Enclosure 2 - Draft Qualtiy Assurance Surveillance Plan (QASP).pdf

PDF 95 KB Posted

Attached to
Draft RFP - Mars Telecommunications Network (MTN) Federal contract opportunity
Solicitation number
80GSFC26R0011
Issued by
National Aeronautics and Space Administration Goddard Space Center

About this file

This document is a Government Quality Assurance Surveillance Plan (QASP) for the Mars Telecommunications Network (MTN) contract administered by NASA Goddard Space Flight Center (GSFC). The QASP is not part of the contract itself but serves as an informational tool for monitoring contractor performance in accordance with FAR 46.601 and NFS 1846.401. The contract is structured as a Firm-Fixed-Price (FFP) agreement with contract number to be determined (TBD).

The MTN contract encompasses three distinct phases: (1) Development through Implementation, (2) Launch through Relay Commissioning at Mars, and (3) Relay Operations. The contractor is required to deliver a complete Mars telecommunications system including all associated development, integration, testing, launch, and operational services to achieve full operational capability at Mars and provide relay services for five Earth-years. The Government employs an insight-based surveillance strategy supplemented by limited oversight on high-impact activities such as fault tolerance analysis, subsystem and system-level testing, critical event planning, risk management, and problem resolution. The surveillance team comprises MTN Project Manager, Engineering Personnel, Procurement Personnel, Program Personnel (COR), Safety and Mission Assurance Personnel, Information Technology Security Personnel, Property Administrator Personnel, and Project Planning and Control Lead. Performance is evaluated across six criteria: Schedule Performance (with required hardware delivery by December 31, 2028, and full operational readiness by end of calendar year 2030), Technical Performance (meeting requirements in Attachment J-01 across four MTN mission objectives), Cost Control, Management Effectiveness, Quality Assurance adherence, and NASA Engagement effectiveness. The Contracting Officer completes regular Contractor Performance Assessment Reporting System (CPARS) evaluations aligned with program phases and milestones, which are reviewed by the contractor and recorded in the Past Performance Information Retrieval System (PPIRS).

View the file

Other files for this federal contract opportunity

Other files attached to Draft RFP - Mars Telecommunications Network (MTN), newest first.
File Type Posted
MTN - DRFP - Questions and Answers - Update.pdf PDF
MTN - DRFP Questions and Answers.pdf PDF
MTN Industry Day Presentation 04-09-26.pdf PDF
MTN Industry Day Questions and Answers 04-09-26.pdf PDF
MTN Industry Day Registered Attendees 04-09-26.pdf PDF
Attachment B - Draft MTN Objectives and Requirements Rev A 4-8-26.pdf PDF
Exhibit 10 Draft CASQ 4-8-26.xlsx XLSX spreadsheet
Exhibit 12 Draft MTN Proposal Mission Trajectory Instructions 4-8-26.pdf PDF
Exhibit(s) 2 - 9 - Price 4-8-26.xlsx XLSX spreadsheet
Draft RFP MTN Update 2 Summary 4-8-26.pdf PDF
Enclosure 1 - Performance Work Statement 4-8-26.pdf PDF
Exhibit 1 - Statement of Objectives (SOO) 4-8-26.pdf PDF
Exhibit 11 Draft Past Performance Questionnaire 4-8-26.pdf PDF
Exhibits - 2 - 8 - Draft Price.xlsx XLSX spreadsheet
Exhibit 10 - Draft Past Performance Questionnaire.pdf PDF
Attachment B - Draft MTN Objectives and Requirements.pdf PDF
Attachment E - Draft IDIQ Fixed Price Labor Matirx.pdf PDF
Attachment F - Draft Data Requirements Deliverables (DRDs).pdf PDF
Enclosure 1 - Draft Performance Work Statement.pdf PDF
Exhibit 11 - Draft MTN Proposal Mission Trajectory Instructions.pdf PDF
Draft RFP - MTN Cover Letter.pdf PDF
DRFP - 80GSFC26R0011.pdf PDF
Attachment G - Draft Government Furnished Equipment (GFE).pdf PDF
Attachment H - Draft CDRLS - Non-Technical DRDs.pdf PDF
Attachment K - Draft Organizational Conflict of Interest (OCI) Avoidance Plan.pdf PDF
Exhibit 1 - Draft Statement of Objectives (SOO).pdf PDF
Exhibit 9 - Draft CASQ.xlsx XLSX spreadsheet
Attachment A - Draft MTN Performance Work Statement (PWS).pdf PDF
Attachment J -Draft IT Security Management Plan.pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MARS TELECOMMUNICATIONS NETWORK (MTN)

QUALITY ASSURANCE SURVEILLANCE PLAN

(QASP)

1.0 INTRODUCTION

1.1 Purpose

The purpose of this Government Quality Assurance Surveillance Plan (QASP) is to define the overall framework the NASA Goddard Space Flight Center (GSFC) intends to use to monitor and survey Contractor performance under the Mars Telecommunications Network (MTN) Contract No. TBD. This Firm-Fixed-Price (FFP) contract provides for the Government to obtain a Mars telecommunications system, including all associated development, integration, test, launch, and operational services necessary to achieve full operational capability at Mars and provide relay services for five Earth-years.

The QASP is a Government-developed surveillance tool prepared in accordance with FAR

46.601 and NFS 1846.401. It is not part of the contract, per NFS 1846.401(a)(iii), but is provided to the Contractor for informational purposes only.

1.2 Scope

This QASP has been developed to evaluate Contractor performance while executing the Performance Work Statement (PWS), which is delivered by the Contractor and incorporated into the contract upon award. It is designed to provide an effective surveillance framework for monitoring Contractor performance, deliverables, processes, and products provided under this MTN contract across all three contract phases:

(1) Development through Implementation

(2) Launch through Relay Commissioning at Mars

(3) Relay Operations

This QASP defines the process the Government will follow to obtain data, evaluate the Contractor, and determine if contract performance conforms to contract requirements.

The Contractor, and not the Government, is responsible for management and quality control actions to meet the terms of the contract.

The role of the Government is quality assurance to ensure contract standards are achieved. The Contractor will provide Government insight into its program of inspections and monitoring actions. The first major step toward ensuring a self-correcting contract is to confirm that the quality control program defined at the beginning of the contract provides sufficient measures to establish high confidence of success. Once the quality control program is understood, careful application of the processes and standards will ensure a robust quality assurance program.

This plan is applicable to all work performed and all products and deliverables provided by the MTN Contractor. Throughout this QASP, the term "Contractor" is used. Unless explicitly stated otherwise, the term "Contractor" applies to both the MTN prime Contractor and any and all of its subcontractors.

2.0 FORMS OF SURVEILLANCE

2.1 Surveillance Strategies

Insight

Insight is an assurance process that uses performance requirements and, where definable, performance metrics to ensure process capability, product quality, and end-item effectiveness. Insight relies on gathering a set of product or process data that provides adequate visibility into the integrity of the product or process. Data may be acquired from Contractor records, typically in a non-intrusive parallel method.

Insight as applied to this contract will allow the Contractor to assume increased responsibility and accountability for the integrity of processes. Insight will rely heavily on evaluating planned contract deliverables, performance standards, and existing Contractor procedures and working documents. The specific mechanisms and processes by which the Government will exercise insight are defined in the Contractor-delivered DRD-PM-08, Insight and Oversight Implementation Plan.

Oversight

The Government will gather information pertaining to the Contractor's processes through direct involvement and/or inspection and will monitor those processes directly. The Government's exercise of oversight will be determined necessary by the Contracting Officer's Representative (COR).

The Government may use a variety of surveillance methods to evaluate Contractor performance. Government surveillance will be conducted on a non-interference basis and in a manner that will not substantially delay work being performed by the Contractor. The specific oversight mechanisms and processes are further defined in the Contractor-delivered DRD-PM-08, Insight and Oversight Implementation Plan. Government oversight will be applied to a limited set of activities and processes with high impact to mission success such as fault tolerance, subsystem and system level testing and acceptance, deviations from plans, critical event planning, risk management, and problem/anomaly diagnosis and resolution.

2.2 Surveillance Team

All surveillance activities will be implemented using NASA and NASA support-contractor personnel, a delegated agency (e.g., Defense Contract Management Agency (DCMA)), and/or surveillance support personnel. The surveillance team will be composed of:

• MTN Project Manager

• MTN Engineering Personnel

• MTN Procurement Personnel (i.e., CO, Contract Specialist)

• MTN Program Personnel (i.e., COR)

• MTN Safety and Mission Assurance Personnel

• MTN Information Technology Security Personnel

• MTN Property Administrator Personnel

• MTN Project Planning and Control Lead

The MTN Project Manager is responsible for the overall programmatic and technical health of the MTN contract. The MTN Project Manager serves as the senior Government representative for day-to-day program execution, provides leadership and direction to the surveillance team, and maintains visibility into Contractor performance across all contract phases. The MTN Project Manager, in collaboration with the CO and COR, is responsible for preparing and submitting regular Contractor Performance Assessment Reporting System (CPARS) evaluations, which will be reviewed by the Contractor and will become part of the Past Performance Information Retrieval System (PPIRS).

MTN Engineering Personnel, in coordination with the Project Manager, are responsible for exercising insight and oversight of the technical aspects of the contract. Engineering personnel perform these functions through regular interaction with the Contractor in technical meetings, particularly those related to key decisions, risks, and evaluation of milestone deliveries.

The MTN CO is responsible for ensuring performance of all necessary actions for effective contracting, ensuring compliance with the terms of the contract, and safeguarding the interests of the United States in its contractual relationships. The CO will also assure that the Contractor receives impartial, fair, and equitable treatment under this contract. The CO is ultimately responsible for the final determination of the adequacy of the Contractor's performance.

The MTN COR is designated in writing by the CO to act as his/her authorized technical representative to assist in administering the contract. The COR monitors the technical work performed under the contract, evaluates Contractor performance, serves as the primary interface between the Contractor and the CO for all technical matters, reports on contract status to Project Management, and recommends corrective action when necessary. The COR is not empowered to make any contractual commitments, authorize any contractual changes on the Government's behalf, or in any way direct the Contractor to operate in conflict with the contract terms and conditions. Any changes that the Contractor deems may affect the contract price, terms, or conditions shall be referred to the CO for action. The COR's limitations of authority are contained in the NASA Form 1634, COR Delegation.

MTN Safety and Mission Assurance Personnel will monitor the Contractor's compliance with applicable safety and health requirements throughout all phases of the MTN program, including development, integration, test, launch, and operational activities. Surveillance will be conducted on a non-interference basis consistent with the overall surveillance strategy defined in this plan.

MTN Information Technology Security Personnel will monitor the Contractor's compliance with applicable IT security requirements throughout the MTN program lifecycle. IT security surveillance will be conducted in alignment with the IT systems security framework and applicable NASA and NIST cybersecurity standards.

MTN Property Administrator will monitor and administer Government property, if any, provided to or acquired by the Contractor under this contract, in accordance with applicable FAR and NASA FAR Supplement property administration requirements.

MTN Project Planning and Control Lead applies financial oversight in the context of a firm, fixed price (FFP) contract inclusive of evaluation of milestone deliveries, implementation of change orders, and other schedule or price related matters.

2.3 Communications

The Government and Contractor will maintain regular communication throughout all phases of the MTN contract. Communication methods will include, but are not limited to:

• Periodic technical and programmatic reviews

• Technical Interchange Meetings (TIMs)

• Electronic mail

• Informal discussions

• Other communication methods as required

The specific engagement mechanisms, touchpoints, and communication structures are further defined in the Contractor-delivered DRD-PM-08, Insight and Oversight Implementation Plan, and are aligned with the NASA Engagement Plan.

2.4 Evaluation and Reporting

Government evaluation of Contractor performance will be milestone and deliverable-based, consistent with the FFP contract structure. Evaluation and reporting activities will include:

• Review and acceptance of contract deliverables at defined milestones

• Assessment of Contractor performance against the milestone payment schedule

• Evaluation of technical progress at key program reviews and decision gates

• Inspection of deliverable hardware, software, and documentation

• Review of Contractor-submitted reports and data products

2.5 Work Review and Performance Monitoring

The Government will evaluate the Contractor's accomplishment of technical and programmatic objectives through the following activities:

• Periodic meetings with the Contractor to review progress and identify and resolve problems and risks

• Review of Contractor milestone completion and deliverable acceptance across all three contract phases

• Participation in key technical reviews, including design reviews, test and qualification reviews, and operational readiness reviews

• Access to facilities and testing activities as appropriate, consistent with DRD-PM-

• Participation in risk management meetings

• Participation in problem, failure, and anomaly review boards

• Preparation and submission of Contractor Performance Assessment Reporting

System (CPARS) reports

• Conduct of inspection and acceptance of Contractor deliverables and hardware

• Review of Contractor safety procedures and performance

• Validation that the Contractor is performing in accordance with required contractual plans (e.g., testing, integration, quality assurance) through physical inspection, review of submitted reports, and meetings with the Contractor's program manager

2.6 Record Keeping and Documentation

The COR is responsible for maintaining accurate and complete records of the Contractor's performance. The COR is responsible for collecting performance evaluation documentation and maintaining any other material that reflects the quality of Contractor performance. Even though the Contractor is responsible for ensuring performance compliance under their quality control requirements, the Government will give the Contractor prompt notice of deficiencies observed by the COR. This does not imply that the Government is obligated to carry out quality control inspections for the Contractor, but that on discovering a problem, the Government will inform the Contractor in detail of the incident. The COR will keep the CO informed of any issues brought to the attention of the Contractor.

If performance issues arise, they will be discussed immediately between the CO, COR, and Contractor. Action plans will be developed and resolutions tracked for closure by the Contractor and Government.

During the course of the contract, the COR shall retain a copy of all surveillance documentation. At the end of each surveillance period, these records shall be forwarded to the Contracting Officer for inclusion in the contract file. When a specific deliverable or milestone becomes unsatisfactory during a surveillance period, a copy of the documentation supporting the unsatisfactory performance shall be forwarded to the Contracting Officer for action between the Government (CO and COR) and the Contractor.

2.7 Contract Administration

The Contractor will maintain effective communication within its own organization, including subcontractors. Problems, technical issues, and programmatic changes will be promptly communicated to all concerned parties. Prime Contractor communication with subcontractors will be seamless and transparent to the Government.

3.0 CRITERIA FOR EVALUATING PERFORMANCE

The Contractor's performance across all areas of the MTN contract will be monitored to assure that ineffective or wasteful methods are not being used. As required by FAR 42.1502 and GPR 5100.2, Supplier Performance Evaluations, the CO, in collaboration with the COR, will complete Contractor Performance Assessment Reporting System (CPARS) evaluations on a regular basis, aligned with MTN program phases and milestones. CPARS evaluations will also be reviewed by the Contractor and will become part of the Past Performance Information Retrieval System (PPIRS).

Performance will be evaluated against the following criteria:

• Schedule Performance: The Contractor's ability to meet milestone dates, deliver hardware and software on schedule, and maintain the required hardware delivery date of December 31, 2028, and full operational readiness at Mars by end of calendar year 2030

• Technical Performance: The Contractor's ability to meet performance requirements specified in Attachment J-01 across all four MTN mission objectives

• Cost Control: The Contractor's ability to execute within the FFP contract value and manage program risks that could affect cost

• Management Effectiveness: The Contractor's ability to manage the program, subcontractors, risks, and issues in a transparent and effective manner

• Quality Assurance: The Contractor's adherence to the quality control program, standards, and verification plans

• NASA Engagement: The Contractor's effectiveness in providing NASA with the insight and visibility necessary to support informed decision-making, consistent with DRD-PM-08

In the event of a finding that requires immediate attention, the COR will notify the CO of the situation for necessary action. The Contractor will be required to submit a written response and any corrective action steps needed.

4.0 SUMMARY

This Government Quality Assurance Surveillance Plan defines the framework GSFC will use to monitor the MTN contract and assure that the Contractor performs in accordance with the terms and conditions of the contract. GSFC will employ an insight-based surveillance strategy, as further defined in the Contractor-delivered DRD-PM-08, Insight and Oversight Implementation Plan. The goal is to balance the level of Government surveillance with the perceived impacts and risks of mission failure across all three phases of the MTN program, while enabling the Contractor the flexibility to execute the program efficiently and meet the aggressive schedule requirements.