This document is a comprehensive Request for Information (RFI) response spreadsheet for the Fort Thompson Duplex Construction project by the Indian Health Service (IHS). The solicitation (No. 75H70125R00076) is a 100% set-aside for Indian Small Business Economic Enterprises (ISBEE) under NAICS code 236116, with a $45 million size standard, seeking to construct one duplex building with an option for a second building at the Fort Thompson Service Unit in South Dakota. The project involves constructing staff quarters with a 365-calendar day performance period and will be awarded as a Firm Fixed Price (FFP) construction contract using a lowest price technically acceptable (LPTA) evaluation methodology.
The RFI response addresses 74 detailed technical questions covering various aspects of construction, including structural modifications (e.g., floor trusses), material specifications (waterproofing, sheathing, flooring), mechanical systems (HVAC changed to air source heat pump), electrical requirements, and compliance details. Key technical changes include switching from TJI to 18" floor trusses, modifying HVAC to an air source heat pump, using R6-Zip sheathing, and specifying waterproofing membranes. Additional requirements include Buy American compliance, specific tracer wire specifications, and TERO fees. The project requires detailed submittals, adherence to specific material standards, and comprehensive documentation of construction methods and materials.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B05 Amendment 6.pdf | ||
| S111.pdf | ||
| B05 Amendment 5.pdf | ||
| B05 Amendment 4.pdf | ||
| RFIs 11.12.2025.xlsx | XLSX spreadsheet | |
| RFIs 11.07.2025.xlsx | XLSX spreadsheet | |
| B05 Amendment 3.pdf | ||
| RFIs 11.05..2025.xlsx | XLSX spreadsheet | |
| B05 Amendment 2.pdf | ||
| B05 Amendment 1.pdf | ||
| RFIs 10.31.2025.xlsx | XLSX spreadsheet | |
| Site Visit sign in 10.15.25.pdf | ||
| Specifications Vol 2_Duplex Construction.pdf | ||
| RFIs 10.29.2025.xlsx | XLSX spreadsheet | |
| Specifications Vol 1_Duplex Construction.pdf | ||
| Geotech report.pdf | ||
| RFIs 10.23.2025.xlsx | XLSX spreadsheet | |
| B01 25R00076.pdf | ||
| Attachment 2 SOW.pdf | ||
| Attachment 5 Self Performed Calculation Sheet.docx | DOCX document | |
| Attachment 4 Civil Plans.pdf | ||
| Attachment 6 Company Specialized Experience Form.docx | DOCX document | |
| Attachment 3 Crawlspace Plans.pdf | ||
| Attachment 8 IHS IEE Representation Form.pdf | ||
| Attachment 1 Wage Determination SD20250003.pdf | ||
| Attachment 7 Past Performance Questionnaire.docx | DOCX document |
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Number | RFI | Response |
| 1 | What material is the water proofing membrane shown on the concrete foundation walls? Is it a fabric type membrane or a painted on petroleum based type of membrane? Is a specification avaialble? | See specifications - Division 07 |
| 2 | The appliances are tagged “To Be Determined”. Are the appliances to be included? Is there a specification available? | See specifications - Section 113013 |
| 3 | Are window shades to be included? I do not see a reference on the window page. | See specifications - Section 122413 |
| 4 | Has anyone inquired about changing the I-Joist floor assembly to 18” floor trusses, similar to the duplexes in Wanblee, Kyle and Pine Ridge? | Yes, the design has been revised to floor trusses. |
| 5 | What is a T-BUR line is? Is this an internal IHS line? | Telephone - Buried |
| 6 | Is a specification book and geo tech report available for these duplexes? | See SAM.gov posting updated 10/24/2025 |
| 7 | Structural drawings show stair framing but no stairs appear in the architectural. Please confirm that there are no stairs. | confirmed - there are no stairs |
| 8 | Structural framing plan looks like the TJI’s are bearing on a ledge on the inside of the foundation, but the detail shows it bearing on top of the foundation. Please confirm construction. | TJI design was modified to floor trusses. The framing bears on the top of the foundation wall. |
| 9 | How is the party wall to be framed as there are no details. Should we include an extra TJI and a gable end truss at each wall? Please clarify. | TJI design was modified to floor trusses. Party wall framing doesn't require any addition framing members |
| 10 | Civil plans shown 1” PE water service line feeding duplexes. Does this line need to be larger to also accommodate the fire sprinkler system? | Domestic water service size is 1" |
| 11 | Are we to bid the project to include the ground source heat pump and in-ground hydronic piping system, or will this be changed to a forced air system? If forced air, will it be electric or gas? | HVAC design was revised to an air source heat pump design. Supplementary electric heating is included. No gas heating. See updated sheets M601 - M701 |
| 12 | Plans show water lines and back flow preventer in the garages, which could be a freeze concern. Shall we plan on having this plumbing relocated to the mechanical rooms? | Garages have a unit heater to prevent freezing. If plumbing can be coordinated to relocate to mechanical rooms, this is an acceptable alternative to the design on the plans. |
| 13 | Will the answers previously provided to the RFI's submitted during the 2023 solicitation for this project apply to this current solicitation? It appears the drawings have not changed from 2023. If so, please issue formally. | This is a new solicitaiton, previous RFI's will not be considered. |
| 14 | The interior elevations show that the exterior of the cabinets are Oak (wood) but the interiors are white melamine. Do you want the entire cabinet to be residential quality wood? Or do you want a high-quality commercial cabinet with an interior of white melamine shelf/interior finish and the outside being a flat oak veneer door? Typically, we would use plastic laminate on the exterior in lieu of oak veneer as veneer is much more expensive. | See attached specification 064116 |
| 15 | Please provide color information for the cabinets. | See attached specification 064116 |
| 16 | Elevations call for countertops to be Plastic laminate countertops w/ 3mm PVC edges but the detail shown on 11/A411 shows a solid surface SS-1 countertop. Please confirm what material we are to bid as countertops for both kitchen an bath areas. | Use solid surface countertops |
| 17 | Will there be window sills other than a drywall return? If so, what is the material? | Drywall returns |
| 18 | What type of brackets do you want under the restroom laminate shelves in the restrooms(9/A411)? | Include in a submittal |
| 19 | Please confirm that this bid should on the Northern Cheyenne Tribe (as indicated in the TOPR) since Fort Thompson, SD is located within the Crow Creek Sioux Reservation. | confirmed - Fort Thompson is located within the Crow Creek Reservation |
| 20 | As far as the sanitary goes, only two duplexes are being constructed at this time so should we plan on tying into the existing sanitary on both North and South sides as well as including both manholes and only installing the services for the two duplexes or all 4? | Yes, that is correct. |
| 21 | As far as the watermain goes, only two duplexes are being constructed at this time so should we plan on tying into the existing watermain on both the North and South sides as well and only installing the services for the two duplexes or all 4? Or should we just figure installing all underground utilities? | Only install the water service to the units being constructed now. |
| 22 | Is there a specifications document? | See SAM.gov posting updated 10/24/2025 |
| 23 | Will the SD state plumbing commission be inspecting plumbing or not due to tribal laws? | No they will not. |
| 24 | Do we need to include a submittal of all materials, faucets and equipment needed for the plumbing or will the IHS provide that? | Include in a submittal. |
| 25 | Would a submittal be needed to change domestic water piping from overhead to the crawlspace due to cold climate? We cannot pipe water in unconditioned space | Include in a submittal |
| 26 | It is unclear what the scope is of the site utilities required as part of this RFP. The SOW references C204, C308, C309 and C310, which all show the new utility mains for 4 units. Are we to install the new water and sewer mains and manholes as shown on C204 as part of this project, or are the mains already installed, and we are just tying into them for the new duplexes? Please clarify what is required. | The mains are not installed. Install new sewer including both manholes. Water and sewer service will only be needed to the units currently being constructed |
| 27 | Sheet A103 roof system indicate shingled roof, can you provide the specifications requirements for shingle roof system? | We would prefer shingled roof system Also see supplemental specification. |
| 28 | Sheet A201 indicates steel siding, can you provide the specification requirements for Steel Siding System? | The steel siding was later revised to engineered wood siding – Hadie/LP Siding and Trim or similar. Also, if revising to shingles, replacing the metal fascia and soffit with engineered wood could be a appropriate option. |
| 29 | Section 095113 Acoustical Panel Ceilings is indicated in the table of contents, can you confirm that the scope of work does not include any acoustical panels and this section should be removed from the table of contents? | Yes, that is correct. |
| 30 | Section 113013 Residential Appliances – the Fridge, Washer, Dryer are not defined in the specifications, can you provide the required specification details? | Those items will be owner provided. |
| 31 | Sheet A411 The enlarged floor plan at the kitchen area does not provide the framing dimensions for the interior walls can you provide these dimensions and layout? | Dimension added. See attached floor plan. |
| 32 | Does the R6 Zip system meet the shear wall design parameters? | R6 zip panels meet the required shear wall parameters, but do require the use of 10d nails for installation |
| 33 | Section 013100 Project Management and Coordination – Can the submittals, RFI’s and Submittal register, and other project correspondence be utilized thru FTP Procore System? | Yes |
| 34 | 013233 Photographic Documentation 1.4 A Photographer: Engage a qualified photographer to take construction photographs. Can the photos be taken by our project Superintendent? | Yes |
| 35 | 013300 Submittal Procedure 1.7 Delegated Design Can you clarify if any products incorporated into the project require a delegate design? | Fire Sprinkler System is a delegated design. |
| 36 | 014000 1.6 B Contractors Quality Control Staff - Can the Quality Control Supervisor also serve as the superintendent? | Yes |
| 37 | 015000 Temporary Facilities and Controls 2.1 B Portable Chain Link Fence can you provide the location of the temporary staging area for each location to incorporate the temporary fencing. | The temporary staging area will be close to duplex sites. |
| 38 | 017700 Closeout Procedures 1.9 Warranties Can you clarify the warranty period to be 1 year after substantial completion of each individual duplex? | Yes, where the warranty period refers to substantial completion, this is the substantial completion of each duplex. |
| 39 | 019113 1.4 Commissioning Team B1 Can you confirm the Commissioning agent is hired by IHS? | The contractor shall hire the commissioning agent. The checklists should be concise for residential construction. |
| 40 | The Finish Schedule indicates wood base can you provide the finish carpentry specification for the base materials? | Industry standard base for LVP flooring, ie. Subfloor and underlayment. |
| 41 | Can you provide the location of Division 092216 Non Structural Metal Framing and indicate the wall type required. | Wood framing |
| 42 | Section 013300 Submittal Procedures 1.4C states that the submittal review time is 14 calender days, does this duration include the VA, A/E and any consultants? | Yes |
| 43 | Are there any seismic requirements? If there are, have they been incorporated with the design already? | Seismic requirements for the building structure have already been incorporated into the design |
| 44 | Can you provide the support backing details and material requirements for wall mounted accessories including the grab bars and shower seats to support 250 lbf as indicated in section 102800 Toilet and Bath Accessories. | Blocking should be provided per the accessory manufacturer's recommendations, which should also meet the 250 lbf requirements. |
| 45 | 061000 Rough Carpentry 2.3 Fire-Retardant Treated Materials E – Can you define the locations of treated materials for clarity ie sill plate, Interior Wood Blocking, Clarify the roof structure treated components required, etc. are their other locations required? | Roof sheathing as indicated on the roof plan should be the only required fire-retardant material needed. |
| 46 | 061600 Sheathing 2.2 Wall Sheathing A identifies Glass-Mat Gypsum Sheathing the plans indicate R6- Zip Sheathing in the wall section on detail 1 on sheet A311 can you please clarify which product is required for the exterior wall sheathing and provide appropriate specifications? | R6-Zip is the appropriate exterior wall sheathing |
| 47 | 061600 Sheathing 2.2 A 2 Roof Sheathing can you define the appropriate materials for the roof sheathing and update the specifications for section 2.2 | Roof sheathing shall be per the notes on sheet S112 |
| 48 | 061600 Sheathing 2.2 A 3 Subfloor Sheathing can you define the appropriate materials for the Subfloor sheathing and update the specifications for section 2.2 | Floor sheathing shall be per the notes on sheet S111 |
| 49 | 072715 Air Barriers – can you clarify the use of air barriers as the plans indicate R6-Zip sheathing with barriers? | Zip sheathing as installed per the manufacturer’s meets requirements of an air barrier as required by code. |
| 50 | Can you provide a detailed exterior wall section to utilize standard sheathing and air barrier and if it would be acceptable in lieu of the R6-Zip sheathing? | Provide R6-Zip Sheathing as indicated |
| 51 | Section 096519 2.2 products identified in specifications include Armstrong Theorem, Shaw Floorte and Mohawk Solidtech, Theorem is a glue down, Floorte & Solidtech are floating floors. The flooring installer recommends to use a glue down product. Can you review the products and clarify the type of floor to use? | Either glue-down or floating vinyl plank flooring is acceptable. Please provide submittal for review. The accepted flooring shall be installed in accordance with the manufacturer’s recommended installation practices and the project specifications. |
| 52 | Section 096519 2.2 products LVT Flooring can you identify the wear layer, The flooring installer would recommend a 12 mil wear layer. Mohawk and Shaw both have glue down LVP in 12 mil wear layer. | For this residential application, provide a flooring product with a minimum 12mil wear layer. Please submit product data for review |
| 53 | Can you provide the windows specifications as it appears to be missing from the specifications? | Separate vinyl window specification provided |
| 54 | Section 088000 Glazing is this section referring to the windows? | Separate vinyl window specification provided |
| 55 | The Room Finish Schedule noted the floor base to be wood - Specification section 096513 Resilient Bas & Accessories indicates Rubber Base. Can you clarify if wood base is required and remove section 096513 from this scope. | See answer to #40 |
| 56 | Section 099113 Exterior Painting Can you clarify the exterior painting locations as most of the products are prefinished ie roof, gutters, downspouts, siding etc. | Unfinished metal, such as doors and galvanized penetrations or any other unfinished materials, should be painted. Concrete being the exception. |
| 57 | Can you provide a head, jamb and sill detail for the windows and doors for clarity? | Windows should be flanged units and taped/flashed for positive drainage per the air barrier/sheathing manufacturer’s recommendations. If window details are still needed they can be provided. |
| 58 | Section 099123 Interior Painting 1.1 Summary Concrete, Steel and Galvanized Metal are indicated to be painted can you provide clarity on the location of these materials as they do not appear to be included in the plans? | Concrete should not be painted. Unfinished/ primed steel should be painted. Galvanized wall penetrations should be finished to match adjacent construction. |
| 59 | Section 122413 Roller Window Shades 1.2 B 1 Submittals indicate motor-operated shades can you clarify if motor shades are required? | Motor roller shades are not required. Chain/chord operation is acceptable. |
| 60 | For the electrical cane you please confirm they MC cable is to be used. Per the specifications it states that MC cable is to be used, but type NM cable is listed. | Based on the anticipated construction type, either MC cable or NM cable may be used for most, if not all, branch circuits. Ensure installation complies with the requirements of NEC articles 330 (MC cable) and 334 (NM Cable). |
| 61 | Also there is a specification section on cameras, but I do not see anything on the plans. | Cameras are not needed |
| 62 | After reviewing the specifications, we noticed references to asphalt paving; however, there is no indication of asphalt work shown on the plans or mentioned elsewhere. Should asphalt paving be included in our proposal, or will that work be completed under a separate contract at a later date? | Correct, there is no asphalt paving |
| 63 | The specifications also reference a stormwater system, but if no asphalt paving is included, the system cannot be installed with a gravel road, and curb and gutter would not be necessary. Please confirm the intended scope regarding stormwater, curb, and gutter. | Correct, there is no need for a stormwater system, or curb & gutter. |
| 64 | The specifications mention both dampproofing and waterproofing. Will dampproofing alone be acceptable for this project? | Use waterproofing membrane |
| 65 | The plans call for a ZIP System exterior sheathing, while the specifications refer to a non-bituminous air barrier. Please confirm if the ZIP System will satisfy the air barrier requirement. | Zip sheathing as installed per the manufacturer’s meets requirements of an air barrier as required by code. |
| 66 | Do the materials need to be “Buy American” compliant? | Yes |
| 67 | Is gasketed joint SDR35 PVC pipe allowed? | Yes, SDR35 PVC gasketed joints are acceptable for gravity sanitary sewer systems |
| 68 | The ductile fitting spec mentions C110, but C153 is much more common for MJ fittings. Can C153 be used? | C153 (compact fittings) are acceptable. |
| 69 | The ductile fitting spec mentions cement mortar lining and FBE coating, but both cannot be used on a fitting. Should the fittings be cement lined/bituminous coated or should they be FBE inside and out? | Fittings shall be cement-mortar lined interior and sealed coated |
| 70 | Would SIDR7 IPS Poly be allowed for the 1” water services? | SIDR& IPS Poly is acceptable. |
| 71 | I saw that tracer wire is going to be required for both sanitary and water, but I didn’t see a spec for it. Would 12GA PE45 Kristech be acceptable? This is the most common tracer wire used in South Dakota. | Yes, 12ga PE45 Kris-Tech is acceptable and approved for South Dakota projects. |
| 72 | Responses to RFI's 4, 8 and 9 all refer to the TJI floor framing being changed to floor trusses. With 18” deep floor trusses is it the intention to still use the beam for bearing, or will they be clear span? If it’s clear span, 28’ is pushing it for 18” deep, we’ll have to go 16”oc. If the beam is still there, they could be 19.2” or 24”oc. Is there a revised structural drawing or detail which showing the change to floor trusses? Please provide revised framing plan showing this revision. | The floor framing consists of 18" trusses spaced at 16" o.c., as shown on Sheet S111. The intermediate bearing beam was removed from the design. Disregard the Not in Contract note |
| 73 | Is Section 71113 Bituminous Waterproofing to be applied to the foundation wall in lieu of section 71416? | In all likelihood 71113 Bituminous Waterproofing should be applied to the foundation wall in lieu of section 71416. Section 71416 should be implemented if the site drainage report indicates these type of supplemental measures should be taken. |
| 74 | Please verify where Section 71416 Cold Fluid Waterproofing is to be applied, including the Protection Course and Drainage Panels noted in the same section. No details show this in the plans. If this assembly is to be applied to the foundation walls, please confirm. | Section 71416 should be implemented if the site drainage report indicates these type of supplemental measures should be taken, in lieu of 71113. Site specific details can be provided if conditions warrant. |