This is a Business Case Analysis Template for the Commercial Low Earth Orbit (LEO) Destination System (CLDS) contract opportunity, designed to collect financial projections and cost estimates from offerors for the period of Calendar Year 2027 through 2042. The template is comprised of multiple worksheets that require offerors to provide detailed yearly revenue, cost, and basis of estimate (BOE) information in millions of dollars, escalated to then-year dollars.

The template includes four primary cost line items (CLINs): CLIN 1 covers Design and Development costs; CLIN 2 addresses Design, Flight Unit Build/Test, Certification, and Transportation Delta Certification costs, with provisions for up to five separate hardware elements; and CLIN 3 encompasses End-to-End Mission Operations Services including sustaining engineering, mission operations, crew and cargo transportation, and on-orbit activities. Offerors must project revenues from multiple sources including NASA development and certification contributions, loans, investments, corporate contributions, and utilization fees from NASA, sovereign governments, and commercial customers across transportation and habitation services. The Cost Summary BOE worksheet requires itemization by proposed labor (fully burdened), subcontractors (fully burdened), non-labor resources (material, equipment, other direct costs, travel), and indirect costs. The ProForma Cash Flow worksheet automatically pulls cost data and requires narrative explanations for each revenue stream. The Cost BOE Breakdown worksheet mandates detailed basis of estimate documentation referencing specific proposal sections for each cost category, including vendor quotes, historical cost examples, or engineering judgments. Additionally, the Corporate Contribution worksheet requires offerors to identify prior contractor investments and coincident contractor investments, government resources, and calculate the overall corporate contribution percentage relative to total effort through CLIN 2. Key assumptions include NASA purchasing Early Services missions in the first year available (no more than two) and Standard Services missions at a rate of two 6-month missions per year with two NASA crew members per mission beginning the first year of availability.

View the file

Other files for this federal contract opportunity

Other files attached to Commercial Low Earth Orbit (LEO) Destination Contract (CLDC) Request for Proposal, newest first.
File Type Posted
80JSC027R0004 Cover Letter Enclosure 2 Attachment J-01_CLDC Final SOW_redlined.pdf PDF
80JSC027R0004 Attachment J-01_CLDC Final SOW.pdf PDF
80JSC027R0004 Attachment L-09 CLIN 1 Model Task Order.pdf PDF
00_Final Request for Proposal (RFP) Cover Letter.pdf PDF
80JSC027R0004 Cover Letter Enclosure 2 Final RFP redline.pdf PDF
80JSC027R0004 Final RFP.pdf PDF
80JSC027R0004 Attachment J-02_CLDC Final RFP DRD.pdf PDF
80JSC027R0004 CLDC-012 Attachment CPIC DRD Template for IT Portfolio PPM Data Collection.xlsx XLSX spreadsheet
80JSC027R0004 CLDC-013 Attachment CITAR Report Template.xlsx XLSX spreadsheet
80JSC027R0004 CLDC-212 Attachment Crew Provisions.xlsx XLSX spreadsheet
80JSC027R0004 Attachment L-01 Price Template.xlsx XLSX spreadsheet
80JSC027R0004 Attachment L-04 Contractor Responsibility Matrix.xlsx XLSX spreadsheet
CLDC Attachment J-18 DD 254.pdf PDF
80JSC027R0004 CLDC-014 Attachment NASA C-SCRM Plan Questionnaire.xlsx XLSX spreadsheet
80JSC027R0004 Attachment L-02 Past Performance Matrix.xlsx XLSX spreadsheet
00_Cover Letter Enclosure 1 - Summary of Changes Final.pdf PDF
80JSC027R0004 Cover Letter Enclosure 2 Attachment J-02_CLDC Final RFP DRD_redlined.pdf PDF
80JSC027R0004 Cover Letter Enclosure 4 CLDC RFP Feedback Template.xlsx XLSX spreadsheet
Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Overview_Instructions

Attachment L-07: Business Case Analysis Template
Business Case Analysis Template
Commercial LEO Destination System (CLDS)
Revenue, Cost and Commercial Segment Project Financing Instructions
Overview
- The purpose of this workbook is to collect projected yearly revenue, cost and basis of estimate information for the CLDS from CY 2027 through CY 2042
- This workbook has separate worksheets for Cost Summary BOE, ProForma Cash Flow, Cost BOE Breakdown and Corporate Contribution
- The Business and Technical Approaches should all correlate with one another. The types of Revenue and Cost Projections included in the offeror's workbook should be reflected in their Commercialization, Financial and Technical Approach sections of other documents.
- Below are instructions covering each of these worksheets
Cost Summary BOE Instructions
- CLIN 1: Cost of Design and Development: Provide the costs associated with Design and Development effort for the period of performance.
- CLIN 2: Cost of Design, Flight Unit Build/Test, Certification, Transportation Delta Certification: Provide the costs associated with production, integration and test of the flight element(s), including any loose outfitting hardware such as cables or crew provisions launched separately (if applicable); Provide cost associated with each element including launch vehicle transportation for each element.
- CLIN 3: Operations Costs: This includes but is not limited to sustaining engineering, Mission Ops (both ground segment, vehicle processing and on-orbit activities). Also, provide the costs associated with each revenue stream. Include the crew and cargo transportation to and from orbit. Please enter costs into the years that costs are incurred for these services. The CLIN 3 Operations costs is for End-to-End Services which can incorporate GFTSS as the transportation methodology in the End-to-End pricing. If the Offeror proposes multiple mission types to be available the Offeror should trace the costs to their IMS.

ASSUMPTIONS:

-CLIN 3 shall assume NASA will buy Early Services if offered (Mission A or B) the first year they are available (but no more than 2 early A or B missions) -CLIN 3 shall assume NASA will buy a Standard Services Mission the first year it is available and continue at a rate of 2, 6-month missions per year, with 2 NASA crew on each Mission.

ProForma Cash Flow - Revenue & Narrative Cost Projections Worksheet Instructions
General Assumptions
- Revenues and costs are to be entered in then year dollars (escalated)
- Revenues and costs are to be entered in millions of dollars
- Cost information will be automatically pulled from the Cost Summary BOE worksheet
- OFI refers to cells for user inputs (Offeror Furnished Information)
- Include a narrative explanation for each revenue source
ProForma Cash Flow Instructions
- Provide funding and primary revenue streams by product/service as prescribed in the Cash Flow worksheet. If there are other categories than the ones listed, there is an Other section with OFI for inclusion.
Proposal Reference or Rationale Instructions (Cost BOE Breakdown worksheet)
- Using the data submitted in the Cost Summary BOE and ProForma Cash Flow tabs, provide a high level basis of estimate. Include vendor quote, historical cost example, in-house estimate or engineering judgement referencing specific Business and Technical Approach descriptions on how each revenue stream or cost category was developed. For example, "Module of similar design and systems previously built in house, estimate based on historical in-house costs, commercialization features based on vendors A and B quotes. Module in-house development and design described in section X and commercialization features described in section Y."
Corporate Contribution Worksheet
- Offeror shall fill in the grey cells

Cost Summary BOE

CLDS Cost Summary BOE
Provider:
Dollars In Millions
CLIN 1 INITIAL DEVELOPMENT
Elements Of CostCY27
CY28
CY29
CY30
CY31
CY32
CY33
CY34
CY35
CY36
CY37
CY38
CY39
CY40
CY41
CY42
Total
4/1/2027-12/31/20271/1/2028-12/31/20281/1/2029-12/31/20291/1/2030-12/31/20301/1/2031-12/31/20311/1/2032-12/31/20321/1/2033-12/31/20331/1/2034-12/31/20341/1/2035-12/31/20351/1/2036-12/31/20361/1/2037-12/31/20371/1/2038-12/31/20381/1/2039-12/31/20391/1/2040-12/31/20401/1/2041-12/31/20411/1/2042-3/31/2042
Proposed Labor Cost (fully burdened)
Total Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Subcontractors Cost (fully burdened)
Total Subcontractor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Non-Labor Resources (unburdened)
Material$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Equipment$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Other Direct Costs$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Travel$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Non-Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Indirect Cost (Non-Labor)
Total Indirect$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

Total 0% $ - 0 0% $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 $ - 0 Total price to contractor (not to NASA)

CLIN 2 CLDS DEVELOPMENT & CERTIFICATION
Element #1 (repeat if multiple elements)
Elements Of CostCY27
CY28
CY29
CY30
CY31
CY32
CY33
CY34
CY35
CY36
CY37
CY38
CY39
CY40
CY41
CY42
Total
4/1/2027-12/31/20271/1/2028-12/31/20281/1/2029-12/31/20291/1/2030-12/31/20301/1/2031-12/31/20311/1/2032-12/31/20321/1/2033-12/31/20331/1/2034-12/31/20341/1/2035-12/31/20351/1/2036-12/31/20361/1/2037-12/31/20371/1/2038-12/31/20381/1/2039-12/31/20391/1/2040-12/31/20401/1/2041-12/31/20411/1/2042-3/31/2042
Proposed Labor Cost (fully burdened)
Total Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Subcontractors Cost (fully burdened)
Transportation - Launch Vehicle$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Delta Certification - Crew/Cargo Vehicle$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Subcontractor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Non-Labor Resources (unburdened)
Material$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Equipment$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Other Direct Costs$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Travel$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Non-Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Indirect Cost (Non-Labor)
Total Indirect$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

Total 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 $ - 0

CLIN 2 CLDS DEVELOPMENT & CERTIFICATION
Element #2 (repeat if multiple elements)
Elements Of CostCY27
CY28
CY29
CY30
CY31
CY32
CY33
CY34
CY35
CY36
CY37
CY38
CY39
CY40
CY41
CY42
Total
4/1/2027-12/31/20271/1/2028-12/31/20281/1/2029-12/31/20291/1/2030-12/31/20301/1/2031-12/31/20311/1/2032-12/31/20321/1/2033-12/31/20331/1/2034-12/31/20341/1/2035-12/31/20351/1/2036-12/31/20361/1/2037-12/31/20371/1/2038-12/31/20381/1/2039-12/31/20391/1/2040-12/31/20401/1/2041-12/31/20411/1/2042-3/31/2042
Proposed Labor Cost (fully burdened)
Total Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Subcontractors Cost (fully burdened)
Transportation - Launch Vehicle$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Delta Certification - Crew/Cargo Vehicle$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Subcontractor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Non-Labor Resources (unburdened)
Material$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Equipment$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Other Direct Costs$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Travel$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Non-Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Indirect Cost (Non-Labor)
Total Indirect$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

Total 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 $ - 0

CLIN 2 CLDS DEVELOPMENT& CERTIFICATION
Element #3 (repeat if multiple elements)
Elements Of CostCY27
CY28
CY29
CY30
CY31
CY32
CY33
CY34
CY35
CY36
CY37
CY38
CY39
CY40
CY41
CY42
Total
4/1/2027-12/31/20271/1/2028-12/31/20281/1/2029-12/31/20291/1/2030-12/31/20301/1/2031-12/31/20311/1/2032-12/31/20321/1/2033-12/31/20331/1/2034-12/31/20341/1/2035-12/31/20351/1/2036-12/31/20361/1/2037-12/31/20371/1/2038-12/31/20381/1/2039-12/31/20391/1/2040-12/31/20401/1/2041-12/31/20411/1/2042-3/31/2042
Proposed Labor Cost (fully burdened)
Total Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Subcontractors Cost (fully burdened)
Transportation - Launch Vehicle$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Delta Certification - Crew/Cargo Vehicle$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Subcontractor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Non-Labor Resources (unburdened)
Material$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Equipment$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Other Direct Costs$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Travel$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Non-Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Indirect Cost (Non-Labor)
Total Indirect$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

Total 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 $ - 0

CLIN 2 CLDS DEVELOPMENT & CERTIFICATION
Element #4 (repeat if multiple elements)
Elements Of CostCY27
CY28
CY29
CY30
CY31
CY32
CY33
CY34
CY35
CY36
CY37
CY38
CY39
CY40
CY41
CY42
Total
4/1/2027-12/31/20271/1/2028-12/31/20281/1/2029-12/31/20291/1/2030-12/31/20301/1/2031-12/31/20311/1/2032-12/31/20321/1/2033-12/31/20331/1/2034-12/31/20341/1/2035-12/31/20351/1/2036-12/31/20361/1/2037-12/31/20371/1/2038-12/31/20381/1/2039-12/31/20391/1/2040-12/31/20401/1/2041-12/31/20411/1/2042-3/31/2042
Proposed Labor Cost (fully burdened)
Total Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Subcontractors Cost (fully burdened)
Transportation - Launch Vehicle$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Delta Certification - Crew/Cargo Vehicle$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Subcontractor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Non-Labor Resources (unburdened)
Material$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Equipment$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Other Direct Costs$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Travel$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Non-Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Indirect Cost (Non-Labor)
Total Indirect$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

Total 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 $ - 0

CLIN 2 CLDS DEVELOPMENT & CERTIFICATION
Element #5 (repeat if multiple elements)
Elements Of CostCY27
CY28
CY29
CY30
CY31
CY32
CY33
CY34
CY35
CY36
CY37
CY38
CY39
CY40
CY41
CY42
Total
4/1/2027-12/31/20271/1/2028-12/31/20281/1/2029-12/31/20291/1/2030-12/31/20301/1/2031-12/31/20311/1/2032-12/31/20321/1/2033-12/31/20331/1/2034-12/31/20341/1/2035-12/31/20351/1/2036-12/31/20361/1/2037-12/31/20371/1/2038-12/31/20381/1/2039-12/31/20391/1/2040-12/31/20401/1/2041-12/31/20411/1/2042-3/31/2042
Proposed Labor Cost (fully burdened)
Total Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Subcontractors Cost (fully burdened)
Transportation - Launch Vehicle$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Delta Certification - Crew/Cargo Vehicle$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Subcontractor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Non-Labor Resources (unburdened)
Material$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Equipment$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Other Direct Costs$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Travel$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Non-Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Indirect Cost (Non-Labor)
Total Indirect$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

Total 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 $ - 0

Total CLIN 2 (including multi-element)
Elements Of CostCY27
CY28
CY29
CY30
CY31
CY32
CY33
CY34
CY35
CY36
CY37
CY38
CY39
CY40
CY41
CY42
Total
4/1/2027-12/31/20271/1/2028-12/31/20281/1/2029-12/31/20291/1/2030-12/31/20301/1/2031-12/31/20311/1/2032-12/31/20321/1/2033-12/31/20331/1/2034-12/31/20341/1/2035-12/31/20351/1/2036-12/31/20361/1/2037-12/31/20371/1/2038-12/31/20381/1/2039-12/31/20391/1/2040-12/31/20401/1/2041-12/31/20411/1/2042-3/31/2042
Proposed Labor - Element 1$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Proposed Labor - Element 2$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Proposed Labor - Element 3$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Proposed Labor - Element 4$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Proposed Labor - Element 5$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Subcontractors Cost - Element 1$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Subcontractors Cost - Element 2$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Subcontractors Cost - Element 3$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Subcontractors Cost - Element 4$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Subcontractors Cost - Element 5$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Total Subcontractor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Non-Labor Resources - Element 1$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Non-Labor Resources - Element 2$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Non-Labor Resources - Element 3$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Non-Labor Resources - Element 4$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Non-Labor Resources - Element 5$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Total Non-Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Indirect Cost (Non-Labor) - Element 1$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Indirect Cost (Non-Labor) - Element 2$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Indirect Cost (Non-Labor) - Element 3$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Indirect Cost (Non-Labor) - Element 4$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Indirect Cost (Non-Labor) - Element 5$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ - 0
Total Indirect$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

Total 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 $ - 0

CLIN 3 MISSION SERVICES - End-to-End Services
Elements Of CostCY27
CY28
CY29
CY30
CY31
CY32
CY33
CY34
CY35
CY36
CY37
CY38
CY39
CY40
CY41
CY42
Total
4/1/2027-12/31/20271/1/2028-12/31/20281/1/2029-12/31/20291/1/2030-12/31/20301/1/2031-12/31/20311/1/2032-12/31/20321/1/2033-12/31/20331/1/2034-12/31/20341/1/2035-12/31/20351/1/2036-12/31/20361/1/2037-12/31/20371/1/2038-12/31/20381/1/2039-12/31/20391/1/2040-12/31/20401/1/2041-12/31/20411/1/2042-3/31/2042
Proposed Labor Cost (fully burdened)
Total Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Subcontractors Cost (fully burdened)
Transportation Crew$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Transportation Cargo$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Subcontractor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Non-Labor Resources (unburdened)
Material$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Equipment$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Other Direct Costs$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Travel$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Total Non-Labor$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0
Indirect Cost (Non-Labor)
Total Indirect$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0$ - 0

Total 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 0% $ - 0 $ - 0

ProForma Cash Flow

CLDS ProForma_Revenue and Cost Information
Provider:
Dollars In Millions

Pro Forma Operating Income/Loss Statement

Operating Revenue/Investments ($M)

Enterprise-Related Revenue CY27 CY28 CY29 CY30 CY31 CY32 CY33 CY34 CY35 CY36 CY37 CY38 CY39 CY40 CY41 CY42 Total Narrative Explanation (proposal pg # if applicable)

Non-Mission Specific Revenue00000000000000000
NASA Development & Certification ContributionOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0
LoansOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0To include financing details; identify each source and individual value
InvestmentOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0To include investment details; identify each source and individual value
Corporate ContributionOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0
Other (Include Description)OFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0Other sources; identify each source and individual value
Utilization00000000000000000
NASAOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0
Sovereign Govt.OFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0
Commercial SalesOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0
Seat Sales00000000000000000
NASA TransportationOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0
NASA HabitiationOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0
Sovereign Govt. TransportationOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0
Sovereign Govt. HabitationOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0
Commercial Sales TransportationOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0
Commercial Sales HabitationOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFIOFI0

Total Revenue 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Operating Cost ($M)

Enterprise Costs CY27 CY28 CY29 CY30 CY31 CY32 CY33 CY34 CY35 CY36 CY37 CY38 CY39 CY40 CY41 CY42 Total Proposal Pg. Reference

CLIN 1 - Total Line000
CLIN 2 - Total Line0000000000000000
CLIN 3 - Total Line0000000000000000
Yearly Total Costs00000000000000000
Cash Flow ($M)
YearCY27CY28CY29CY30CY31CY32CY33CY34CY35CY36CY37CY38CY39CY40CY41CY42TotalProposal Pg. Reference
Positive/Negative Cash Flow00000000000000000
Cumulative Positive/Negative Cash Flow00000000000000000

Cost BOE Breakdown

CLDS Cost BOE Breakdown
Provider:
Dollars In Millions

Cost BOE Breakdown

CLDS Non-Recurring Engineering (NRE) Cost$MBasis of Estimate for NRE Costs with page referance in proposal
This represents the total NRE for Element #1 by lowest reportable work element, including reimbursable NASA services
Element #1
Work Element 1 (I.e. Major components, program management, overhead, etc) - OFI
Work Element 2 - OFI
Work Element 3 - OFI
OFI
Element #2
Element #3
Element #4
OFI
Total Hardware Development Subtotal
Recurring Engineering (RE) Flight Unit Build/ Integrate / Test Cost$MBasis of Estimate for Recurring Cost with page referance in proposal
This represents the total RE for Element #1 by lowest reportable work element, including reimbursable NASA services
Element #1
Work Element 1 - OFI
Work Element 2 - OFI
Work Element 3 - OFI
OFI
Element #2
Element #3
Element #4
OFI
Spares (Only if pre-positioned or bulk buy)
Incremental Outfitting Hardware and Delivery (if applicable)
Build/Test
On-Orbit Integration
Total Flight Unit Build, Integration and Test Costs Subtotal
Operations Costs$MBasis of Estimate for Operations Costs with page referance in proposal
Define quantity and type of crew per year, length of crew stay, and quantity of consumables and experiments flown per year
Sustaining Engineering
Ground Segment
Mission Control/Operations
Mission Integration
Space/Space and Space/Ground Comm
IT, Security
Other (OFI)
Vehicle
On-orbit maintenance
Spares (not pre-positioned/purchased as bulk by with NRE)
Consumables
Other (OFI)
Cost of Utilization (Professional, NASA, Sovereign, Tourist)
Training/Integration
On-Orbit Accommodations
Consumables
Cargo Transportation Cost Upmass/Downmass
Other (OFI)
Cost of Crew Accommodations (Professional, NASA, Sovereign, Tourist)
Training/Integration
On-Orbit Accommodations
Consumables
Crew Transportation Seat Cost
Other (OFI)
Personnel (Wages/Labor)
Operations Cost Subtotal
Transportation Cost$MBasis of Estimate for Transportation Cost with page referance in proposal
Define number of flights per year, price per kg for cargo, price per seat for crew
Element Launch Cost
Additional Element Launch (OFI)
Vehicle Processing
Crew/Visitor Transportation Seat Cost
Cargo Resupply Transportation Cost
Transportation Subtotal
Other Costs$MBasis of Estimate for Other Costs with page referance in proposal
Provide details for each of these "other" costs
Project Financing Source 1
Principal
Interest
Insurance
Licensing
Programmatic Inteface Requirements for Accessing Contract Data
Other (OFI)
Other Costs Subtotal

Corporate Contribution

Attachment L-07: Commercial LEO Destination Contract
Corporate Contribution Worksheet
PROVIDER NAME:
PRIOR CONTRACTOR INVESTMENTS
Fair market value of un-reimbursed* use of equipment and facilities:$1.00
Cost (not including fee) of un-reimbursed* Direct Labor:$1.00
Un-reimbursed* Materials and Other Direct Costs (not including travel or fee):$1.00
Completed Internal Research and Development projects$1.00% Applicable:50%$0.50
SUBTOTAL$3.50
COINCIDENT CONTRACTOR INVESTMENT**
Fair market value of un-reimbursed* use of equipment and Facilities$1.00
Cost (not including fee) of un-reimbursed* Direct Labor$1.00
Un-reimbursed* Materials and Other Direct Costs (inc. Travel, not including fee)$1.00
SUBTOTAL$3.00
CALCULATED TOTAL ALLOWABLE CORPORATE CONTRIBUTION$6.00
GOVERNMENT RESOURCES** (GFP/GFE/Subject Matter Expertise)
Estimated value of federally funded participants and/or the non-reimbursable use of federal government facilities$1.00
REQUESTED PRICE TO GOVERNMENT** (SHOULD NOT INCLUDE COST OF REIMBURSABLE NASA RESOURCES OR FUTURE PURCHASED SERVICES)$1.00
CALCULATED OVERALL EFFORT**$8.00
CALCULATED CORPORATE CONTRIBUTION75.0%
*Un-reimbursed means not funded in any way by the U.S. Government. External State or private funding is acceptable.
**Through CLIN 2

File details come from the government source that posted it. Updated .