Amendment 2 QAs.pdf

PDF 138 KB Posted

Attached to
INFLATABLE AERODYNAMIC DECELERATORS Final RFP Federal contract opportunity
Solicitation number
80LARC22R0016
Issued by
National Aeronautics and Space Administration Langley Research Center

About this file

This document contains questions and answers regarding a final request for proposal for inflatable aerodynamic decelerators. The solicitation seeks proposals for the research and development of inflatable heat shields and aeroshell technologies to enable future planetary science missions. Key details include that cost forms will be amended to separately account for travel and materials indirect cost rates. Subcontractors are only required to submit their cost volumes and narratives to the government. Significant subcontractors performing 25% or more of any technical performance area must be identified along with the hours allocated to their work. The solicitation involves work at the National Aeronautics and Space Administration Langley Research Center but does not specify proposal due or award dates.

View the file

Other files for this federal contract opportunity

Other files attached to INFLATABLE AERODYNAMIC DECELERATORS Final RFP, newest first.
File Type Posted
IAD_Source Selection Decision_FINAL_v2_19OCT22.pdf PDF
IAD_Source Selection Decision_FINAL.9.19.2022.pdf PDF
Amendment 4 SF30 9 Mar 22.pdf PDF
Att L1 - Cost form-IAD-Amendment 4.xlsx XLSX spreadsheet
Amendment 4 QAs.pdf PDF
IAD FINAL RFP PPTO_Amended 8 MAR22.pdf PDF
Amendment 3 SF30 8 Mar 22.pdf PDF
Amendment 3 QAs.pdf PDF
Amendment 2 SF30 1 Mar 22.pdf PDF
IAD FINAL RFP PPTO_Amended 1MAR22.pdf PDF
Att L1 - Cost form-IAD-Amendment 2.xlsx XLSX spreadsheet
Direct Labor Classification_IAD IDIQ 22Feb22.pdf PDF
Amendment 1 SF30-16c-2.pdf PDF
Copy of Att L1 - Cost form-IAD-Amended 22Feb22.xlsx XLSX spreadsheet
Final RFP QAs 22 Feb 2022.pdf PDF
IAD FINAL RFP PPTO_Amended22Feb2022.pdf PDF
IAD Pre Proposal_Conf_Presentation Feb 10 2022.pdf PDF
Bidders Library.zip ZIP file
L-5 Sample Past Performance Consent Letter.pdf PDF
L-4 IAD Direct Labor Classification_Descriptions.pdf PDF
IAD Exhibit B Final 31Jan22.pdf PDF
L-6 Small Business Subcontracting Plan Instructions.pdf PDF
L-3 SF1408.pdf PDF
L1 - Cost form-IAD Final.xlsx XLSX spreadsheet
SOW for IAD IDIQ Final 31Jan22.pdf PDF
IAD FINAL RFP PPTO_31Jan22.pdf PDF
L-2 Black Out Notice for IAD_Signed.pdf PDF
IAD_Final Request for Proposal (RFP) Cover Letter_signed.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

As of March 1, 2022

Amendment 2 Final RFP Questions (Solicitation 80LARC22R0016)

Q1. The model contract has a table that you want us to complete by CLIN (See below).

Apparently, you want us to provide numbers for CPPF Task Orders and numbers for FFP task orders. How are we supposed to do that? The Cost forms that you provided to develop a Ceiling price and use an average of the fee for CPFF task orders and FFP task orders based upon the numbers we plug in on your Cost Form 2a worksheet for fee/profit. They also use the hours that you provided, and you only provided hours for the Base 5-year period, not for the options; Form 1, only shows the base 5-year period (See below) and there are no hours or ODC dollars identified for the Option years. Are you suggesting that we need to complete two sets of cost forms for each Track? Your forms use an average of the Fee/Profit proposed to develop the Ceiling price. To get the numbers for the CLIN structure you are asking for we would have to do 2 sets of cost forms, one assuming all CPFF task orders and one assuming all FFP task orders. What is the ceiling price of the contract based on? Is it your Cost form A as shown below with our rates for the base 5-year period only using the total hours and ODC that you provided and an average fee? Is it the sum of this form completed for CPFF task orders only, plus the sum of this form completed for FFP task orders only? Is it the sum of either of these plus the options?

Response: Section B.4 of the RFP will be amended to reflect TBDs for this table. The table will be populated by the CS/CO before award. The maximum ceilings (per track) have been added for edification.

Q2. Attachment L-1 Form 1: The ODC Plug Number corresponds with the one field for ODC indirect burden percentage. However, the offeror’s burdens for materials vs travel, for example, are different.

Could you provide a breakdown of the anticipated ODCs (i.e., 40% of plug is travel, 60% is materials) so the offeror could split the “plug number” proportionately and burden properly.

Response: Cost forms will be amended accordingly. New columns have been added to accommodate travel and materials separately.

Q3. Attachment L-1 Form 2: This form requests COMPOSITE burden rates, but also notes that it “shall be submitted by each significant subcontractor”. Should the subcontractors still be required to submit this form if they are not providing any composite rates?

As of March 1, 2022

Response: If subcontractors are not providing rates (e.g., subcontractor for material) the answer is no.

If the subcontractor is submitting labor rates, the answer is yes.

Q4. Attachment L-1 Form 4a: Should the subcontractor rates that go into Column J of this form be the subcontractor rates with or without Offeror burdens?

Response: The rates in Column J on Form 4 are without offeror burdens. These rates flow to Form 3 column C through L, as appropriate. Offeror burdens are applied on form 3 in columns N through W.

Q5. RFP Section L.16(d): It is our understanding that the subcontractors shall only be required to submit their unsanitized excel workbook and supporting cost Narrative to the government, which would constitute Volume III of the submission. This question is to confirm that there is no need for Subcontractors to submit Volume I, II or IV separately (their contributions to those sections will be included in the Prime’s submission of Volumes I, II, and IV).

Response: This is correct. Volume III only shall be submitted by subcontractors.

Q6. Past Performance: Per the solicitation, Significant Subcontractors are required to perform “25% or more of any one of the technical performance areas listed in L.17(b)”. How do we demonstrate that those thresholds have been met?

Response: The cost forms would indicate this. When allocating the composite weight to subcontractors, ensure that significant subcontractors receive adequate weight so that the hours of performance in the Proposed Effort reflect 25% or more of the work when calculated by taking the composite percentages times the hours (% x hours). We also bring to your attention the requirement to complete the table in L.18(d)(15) regarding significant contractors.