Items 530 and 540 is included in the respective concrete item and is not separately payable under Item 550. Do not measure the same concrete area under both items.
E. The 8-inch aggregate base applies only to the ADA concrete parking area. Sidewalks and driveway aprons receive the 6-inch aggregate base specified under Item 530.
3.7 AGGREGATE BASE AND ASPHALT PAVEMENT
A. Item 550 — 6-inch Compacted PennDOT 2A Aggregate Base: Unit SY of completed and accepted aggregate base at the specified compacted thickness within the pavement limits shown.
B. Item 560 — 4-inch Superpave 25 mm Base Course: Unit SY of completed and accepted asphalt base course at the specified compacted thickness.
C. Item 570 — 2-inch Superpave 19 mm Binder Course: Unit SY of completed and accepted asphalt binder course at the specified compacted thickness.
D. Item 580 — 1-1/2-inch Superpave 9.5 mm Wearing Course: Unit SY of completed and accepted asphalt wearing course at the specified compacted thickness.
E. Measure each separately scheduled layer by horizontal plan area within its authorized limits. Where layers occupy the same footprint, measure that footprint separately under each applicable layer item. Do not increase quantities for waste, laps or unauthorized construction.
F. Include excavation to the pavement section, final subgrade preparation and compaction under Item 550.
Exclude bulk earthwork paid under Item 140 and demolition paid under Item 130. Do not duplicate excavation costs between these items.
G. Include materials, placement, compaction, joints, required testing and correction of test locations in the applicable course item. Include required tack or prime coat with the course placed immediately above that treatment. Include sawcutting and tie-ins required for new pavement installation in the corresponding course item, excluding demolition cuts paid under Item 130.
H. Exclude aggregate base included with concrete paving, curb, utility bedding or stormwater facilities. Restoration of Contractor-caused damage is not separately payable.
3.8 ADA ACCESSIBLE PARKING SIGN ASSEMBLIES
A. Item 590 — ADA Accessible-Parking Sign Assemblies: Unit EA per complete proposed assembly shown. Count a required van-accessible supplemental panel installed on the same support as part of that assembly, not as an additional assembly.
B. Include sign panels, posts, hardware, excavation, foundation or anchorage and installation shown.
C. Civil signage is limited to the proposed ADA accessible-parking sign assemblies. Exclude other new signage and Structural bollards, including bollard foundations and anchorage.
3.9 PAVEMENT MARKINGS
A. Item 600 — Pavement Markings: Unit LS for all civil pavement markings shown, including parking-space lines, accessible-parking symbols, access-aisle hatching, arrows, stop bars and other indicated markings.
B. Include layout, surface preparation, materials, application, protection and correction of deficient work. Include temporary markings only where assigned by the Contract Documents.
3.10 FINISH GRADING AND SEEDING
A. Item 160 — Finish Grading and Seeding: Unit LS for complete permanent landscape restoration within the indicated limits and areas disturbed by authorized civil work, excluding work expressly assigned elsewhere.
B. Include fine grading, respreading accepted stockpiled topsoil and supplying additional topsoil required for the specified finished depth, soil testing/amendments, seed, mulch or blankets required for permanent establishment, watering, maintenance, reseeding and repair until the specified acceptance requirements are met.
C. Bulk excavation, embankment construction and initial topsoil stripping and stockpiling are included under Item 140, Bulk Earthwork and Rough Grading. Temporary stabilization and temporary E&S blankets are included under Item 150, Erosion and Sediment Control. Include permanent stabilization once, under this item or another expressly assigned permanent treatment item.
3.11 EROSION AND SEDIMENT CONTROL
A. Item 150 — Erosion and Sediment Control: Unit LS for complete temporary E&S work assigned to the Contractor by the approved standalone E&S plans furnished with the Contract Drawings, applicable permits and Section
015723.00. E&S requirements remain part of the Contract Work even where individual controls are not repeated on the civil construction drawings.
B. Include installation before disturbance; construction entrances; perimeter controls; inlet protection; temporary diversions, conveyances and stabilization; maintenance, cleaning and replacement; Contractor inspections and records; required meeting attendance; authorized removal; and restoration associated with removal.
C. Maintain assigned controls for the Contract-required duration and coordinate transfer of continuing obligations at closeout. Do not remove controls or discontinue maintenance solely because an interim payment milestone has been reached.
D. Permanent PCSM facilities are paid under Items 280 and 290. Permanent finish grading and seeding are paid under Item 160. Construction sediment removal and restoration of stormwater facility performance before acceptance are included in the respective facility lump sum.
3.12 MOBILIZATION
A. Item 110 — Mobilization: Unit LS for civil mobilization and demobilization. Coordinate with any project-wide mobilization item so that the same costs are not included twice.
B. Include initial movement of personnel and equipment, civil temporary facilities, startup coordination, general civil construction layout, administrative startup and closeout, compilation of civil record-drawing information, final general cleanup and demobilization.
C. Item-specific testing, product submittals, quantity records, installation documentation and cleanup necessary to complete individual work items are included in those items.
D. Submit a supported schedule of values for progress payment. Apply mobilization payment limitations, retainage and closeout requirements stated in the Agreement and Division 01. This Section establishes no independent percentage cap or advance-payment entitlement.
3.13 UNDERGROUND ROOF DRAINAGE PIPE
A. Item 210 — 6-inch PVC Underground Roof Drainage Pipe and Item 220 — 8-inch PVC Underground Roof Drainage Pipe: Unit LF, separately measured by diameter along the installed alignment from the civil connection point shown to the inside face of the receiving structure or designated outlet or connection.
B. Include pipe, underground bends and fittings, joints, civil cleanouts, excavation, bedding, specified backfill, compaction, ordinary trench support and dewatering, testing, cleaning and completion of the civil connection to the MEP-provided assembly.
C. Exclude building roof drainage, aboveground downspouts, downspout boots and transition adapters assigned to MEP. Coordinate connection sizes, elevations and installation sequence with MEP.
D. Measure shared downstream storm pipe under its designated storm sewer item only. Do not measure the same pipe length under both roof drainage and storm sewer items. Separately scheduled surface restoration is paid under its corresponding item.
3.14 SANITARY SEWER PIPE AND APPURTENANCES
A. Item 410 — 6-inch PVC Gravity Sanitary Sewer Pipe: Unit LF measured along installed pipe centerline between inside faces of structures and designated connection limits. Include excavation, bedding, pipe, joints, fittings, specified backfill, compaction, ordinary trench support and dewatering, testing and cleaning.
B. Item 420 — Sanitary Sewer Manhole SAN MH-2: Unit EA per complete assembly shown. Include excavation, foundation preparation, base, structure, risers, frame and cover, steps where required, pipe penetrations and seals, channel and bench construction, backfill, compaction, testing and final adjustment to grade.
C. Item 430 — Connection to Existing Sanitary/Septic System: Unit LS for the complete connection within the limits shown. Include exposure and protection of the existing facility, verification of connection conditions, required openings, connection fittings and seals, assigned modifications and closures, temporary service measures assigned to civil, backfill, compaction and testing. Exclude new pipe lengths and structures separately measured under other items.
D. Item 440 — 1-1/2-inch PVC Sanitary Force Main: Unit LF measured along installed pipe centerline between designated connection points. Include excavation, bedding, pressure pipe, pressure-rated joints and fittings, specified backfill, compaction, ordinary trench support and dewatering, restraint and appurtenances assigned to the civil force main, hydrostatic testing and cleaning.
E. Item 450 — Sanitary Sewer Cleanouts: Unit EA per complete assembly shown. Include fittings, riser, cap, protective enclosure or pad where detailed, excavation, bedding, backfill, compaction and installation.
F. Do not include separately scheduled manholes or cleanouts in pipe unit prices. Do not deduct incidental fittings from measured pipe length. Do not include the same connection work under both a pipe item and Item 430.
G. Exclude MEP pumping and dosing equipment, controls, alarms, electrical work, and structures and associated excavation or backfill assigned to MEP. Perform civil work to the connection limits indicated on the Contract Drawings. Coordinate installation and testing with the MEP Contractor at those interfaces.
3.15 SITE DEMOLITION AND REMOVALS
A. Item 130 — Site Demolition and Removals: Unit LS for civil demolition, removals and assigned relocations shown, coordinated with Section 024119.00.
B. Include protection of items to remain; designated pavement, concrete, curb and utility removals; demolition sawcutting; disconnections and closures assigned to civil; salvage and reinstallation where indicated; loading, hauling, lawful ordinary disposal and cleanup.
C. Include removal of existing bollards and removal or relocation of existing site features only where expressly assigned to civil on the Contract Drawings. Coordinate features requiring Architectural, Structural, MEP or utility work with the responsible trade.
D. Exclude clearing and grubbing paid under Item 120, building or Structural demolition, planned propane-tank work assigned to MEP, and unknown contamination or tanks governed by the environmental procedures.
E. Do not include the same removals in a new-construction item. Excavation inherent in installing new work remains included in the corresponding new-work item unless expressly designated otherwise.
3.16 BULK EARTHWORK AND ROUGH GRADING
A. Item 140 — Bulk Earthwork and Rough Grading: Unit LS for authorized general site earthwork outside excavation and backfill assigned to pipe, structure, pavement, concrete or stormwater facility items.
B. Include topsoil stripping and stockpiling, bulk excavation, embankment, ordinary required import and export, moisture conditioning, compaction, rough grading, Contractor-required testing, stockpile management and lawful ordinary excess-material disposal.
C. Exclude clearing and grubbing paid under Item 120, demolition paid under Item 130, temporary E&S controls paid under Item 150, and permanent finish grading, topsoil placement and seeding paid under Item 160.
D. Include ordinary earthwork necessary for the indicated grades and sections. Evaluate authorized additional unsuitable-soil removal and replacement under the Contract change procedures. Do not duplicate excavation or fill quantities or costs assigned to another scheduled item.
3.17 PARKING BUMPERS
A. Item 520 — Concrete Bumper Blocks: Unit EA per complete accepted parking-bumper assembly shown.
B. Include units, pins or anchors, bedding where required, layout and installation in accordance with Section 321713.00.
C. Parking bumpers are distinct from Structural bollards and their foundations.
3.18 TRENCH DRAIN AND RIPRAP
A. Item 310 — Trench Drain TD-1: Unit EA per complete trench-drain assembly shown. Include the full indicated length of channel, grates, anchors, excavation, foundation, concrete encasement where detailed, end treatments and outlet adapter. External connecting pipe is paid under its scheduled pipe item.
B. Item 300 — R-3 Riprap, Including Geotextile: Unit CY of completed and accepted riprap measured in place within the detailed limits. Include excavation, subgrade preparation, bedding where detailed, geotextile, stone and placement. Geotextile is incidental and is not measured separately.
C. Determine riprap volume from accepted field dimensions and the detailed placement thickness. Do not use loose truck volume or stone delivery tonnage alone as the payment quantity. Material placed outside authorized limits is not separately payable.
D. Exclude temporary rock filters paid under Item 150. Do not include separately scheduled permanent riprap in Items 280 or 290.
3.19 CLEARING AND GRUBBING
A. Item 120 — Clearing and Grubbing: Unit LS for complete clearing and grubbing within the indicated limits in accordance with Section 311000.00.
B. Include removal of designated vegetation, trees, brush, stumps and roots; required protection of vegetation to remain; loading, hauling, lawful disposal; and backfilling and compaction of resulting voids.
C. Exclude topsoil stripping and stockpiling paid under Item 140, demolition paid under Item 130, temporary E&S controls paid under Item 150, and permanent finish grading and seeding paid under Item 160.
D. Replacement tree or shrub planting is excluded unless expressly assigned to this item by the Contract Documents.
END OF SECTION 01 22 00.00 - UNIT PRICES
SECTION 01 57 23.00 TEMPORARY STORM WATER POLLUTION CONTROL
JACKSON TOWNSHIP TEMPORARY STORM WATER POLLUTION CONTROL SECTION 01 57 23.00
SECTION 01 57 23.00
TEMPORARY STORM WATER POLLUTION CONTROL
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes:
1. Temporary erosion and sediment control measures, temporary stabilization, pollution prevention, inspections, maintenance, and removal of temporary controls indicated on the approved erosion and sediment control plans.
B. Related Requirements:
1. Section 311000.00 Site Clearing: Clearing, grubbing, and topsoil stripping and stockpiling.
2. Section 312000.00 Earth Moving: Excavation, grading, backfill, and control of water in excavations.
3. Section 329113.00, Soil Preparation: Topsoil and soil amendments.
4. Section 329200.00, Turf and Grasses: Seed, lime, fertilizer, mulch, seeding, and permanent vegetative establishment.
5. Section 334200.00, Stormwater Conveyance, and Section 334600.00, Subdrainage: Permanent drainage facilities and protection during construction.
1.2 APPROVED PLANS AND PERMIT REQUIREMENTS
A. Perform the work in accordance with the approved erosion and sediment control plans (E&S Plan), construction sequence, applicable project permit conditions, and this Section. Keep the approved plans, permit documents, and inspection records available at the project site.
B. The approved plans establish the minimum erosion and sediment control measures. Provide additional maintenance and corrective measures necessary to prevent accelerated erosion and sediment discharge from construction operations.
C. Do not revise approved measures, locations, or construction sequencing without review by the Architect and Civil Engineer and required approval by the County Conservation District and other applicable regulatory agencies. Process changes through the Contract change procedures. Do not alter the approved design solely on the basis of a product submittal.
1.3 PREINSTALLATION MEETINGS
A. Before earth disturbance, coordinate an on-site preconstruction meeting with the York County Conservation District (YCCD), Owner/permittee, Architect, Site Engineer, Contractor, operators, and the licensed professional/designee responsible for PCSM critical stages. Provide all invited attendees at least seven days' notice as required by 25 Pa. Code 102.5(e), unless DEP/YCCD provides a written waiver; comply with any longer project permit notice.
B. Coordinate the meeting through the permittee. Where required for the project NPDES permit, provide YCCD the recorded PCSM instrument before scheduling the meeting. Do not assume that this earthwork conference substitutes for the required permit preconstruction meeting.
C. Review the approved E&S/PCSM plans and permit conditions, limits of disturbance, construction sequence, initial controls, temporary stabilization, dewatering, inspection/reporting personnel, SCM critical stages and licensed-professional observations. Identify required District notifications and inspection/maintenance records.
Do not begin earth disturbance before required permit prerequisites and the meeting are completed.
D. Coordinate this conference with Section 015723.00. Retain meeting records and identify responsibilities and unresolved items before affected work proceeds.
1.4 ACTION SUBMITTALS
A. Product Data: Before installation, submit manufacturer product data and installation instructions for each manufactured control used, including:
1. Compost filter sock: Diameter, sock fabric properties, compost specifications, stakes, and anchoring.
2. Inlet protection devices: Configuration, filtration properties, attachment, and overflow provisions.
3. Pumped-water filter bags: Fabric properties, seams, allowable pumping rate, and discharge arrangement.
4. Erosion-control blankets and geotextiles: Material, performance properties, anchoring, and installation instructions.
5. Mulch binders and tackifiers: Application rates and documentation of suitability for the proposed use without toxicity to native plant and animal species.
6. Manufactured components of concrete washout facilities, where used.
B. Proposed Plan Revisions: Identify the reason for each proposed change, revised details and locations, and effects on construction sequencing. Submit for review before implementation and obtain approvals required by Article 1.2.
1.5 INFORMATIONAL SUBMITTALS
A. Material Certifications: Submit before incorporating materials into the Work:
1. Manufacturer certification that erosion-control matting complies with the specified requirements.
2. Certification that compost and sock fabric comply with the specified material requirements.
3. Supplier certification identifying size and gradation of aggregate for construction entrances, rock filters, and riprap.
B. Inspection and Maintenance Reports: Maintain written reports of required inspections. Include inspection date and time, inspector name, precipitation and site conditions, condition and effectiveness of controls, deficiencies, required corrective actions, and dates maintenance and repairs were completed. Keep reports available on site and furnish copies to the Architect and Civil Engineer.
C. Approval Documentation: Submit copies of regulatory approvals for revisions before implementing the revisions.
Provide documentation of required inspections and authorization for removal of temporary controls.
D. Submit topsoil, fertilizer, lime, seed-mixture, and inoculant certifications under Sections 329113.00 and 329200.00, as applicable. Do not duplicate those submissions under this Section.
1.6 QUALITY ASSURANCE
A. Designate a qualified erosion and sediment control coordinator experienced with similar construction. Identify the coordinator to the Owner, Architect, and Civil Engineer before earth disturbance.
B. Use personnel trained and experienced in installation, inspection, and maintenance of the specified measures.
Coordinate Contractor responsibilities with the permittee and co-permittee responsibilities identified in the project permit.
1.7 PROJECT PLAN COORDINATION
A. The approved E&S site layout, construction sequence, numbered controls, and permit conditions form the basis of this work. Details alone do not establish control locations. Maintain the incorporated plan set at the site and coordinate controls with the current disturbance boundary.
B. York County Conservation District is the project conservation district. References to another county district in generic notes do not change the project notification and coordination requirements.
C. Suspected contaminated soil or water shall be handled under Section 024119.00. Sediment-control devices and ordinary filter bags do not authorize treatment or discharge of contaminated water. Obtain the required characterization and accepted handling method before pumping or discharge.
2.1…