ATTACHMENT A – CLARIFICATIONS TO ALL POTENTIAL OFFERORS
| Index |
| Section |
| Question |
| Answer |
| 1 |
| G-4, Contract Administration Data, 1852.245-71, INSTALLATION – ACCOUNTABLE GOVERNMENT PROPERTY (c) (2) Office Furniture |
| Request the Government add “to include standing desks” |
| No. The successful Offeror may provide standing desks at their own expense. |
| 2 |
| J-1-3 PWS, Para 3.2.4, Organizational Conflict of Interest (OCI) Plan |
| If you do not have a Federal Government contract at this time, do you still need to submit an Organizational Conflicts of Interest document? |
| Yes. An Organizational Conflict of Interest (OCI) Plan shall be submitted in accordance with DRD 1656MA-002. The Plan describes the Offeror’s approach to identifying, resolving, and reporting both potential OCIs during proposal submission and future OCIs that may occur following the award of this contract. |
| 3 |
| J-1 PWS, Para 4.1.23 |
| The following requirement needs clarification: |
4.1.23 Manage all program and project data documentation and ensure IT Security requirements are in place.
We interpret the scope as
4.1.23 Manage all program and project data documentation within the NASA provided data system and ensure IT Security requirements, existing policies and procedures, are in place and being followed.
The interpretation is correct. However, further clarification via revision to the referenced PWS section is not required.
| 4 |
| J-1-14, PWS, MSFC-4 |
| MSFC-4 includes a requirement for one (1) Project Coordinator. The place of performance states it is both on-site at MSFC and on-site at NASA HQ. Please clarify the correct place of performance. |
| Attachment J-1A, Mission Labor Requirements, indicates the provision of 1 WYE to support MSFC-4. The individual will be at NASA HQ full-time and travel to MSFC as required. The language in MSFC-4 is updated in this amendment to clarify place of performance. |
| 5 |
| J-1A, Mission Labor Requirements, 1 – 10 |
L-2-1 Attachment J-1A, Attachment L-1
| There appears to be a disconnect regarding the number of Project Coordinator 4 WYEs for MSFC in Option Period 7 in Attachment J-1A (12.9 WYE) and Attachment L-1 (11.9 WYE). Will the Government please confirm the correct total number of Project Coordinator 4 WYEs for MSFC for Option Period 7? |
| Total WYEs confirmed and corrections to Attachment L-1are included in this amendment to reflect the total WYEs in Attachment J-1A. |
| 6 |
| J-3, Labor Category Descriptions |
| Several incumbents do not meet the education requirements in this section and therefore would not be able to transition to the new contract. Can years of experience be substituted for a degree to ensure 100% incumbent transition? If so, how many years of experience may be substituted for AA, AS, BA, and BS degrees? |
| The education and experience levels delineated in Attachment J-3, Labor Category Descriptions, are "desired" provided that the employee is fully capable of performing the tasks described in the "Job Description" column. |
| 7 |
| J-3, Labor Category Descriptions |
| Can advanced degrees substitute for some years of experience? For example, if a requirement states 10 years of experience and a BS degree, can a MS degree only require 6 years of experience and a PhD only require 4 years of experience? |
| The education and experience levels delineated in Attachment J-3, Labor Category Descriptions, are "desired" provided that the employee is fully capable of performing the tasks described in the "Job Description" column. |
| 8 |
| J-8-6, PRS, Definitions Table |
| The definitions for Excellent and Very Good are the same with the only differentiator being “few” vs. “some”. Given that there is a performance-based price deduction for failure to achieve an excellent customer rating, will the government please provide more quantitative differentiators in the definitions? |
| The definitions provided are leveraged from those definitions utilized to evaluate contractor performance in the Contractor Performance Assesment Reporting System (CPARS). |
| 9 |
| L-10, 1852.215-81 PROPOSAL PAGE LIMITATIONS (c) |
Attachment A—Clarifications to All Potential Offerors, question #14
| Paragraph (c) states that there are “No” exceptions to the 12-point font size rule for graphics and pictures. Does this also extend to headers and footers? These do not contain proposal content but do affect margins. We would like to use company logos as well. We respectfully ask the Government to please reconsider making an exception for these. |
| In accordance with paragraph (b) (4) of 1852.215-81, each volume page shall identify the Offeror’s name, solicitiation number, and date. In place of the company name, the offeror’s company logo may be inserted in a format other than Times New Roman 12-point font within the header/footer only if the logo does not impact the margin restrictions cited in paragraph (b) of 1852.215-81. |
| 10 |
| L-10, 1852.215-81, PROPOSAL PAGE LIMITATIONS, (F) |
| We just noticed the requirement for graphics and tables to be 12pt. We request the Government modify this requirement to 10pt as making graphics and tables with type that large is challenging and would result in considerably large graphics and wasted space between sections where a graphic that large wouldn't fit on the remaining page before or after narrative. |
| In accordance with paragraph (b) (6) (F) of 1852.215-81, font shall not be smaller than 12 point font to include text, charts, tables, figures, pictures, and other objects. Landscape format may be utilized to accommodate this restriction considering the limitations described in paragraph (b) (6) (C). |
| 11 |
| L-10, 1852.215-81 PROPOSAL PAGE LIMITATIONS, (c) |
Attachment A—Clarifications to All Potential Offerors, question # 14
SUBFACTOR 2-Technical Approach (TA), subparagraph (d)
| The Attachment A answer to question 14 seems inconsistent with the referenced Section L paragraph (c). Please clarify if we are correct in our understanding that the paragraph (c) directs bidders to identify any exclusions, including Tables of Contents, title pages, and the requirement for a detailed compliance matrix. |
| The purpose of paragraph (c) of 1852.215-81 is for the Government to identify exclusions from the page counts established for the page limited volumes. The Government has identified two exclusions to the Mission Suitability page limitation to include Attachment L-5, Personnel and Fringe Benefit Forms and copies of salary surveys, which are reflected in this amendment. |
1852.215-81, PROPOSAL PAGE LIMITATIONS,
(b)(1)
| Please confirm that no hard-copy submission is required and that all submitted material shall be electronic. |
| Confirmed. No hard-copy submissions will be accepted. In accordance with 1852.215-81, Proposal Page Limitations, paragraph (b) (1) Offerors shall “Submit two identical electronic copies of the proposal on Universal Serial Bus (USB) drives.” |
| 13 |
| L-15, 52.215-92, PROPOSAL MARKING AND DELIVERY |
| In what format should the past performance volume, draft OCI plan, etc. be submitted? Hardcopy or USB? |
| In accordance with 1852.215-81, Proposal Page Limitations, paragraph (b) (1) Offerors shall “Submit two identical electronic copies of the proposal on Universal Serial Bus (USB) drives.” |
| 14 |
| L-13, MSFC 52.209-93, NOTICE OF POTENTIAL ORGANIZATIONAL CONFLICTS OF INTEREST |
| Can a subcontractor supporting the Prime CPSS Contract holder be subject to organizational confilicts of interest, conflicting them out of priming work within MSFC or any other part of NASA? |
| Yes. In accordance with MSFC 52.209-93, paragraphs (b) and (c), the Government has identified potential types of conflicts of interest that may arise as a result of proposal submission or as a result of contract award. These potential OCIs may occur for both the Offeror and its subcontractor(s) relative to its proposal and any current and future contracts held by the Offeror and its subcontractor(s) within the Agency. |
It is the Offeror’s responsibility to assess whether an OCI is associated with its proposal and propose resolutions that may include limitations on the future contracting abilities of the Offeror and/or its subcontractors, if necessary.
| 15 |
| L-13, MSFC 52.209-93, NOTICE OF POTENTIAL ORGANIZATIONAL CONFLICTS OF INTEREST |
| Can supporting the CPSS work as a subcontractor create an OCI for priming develompent and/or IT enginieering work? |
| Yes. In accordance with MSFC 52.209-93, paragraphs (b) and (c), the Government has identified potential types of conflicts of interest that may arise as a result of proposal submission or as a result of contract award. These potential OCIs may occur for both the Offeror and its subcontractor(s) relative to its proposal and any current and future contracts held by the Offeror and its subcontractor(s) within the Agency. |
It is the Offeror’s responsibility to assess whether an OCI is associated with its proposal and propose resolutions.
| 16 |
| L-15, MSFC 52.215-91, DUE DATE FOR RECEIPT OF PROPOSALS OR QUOTATIONS PARAGRAPH (a), Due Date |
| With the release of the Final RFP on September 17 rather than the expected date of September 12, and the new proposal delivery date of October 18 rather than the previous October 24, bidders have lost 10 days of proposal development schedule time, including two weekends, which are critical. Bidders carefully schedule and allocate costly resources based on schedules, and this loss of time has a tremendous impact. We respectfully ask that the Government please return to the DRFP due date of October 24th to allow the highest quality proposals from all bidders. |
| The proposal submission deadline is based on FAR 5.203 which requires at least a 45-day response time for receipt of proposals from the date of publication of the notice which was posted on August 29, 2019. |
| 17 |
| L-19, MA-3, (2) and MA-3, (3) (i) |
MA-3, (3) (iv)
| The nature and size of salary survey information and reports, particularly salary survey results for all locations identified in the EPM, will likely exceed the page limitation of the volume. Will they government remove these reports from the volume’s page count or clarify the level of salary survey information to be included in Section MA-3? |
| The salary surveys have been excluded from the Mission Suitability Volume page limitation as part of this amendment. |
| 18 |
| L-19 and L-21 |
| MA-3, section (3), page L-19 deletes reference to “major” subcontractors and therefore establishes a requirement for all subcontractors to provide a TCP. Later, on page L-21, Section (3) (v), the language retains the reference to “major” subcontractors. Are all subcontractors required to submit the referenced Personnel and Fringe Benefit Forms? |
| Yes. All subcontractors will be required to submit Total Compension Plans, to include Attachment L-5, Personnel and Fringe Benefit Forms. The solicitiation is revised to remove reference to “major” subcontractor. |
| 19 |
| L-19 through L-21 Volume I-Mission Suitability/Subfactor 1-MA-3 (3), |
| Total Compensation Plan. The page limit for Volume I is 55 pages. On page L-19, instructions clearly state “…offerors shall submit a single integrated Mission Suitability volume within the established page limitation.” Using the available page count to provide the detail requested in the Total Compensation Plan (TCP) for both offerors and all subcontractors with information such as the labor category listings and the methodology and rationale for establishing proposed base labor rates for each labor category will severely limit our ability to be completely responsive to the other requirements of the Mission Suitability Volume. |
Additionally, FAR 52.222-46 Evaluation of the Compensation of Professional Employees, provides specific requirements for addressing your TCP, further limiting the offerors capability to reduce page count. A compliant response could include 8-10 pages for each offeror and subcontractor(s).
NASA has set precedent on the GSFC PAAC V RFP and excluded the TCP from the page limitations.
Will NASA consider excluding the TCP from the Volume I page limits so we can adequately address the TCP, MA and TA requirements?
The Government has identified two exclusions related to the Total Compensation Plan within the Mission Suitability page limitation to include Attachment L-5, Personnel and Fringe Benefit Forms and copies of the salary surveys. These exclusions will be reflected as part of this amendment. In addition the Mission Suitability page limitation has increased from 55 to 60 pages.
L-20 and L-21 MA-3 (3) (v)
| Total Compensation Plan and Attachment L-5; There is an inconsistency in the final RFP between Total Compensation Plan and L-5 instructions. The final RFP requirement is for the prime and all subcontractors to submit a Total Compensation Plan. The requirement for the L-5 Personnel and Fringe Benefits attachment is still only required for the prime and major subcontractors. We request that the government change the L-5 requirement to be consistent with the TCP requirement and apply to all subcontractors, not just major subcontractors. |
| All subcontractors will be required to submit Total Compension Plans, to include Attachment L-5, Personnel and Fringe Benefit Forms. The solicitiation is revised to remove reference to “major” subcontractor. |
| 21 |
| L-20, MA-3 (3) (iv) |
| Providing copies of this information (copies of all information utilized from salary surveys and other sources) would require 2 pages per labor category for 11 locations. This totals 88 pages for 4 labor categories at minimum. Given the significant amount of information associated with the requirement would the government allow this requirement/information to be provided outside of page count? |
| The Government has identified two exclusions related to the Total Compensation Plan within the Mission Suitability page limitation to include Attachment L-5, Personnel and Fringe Benefit Forms and copies of salary surveys. These exclusions will be reflected as part of this amendment. In addition the Mission Suitability page limitation is increased from 55 to 60 pages. |
L-10, 1852.215-81, PROPOSAL PAGE LIMITATIONS (b)(6)(F)
| The requirement is to include copies of all information utilized from salary surveys and all other sources in this section. These copies are in native format and do not allow for conversion to stated font guidelines. Can the copies of this information from salary surveys and other sources be submitted in native format? |
| The Government has identified two exclusions related to the Total Compensation Plan within the Mission Suitability page limitation to include Attachment L-5, Personnel and Fringe Benefit Forms and copies of salary surveys. These exclusions will be reflected as part of this amendment. In addition the page count has increased from 55 to 60 pages. 1852.215-81 is amended to allow salary surveys be submitted in their native format. |
| 23 |
| L-20, MA-3 (3) (iv) (C)-(F) |
| Our response to the information requested for C-E in the most concise manner possible is 10 pages, at a minimum. In addition, the information requested for F in the most concise manner possible is 10 pages, at a minimum. This represents a minimum of 20 pages of the total 55 MS page count. Can the information requested for C-F be included with L-5 and therefore out of page count? |
| This amendment removes (F) as the information is included in Attachment L-5, Personnel and Fringe Benefit Forms. Items (C) (D) and (E) are included in the page count in MA-3. Mission Suitability page count is increased from 55 to 60 pages. |
| 24 |
| L-20. MA-3 (3) (v) |
| The forms shall be included in this volume after the last numbered page (i.e., page 55). |
| The forms shall be included in this volume after the last numbered page (i.e., page 60). |
Volume I, Subfactor 2 – Technical Approach, Paragraph (d)
| “The offeror shall also provide, at the beginning of this volume, a detailed compliance matrix that cross-references the offeror’s numbering structure and corresponding volume page number with all requirements associated with each subfactor in paragraph (c) above.” Is this detailed compliance matrix included in the Volume I 55-page limit? |
| Yes. The compliance matrix is included in the page limitation. |
| 26 |
| L-21, Volume II – Price Factor Instructions |
| Can the IDIQ rates be discounted, if needed, at the task order level? |
| In accordance with Volume II- Price Factor Instructions, paragraph (b), Offerors shall utilize the values resulting from the EPM tool to populate the contract volume, including J-4, Indefinite-Delivery, Indefinite-Quantity Rates. |
| 27 |
| L-22, Volume II – Price Factor Instructions, paragraph (c), subparagraph (4) |
Section 1 – Pricing Information (Narrative)
| Please provide guidance on how bidders are to reconcile the referenced (c) (4) requirement to provide detailed pricing and substantiation data with the Section 1 instructions that do not provide a place for that detailed information. |
| Offerors are to provide all required price information within the Offeror’s Volume II-Price. Within this volume, Sections 1 and 2 shall be utilized to provide the narrative information required by these parts. Section 3 will be the Offeror’s Excel Pricing Model provided in the Excel format of the solicitiation. |
| 28 |
| L-23; Volume II Price Factor Instructions – |
Section 3 Excel Pricing Model (EPM) Price Forms
Attachment L-1; Excel Pricing Model Due to the Fixed Price nature of the proposed cost please provide applicable Service Contract Act, Wage Determination, or Collective Bargaining Agreement information that applies to the labor categories provided in the EPM.
Please confirm that no SCA, WD, or CBA requirements apply.
Confirmed. Neither Service Contract Labor Standards nor collective bargaining agreements apply to this acquisition. Therefore, no wage determination applies.
| 29 |
| L-30, Volume IV – Contract Instructions, Offeror Fill-ins Table, SF33 and SF1449 forms |
| We respectfully request NASA provide partially populated and editable SF33 and SF1449 forms. |
| Editable SF33 and SF 1449 are provided with this amendment. |
| 30 |
| L-1-1, EPM |
| Information in Attachment J-1A, pages 1-10, option year 7 totals 73.9 WYE. Information in the L-1 Excel spreadsheet, Tab A-1, Option Year 7, calls for 72.9 WYE. Please clarify the correct total. |
| Total WYEs confirmed and corrections to Attachment L-1 is included in this amendment to reflect the total WYEs in Attachment J-1A. |
| 31 |
| L-1-1, EPM, Tabs A-2 |
| May we change the formulas in rows 70 and 71 of Tab A-2 to exclude rows 8 and 9 values? |
| No, the formulas shall not be changed. Tab A-2 will be completed by the Prime and each subcontractor for the work assigned to them. Rows 8 and 9 are pre-filled from Tabs B-1 and B-2. When completed, the individual subcontractor will provide the WYEs to the prime to compute the total proposed WYEs. The prime EPM Tab A-2 will include WYEs in rows 70 and 71 that match the total WYEs stated in Attachment J-1A. |
| 32 |
| L-5-1, Personnel and Fringe Benefit Forms, Health Insurance |
| We have more than one health insurance plan employees can choose from, but the L-5 worksheet only allows for one Health Insurance plan. How should we present the different options we offer to employees? |
| A note has been included within this amendment to allow for additional rows to be inserted as necessary. |
| 33 |
| NAICS code |
| The scope of this work is to provide Support Services and not Research and Development. Our conclusion is that NAICS code 541715 does not accurately fit this contract. Will the government consider changing the NAICS code to 541611, which far more accurately describes the work that is expected on this contract? |
| The NAICS code is consistent with market research conducted and Attachment J-1, Performance Work Statement, which supports research and development efforts across multiple programs and projects. |
| 34 |
| Purchase Order |
| Does the 30 days for the Phase–in time include weekend days? If so, please consider changing the Phase-in time from 30 days to 45 days. Most of the work to recruit, interview, select, hire, perform background checks, drug testing and training must be done during the week. If the 30 days include the weekend, the amount of time is actually 20 days (minus the 8 weekend days). To be successful, I think 45 days is more reasonable and realistic if the weekend days are included. |
| Yes. The phase-in purchase order is revised within this amendment from 30 to 45 calendar days. |
| 35 |
| Automated Task Order Management System User Guide and Task Order Routing Process |
| Both documents (the Automated Task Order Management System User Guide and Task Order Routing Process) describe the routing process for task order requests, task plan requests, and task plans. The terms used to describe each step in the processes is not consistent between documents. For example, the Task Order Routing Process includes a swim lane for the role of “CTOPM”. This term is not used in the RFP nor the ATOMS user guide. Will the Government please clarify the various roles involved in the Task Order Routing Process and ensure consistency with the terms used in the ATOMS User Guide? |
| Processes and terms associated with the Automated Task Order Management System will be further defined during contract phase-in. |
| 36 |
| B-3, L-2 and Q&A #34 |
| Will the Government please clarify if the terms “Task Order Management System (TOMS)” and “Automated Task Order Management System (ATOMS)” are interchangeable? |
| Yes. The terms “Task Order Management System (TOMS)” and “Automated Task Order Management System (ATOMS)” are interchangeable. The “ATOMS” acronym will be used henceforth as reflected in this amendment. |
ATTACHMENT B – SUMMARY OF CHANGES
This attachment delineates changes made to the final solicitation, which was posted to FedBizOpps on Septmebr 17, 2019. The changes are a result of comments and questions received from industry and internal reviews. These changes represent all significant changes, but are not intended to be all-inclusive. Grammatical, typographical, and other non-substantive changes have been corrected throughout the RFP.
| 1 |
| A-4, Table of Contents |
| 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2011) |
| 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (DEVIATION 19-02) |
| 2 |
| A-4, Table of Contents |
| 52.219-14 LIMITATIONS ON SUBCONTRACTING (JAN 2017) |
| 52.219-14 LIMITATIONS ON SUBCONTRACTING (DEVIATION 19-02) |
| 3 |
| A-4, Table of Contents |
| 52.222-17 NONDISPLACEMENT OF QUALIFIED WORKERS (MAY 2014) |
| Clause removed |
| 4 |
| A-4, Table of Contents |
| 52.219-30 NOTICE OF SET-ASIDE FOR, OR SOLE SOURCE AWARD TO, WOMEN-OWNED SMALL BUSINESS CONCERNS ELIGIBLE UNDER THE WOMEN-OWNED SMALL BUSINESS PROGRAM (DEC 2015) |
| 52.219-30 NOTICE OF SET-ASIDE FOR, OR SOLE SOURCE AWARD TO, WOMEN-OWNED SMALL BUSINESS CONCERNS ELIGIBLE UNDER THE WOMEN-OWNED SMALL BUSINESS PROGRAM (DEVIATION 19-02) |
| 5 |
| A-6, Table of Contents |
| 1852.215-84, OMBUDSMAN (NOV 2011) ALTERNATE I (JUN 2000) |
| Clause removed |
| 6 |
| A-8, Table of Contents |
| MSFC 52.215-91 DUE DATE FOR RECEIPT OF PROPOSALS OR QUOTATIONS (NOV 2018) |
| MSFC 52.215-91 DUE DATE FOR RECEIPT OF PROPOSALS OR QUOTATIONS (SEPT 2019) |
| 7 |
| I-2, Contract Clauses |
| 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (NOV 2011) |
| 52.219-6 NOTICE OF TOTAL SMALL BUSINESS SET-ASIDE (DEVIATION 19-02) |
| 8 |
| I-2, Contract Clauses |
| 52.219-14 LIMITATIONS ON SUBCONTRACTING (JAN 2017) |
| 52.219-14 LIMITATIONS ON SUBCONTRACTING (DEVIATION 19-02) |
| 9 |
| I-2, Contract Clauses |
| 52.222-17 NONDISPLACEMENT OF QUALIFIED WORKERS (MAY 2014) |
| Clause removed |
| 10 |
| I-2, Contract Clauses |
| 52.219-30 NOTICE OF SET-ASIDE FOR, OR SOLE SOURCE AWARD TO, WOMEN-OWNED SMALL BUSINESS CONCERNS ELIGIBLE UNDER THE WOMEN-OWNED SMALL BUSINESS PROGRAM (DEC 2015) |
| 52.219-30 NOTICE OF SET-ASIDE FOR, OR SOLE SOURCE AWARD TO, WOMEN-OWNED SMALL BUSINESS CONCERNS ELIGIBLE UNDER THE WOMEN-OWNED SMALL BUSINESS PROGRAM (DEVIATION 19-02) |
| 11 |
| I-5, Contract Clauses |
| 1852.215-84, OBUDSMAN (NOV 2011) ALTERNATE I (JUN 2000) |
| Clause removed |
| 12 |
| I-16 1852.216-80 TASK ORDERING PROCEDUR E (OCT 1996) ALTERNATE II (APR 2018) |
| (c) Within 10 calendar days after receipt of the Contracting Officer’s request, the Contractor shall submit a task plan conforming to the request. |
| (c) Within 7 calendar days after receipt of the Contracting Officer’s request, the Contractor shall submit a task plan conforming to the request. |
| 13 |
| J-1-1, PWS 1.0 Introduction |
| N/A |
| The following personnel are authorized to issue orders under this contract who are employed at the Center designated: |
Contracting Officer, HQ Contracting Officer, MSFC Contracting Officer, TBD
| 14 |
| J-1-3, PWS 3.1.3 |
| 3.1.3 Utilize the Government-provided Task Order Management System for responding to task order requests in accordance with NFS 1852.216-80, Task Ordering Procedure-Alternate II. |
| 3.1.3 Utilize the Government-provided Automated Task Order Management System (ATOMS) for responding to task order requests in accordance with NFS 1852.216-80, Task Ordering Procedure-Alternate II. |
| 15 |
| J-1-5, PWS 4.0 Technical Requirements |
| In addition to the Mission Service requirements, IDIQ requirements may be performed under this PWS Section via task orders. Task orders will be initiated, implemented, and administered in a Government-provided Task Order Management System. The following personnel are authorized to issue orders under this contract. All designated personnel are employed by NASA MSFC unless otherwise indicated: |
Contracting Officer, MSFC Contracting Officer, TBD In addition to the Mission Service requirements, IDIQ requirements may be performed under this PWS Section via task orders. Task orders will be initiated, implemented, and administered in a Government-provided ATOMS.
| 16 |
| J-1-10, PWS 5.0 Other Direct Cost (ODC) Requirements |
| Other Direct Cost (ODC) requirements will be ordered through the Government-provided Task Order Management System as IDIQ services. |
| Other Direct Cost (ODC) requirements will be ordered through the Government-provided ATOMS as IDIQ services. |
| 17 |
| J-1-14, MSFC-4 |
| MSFC-4 Requirement Description |
….For the SLS Program Level 1 Office, the Contractor shall provide support both at MSFC and NASA HQ. Support will primarily be performed at NASA HQ…..
MSFC-4 Place of Performance
This requirement provides support for the SLS Program Office located at MSFC. Support for this requirement is on-site at MSFC, Redstone Arsenal, Huntsville, AL and on-site at NASA HQ, Washington, D.C.
MSFC-4 Requirement Description
….For the SLS Program Level 1 Office, the Contractor shall provide support at NASA HQ.
MSFC-4 Place of Performance
This requirement provides support for the SLS Program Office and ESD cross-Program Office located at NASA HQ. Support for this requirement is on-site at NASA HQ, Washington, D.C.
| 18 |
| J-2-20, DRD Re-Procurement Data Package |
Replaced in its entirety
| 19 |
| J-2-23, DRD Progress Report |
Replace in its entirety
| 20 |
| J-7-1, Government-Furnished Computer Software |
| N/A |
| The following list of Commercial-Off-The-Shelf (COTS) and Government-Off-The-Shelf (GOTS) software will be provided for performance of this contract when applicable. This listing does not include standard software loaded by NASA onto Agency desktop computer seats on-site at NASA Centers, including Component Facilities and Technical & Service Support Centers. |
Replaced in its entirety.
| 22 |
| L-8, 1852.215-81 PROPOSAL PAGE LIMITATIONS (APR 2015) |
| Volume I - Mission Suitability, Page Limit, 55 pages |
| Volume I - Mission Suitability, Page Limit, 60 pages |
| 23 |
| L-8, 1852.215-81 PROPOSAL PAGE LIMITATIONS (APR 2015) |
| Each Attachment L-5, Personnel and Fringe Benefit Forms does not count against this volume’s page limitation. |
| Attachment L-5, Personnel and Fringe Benefit Forms and copies of applicable salary surveys, do not count against this volume’s page limitation. |
| 24 |
| L-9, 1852.215-81 PROPOSAL PAGE LIMITATIONS (APR 2015) |
| (b)(2)...Supplemental documentation provided as part of the non-page limited Cost/Price volume (e.g., financial statements, indirect rate letters, audit reports, letters of credit, disclosure statements, pre-award accounting system SF 1408’s) may be provided in their native format (e.g., Adobe, .pdf). Offerors shall not embed sound or video files into the proposal volumes. |
| (b)(2)....Supplemental documentation provided as part of the non-page limited Cost/Price volume (e.g., financial statements, indirect rate letters, audit reports, letters of credit, disclosure statements, pre-award accounting system SF 1408’s) or supporting data related to the Offeror’s TCP (e.g., applicable salary survey) may be provided in their native format (e.g., Adobe, .pdf). Offerors shall not embed sound or video files into the proposal volumes. |
| 25 |
| L-10, 1852.215-81 PROPOSAL PAGE LIMITATIONS (APR 2015) |
| (c) Identify any exclusions to the page limits that are excluded from the page counts specified in paragraph (a) of this provision (e.g. title pages, table of contents) as follows: Attachment L-3, Past Performance Questionnaire, is excluded from the Past Performance volume page limitation. Attachment L-5, Personnel and Fringe Benefit Forms, is excluded from the Mission Suitability volume page limitation. |
| (c) Identify any exclusions to the page limits that are excluded from the page counts specified in paragraph (a) of this provision (e.g. title pages, table of contents) as follows: Attachment L-3, Past Performance Questionnaire, is excluded from the Past Performance volume page limitation. Attachment L-5, Personnel and Fringe Benefit Forms, and copies of applicable salary surveys, are excluded from the Mission Suitability volume page limitation. |
| 26 |
| L-15, MSFC 52.215-91 DUE DATE FOR RECEIPT OF PROPOSALS OR QUOTATIONS (NOV 2018) |
| MSFC 52.215-91 DUE DATE FOR RECEIPT OF PROPOSALS OR QUOTATIONS (NOV 2018) |
| MSFC 52.215-91 DUE DATE FOR RECEIPT OF PROPOSALS OR QUOTATIONS (SEPT 2019) |
| 27 |
| L-15, MSFC 52.215-91 DUE DATE FOR RECEIPT OF PROPOSALS OR QUOTATIONS (NOV 2018) |
| (b) The delivery of the Past Performance volume, Draft Organizational Conflict of Interest (OCI) Plan, and a list of all current NASA contracts and subcontracts, including contract information for the Contracting Officer or COR is requested prior to the specified due date for receipt of proposals. However, early submission is neither required nor a pre-requisite for proposal submission, provided that all volumes are submitted on or before the specified due date and time. |
| (b) If indicated above, the delivery of the Past Performance volume, Draft Organizational Conflict of Interest (OCI) Plan, and a list of all current NASA contracts and subcontracts, including contract information for the Contracting Officer or COR is requested prior to the specified due date and time for receipt of proposals or quotations. However, early submission is neither required nor a pre-requisite for proposal or quotation submission, provided that all volumes are submitted prior to the date and time specified above. |
| 28 |
| L-17, Subfactor 1 - Management Approach |
| (3) Teaming and subcontracting arrangements to include rationale for each of the arrangements, assignment of work, lines of authority, integration of team members or subcontractors into the management and supervisory hierarchy, how management and control policies will be implemented, limitations or exclusions of work by subcontractors, and how work will be performed, controlled, reported, and reviewed. Include potential delegations of authority to site-specific (Center) organizations, as well as organizational and geographical placement of authority to include potential IDIQ requirements across the Agency. |
| (3) Teaming and subcontracting arrangements to include rationale for each of the arrangements, assignment of work by company (to be provided in the Performance Work Statement (PWS) Mission Services WYE Assignment Matrix provided below) to account for all WYEs required by Attachment J-1A, Mission Labor Requirements, lines of authority, integration of team members or subcontractors into the management and supervisory hierarchy, how management and control policies will be implemented, limitations or exclusions of work by subcontractors, and how work will be performed, controlled, reported, and reviewed. Include potential delegations of authority to site-specific (Center) organizations, as well as organizational and geographical placement of authority to include potential IDIQ requirements across the Agency. |
| 29 |
| L-20, (MA-3) Staffing Approach |
| (iv) Methodology and rationale used for establishment of all proposed base labor rate ranges for each labor category as applicable, including consideration of the various differences in skills, education, experience, complexity of various disciplines, and job difficulty as well as the features of the compensation plan designed to enable the offeror to attract and retain qualified employees. Offerors shall also include copies of all information utilized from salary surveys and other sources in order to allow for a complete understanding of, and to establish traceability to, the proposed labor rate ranges. Additionally, offerors shall provide: |
| (iv) Methodology and rationale used for establishment of all proposed base labor rate ranges for each labor category as applicable, including consideration of the various differences in skills, education, experience, complexity of various disciplines, and job difficulty as well as the features of the compensation plan designed to enable the offeror to attract and retain qualified employees. Additionally, offerors shall provide: |
| 30 |
| L-20, (MA-3) Staffing Approach (3) (iv) |
| (F) Hourly base labor rate ranges for each labor category, for each location, for each year, regardless of whether the location will be supported as part of Mission Services or indefinite-delivery, indefinite-quantity (IDIQ) effort. |
| Deleted and renumber of paragraphs in this section. |
| 31 |
| L-21, (MA-3) Staffing Approach (3) (v) |
| Attachment L-5, Personnel and Fringe Benefit Forms for the offeror and all subcontractors, by location (if different), by year, which quantify the offeror’s and major subcontractors personnel policies and fringe benefits, consistent with the Total Compensation Plan...... |
| Attachment L-5, Personnel and Fringe Benefit Forms for the offeror and all subcontractors, by location (if different), by year, which quantify the offeror’s and subcontractors personnel policies and fringe benefits, consistent with the Total Compensation Plan..... |
| 32 |
| L-21, (MA-3) Staffing Approach |
| The forms shall be included in this volume after the last numbered page (i.e., page 50). |
| The forms shall be included in this volume after the last numbered page (i.e., page 60). |
| 33 |
| L-21, (MA-3) Staffing Approach |
| n/a |
| (vi) Offerors shall also include copies of all information utilized from salary surveys and other sources in order to allow for a complete understanding of, and to establish traceability to, the proposed labor rate ranges. The forms shall be included in this volume after the last numbered page (i.e., page 60). |
| 34 |
| L-22, Volume II - Price Factor Instructions (c) (7) |
| (7) In accordance with FAR 16.301-3, Limitations, an offeror’s and applicable subcontractor’s accounting system shall be determined adequate for identifying and segregating costs prior to award of a contract with cost reimbursable elements (training/travel line items). The Price volume shall be prepared in a manner consistent with each company’s current approved accounting system. Offerors and applicable subcontractors shall provide the audit report number and date of approval for their accounting system. If a company’s accounting system has not been approved, state “currently no approved accounting system” and prepare and submit a completed SF1408, Pre-award Survey of Prospective Contractor Accounting System (complete Section II only) as part of this volume. Price volume(s) shall be prepared with sufficient detail to allow direct and indirect rate verification and audit of selected costs by the cognizant audit office. |
| Deleted and renumber of paragraphs in this section. |
Excel Pricing Model
MSFC-5
Option 7 Project Coordinator 4: 3 WYEs
MSFC-5
Option 7 Project Coordinator 4: 4 WYEs
Updated the EPM to reflect the number of WYEs in Attachment J-1A.
| 36 |
| L-2-1, Projected Task Order Requirements |
| The task order requirements below are anticipated to be awarded after the effective date of the contract via the Government-provided Task Order Management System (TOMS). |
| The task order requirements below are anticipated to be awarded after the effective date of the contract via the Government-provided Automated Task Order Management System (ATOMS). |
| 37 |
| L-5-1, Personnel and Fringe Benefit Forms |
| N/A |
| Note: Additional rows may be inserted as necessary. |
| 38 |
| PO-10, MSFC 52.211-94 PERIOD OF PERFORMANCE (MAY 2017) |
| The period of performance for this contract is from 11/01/2020 through 11/30/2020. |
| The period of performance for this contract is from 10/15/2020 through 11/30/2020. |
| 39 |
| PO-14, Purchase Order |
| The Contractor shall perform phase-in activities for a period not to exceed 30 days necessary to assume full responsibility |
| The Contractor shall perform phase-in activities for a period not to exceed 45 days necessary to assume full responsibility |
| 40 |
| PO-15, Purchase Order |
| N/A |
| 9. The Government-provided Automated Task Order Management System (ATOMS) will be available and fully operational during the forty-five (45) day phase-in period. The Contractor shall work closely with the Government to ensure that all task orders are processed such that each can be issued and effective on the first day of the CPSS PC contract period of performance. |
10. The Contractor shall provide a list of users that require access to the ATOMS within the first ten (10) business days of the phase-in period. The Government will provide Contractor user accounts and mandatory training to the Contractor users within the first thirty (30) days of the phase-in period. During the phase-in period, the Contractor shall provide any task order plans in response to task order requests in accordance with NFS 1852.216-80, Task Ordering Procedure-Alternate I, or NFS 1852.216-80 Task Ordering Procedure-Alternate II, of the CPSS PC contract. It is anticipated that any task orders initiated and awarded during the phase-in period will begin on or after the effective date of the CPSS PC contract period of performance.