J01j TAB Report PIMC Campus Projects.pdf
PDF 4 MB Posted
- Attached to
- PIMC ED & CSR (Phoenix, AZ) Federal contract opportunity
- Solicitation number
- 75H701-24-R-00035
About this file
This document is a Test and Balance (TAB) Report for the PIMC Campus Projects located at 4212 N 16th Street, Phoenix, AZ 85016. The report includes details on the testing and balancing of the air handling units (AHU-2 and AHU-4), exhaust fans (EF-3A, EF-3B, and EF-27), and associated VAV boxes and terminal devices. Key findings include AHU-2 operating in full economizer mode, EF-27 having a bad motor, and discrepancies between AHU-4 return air totals and traverse readings indicating potential leakage. The report provides airflow measurements, fan static pressures, motor information, and other system performance details. It also includes a VAV box schedule listing required and final CFM values for the VAV boxes and terminal devices served by the AHUs. Overall, the TAB Report documents the testing and balancing efforts to optimize the performance of the HVAC systems at the PIMC Campus.
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project: PIMC CAMPUS PROJECTS
Location: 4212 N 16TH STREET, PHOENIX AZ 85016
Engineer: ZONA TECHNICAL ENGINEERING
Prepared for: ZONA TECHNICAL ENGINEERING
Project Number:
Date:
Michael Ziegler
Test & Balance Engineer
TAB Technology, Inc.
1912 North Rosemont
Mesa, Az 85205
480-964-0187
25-Jan-23
Associated Air Balance Council Certificate No: 98-01-42
TEST AND BALANCE REPORT
This is to certify that TAB Technology, Inc. has balanced the systems described herein to their optimum performance capabilities. The testing and balancing has been performed in accordance with the standard requirements and procedures of the Associated Air Balance Council and the results are herein recorded.
J01j TAB Report PIMC Campus Projects
TTI
TAB Technology Inc.
Date: 1/10/2022 Tech: BW
Note #
1 AHU-2 was in full economizer at time of readings. It appears we only
EF-27 has a bad motor and is not running at this time.
pre-read a small portion of the areas served by this air handler. The unit traverse CFM is far more than the total from VAV pre-reads.
AHU-4 Is a multi zone system, the return grill total is much less than the return traverse total indicating leakage somewhere in the ceiling.
Technician Notes
The OSA damper was 100% closed at the time of testing.
EF-3A & 3B These fans are setup for one to be a stand by. Both fans were rotated in the cycle to acquire CFM Readings.
Air Handler Test
Project: Date:
System: Tech:
Print ID:
4.06 0.25
4.06 1.08
-0.40 0.82
3.84 0.22
Hz: 65 C to C:
4bn-/78.75/pf/mb/55/pf/sx5g
AHU-2
4.06
3.84
Pre-read VAV Total
5.06
Required Final Traverse Total
TTI
TAB Technology, Inc.
PIMC CAMPUS PROJECTS
AHU-2 BW
Alliance Air Products
6038 34320
01/19/23
3.81
2.98
-1.22
-1.22
4 @20 1848.0
AHU-2 Was in full economizer at the time of testing
DIRECT
DRIVE
VFD
1.15
System Static Set Point:
100%
In - Out - Delta P
Humidifier In - Out -
Delta P
Mark
Manufacturer
Model, Size
Conditions
Total CFM
External/Total Fan
Static Press.
Fan Static Press.
Inlet - Outlet
Cooling Coil
In - Out - Delta P
Heating Coil
In - Out - Delta P
Filter
In - Out - Delta P
Remarks:
NA NA
Motor HP - RPM
Motor Voltage
Motor Amps
Service Factor
Motor Frame
Outside Air
Drive Belts
Fan Pulley
Motor Sheave
Fan RPM
Motor AdJ
IN/OUT:
23.30
480/483/480/3460/3
16.2/16.3/16.3 16.3/16.6/16.4
16.3/16.4/16.4 16.5/16.3/16.4
1848/1854/1843/1851
VAV Box Schedule with Terminal Device
Project: Date: 12/21/22
System: Tech: BW/CD
Print ID:
Area Plan Control Size /
Served Tag Tag Diameter Max Min Max Min
40-B-2 8"/8" NA NA 241 NA
41-B-2 8"/8" NA NA 312 NA
42-B-2 12"/12" NA NA 421 NA
44-B-2 "8/8" NA NA 349 NA
45-B-2 8"/8' NA NA 631 NA
Terminal Normal Cooling Heating
No. Size Velocity CFM Velocity CFM Velocity CFM
40-1 12X12 241 236 247
40-B-2 TOTAL 241 236 247
41-1 12X12 312 319 294
41-B-2 TOTAL 312 319 294
42-1 10X10 122 182 144
42-2 6X12 100 111 102
42-3 6X12 78 90 82
42-4 6X12 121 284 250
42-B-2 TOTAL 421 667 578
44-1 12X12 349 377 339
44-B-2 TOTAL 349 377 339
45-1 10X10 138 131 122
45-2 10X10 136 137 120
45-3 10X10 111 119 112
45-4 10X10 93 90 107
45-5 10X10 153 163 149
45-B-2 TOTAL 631 640 610
Remarks:
TTI
TAB Technology, Inc.
Required CFM Final CFM "K"
Factor Notes
Exsiting Pneumatic Dual Duct VAV
PIMC CAMPUS PROJECTS
Room
Number "K" Notes with Terminal Device
Project: Date: 12/21/22
System: Tech: BW/CD
Print ID:
Area Plan Control Size /
Served Tag Tag Diameter Max Min Max Min
46-B-2 12"/12" NA NA 1,084 NA
48-B-2 8"/8" NA NA 437 NA
49-B-2 8"/8" NA NA 430 NA
Terminal Normal Cooling Heating
No. Size Velocity CFM Velocity CFM Velocity CFM
46-1 10''Ø 129 143 115
46-2 12X12 322 419 332
46-3 12X12 318 442 348
46-4 12X12 315 432 341
46-B-2 1,084 1,436 1,136
48-1 12X12 437 432 386
48-B-2 TOTAL 437 432 386
49-1 10X10 225 280 237
49-2 10X10 205 267 243
49-B-2 TOTAL 430 547 480
Remarks:
Room
Number "K" Notes
TTI
TAB Technology, Inc.
PIMC CAMPUS PROJECTS
Exsiting Pneumatic Dual Duct VAV
Required CFM Final CFM "K"
Factor Notes with Terminal Device
Project: Date: 12/21/22
System: Tech: ME,DE
Print ID:
Area Plan Control Size /
Served Tag Tag Diameter Max Min Max Min
VB-01 8" / 8" NA NA 355 NA
VB-03 8" / 8" NA NA 847 NA
VB-04 8" / 8" NA NA 297 NA
Terminal AS IS Cooling Heating
No. Size Velocity CFM Velocity CFM Velocity CFM
E154 01-1 08''Ø 88 85 54
E122 01-2 08''Ø 85 88 66
E121 01-3 08''Ø 103 97 70
E155 01-4 08''Ø 79 82 67
355 352 257
E127 03-1 08''Ø 231 215 190
E129 03-2 08''Ø 200 217 186
E131 03-3 08''Ø 154 116 106
E155 03-4 08''Ø 262 225 186
847 773 668
E124 04-1 08''Ø 63 154 61
E123 04-2 08''Ø 55 171 54
E128 04-3 08''Ø 42 120 46
E130 04-4 08''Ø 63 206 65
E132 04-5 08''Ø 74 191 75
297 842 301
Remarks:
Room
Number "K" Notes
VB-01 TOTAL
VB-03 TOTAL
VB-04 TOTAL
TTI
TAB Technology, Inc.
PIMC CAMPUS PROJECTS
EXISTING VAVS
Required CFM Final CFM "K"
Factor with Terminal Device
Project: Date: 12/21/22
System: Tech: ME,DE
Print ID:
Area Plan Control Size /
Served Tag Tag Diameter Max Min Max Min
VB-05 8" / 8" NA NA 288 NA
VB-06 8" / 8" NA NA 346 NA
Terminal AS IS Cooling Heating
No. Size Velocity CFM Velocity CFM Velocity CFM
E113 05-1 08''Ø 35 47 28
E108 05-2 08''Ø 87 82 52
E109 05-3 08''Ø 69 77 40
E110 05-4 08''Ø NA NA NA (1)
E111 05-5 08''Ø 97 115 71
288 321 191
E106 06-1 08''Ø 289 286 169
CORR 06-2 08''Ø 57 72 42
346 358 211
Remarks:
Room
Number "K" Notes
1. Locked door no key
VB-05 TOTAL
VB-06 TOTAL
TTI
TAB Technology, Inc.
PIMC CAMPUS PROJECTS
EXISTING VAVS
Required CFM Final CFM "K"
Factor
Terminal Device
Schedule
Project: Date: 01/19/23
System: Tech: BW/DH
Print ID:
No. Size Velocity CFM Velocity CFM Velocity CFM
E121 2-1 08''Ø 1.00 238 238 237
E122 2-2 08''Ø 1.00 220 219 217
E104 2-3 08''Ø 1.00 62 60 66
E156 2-4 12''Ø 1.00 501 512 510
E156 2-5 12''Ø 1.00 722 734 730
E124 2-6 08''Ø 1.00 155 146 147
E123 2-7 08''Ø 1.00 249 254 245
E108 2-8 08''Ø 1.00 NA 142 139
E109 2-9 08''Ø 1.00 148 159 162
E110 2-10 12''Ø 1.00 NA NA NA (1)
E111 2-11 10''Ø 1.00 157 166 155
E130 2-12 08''Ø 1.00 209 211 217
E129 2-13 08''Ø 1.00 270 272 267
E127 2-14 08''Ø 1.00 203 204 198
137 2-15 24X12 1.00 673 688 674
Waiting 2-16 24X12 1.00 570 571 532
Waiting 2-17 24X12 1.00 372 384 399
NA 2-18 18X12 1.00 64 65 64
131 2-19 12X6 1.00 316 302 312
132 2-20 12X6 1.00 36 31 30
132 2-21 12X6 1.00 10 10 11
135 2-22 12X8 1.00 154 153 154
134 2-23 12X8 1.00 215 214 216
130 2-24 12X6 1.00 302 289 289
126 2-25 12X6 1.00 420 427 427
138 2-26 12X6 1.00 180 183 185
127 2-27 18X6 1.00 364 409 405
127 2-28 12X6 1.00 358 365 372
129 2-29 18X6 1.00 536 523 524
125 2-30 12X8 1.00 500 514 507
124 2-31 12X8 1.00 312 311 310
123 2-32 12x6 1.00 200 203 204
8,716 8,959 8,905
All outlets tested with a digital flow hood, which is self-compensating for altitude and back pressure.
Remarks:
Notes
1. Door locked no key.
AHU-2 RETURN TOTAL
TTI
TAB Technology, Inc.
PIMC CAMPUS PROJECTS
AHU-2 RETURN TOTAL
Room
Number
Terminal "K"
NORMAL COOLING HEATING
Air Handler Test
Project: Date:
System: Tech:
Print ID:
4.15 0.02
4.15
-0.11 0.81
4.17 0.33
4.15 0.33
Hz: 60 C to C:
C8254-FCH-L
AHU-4
3.84
4.15
Preliminary
5.07
Required Final Traverse Total
TTI
TAB Technology, Inc.
PIMC CAMPUS PROJECTS
AHU-4 BW
ENERGY LABS
01/19/23
4.17
4.15
-0.92
-0.92
5.0 1765+/-
3.82
1 OSA DAMPER 100% CLOSED
DIRECT
DRIVE
VFD
184T
1.15
System Static Set Point:
(1)
Cold Deck Final
Filter In - Out
Hot Deck Final Filter
In - Out
Mark
Manufacturer
Model, Size
Conditions
Total CFM
External/Total Fan
Static Press.
Fan Static Press.
Inlet - Outlet
Cooling Coil
In - Out - Delta P
Heating Coil
In - Out - Delta P
Filter
In - Out - Delta P
Remarks:
NA NA NA
Motor HP - RPM
Motor Voltage
Motor Amps
Service Factor
Motor Frame
Outside Air
Drive Belts
Fan Pulley
Motor Sheave
Fan RPM
Motor AdJ
IN/OUT:
6.20
480/483/480/3460/3
5.2/5.3/5.2
J01j TAB Report PIMC Campus Projects dave Highlight 0.0 dave Highlight
Exhaust Fan Test
Project: Date: 01/19/23
System: Tech: BW
Print ID:
Req'd Final Req'd Final Req'd Final Req'd Final
3,552 19,907
0.86 1.68
-0.69 -1.35
0.17 0.33
2.0 2 @15.0
1755 1762 1770 1383/1385
460/3 480/480
483/3 460/3
480/480
483/3
2.75 1.2/1.2
1.1 17.90
10.1/10.4/
10.6
10.6/10.5/
1762 1383/1385
Remarks:
TTI
TAB Technology, Inc.
PIMC CAMPUS PROJECTS
RF-4 and RF-2
Conditions
Mark
RF-4 RF-2
Manufacturer ENERGY LABS Alliance Air Products
Motor RPM
Model, Size
C8254-FCH-L 4BN-78.75
Total CFM
Fan Static Pressure
Fan Inlet Pressure
Fan Outlet Pressure
Motor HP
Motor Volts/Phase
Motor Amps
Fan RPM
Motor Sheave
DIRECT
Fan Pulley
DRIVE DRIVE
DIRECT
Motor Frame 145T 254
Drive Belt(s)
VFD VFD
Center to Center
NA NA
Motor Service Factor
1.15 1.15
Sys Static Set Point
NA NA
Motor Adjust In/Out
NA NA
Herts
60.00 56.00
Schedule
Project: Date: 12/21/22
System: Tech: ME/DE
Print ID:
No. Size Velocity CFM Velocity CFM Velocity CFM
E101 Z1-1 10''Ø 117 117 254
E101 Z1-2 10''Ø 103 103 222
E101 Z1-3 10''Ø 96 96 191
E101 Z1-4 10''Ø 101 101 246
417 417 913
E120 Z2-1 12''Ø 269 269 516
E153 Z2-2 10''Ø 247 247 532
E118 Z2-3 08''Ø 143 143 522
E118 Z2-4 08''Ø 166 166 523
825 825 2,093
E153 Z3-1 10''Ø 57 57 111
E116 Z3-2 10''Ø 61 61 124
E115 Z3-3 10''Ø 76 76 138
E115 Z3-4 10''Ø 66 66 119
E105 Z3-5 08''Ø 104 104 132
E117 Z3-6 06''Ø 36 36 76
400 400 700
All outlets tested with a digital flow hood, which is self-compensating for altitude and back pressure.
Remarks:
Notes
1. Not installed
TTI
TAB Technology, Inc.
PIMC CAMPUS PROJECTS
AHU-B-2 RETURN
Room
Number
Terminal "K"
AS IS COOLING HEATING
ZONE 1 TOTAL
ZONE 2 TOTAL
ZONE 3 TOTAL
J01j TAB Report PIMC Campus Projects dave Highlight dave Highlight 2,093 dave Highlight dave Highlight dave Highlight dave Highlight dave Text Box 1,642 dave Text Box 3,706
Schedule
Project: Date: 12/21/22
System: Tech: ME,DE
Print ID:
No. Size Velocity CFM Velocity CFM Velocity CFM
E119 EXR-4-1 14''Ø 1.00 35 38 37
E120 EXR-4-2 10''Ø 1.00 302 312 318
E153 EXR-4-3 14''Ø 1.00 478 469 487
E101 EXR-4-4 14''Ø 1.00 337 332 330
E101 EXR-4-5 14''Ø 1.00 310 312 317
AHU 4 RETURN TOTAL 1,462 1,463 1,489
All outlets tested with a digital flow hood, which is self-compensating for altitude and back pressure.
Remarks:
Notes
TTI
TAB Technology, Inc.
PIMC CAMPUS PROJECTS
AHU-4 RETURN TOTAL
Room
Number
Terminal "K"
NORMAL COOLING HEATING
Duct Traverse Test Sheet
Project: Date: 01/19/23
System: Tech: BW
Print ID:
Design Preliminary Final
FPM CFM FPM CFM FPM CFM Static Pressure
AHU-4
ZONE 1 953 (1)
ZONE 2 14"X12" 1.160 1896 2212 2.35
ZONE 3 18"X12" 1.500 498 747 3.16
SUPPLY TOTAL 3912 3.16
AHU-4 24"X24" 4.000 888 3552 -0.49
RETURN TOTAL
AHU-2
SUPPLY TOTAL 120"X96" 80.000 429 34320
AHU-2
RETURN TOTAL18 @ 3.25"X47.5"19.290 1032 19907
AHU-2
OSA 1 19 @ 4"X55" 29.020 699 20285
OSA 2 19 @ 4"X37" 19.520 688 13430
OSA TOTAL 33715
EF-3A&3B 12''Ø 0.785 1519 1192 -1.21
EF-27 18''Ø 1.760 (2)
Remarks:
1. Calculated air flow, no reliable traverse location found
2. Fan has a bad motor, not running.
TTI
TAB Technology, Inc.
DUCT TRAVERSE
System
Zone/Branch
Duct
Size
Area
(sq. ft.)
PIMC CAMPUS PROJECTS
Exhaust Fan Test
Project: Date: 01/19/23
System: Tech: BW
Print ID:
Req'd Final Req'd Final Req'd Final Req'd Final
586 596 (2)
NA NA
-1.21 -1.27
NA NA
0.5 0.5 2.0
1725 NA 1725 NA 1740
208/1 211/1 208/1 211/1 208/1
3.70 2.50 3.70 2.40 11.80
NA NA
Remarks:
1. Unable to shut fan down due to COVID
2. Bad motor not running.
Motor RPM
Motor HP
60.00
Motor Frame
60.00
2"/2" 2"/2" 4"/2"
NA NA
Herts
Sys Static Set Point
Motor Adjust In/Out
Center to Center
Conditions
Motor Service Factor
1.25 1.25 1.00
16" 16" 18"
NA
Model, Size
Manufacturer
Drive Belt(s)
Fan Pulley
Motor Sheave
Fan RPM
Motor Amps
Total CFM
Fan Outlet Pressure
Fan Inlet Pressure
Fan Static Pressure
Motor Volts/Phase
NA NA AX49
56 56 182T
1VL40 X 5/8 1VL40 X 5/8 1vl56 x 1 1/8
NA NA NA
TWIN CITY FAN TWIN CITY FAN TWIN CITY FAN
TFE-90C7 TFE-90C7 TFE-15OC11
TTI
TAB Technology, Inc.
EF-3A EF-3B EF-27
PIMC CAMPUS PROJECTS
EF-3A, EF-3B, EF-27
Mark
Schedule
Project: Date: 12/21/22
System: Tech: ME/DE
Print ID:
No. Size Velocity CFM Velocity CFM Velocity CFM
E119 1A-1 8 1.00 119
E102 1-1 08''Ø 1.00 173
E103 1-2 08''Ø 1.00 132
E125 1-3 06''Ø 1.00 20
E126 1-4 06''Ø 1.00 30
E131 1-5 08''Ø 1.00 500
E132 1-6 08''Ø 1.00 577
E112 1-7 06''Ø 1.00 44
All outlets tested with a digital flow hood, which is self-compensating for altitude and back pressure.
Remarks:
Notes
1. Bad Fan Motor
TTI
TAB Technology, Inc.
PIMC CAMPUS PROJECTS
Exhaust
Room
Number
Terminal "K"
Required Preliminary Final
0.004
-0.008
+0.003
-0.005
Wall -0.002
-0.004
-0.11-0.006-0.003
REVIEW DURRANT
REMODEL FROM 2009
Emergency Department
41-1 44-1
40-1
42-2 42-342-4
42-1
46-2 46-3 46-4 46-5
45-1
45-2 45-3 45-4 45-5
49-1
49-2
49-3
2-15 2-16 2-17
2-18
2-19
2-20 2-21
2-22
2-23
2-24
2-25
2-26
2-27
2-
2-
2-
2-
2-32
VB
VB
VB
R-1
8Ø
R-1
8Ø
VB-3
VB-4
VB-5
NOTE:
REFER TO SHEET M4A FOR
MECHANICAL SYMBOLS SCHEDULE.
NOTE:
REFER TO ARCHITECTURAL RCP FOR
SUPPLY/DIFFUSER GRILLE PLACEMENT.
VB
VB
8"Ø UP TO
EF-3 ON ROOF
VB
R-1
12Ø
T-2
6Ø
T-1
6Ø
T-2
6Ø
T-1
6Ø
8"Ø UP TO
EF-2 ON ROOF
VB-BOX
26X10
CONNECT
TO EXISTING
12X6
CONNECT
TO EXISTING
GENERAL NOTES:
A. CONTRACTOR TO FIELD VERIFY EXISITING CONDITIONS.
B. MECHANICAL CONTRACTOR TO COORDINATE DEMOLITION
AND NEW CONSTRUCTION WITH OTHER TRADES.
M2A
HVAC NEW CONSTRUCTION
PHASE 1
TD
JH
4' 8'0 16'
NORTH
EMERGENCY DEPARTMENT HVAC NEW CONSTRUCTION PLAN
P H
O E
N I X
N
D I A
N
M
E D
I C
A L
C
E N
T E
R
R E
M O
D E
L
P
H A
S E
P H
O E
N I X
A
R I Z
O N
A
R
D ANTRU R
E M
E R
G E
N C
Y
D
E P
A R
T M
E N
T
C C
E
A
S B
U I L T
T
REVISIONS
AS-BUILT SET 3-6-120
01-1
01-4
1-4 1-3
2-5 2-4
2-6 2-7
03-1
03-2
03-3
03-4
04-1 04-2
04-3
04-4
04-5
06-1
06-2
05-1
05-2
05-3
05-4
05-5
1-5 1-6
1-7
2-8
2-9
2-10
2-11
2-12
2-13
2-14
-0.015
-0.010
-0.006
-0.009
-0.007 -0.010
-0.004
-0.005
+0.009
0.006
-0.009
-0.010
-0.021
-0.029
14x6
VB
VB
S-1
8Ø
S-1
10Ø
S-1
12Ø
S-3
10Ø
S-3
10Ø
S-3
10Ø
S-3
10Ø
S-1
8Ø
S-1
10Ø
S-1
10Ø
S-2
6Ø
E-1
6Ø
R-1
12Ø
E-2
14Ø
VB
10Ø UP TO
EF-1 ON ROOF
T-1
8Ø
VB-7
4-3
VB-1
VB-2
VB-6
4-1
4-2
NOTE:
SEE SHEET M4B FOR MECHANICAL
SYMBOLS SCHEDULE.
NOTE:
REFER TO ARCHITECTURAL RCP FOR
SUPPLY/DIFFUSER GRILLE PLACEMENT.
T
T
T
T
T
T
T
E-2
8Ø
T-1
8Ø
E-1
14Ø
T-2
6Ø
T-1
6Ø
T-2
6Ø
T-2
6Ø
T-1
6Ø
T-1
6Ø
T-2
6Ø
T-1
6Ø
T-2
6Ø
T-1
6Ø
Ø
Ø
Ø
Ø
6Ø
6Ø
8X8
GENERAL NOTES:
A. CONTRACTOR TO FIELD VERIFY EXISITING CONDITIONS.
B. MECHANICAL CONTRACTOR TO COORDINATE DEMOLITION
AND NEW CONSTRUCTION WITH OTHER TRADES.
M2B
HVAC NEW CONSTRUCTION
PHASE 2
TD
JH
P H
O E
N
X
N
D I A
N
M
E D
I C
A L
C
E N
T E
R
R E
M O
D E
L
P
H A
P H
O E
N I X
A
R I Z
O N
A
E M
E R
G E
N C
Y
D
E P
A R
T M
E N
T
4' 8'0 16'
NORTH
EMERGENCY DEPARTMENT HVAC NEW CONSTRUCTION PLAN
C C
E
A
S B
U I L T
T
REVISIONS
AS-BUILT SET 3-6-120
C O
N F
IR
M
S T
A T
U S
O F
H A
N D
S K
E T
C H
E D
M O
D
IF
IC
A
T
IO
N S
IN
N
E X
T S
H E
E T
01-1
01-2
01-3
01-4
Z1-1
Z1-2
Z1-3
Z1-4
Z2-1
Z2-2
Z2-3
Z2-4
Z3-1
Z3-2
Z3-3
Z3-4
Z3-5
Z3-6
4-1
4-2
2-1
4-3
2-2
4-4
4-5
2-3
2-4
2-5
2-6
1-1
1-2
1-31-4
1A-1
2-7
+0.009
+0.002
-0.012
0.002
0.006 -0.009
-0.012
-0.008
-0.011
0.002