Electrical_Construction_Services_BPA_Questions1.docx.pdf
PDF 117 KB Posted
- Attached to
- Multiple Award Construction Blanket Purchase Agreement for Electrical Disciplines Federal contract opportunity
- Solicitation number
- 80KSC018Q0028
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Master_BPA_Rev_1.pdf | ||
| Amendment_00002.pdf | ||
| Sept_6th_BPA_sign_in_sheet.pdf | ||
| Appendix_32.JPG | JPG image | |
| Electrical_Construction_Services_BPA_Questions.pdf | ||
| Tab_40_-_Amend_SF30-_Nov16.pdf | ||
| Appendix_12_Rev.pdf | ||
| SIMPLEX_JOFOC_2018.pdf | ||
| Master_BPA_Agreement_Rev.pdf | ||
| Attachments.pdf | ||
| Appendices.pdf | ||
| 80KSC018Q0028.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Control Number 99079
1.) The documents that were received today do not show the fire alarm layout and what is to be removed and or replaced. Where can I find this information? I would need panel layout, new components proposed, room layout showing locations and quantity, what is to be removed and what is staying.
Answer: The fire alarm SOWs provide the information requested. Please refer to the set of attachments at the end of each BPA.
Project Control Number 99217
2.) The documents that were received today for the maintenance building do not show any details about a solar power installation. Where can I find this information? I would need panel layout and location, brands we can install, overall power requirements, battery backup system or microswitch type installation only, panels modified in electrical room, location for new equipment.
Answer: NASA provided the drawings associated with the facility where the proposed system will be installed. The
SOW states any proposed system can utilize K6-1446K standing seam metal roof (attachment up to the contractor as long as proposed meets all current wind load requirement for KSC coastline) and placement of the inverter(s) can be located within the existing electrical room. NASA is leaving all details (other than FSEC certification) up to the contractor to utilize the existing infrastructure to provide NASA with a robust American made (Buy American Act compliant) 75kW grid-tie system. Any proposed system shall be connected to a panel within the facility electrical room and output through the existing facility meter.
General Master BPA Questions
3.) Is it necessary to send OF Form 336 for bid submission….or is Appendix 4 sufficient? Reference Section 17 of
SF1442.
Answer: Yes, it is required to fill out and submit OF Form 336 and Appendix 4 with your bid submission.
4.) Is it necessary to submit safety past performance volume? Not included on the contractor submittal requirement handout. Reference BPA Agreement Section 9.2.
Answer: Yes, IAW with Section 9.2 of the Master BPA Agreement shall be included in your offer submission.
Project Control Number 99708 Remove UPS
5.) Is EMT an acceptable raceway? Reference Statement of Work.
Answer: EMT is permitted in the administrative areas of the LCC, at diameters permitted by the National Electric
Code.
Project Control Number 99711 Lighting at VAB
6.) Is EMT an acceptable raceway? Reference Statement of Work.
Answer: Rigid Conduit only in the VAB. Rigid conduit shall be ¾” or greater diameter. EMT is not permitted in the VAB.