About this file

This document comprises plumbing specifications for Jackson Township's renovation and addition project to an existing municipal building, along with construction of new storage and salt storage facilities located in Spring Grove, Pennsylvania. The specifications detail common work results for plumbing systems, including equipment installation requirements, painting and finishing protocols, concrete bases, and supports and anchorages. Additional sections establish requirements for common motor specifications for plumbing equipment; expansion fittings and loops for piping systems; sleeves and sleeve seals; escutcheons and floor plates; meters and gauges; general-duty valves; and hangers and supports for plumbing piping and equipment. Sealed bids for Contract 2: Plumbing Construction will be received online via the PennBid Program until 1:00 PM EST on Tuesday, December 8, 2026, with public opening at the same time. Bidding documents became available November 4, 2026, at no cost through PennBid. A pre-bid conference is scheduled for Tuesday, November 10, 2026, at 10:00 AM EST on-site at 439 Roths Church Road, Spring Grove, Pennsylvania, with attendance highly recommended but not mandatory. Contract awards will occur at a regularly scheduled Jackson Township meeting on January 4, 2027. The contract term is four hundred calendar days from the date specified in the Notice to Proceed.

Each bidder must submit a bid bond or certified check payable to Jackson Township in the amount of 10 percent of the maximum bid and must provide evidence of qualifications to perform the work. The project is subject to Pennsylvania's Prevailing Wage Act, approved August 15, 1961 (Act 442, P.L. 987), as amended. The specifications encompass detailed technical requirements across multiple plumbing disciplines, including quality assurance standards, product specifications, and execution procedures aligned with industry standards such as ASME, AWS, MSS, and ASTM. Jackson Township reserves the right to accept any bid, waive any informalities, or reject any or all bids.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

JACKSON TOWNSHIP COMMON WORK RESULTS

FOR PLUMBING

220500-1

SECTION 220500 - COMMON WORK RESULTS FOR PLUMBING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes the following:

1. Equipment installation requirements common to equipment sections.

2. Painting and finishing.

3. Concrete bases.

4. Supports and anchorages.

1.3 DEFINITIONS

A. Basis of Design Products:

1. The "basis of design" products named on the contract drawings and throughout the project manual constitute the engineer’s design.

2. The phrase "or comparable product by one of the following" throughout the project manual implies that the comparable products are accepted as equal; however, the conditions of AIA document A201-2007 regarding shop drawings, product data and samples apply with regards to deviations from the contract documents.

3. If products other than the "basis of design" differ from the engineer’s design to the extent that modifications to structural, mechanical, electrical, or any other affected discipline's design is required to install the product properly, then all such modifications shall be done at the expense of the Contractor.

B. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe and duct chases, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawlspaces, and tunnels.

C. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and mechanical equipment rooms.

D. Exposed, Exterior Installations: Exposed to view outdoors or subject to outdoor ambient temperatures and weather conditions. Examples include rooftop locations.

E. Concealed, Interior Installations: Concealed from view and protected from physical contact by building occupants. Examples include above ceilings and chases.

F. Concealed, Exterior Installations: Concealed from view and protected from weather conditions and physical contact by building occupants but subject to outdoor ambient temperatures.

Examples include installations within unheated shelters.

220500-2

G. The following are industry abbreviations for plastic materials:

1. CPVC: Chlorinated polyvinyl chloride plastic.

2. PE: Polyethylene plastic.

3. PVC: Polyvinyl chloride plastic.

H. The following are industry abbreviations for rubber materials:

1. EPDM: Ethylene-propylene-diene terpolymer rubber.

2. NBR: Acrylonitrile-butadiene rubber.

1.4 QUALITY ASSURANCE

A. Steel Support Welding: Qualify processes and operators according to AWS D1.1, "Structural Welding Code--Steel."

B. Steel Pipe Welding: Qualify processes and operators according to ASME Boiler and Pressure Vessel Code: Section IX, "Welding and Brazing Qualifications."

1. Comply with provisions in ASME B31 Series, "Code for Pressure Piping."

2. Certify that each welder has passed AWS qualification tests for welding processes involved and that certification is current.

3. Electrical Characteristics for Plumbing Equipment: Equipment of higher electrical characteristics may be furnished provided such proposed equipment is approved in writing and connecting electrical services, circuit breakers, and conduit sizes are appropriately modified. If minimum energy ratings or efficiencies are specified, equipment shall comply with requirements. Electrical modifications shall be done at the expense of the Plumbing Contractor.

C. Installing Contractor shall submit appropriate forms to Pennsylvania Department of Labor and Industry – Boiler Division for approval of boilers, unfired pressure vessels, or other equipment under their jurisdiction before installation of equipment. Contractor shall also submit appropriate fees. Contractor shall arrange for inspection and obtain approval for installation. If installation fails inspection, Contractor shall arrange for re-inspection until approval is granted.

1.5 DELIVERY, STORAGE, AND HANDLING

A. Deliver pipes and tubes with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe end damage and to prevent entrance of dirt, debris, and moisture.

B. Store plastic pipes protected from direct sunlight. Support to prevent sagging and bending.

1.6 COORDINATION

A. Arrange for pipe spaces, chases, slots, and openings in building structure during progress of construction, to allow for plumbing installations.

B. Coordinate installation of required supporting devices and set sleeves in poured-in-place concrete and other structural components as they are constructed.

220500-3

1.7 ACCESS PANELS

A. Contractor shall provide access panels for all concealed equipment, valves, strainers, control devices, cleanouts, traps, and other items and devices requiring maintenance or access for service, adjustment, balancing or manual operation in his work scope.

1. General maintenance access panels ARE NOT shown on Drawings. Contractor installing the item requiring access shall coordinate locations, sizes, quantities, etc., and shall provide and install access panels as required. Door sizes shall be 12 inches x 12 inches for hand access, 18 inches x 18 inches for shoulder access and 24 inches x 24 inches for full body access where required.

a. In new construction, the Contractor for General Construction shall provide the rough framed opening, and in the case of flush, frameless access panels in gypsum board applications, shall perform all drywall finishing. The Contractor for General Construction shall paint all access panels that are not prefinished or are otherwise intended to be left exposed.

b. In existing construction, the Contractor installing the item requiring access shall cut and patch the required openings and shall provide and install the access panels as required. Unless the surface where the access panel is cut in and patched is already specified to be finished by the General Contractor, the Contractor installing the item requiring access shall paint all access panels that are not prefinished or are otherwise intended to be left exposed.

c. Refer to Division 1 Section “Cutting and Patching” for additional information and approved access panel types.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 PIPING SYSTEMS - COMMON REQUIREMENTS

A. Install piping according to the following requirements and Division 22 Sections specifying piping systems.

B. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping systems. Indicated locations and arrangements were used to size pipe and calculate friction loss, expansion, pump sizing, and other design considerations. Install piping as indicated unless deviations to layout are approved on Coordination Drawings.

C. Install piping in concealed locations, unless otherwise indicated and except in equipment rooms and service areas.

D. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise.

E. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.

F. Install piping to permit valve servicing.

220500-4

G. Install piping at indicated slopes.

H. Install piping free of sags and bends.

I. Install fittings for changes in direction and branch connections.

J. Install piping to allow application of insulation.

K. Select system components with pressure rating equal to or greater than system operating pressure.

L. Fire-Barrier Penetrations: Maintain indicated fire rating of walls, partitions, ceilings, and floors at pipe penetrations. Seal pipe penetrations with firestop materials. Refer to Division 07 Section "Penetration Firestopping" for materials.

M. Verify final equipment locations for roughing-in.

N. Refer to equipment specifications in other Sections of these Specifications for roughing-in requirements.

3.2 PIPING JOINT CONSTRUCTION

A. Join pipe and fittings according to the following requirements and Division 22 Sections specifying piping systems.

B. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.

C. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings before assembly.

D. Soldered Joints: Apply ASTM B 813, water-flushable flux, unless otherwise indicated, to tube end. Construct joints according to ASTM B 828 or CDA's "Copper Tube Handbook," using lead-free solder alloy complying with ASTM B 32.

E. Threaded Joints: Thread pipe with tapered pipe threads according to ASME B1.20.1. Cut threads full and clean using sharp dies. Ream threaded pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as follows:

1. Apply appropriate tape or thread compound to external pipe threads unless dry seal threading is specified.

2. Damaged Threads: Do not use pipe or pipe fittings with threads that are corroded or damaged. Do not use pipe sections that have cracked or open welds.

F. Welded Joints: Construct joints according to AWS D10.12, using qualified processes and welding operators according to Part 1 "Quality Assurance" Article.

G. Flanged Joints: Select appropriate gasket material, size, type, and thickness for service application. Install gasket concentrically positioned. Use suitable lubricants on bolt threads.

3.3 PIPING CONNECTIONS

A. Make connections according to the following, unless otherwise indicated:

220500-5

1. Install unions, in piping NPS 2 and smaller, adjacent to each valve and at final connection to each piece of equipment.

2. Install flanges, in piping NPS 2-1/2 and larger, adjacent to flanged valves and at final connection to each piece of equipment.

3. Dry Piping Systems: Install dielectric unions and flanges to connect piping materials of dissimilar metals.

4. Wet Piping Systems: Install dielectric coupling and nipple fittings to connect piping materials of dissimilar metals.

3.4 EQUIPMENT INSTALLATION - COMMON REQUIREMENTS

A. Install equipment to allow maximum possible headroom unless specific mounting heights are indicated.

B. Install equipment level and plumb, parallel, and perpendicular to other building systems and components in exposed interior spaces, unless otherwise indicated.

C. Install Plumbing equipment to facilitate service, maintenance, and repair or replacement of components. Connect equipment for ease of disconnecting, with minimum interference to other installations. Extend grease fittings to accessible locations.

D. Install equipment to allow right of way for piping installed at required slope.

3.5 PAINTING

A. Painting of Plumbing systems, equipment, and components is specified in Division 09 Sections "Interior Painting" and "Exterior Painting."

B. Damage and Touchup: Repair marred and damaged factory-painted finishes with materials and procedures to match original factory finish.

3.6 CONCRETE BASES

A. Concrete Bases: Anchor equipment to concrete base according to equipment manufacturer's written instructions and according to seismic codes at Project.

1. Construct concrete bases of dimensions indicated, but not less than 4 inches larger in both directions than supported unit.

2. Install dowel rods to connect concrete base to concrete floor. Unless otherwise indicated, install dowel rods on 18-inch centers around the full perimeter of the base.

3. Install epoxy-coated anchor bolts for supported equipment that extend through concrete base, and anchor into structural concrete floor.

4. Place and secure anchorage devices. Use supported equipment manufacturer's setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

5. Install anchor bolts to elevations required for proper attachment to supported equipment.

6. Install anchor bolts according to anchor-bolt manufacturer's written instructions.

7. Use 3000-psi, 28-day compressive-strength concrete and reinforcement as specified in

Division 03 Section "Cast-in-Place Concrete."

220500-6

3.7 ERECTION OF METAL SUPPORTS AND ANCHORAGES

A. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor HVAC materials and equipment.

B. Field Welding: Comply with AWS D1.1.

END OF SECTION 220500

JACKSON TOWNSHIP COMMON MOTOR REQUIREMENTS

FOR PLUMBING EQUIPMENT

220513-1

SECTION 220513 - COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes general requirements for single-phase general-purpose, horizontal, small and medium, squirrel-cage induction motors for use on ac power systems up to 600 V and installed at equipment manufacturer's factory or shipped separately by equipment manufacturer for field installation.

1.3 COORDINATION

A. Coordinate features of motors, installed units, and accessory devices to be compatible with the following:

1. Motor controllers.

2. Torque, speed, and horsepower requirements of the load.

3. Ratings and characteristics of supply circuit and required control sequence.

4. Ambient and environmental conditions of installation location.

PART 2 - PRODUCTS

2.1 GENERAL MOTOR REQUIREMENTS

A. Comply with NEMA MG 1 unless otherwise indicated.

B. Comply with IEEE 841 for severe-duty motors.

2.2 MOTOR CHARACTERISTICS

A. Duty: Continuous duty at ambient temperature of 40 deg C and at altitude of 3300 feet above sea level.

B. Capacity and Torque Characteristics: Sufficient to start, accelerate, and operate connected loads at designated speeds, at installed altitude and environment, with indicated operating sequence, and without exceeding nameplate ratings or considering service factor.

JACKSON TOWNSHIP COMMON MOTOR REQUIREMENTS

FOR PLUMBING EQUIPMENT

220513-2

2.3 SINGLE-PHASE MOTORS

A. Motors larger than 1/20 hp shall be one of the following, to suit starting torque and requirements of specific motor application:

1. Permanent-split capacitor.

2. Split phase.

3. Capacitor start, inductor run.

4. Capacitor start, capacitor run.

B. Multispeed Motors: Variable-torque, permanent-split-capacitor type.

C. Bearings: Prelubricated, antifriction ball bearings or sleeve bearings suitable for radial and thrust loading.

D. Motors 1/20 HP and Smaller: Shaded-pole type.

E. Thermal Protection: Internal protection to automatically open power supply circuit to motor when winding temperature exceeds a safe value calibrated to temperature rating of motor insulation.

Thermal-protection device shall automatically reset when motor temperature returns to normal range.

PART 3 - EXECUTION (Not Applicable)

END OF SECTION 220513

JACKSON TOWNSHIP EXPANSION FITTINGS AND

LOOPS FOR PLUMBING PIPING

220516-1

SECTION 220516 - EXPANSION FITTINGS AND LOOPS FOR PLUMBING PIPING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Flexible-hose packless expansion joints.

2. Metal-bellows packless expansion joints.

3. Rubber packless expansion joints.

4. Grooved-joint expansion joints.

5. Pipe loops and swing connections.

6. Alignment guides and anchors.

B. Plumbing contractor is responsible to design, select and submit signed and sealed calculations for thermal expansion and anchoring of all plumbing piping systems. Expansion devices to be installed in all straight runs of piping over 50 feet. Expansion devices to be installed at a maximum of 150 feet on center.

1.3 PERFORMANCE REQUIREMENTS

A. Compatibility: Products shall be suitable for piping service fluids, materials, working pressures, and temperatures.

B. Capability: Products to absorb 200 percent of maximum axial movement between anchors.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

1.5 INFORMATIONAL SUBMITTALS

A. Welding certificates.

B. Product Certificates: For each type of expansion joint, from manufacturer.

1.6 CLOSEOUT SUBMITTALS

A. Maintenance Data: For expansion joints to include in maintenance manuals.

220516-2

1.7 QUALITY ASSURANCE

A. Welding Qualifications: Qualify procedures and personnel according to the following:

1. AWS D1.1/D1.1M, "Structural Welding Code - Steel."

2. ASME Boiler and Pressure Vessel Code: Section IX.

PART 2 - PRODUCTS

2.1 PACKLESS EXPANSION JOINTS

A. Metal-Bellows Packless Expansion Joints:

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Adsco Manufacturing LLC.

b. American BOA, Inc.

c. Badger Industries, Inc.

d. Expansion Joint Systems, Inc.

e. Flex Pression Ltd.

f. Flex-Hose Co., Inc.

g. Flex-Weld, Inc.

h. Flexicraft Industries.

i. Flo Fab inc.

j. Hyspan Precision Products, Inc.

k. Mason Industries, Inc.

l. Metraflex Company (The).

m. Proco Products, Inc.

n. Senior Flexonics Pathway.

o. Tozen Corporation.

p. U.S. Bellows, Inc.

q. Unaflex.

r. Unisource Manufacturing, Inc.

s. Universal Metal Hose.

t. WahlcoMetroflex.

2. Standards: ASTM F 1120 and EJMA's "Standards of the Expansion Joint Manufacturers Association, Inc."

3. Type: Circular, corrugated bellows with external tie rods.

4. Minimum Pressure Rating: 175 psig unless otherwise indicated.

5. Configuration: double joint with base class(es) unless otherwise indicated.

6. Expansion Joints for Copper Tubing: Multi-ply phosphor-bronze bellows, copper pipe ends, and brass shrouds.

a. End Connections for Copper Tubing NPS 2 and Smaller: Solder joint.

B. Rubber Packless Expansion Joints:

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Amber/Booth Company, Inc.

http://www.specagent.com/LookUp/?uid=123456890303&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890304&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890305&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890306&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890307&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890308&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890310&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890309&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890311&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890312&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890322&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890313&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890314&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890315&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890316&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890317&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890318&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890319&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890320&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890321&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890324&mf=&src=wd

220516-3

b. Flex-Hose Co., Inc.

c. Flex-Weld, Inc.

d. Flexicraft Industries.

e. Garlock Sealing Technologies.

f. General Rubber Corporation.

g. Mason Industries, Inc.

h. Metraflex Company (The).

i. Proco Products, Inc.

j. Red Valve Company, Inc.

k. Tozen Corporation.

l. Unaflex.

m. Unisource Manufacturing, Inc.

2. Standards: ASTM F 1123 and FSA's "Technical Handbook: Non-Metallic Expansion Joints and Flexible Pipe Connectors."

3. Material: Fabric-reinforced rubber complying with FSA-NMEJ-703.

4. Arch Type: multiple arches with external control rods.

5. Spherical Type: multiple spheres with external control rods.

6. Minimum Pressure Rating for NPS 1-1/2 to NPS 4: 150 psig at 220 deg F.

7. Minimum Pressure Rating for NPS 5 and NPS 6: 140 psig at 200 deg F.

8. Minimum Pressure Rating for NPS 8 to NPS 12: 140 psig at 180 deg F.

9. Material for Water: EPDM.

10. End Connections: Full-faced, integral steel flanges with steel retaining rings.

2.2 GROOVED-JOINT EXPANSION JOINTS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Anvil International, Inc.

2. Shurjoint Piping Products.

3. Victaulic Company.

B. Description: Factory-assembled expansion joint made of several grooved-end pipe nipples, couplings, and grooved joints.

C. Standard: AWWA C606, for grooved joints.

D. Nipples: Galvanized, ASTM A 53/A 53M, Schedule 40, Type E or S, steel pipe with grooved ends.

E. Couplings: Seven, flexible type for steel-pipe dimensions. Include ferrous housing sections, EPDM gasket suitable for cold and hot water, and bolts and nuts.

2.3 ALIGNMENT GUIDES AND ANCHORS

A. Alignment Guides:

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. Adsco Manufacturing LLC.

b. Advanced Thermal Systems, Inc.

http://www.specagent.com/LookUp/?uid=123456890325&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890327&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890326&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890328&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890329&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890330&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890331&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890332&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890333&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890334&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890335&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890336&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890337&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890338&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890339&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890340&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890341&mf=&src=wd

220516-4

c. Flex-Hose Co., Inc.

d. Flex-Weld, Inc.

e. Flexicraft Industries.

f. Hyspan Precision Products, Inc.

g. Mason Industries, Inc.

h. Metraflex Company (The).

i. Senior Flexonics Pathway.

j. U.S. Bellows, Inc.

k. Unisource Manufacturing, Inc.

2. Description: Steel, factory-fabricated alignment guide, with bolted two-section outer cylinder and base for attaching to structure; with two-section guiding spider for bolting to pipe.

B. Anchor Materials:

1. Steel Shapes and Plates: ASTM A 36/A 36M.

2. Bolts and Nuts: ASME B18.10 or ASTM A 183, steel hex head.

3. Washers: ASTM F 844, steel, plain, flat washers.

4. Mechanical Fasteners: Insert-wedge-type stud with expansion plug anchor for use in hardened portland cement concrete, with tension and shear capacities appropriate for application.

a. Stud: Threaded, zinc-coated carbon steel.

b. Expansion Plug: Zinc-coated steel.

c. Washer and Nut: Zinc-coated steel.

5. Chemical Fasteners: Insert-type-stud, bonding-system anchor for use with hardened portland cement concrete, with tension and shear capacities appropriate for application.

a. Bonding Material: ASTM C 881/C 881M, Type IV, Grade 3, two-component epoxy resin suitable for surface temperature of hardened concrete where fastener is to be installed.

b. Stud: ASTM A 307, zinc-coated carbon steel with continuous thread on stud unless otherwise indicated.

c. Washer and Nut: Zinc-coated steel.

PART 3 - EXECUTION

3.1 EXPANSION-JOINT INSTALLATION

A. Install expansion joints of sizes matching sizes of piping in which they are installed.

B. Install metal-bellows expansion joints according to EJMA's "Standards of the Expansion Joint Manufacturers Association, Inc."

C. Install rubber packless expansion joints according to FSA-NMEJ-702.

D. Install grooved-joint expansion joints to grooved-end steel piping http://www.specagent.com/LookUp/?uid=123456890342&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890344&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890343&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890345&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890350&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890346&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890347&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890348&mf=&src=wd http://www.specagent.com/LookUp/?uid=123456890349&mf=&src=wd

220516-5

3.2 PIPE LOOP AND SWING CONNECTION INSTALLATION

A. Install pipe loops cold-sprung in tension or compression as required to partly absorb tension or compression produced during anticipated change in temperature.

B. Connect risers and branch connections to mains with at least five pipe fittings including tee in main.

C. Connect risers and branch connections to terminal units with at least four pipe fittings including tee in riser.

D. Connect mains and branch connections to terminal units with at least four pipe fittings including tee in main.

3.3 ALIGNMENT-GUIDE AND ANCHOR INSTALLATION

A. Install alignment guides to guide expansion and to avoid end-loading and torsional stress.

B. Install two guide(s) on each side of pipe expansion fittings and loops. Install guides nearest to expansion joint not more than four pipe diameters from expansion joint.

C. Attach guides to pipe and secure guides to building structure.

D. Install anchors at locations to prevent stresses from exceeding those permitted by ASME B31.9 and to prevent transfer of loading and stresses to connected equipment.

E. Anchor Attachments:

1. Anchor Attachment to Black-Steel Pipe: Attach by welding. Comply with ASME B31.9 and ASME Boiler and Pressure Vessel Code: Section IX, "Welding and Brazing Qualifications."

2. Anchor Attachment to Galvanized-Steel Pipe: Attach with pipe hangers. Use MSS SP-69, Type 42, riser clamp welded to anchor.

3. Anchor Attachment to Copper Tubing: Attach with pipe hangers. Use MSS SP-69, Type 24, U-bolts bolted to anchor.

F. Fabricate and install steel anchors by welding steel shapes, plates, and bars. Comply with ASME B31.9 and AWS D1.1/D1.1M.

1. Anchor Attachment to Steel Structural Members: Attach by welding.

2. Anchor Attachment to Concrete Structural Members: Attach by fasteners. Follow fastener manufacturer's written instructions.

G. Use grout to form flat bearing surfaces for guides and anchors attached to concrete.

END OF SECTION 220516

JACKSON TOWNSHIP SLEEVES AND SLEEVE SEALS

FOR PLUMBING PIPING

220517-1

SECTION 220517 - SLEEVES AND SLEEVE SEALS FOR PLUMBING PIPING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Sleeves.

2. Stack-sleeve fittings.

3. Sleeve-seal systems.

4. Sleeve-seal fittings.

5. Grout.

6. Silicone sealants.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

PART 2 - PRODUCTS

2.1 SLEEVES

A. Cast-Iron Wall Pipes: Cast or fabricated of cast or ductile iron and equivalent to ductile-iron pressure pipe, with plain ends and integral waterstop unless otherwise indicated.

B. Galvanized-Steel Wall Pipes: ASTM A 53/A 53M, Schedule 40, with plain ends and welded steel collar; zinc coated.

C. Galvanized-Steel-Pipe Sleeves: ASTM A 53/A 53M, Type E, Grade B, Schedule 40, zinc coated, with plain ends.

D. PVC-Pipe Sleeves: ASTM D 1785, Schedule 40.

E. Galvanized-Steel-Sheet Sleeves: 0.0239-inch minimum thickness; round tube closed with welded longitudinal joint.

F. Molded-PE or -PP Sleeves: Removable, tapered-cup shaped, and smooth outer surface with nailing flange for attaching to wooden forms.

G. Molded-PVC Sleeves: With nailing flange for attaching to wooden forms.

220517-2

2.2 STACK-SLEEVE FITTINGS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Smith, Jay R. Mfg. Co.

2. Zurn Specification Drainage Operation; Zurn Plumbing Products Group.

B. Description: Manufactured, cast-iron sleeve with integral clamping flange. Include clamping ring, bolts, and nuts for membrane flashing.

1. Underdeck Clamp: Clamping ring with setscrews.

2.3 SLEEVE-SEAL SYSTEMS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Advance Products & Systems, Inc.

2. CALPICO, Inc.

3. Metraflex Company (The).

4. Pipeline Seal and Insulator, Inc.

5. Proco Products, Inc.

B. Description: Modular sealing-element unit, designed for field assembly, for filling annular space between piping and sleeve.

1. Sealing Elements: EPDM-rubber interlocking links shaped to fit surface of pipe. Include type and number required for pipe material and size of pipe.

2. Pressure Plates: Carbon steel.

3. Connecting Bolts and Nuts: Carbon steel, with corrosion-resistant coating, of length required to secure pressure plates to sealing elements.

2.4 SLEEVE-SEAL FITTINGS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Presealed Systems.

B. Description: Manufactured plastic, sleeve-type, waterstop assembly made for imbedding in concrete slab or wall. Unit has plastic or rubber waterstop collar with center opening to match piping OD.

2.5 GROUT

A. Standard: ASTM C 1107/C 1107M, Grade B, post-hardening and volume-adjusting, dry, hydraulic-cement grout.

B. Characteristics: Nonshrink; recommended for interior and exterior applications.

C. Design Mix: 5000-psi, 28-day compressive strength.

http://www.specagent.com/LookUp/?uid=123456816667&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456816669&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456801958&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456801959&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456801960&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456801961&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456801962&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456816672&mf=04&src=wd

220517-3

D. Packaging: Premixed and factory packaged.

2.6 SILICONE SEALANTS

A. Silicone, S, NS, 25, NT: Single-component, nonsag, plus 25 percent and minus 25 percent movement capability, nontraffic-use, neutral-curing silicone joint sealant, ASTM C920, Type S, Grade NS, Class 25, Use NT.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

a. Dow Corning Corporation.

b. GE Construction Sealants; Momentive Performance Materials Inc.

2. Sealant shall have a VOC content of 250 g/L or less.

3. Sealant shall comply with the testing and product requirements of the California

Department of Public Health's "Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."

B. Silicone, S, P, 25, T, NT: Single-component, pourable, plus 25 percent and minus 25 percent movement capability, traffic- and nontraffic-use, neutral-curing silicone joint sealant; ASTM C920, Type S, Grade P, Class 25, Uses T and NT. Grade P Pourable (self-leveling) formulation is for opening in floors and other horizontal surfaces that are not fire rated.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

a. May National Associates, Inc.; a subsidiary of Sika Corporation.

2. Sealant shall have a VOC content of 250 g/L or less.

3. Sealant shall comply with the testing and product requirements of the California

Department of Public Health's "Standard Method for the Testing and Evaluation of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."

C. Silicone Foam: Multicomponent, silicone-based liquid elastomers that, when mixed, expand and cure in place to produce a flexible, nonshrinking foam.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

a. Smooth-On.

2. Sealant shall have a VOC content of 250 g/L or less.

3. Sealant shall comply with the testing and product requirements of the California

Department of Public Health's "Standard Method for the Testing and Evaluation http://www.specagent.com/Lookup?ulid=13014 http://www.specagent.com/Lookup?uid=123457078120 http://www.specagent.com/Lookup?uid=123457078121 http://www.arcomnet.com/sustainable_design.aspx?topic=345 http://www.arcomnet.com/sustainable_design.aspx?topic=46 http://www.specagent.com/Lookup?ulid=13015 http://www.specagent.com/Lookup?uid=123457078126 http://www.arcomnet.com/sustainable_design.aspx?topic=345 http://www.arcomnet.com/sustainable_design.aspx?topic=46 http://www.specagent.com/Lookup?ulid=13013 http://www.specagent.com/Lookup?uid=123457078118 http://www.arcomnet.com/sustainable_design.aspx?topic=345 http://www.arcomnet.com/sustainable_design.aspx?topic=46

220517-4 of Volatile Organic Chemical Emissions from Indoor Sources Using Environmental Chambers."

PART 3 - EXECUTION

3.1 SLEEVE INSTALLATION

A. Install sleeves for piping passing through penetrations in floors, partitions, roofs, and walls.

B. For sleeves that will have sleeve-seal system installed, select sleeves of size large enough to provide 1-inch annular clear space between piping and concrete slabs and walls.

1. Sleeves are not required for core-drilled holes.

C. Install sleeves in concrete floors, concrete roof slabs, and concrete walls as new slabs and walls are constructed.

1. Permanent sleeves are not required for holes in slabs formed by molded-PE or -PP sleeves.

2. Cut sleeves to length for mounting flush with both surfaces.

a. Exception: Extend sleeves installed in floors of mechanical equipment areas or other wet areas 2 inches above finished floor level.

3. Using grout, seal the space outside of sleeves in slabs and walls without sleeve-seal system.

D. Install sleeves for pipes passing through interior partitions.

1. Cut sleeves to length for mounting flush with both surfaces.

2. Install sleeves that are large enough to provide 1/4-inch annular clear space between sleeve and pipe or pipe insulation.

3. Seal annular space between sleeve and piping or piping insulation; use joint sealants appropriate for size, depth, and location of joint. Comply with requirements for sealants specified in Section 079200 "Joint Sealants."

E. Fire-Barrier Penetrations: Maintain indicated fire rating of walls, partitions, ceilings, and floors at pipe penetrations. Seal pipe penetrations with firestop materials. Comply with requirements for firestopping specified in Section 078413 "Penetration Firestopping."

3.2 STACK-SLEEVE-FITTING INSTALLATION

A. Install stack-sleeve fittings in new slabs as slabs are constructed.

1. Install fittings that are large enough to provide 1/4-inch annular clear space between sleeve and pipe or pipe insulation.

2. Secure flashing between clamping flanges for pipes penetrating floors with membrane waterproofing. Comply with requirements for flashing specified in Section 076200 "Sheet Metal Flashing and Trim."

3. Install section of cast-iron soil pipe to extend sleeve to 2 inches above finished floor level.

4. Extend cast-iron sleeve fittings below floor slab as required to secure clamping ring if ring is specified.

220517-5

5. Using grout, seal the space around outside of stack-sleeve fittings.

B. Fire-Barrier Penetrations: Maintain indicated fire rating of floors at pipe penetrations. Seal pipe penetrations with firestop materials. Comply with requirements for firestopping specified in Section 078413 "Penetration Firestopping."

3.3 SLEEVE-SEAL-SYSTEM INSTALLATION

A. Install sleeve-seal systems in sleeves in exterior concrete walls and slabs-on-grade at service piping entries into building.

B. Select type, size, and number of sealing elements required for piping material and size and for sleeve ID or hole size. Position piping in center of sleeve. Center piping in penetration, assemble sleeve-seal system components, and install in annular space between piping and sleeve. Tighten bolts against pressure plates that cause sealing elements to expand and make a watertight seal.

3.4 SLEEVE-SEAL-FITTING INSTALLATION

A. Install sleeve-seal fittings in new walls and slabs as they are constructed.

B. Assemble fitting components of length to be flush with both surfaces of concrete slabs and walls. Position waterstop flange to be centered in concrete slab or wall.

C. Secure nailing flanges to concrete forms.

D. Using grout, seal the space around outside of sleeve-seal fittings.

3.5 SLEEVE AND SLEEVE-SEAL SCHEDULE

A. Use sleeves and sleeve seals for the following piping-penetration applications:

1. Exterior Concrete Walls above Grade:

a. Piping Smaller Than NPS 6: Cast-iron pipe sleeves.

b. Piping NPS 6 and Larger: Cast-iron pipe sleeves.

2. Exterior Concrete Walls below Grade:

a. Piping Smaller Than NPS 6: Cast-iron pipe sleeve with sleeve-seal system.

1) Select sleeve size to allow for 1-inch annular clear space between piping and sleeve for installing sleeve-seal system.

b. Piping NPS 6 and Larger: Cast-iron pipe sleeve with sleeve-seal system.

1) Select sleeve size to allow for 1-inch annular clear space between piping and sleeve for installing sleeve-seal system.

3. Concrete Slabs-on-Grade:

a. Piping Smaller Than NPS 6: Cast-iron pipe sleeve with sleeve-seal system.

220517-6

1) Exception: Not required for fixture piping through slab. EX: Water closet flange, floor drain, etc.

2) Select sleeve size to allow for 1-inch annular clear space between piping and sleeve for installing sleeve-seal system.

b. Piping NPS 6 and Larger: Cast-iron pipe sleeve with sleeve-seal system.

4. Concrete Slabs above Grade:

a. Piping Smaller Than NPS 6: Galvanized-steel-pipe sleeves.

b. Piping NPS 6 and Larger: Galvanized-steel-pipe sleeves,

5. Interior Partitions:

a. Piping Smaller Than NPS 6: Galvanized-steel-pipe sleeves.

b. Piping NPS 6 and Larger: Galvanized-steel-sheet sleeves.

END OF SECTION 220517

JACKSON TOWNSHIP ESCUTCHEONS FOR

PLUMBING PIPING

213216-1

SECTION 220518 - ESCUTCHEONS FOR PLUMBING PIPING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Escutcheons.

2. Floor plates.

1.3 DEFINITIONS

A. Existing Piping to Remain: Existing piping that is not to be removed and that is not otherwise indicated to be removed and salvaged, or removed and reinstalled.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

1. BrassCraft Manufacturing Co.; a Masco company.

2. Keeney Manufacturing Company.

3. Oatey Plumbing Products.

4. PASCO Specialty & Mfg., Inc.

5. ProFlo; a Ferguson Enterprises, Inc. brand.

2.2 ESCUTCHEONS

A. One-Piece, Steel Type: With polished, chrome-plated finish and setscrew fastener.

B. One-Piece, Cast-Brass Type: With polished, chrome-plated finish and setscrew fastener.

C. One-Piece, Deep-Pattern Type: Deep-drawn, box-shaped brass with chrome-plated finish and spring-clip fasteners.

http://www.specagent.com/Lookup?ulid=13050 http://www.specagent.com/Lookup?uid=123457079850 http://www.specagent.com/Lookup?uid=123457079851

213216-2

D. One-Piece, Stamped-Steel Type: With chrome-plated finish and spring-clip fasteners.

E. Split-Plate, Stamped-Steel Type: With polished, chrome-plated finish; concealed and exposed-rivet hinge; and spring-clip fasteners.

2.3 FLOOR PLATES

A. One-piece Floor Plates: Cast brass with polished chrome-plated finish.

B. Split Floor Plates: Cast brass with polished chrome-plated finish and concealed hinge.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install escutcheons for piping penetrations of walls, ceilings, and finished floors.

B. Install escutcheons with ID to closely fit around pipe, tube, and insulation of insulated piping and with OD that completely covers opening.

1. Escutcheons for New Piping:

a. Piping with Fitting or Sleeve Protruding from Wall: One-piece, deep-pattern type.

b. Chrome-Plated Piping: One-piece, cast-brass type with polished, chrome-plated finish.

c. Insulated Piping: One-piece, stamped-steel type with polished chrome-plated finish.

d. Bare Piping at Wall and Floor Penetrations in Finished Spaces: One-piece, cast-brass type with polished, chrome-plated finish.

e. Bare Piping at Wall and Floor Penetrations in Finished Spaces: One-piece, stamped-steel type, with polished chrome-plated finish.

f. Bare Piping at Ceiling Penetrations in Finished Spaces: One-piece, cast-brass type with polished, chrome-plated finish.

g. Bare Piping at Ceiling Penetrations in Finished Spaces: One-piece, stamped-steel type, with polished chrome-plated finish.

h. Bare Piping in Unfinished Service Spaces: One-piece, cast-brass type with polished, chrome-plated finish.

i. Bare Piping in Unfinished Service Spaces: One-piece, stamped-steel type with polished chrome-plated finish.

j. Bare Piping in Equipment Rooms: One-piece, cast-brass type with polished chrome-plated finish.

k. Bare Piping in Equipment Rooms: One-piece, stamped-steel type with polished chrome-plated finish.

2. Escutcheons for Existing Piping to Remain:

a. Chrome-Plated Piping: Split-casting, stamped steel with concealed or exposed-rivet hinge with polished, chrome-plated finish.

b. Insulated Piping: Split-plate, stamped steel with concealed or exposed-rivet hinge with polished, chrome-plated finish

213216-3

c. Bare Piping at Wall and Floor Penetrations in Finished Spaces: Split-plate, stamped steel with concealed or exposed-rivet hinge with polished, chrome-plated finish.

d. Bare Piping at Ceiling Penetrations in Finished Spaces: Split-plate, stamped steel with concealed or exposed-rivet hinge with polished, chrome-plated finish.

e. Bare Piping in Unfinished Service Spaces: Split-plate, stamped steel with concealed or exposed-rivet hinge with polished, chrome-plated finish.

f. Bare Piping in Equipment Rooms: Split-plate, stamped steel with concealed or exposed-rivet hinge with polished, chrome-plated finish.

C. Install floor plates for piping penetrations of equipment-room floors.

D. Install floor plates with ID to closely fit around pipe, tube, and insulation of piping and with OD that completely covers opening.

1. New Piping: One-piece, floor-plate type.

2. Existing Piping: Split floor-plate type.

3.2 FIELD QUALITY CONTROL

A. Replace broken and damaged escutcheons and floor plates using new materials.

END OF SECTION 220518

JACKSON TOWNSHIP METERS AND GAGES

220519-1

SECTION 220519 - METERS AND GAGES FOR PLUMBING PIPING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Bimetallic-actuated thermometers.

2. Filled-system thermometers.

3. Liquid-in-glass thermometers.

4. Thermowells.

5. Dial-type pressure gages.

6. Gage attachments.

7. Test plugs.

8. Test-plug kits.

B. Related Sections:

1. Section 221119 "Domestic Water Piping Specialties" for water meters.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

1.4 INFORMATIONAL SUBMITTALS

A. Product Certificates: For each type of meter and gage, from manufacturer.

1.5 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For meters and gages to include in operation and maintenance manuals.

PART 2 - PRODUCTS

2.1 LIQUID-IN-GLASS THERMOMETERS

A. Metal-Case, Industrial Style, Liquid-in-Glass Thermometers:

220519-2

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

a. Weiss Instruments, Inc.

b. Weksler Glass Thermometer Corp.

c. WIKA Instrument Corporation.

2. Standard: ASME B40.200.

3. Case: Cast aluminum; 6-inch nominal size.

4. Case Form: Back angle unless otherwise indicated.

5. Tube: Glass with magnifying lens and blue organic liquid.

6. Tube Background: Nonreflective aluminum with permanently etched scale markings graduated in deg F and deg C.

7. Window: Glass or plastic.

8. Stem: Aluminum or brass and of length to suit installation.

a. Design for Thermowell Installation: Bare stem.

9. Connector: 3/4 inch, with ASME B1.1 screw threads.

10. Accuracy: Plus or minus 1 percent of scale range or one scale division, to a maximum of

1.5 percent of scale range.

2.2 THERMOWELLS

A. Thermowells:

1. Standard: ASME B40.200.

2. Description: Pressure-tight, socket-type fitting made for insertion into piping tee fitting.

3. Material for Use with Copper Tubing: CNR or CUNI.

4. Material for Use with Steel Piping: CRES.

5. Type: Stepped shank unless straight or tapered shank is indicated.

6. External Threads: NPS 1/2, NPS 3/4, or NPS 1, ASME B1.20.1 pipe threads.

7. Internal Threads: 1/2, 3/4, and 1 inch, with ASME B1.1 screw threads.

8. Bore: Diameter required to match thermometer bulb or stem.

9. Insertion Length: Length required to match thermometer bulb or stem.

10. Lagging Extension: Include on thermowells for insulated piping and tubing.

11. Bushings: For converting size of thermowell's internal screw thread to size of thermometer connection.

B. Heat-Transfer Medium: Mixture of graphite and glycerin.

2.3 PRESSURE GAGES

A. Direct-Mounted, Metal-Case, Dial-Type Pressure Gages:

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. AMETEK, Inc.; U.S. Gauge.

b. Ashcroft Inc.

c. Trerice, H. O. Co.

d. Weksler Glass Thermometer Corp.

http://www.specagent.com/Lookup?ulid=1691 http://www.specagent.com/Lookup?uid=123457058306 http://www.specagent.com/Lookup?uid=123457058311 http://www.specagent.com/Lookup?uid=123457058307 http://www.specagent.com/LookUp/?uid=123456821069&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456808067&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456808076&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456821070&mf=04&src=wd

220519-3

2. Standard: ASME B40.100.

3. Case: Sealed Solid-front, pressure relief type(s); cast aluminum or drawn steel; 4-1/2-inch nominal diameter.

4. Pressure-Element Assembly: Bourdon tube unless otherwise indicated.

5. Pressure Connection: Brass, with NPS 1/2, ASME B1.20.1 pipe threads and bottom-outlet type unless back-outlet type is indicated.

6. Movement: Mechanical, with link to pressure element and connection to pointer.

7. Dial: Nonreflective aluminum with permanently etched scale markings graduated in psi.

8. Pointer: Dark-colored metal.

9. Window: Glass.

10. Ring: Metal.

11. Accuracy: Grade A, plus or minus 1 percent of middle half of scale range.

2.4 GAGE ATTACHMENTS

A. Snubbers: ASME B40.100, brass; with NPS 1/2, ASME B1.20.1 pipe threads and porous-metal-type surge-dampening device. Include extension for use on insulated piping.

B. Valves: Brass or stainless-steel needle, with NPS 1/2, ASME B1.20.1 pipe threads.

2.5 TEST PLUGS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Peterson Equipment Co., Inc.

2. Trerice, H. O. Co.

3. Weksler Glass Thermometer Corp.

B. Description: Test-station fitting made for insertion into piping tee fitting.

C. Body: Brass or stainless steel with core inserts and gasketed and threaded cap. Include extended stem on units to be installed in insulated piping.

D. Thread Size: NPS 1/2, ASME B1.20.1 pipe thread.

E. Minimum Pressure and Temperature Rating: 500 psig at 200 deg F.

F. Core Inserts: Chlorosulfonated polyethylene synthetic and EPDM self-sealing rubber.

2.6 TEST-PLUG KITS

A. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. Peterson Equipment Co., Inc.

2. Trerice, H. O. Co.

3. Weiss Instruments, Inc.

B. Furnish one test-plug kit(s) containing one thermometer(s), one pressure gage and adapter, and carrying case. Thermometer sensing elements, pressure gage, and adapter probes shall be of diameter to fit test plugs and of length to project into piping.

http://www.specagent.com/LookUp/?uid=123456808118&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456808120&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456808121&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456808125&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456808127&mf=04&src=wd http://www.specagent.com/LookUp/?uid=123456808128&mf=04&src=wd

220519-4

C. Low-Range Thermometer: Small, bimetallic insertion type with 1- to 2-inch- diameter dial and tapered-end sensing element. Dial range shall be at least 25 to 125 deg F.

D. High-Range Thermometer: Small, bimetallic insertion type with 1- to 2-inch- diameter dial and tapered-end sensing element. Dial range shall be at least 0 to 220 deg F.

E. Pressure Gage: Small, Bourdon-tube insertion type with 2- to 3-inch- diameter dial and probe.

Dial range shall be at least 0 to 200 psig.

F. Carrying Case: Metal or plastic, with formed instrument padding.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Install thermowells with socket extending to center of pipe and in vertical position in piping tees.

B. Install thermowells of sizes required to match thermometer connectors. Include bushings if required to match sizes.

C. Install thermowells with extension on insulated piping.

D. Fill thermowells with heat-transfer medium.

E. Install direct-mounted thermometers in thermowells and adjust vertical and tilted positions.

F. Install remote-mounted thermometer bulbs in thermowells and install cases on panels; connect cases with tubing and support tubing to prevent kinks. Use minimum tubing length.

G. Install direct-mounted pressure gages in piping tees with pressure gage located on pipe at the most readable position.

H. Install remote-mounted pressure gages on panel.

I. Install valve and snubber in piping for each pressure gage for fluids.

J. Install test plugs in piping tees.

K. Install thermometers in the following locations:

1. Inlet and outlet of each water heater.

2. At outlet of each master thermostatic mixing valve.

L. Install pressure gages in the following locations:

1. Building water service entrance into building.

2. Suction and discharge of each domestic water pump.

3.2 CONNECTIONS

A. Install meters and…