B05 Amdnment A0001-75H70125R00023 Claremore Site Prep for New Clinical Modular Building.pdf

PDF 105 KB Posted

Attached to
Claremore Site Prep for New Clinical Modular Building
Solicitation number
75H70125R00023
Issued by

About this file

This is Amendment A0001 to solicitation 75H70125R00023, issued by the Indian Health Service (IHS) Division of Engineering Services in Seattle. The amendment changes the site visit date from Tuesday, January 28, 2025 at 10:00 AM CST to Thursday, January 30, 2025 at 10:00 AM CST.

The amendment relates to a solicitation for site preparation work for a new clinical modular building at Claremore Indian Hospital. The underlying solicitation is a 100% small business set-aside under NAICS 238910 with a magnitude between $1-5 million. The project involves preparing a site for installation of a five-section 64'8" x 72' modular building, with a 120-day performance period that must be completed by September 15, 2025. The procurement will result in a firm-fixed-price contract awarded using lowest price technically acceptable (LPTA) evaluation criteria.

View the file

Other files

File Type Posted
B05 Amdnment A0007-75H70125R00023 Claremore Site Prep for New Clinical Modular Building.pdf PDF
B05 Amdnment A0006-75H70125R00023 Claremore Site Prep for New Clinical Modular Building.pdf PDF
B01 RFP 75H70125R00023_Revised by Amd 0006.pdf PDF
B05 Amdnment A0005-75H70125R00023 Claremore Site Prep for New Clinical Modular Building.pdf PDF
B05 Amdnment A0004-75H70125R00023 Claremore Site Prep for New Clinical Modular Building.pdf PDF
A-1 Crawl Space Plan 1975.PDF PDF
P14-Location1-4 in sewer distance from bottom of floor where line enters wall.jpg JPG image
Amdnment A0003-75H70125R00023 Claremore Site Prep for New Clinical Modular Building.pdf PDF
1979 Parking lot expansion A-3.PDF PDF
1979 Parking lot expansion A-1.PDF PDF
P4-Domestic Cold Water Supply line above ceiling in rm 821 tie-in location.jpg JPG image
P16-4 in sewer line further south 2.jpg JPG image
1975 P-SERIES-P4 P5 shows topography.PDF PDF
P13-Location 1-4 in sewer line in crawlspace where line enters crawlspace wall under HW 27 .jpg JPG image
M-5 Underfloor Plan - Plumbing - NW.PDF PDF
M-4 Underfloor Plan - Plumbing - SW.PDF PDF
M-6 Floor Plan Plumbing - NE.PDF PDF
Q16-2022 IHS ArchitectEngineerDesignGuide.pdf PDF
M-8 Floor Plan Plumbing - SW.PDF PDF
P12-Location 1-4 in sewer line jog south of concrete wall in crawlspace.jpg JPG image
P10-Yard hydrant north side of building by front entrance.jpg JPG image
P6-East fire hydrant at ER entrance off South Moore Avenue 2-6-2025.jpg JPG image
P7-EVS closet 821 showing south wall where water supply chase will be located.jpg JPG image
Q25-Sewer line location in relation to underfloor in crawlspace print M-5.docx DOCX document
A-5 Floor Plan NW portion 1975.PDF PDF
1979 Parking lot expansion A-2.PDF PDF
P3-Crawlspace wall access Mech room 236.jpg JPG image
M-3 Underfloor Plan - Plumbing - SE.PDF PDF
GPR Job Summary Report - JSR-171324_(20240724_2006).pdf PDF
M-2 Underfloor Plan - Plumbing - NE.PDF PDF
ME-1 Site Plan 1975 Claremore.pdf PDF
P15-4 in sewer line further south.jpg JPG image
P5-Domestic Cold Water Supply line outside of rm 821 above ceiling in Peds hallway 27.jpg JPG image
M-7 Floor Plan Plumbing - SE.PDF PDF
P1-Crawlspace floor access Electrical room 521.jpg JPG image
M-9 Floor Plan Plumbing - NW.PDF PDF
P9-NE fire hydrant by Hwy 20 South Moore Will Rogers blvd-out of service closeup 2-6-2025.jpg JPG image
S-4 Structural-Foundation Plan NW portion 1975.PDF PDF
P2-Crawlspace floor access Safety Office room 159.jpg JPG image
P8-NE fire hydrant by Hwy 20 South Moore Will Rogers blvd-out of service 2-6-2025.jpg JPG image
P11-Yard hydrant north side of building by front entrance-west view.jpg JPG image
B05 Amdnment A0002-75H70125R00023 Claremore Site Prep for New Clinical Modular Building.pdf PDF
B01 Attachment J01 Wage Determination OK20250052 dated 2025 01 03.pdf PDF
B01 Attachment J04 Company Specialized Experience Form Construction.pdf PDF
B01 Attachment J02-F Crawlspace A-1.PDF PDF
B01 Attachment J06 IHS IEE Representation Form.pdf PDF
B01 Attachment J02-D Geotech report 1.pdf PDF
B01 Attachment J02-C Geotech report 2.pdf PDF
B01 RFP 75H70125R00023 Claremore Site Prep for New Clinical Modular Building.pdf PDF
B01 Attachment J05 Past Performance Questionnaire.docx DOCX document
Show 40 more

Latest 50 of 56 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

A0001

Andrew Hart, Contracting Officer

The purpose of this Amendment is to change the Section L. Para L.7.(b) site visit date from Tuesday, January 28, 2025 at 10:00 AM CST to Thursday, January 30, 2025 at 10:00 AM CST.

All other terms and conditions of this solicitation remain unchanged.

Indian Health Service - DES Seattle 701 5th Avenue, Suite 1600 Seattle, WA 98104

75H70125R00023

OK2CAS01H4

1 1

01/13/2025

01/10/2025

File details come from the government source that posted it. Updated .