Exhibit 12 Draft MTN Proposal Mission Trajectory Instructions 4-8-26.pdf

PDF 80 KB Posted

Attached to
Draft RFP - Mars Telecommunications Network (MTN) Federal contract opportunity
Solicitation number
80GSFC26R0011
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

This is an exhibit from a Draft Request for Proposals (DRFP) that specifies the Mission Trajectory Data Package requirements for proposals submitted in response to DRFP No. 80GSFC26R0011.

The document outlines two primary categories of required proposal data. The Trajectory Information section mandates submission of launch vehicle specifications, launch date, C3 energy, and departure launch azimuth; final orbital characteristics at Mars; binary SPICE SPK files or equivalent data for the beginning, middle, and end of the launch window; solar conjunction and eclipse duration information; assumptions regarding finite versus impulsive maneuver implementations; aerobraking assumptions; and a comprehensive Delta-V budget. The Spacecraft Data section requires detailed specifications including wet mass and propellant mass; chemical and/or electric engine parameters such as types, quantity, duty cycles, propellants, specific impulse (Isp), thrust and power characteristics with supporting equations, and mass flow rate calculations; thrust vectors for each planned maneuver; tank capacities with propellant margin allocations; power capability at 1 AU with power margin amounts; Technology Readiness Levels and throughput capabilities for all engines, solar arrays, and power processing electronics; and the momentum control methodology to be employed during quiescent cruise phases and maneuvers.

View the file

Other files for this federal contract opportunity

Other files attached to Draft RFP - Mars Telecommunications Network (MTN), newest first.
File Type Posted
MTN - DRFP - Questions and Answers - Update.pdf PDF
MTN - DRFP Questions and Answers.pdf PDF
MTN Industry Day Presentation 04-09-26.pdf PDF
MTN Industry Day Questions and Answers 04-09-26.pdf PDF
MTN Industry Day Registered Attendees 04-09-26.pdf PDF
Attachment B - Draft MTN Objectives and Requirements Rev A 4-8-26.pdf PDF
Exhibit(s) 2 - 9 - Price 4-8-26.xlsx XLSX spreadsheet
Exhibit 10 Draft CASQ 4-8-26.xlsx XLSX spreadsheet
Enclosure 1 - Performance Work Statement 4-8-26.pdf PDF
Exhibit 1 - Statement of Objectives (SOO) 4-8-26.pdf PDF
Exhibit 11 Draft Past Performance Questionnaire 4-8-26.pdf PDF
Draft RFP MTN Update 2 Summary 4-8-26.pdf PDF
Attachment B - Draft MTN Objectives and Requirements.pdf PDF
Attachment E - Draft IDIQ Fixed Price Labor Matirx.pdf PDF
Attachment F - Draft Data Requirements Deliverables (DRDs).pdf PDF
Enclosure 1 - Draft Performance Work Statement.pdf PDF
Exhibit 11 - Draft MTN Proposal Mission Trajectory Instructions.pdf PDF
Exhibits - 2 - 8 - Draft Price.xlsx XLSX spreadsheet
Exhibit 10 - Draft Past Performance Questionnaire.pdf PDF
Attachment A - Draft MTN Performance Work Statement (PWS).pdf PDF
Attachment J -Draft IT Security Management Plan.pdf PDF
Draft RFP - MTN Cover Letter.pdf PDF
DRFP - 80GSFC26R0011.pdf PDF
Attachment G - Draft Government Furnished Equipment (GFE).pdf PDF
Attachment H - Draft CDRLS - Non-Technical DRDs.pdf PDF
Attachment K - Draft Organizational Conflict of Interest (OCI) Avoidance Plan.pdf PDF
Enclosure 2 - Draft Qualtiy Assurance Surveillance Plan (QASP).pdf PDF
Exhibit 1 - Draft Statement of Objectives (SOO).pdf PDF
Exhibit 9 - Draft CASQ.xlsx XLSX spreadsheet
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DRFP No. 80GSFC26R0011 Exhibit 12

MTN Proposal Mission Trajectory Data Package

1: Trajectory Information:

• Launch vehicle, launch date, C3, and departure launch azimuth

• Final orbit characteristics at Mars

• Binary spice SPK files or equivalent for beginning, middle, and end of launch window

• Solar conjunctions and eclipse durations

• Finite vs. Impulsive maneuver assumptions

• Aerobraking assumptions

• Delta-V budget

2: Spacecraft Data:

• Wet mass, propellant mass

• Chemical and/or electric engine types, number used, duty cycles, propellants, Isp, thrust and power characteristics (provide equations for thrust & power, Isp, mass flow rate)

• Thrust vectors for each maneuver

• Tank capacities and amount of propellant margin

• Power capability at 1 AU and amount of power margin

• Technology Readiness Levels and throughput capabilities of all engines, solar arrays, power processing electronics (PPU), etc.

• Momentum control method during quiescent cruise and during maneuvers

File details come from the government source that posted it. Updated .