Bldg. 2 - Chiller Plant Construction and Associated Projects Federal contract opportunity
Solicitation number
75F40122R00051
Issued by
Department of Health and Human Services Food and Drug Administration Office of Acquisition and Grant Services

About this file

This document package includes drawings, specifications, and responses to questions for a federal contract opportunity to construct a new chiller plant and perform associated projects at a Department of Health and Human Services facility. Key project elements include demolishing existing chillers and chilled water piping; installing new chillers, cooling towers, generators, and switchgear; and commissioning mechanical and electrical systems. The response date for proposals was extended to December 5, 2022. The scope involves multiple phases and options for different components. Pricing is required for unit rates for items such as trenching, undercutting, and daily mobilization, in addition to lump sums for base work and options. Subcontracting plans must meet minimum small business goals and be submitted within 24 hours of bidding.

View the file

Other files for this federal contract opportunity

Show all 18

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

75F40122R00051 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

JEFFERSON AR 72079

HFT-323

3900 NCTR ROAD

Howard Nesmith OAGS - Field Operations Branch

FDA/OO/OFBA/OAGS/DAP

11/26/2022

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION

NO. 0007

5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

08/08/2022

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Bldg. 2 - Chiller Plant Construction and Associated Projects

The purpose for this Amendment is to:

A. Provide Comprehensive List of Answers to ALL Post-Site Visit Questions B. Provide Revised Attachment J-14 HHS Subcontracting Plan Template C. Extend Proposal Due Date

SEE BELOW ATTACHMENT

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

WILLIAM H. NESMITH

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

This Amendment hereby incorporate the following:

A. Comprehensive List of Answers to ALL Post-Site Visit Questions

• Amber highlighted items were previous unanswered questions which are now answered B. Revised Attachment J-14 HHS Subcontracting Plan Template Uploaded (4 Pages) C. Amend the Proposal Due Date as Follows:

From: 11/08/2022 To: 12/05/2022

Light Blue Highlighted color is used as question separators

Chiller Plant - Post Site Visit Questions & Answers Question Answer

I wanted to clear something up wrt the main piece of new electrical gear on this project.

Is the 6000 Amp gear such that you are employing – On Generator Set Paralleling Controls or Paralleling Controls Only in a Separate Cabinet or Paralleling Switchgear. Which method is the intent on this project?

Keyed note 2 on drawing sheet E6.02 says:

"PROVIDE LOGIC AND SMART TYPE MOTOR OPERATED SWITCHES ALONG

WITH INTERLOCK PROTECTION FOR MAIN SWITCHES SO THAT IN THE

EVENT OF LOSS OF POWER FROM T1 OR T2, THE RESPECTIVE MAIN FEED

WILL OPEN AND THE APPROPRIATE GENERATOR BUS TIE WILL CLOSE

ALONG WITH THE STARTING OF GENERATORS TO PICK UP LOADS

AUTOMATICALLY."

Now, how this is accomplished is up to the bidder – the controls can be in the switchgear or in a separate cabinet – no method is preferred and the controls would need to tell the generators to start and synchronize (if they do it by outside controls or by self paralleling is up to the bidder, (our understanding is the most gen sets today will have on board synchronization) – but in any case, the generator / switchgear combination will have to coordinate in order to automatically accomplish keyed note 2. The Load bank would be available for manually testing each individual generator under load.

Please clarify the submittal requirements outlined in L-5 General Proposal Instructions, page 49. Is the intent to place Part I, II and III in the same document, but separately tabbed within to divide the parts? Or, is the intent to have three separate files, each dedicated to the respective part? (Part I – Technical, Part II- Past Performance, Part III-Price).

The intent is to have three seprate files dedicated to each part.

3 Please confirm that tabs/divider pages to facilitate organization will not count against the page limit.

Tabs, Divider, Index, Identification, etc. pages do not count against total page count unless information regarding the proposal is included on those pages.

Referencing the following RFP requirement in L-6 Submission of Offers, Part II, item d. “Any finalized, applicable Contractor Performance Assessment Reports (CPAR) from the CPARS.gov website may be provided in lieu of submitting to the Client the Sample Client Letter and Past Performance Questionnaire for completion. If a CPARS report is used the Offeror shall still complete the Relevance of the referenced contract to the current requirement in the PPEQ and shall compare and contrast their completed contracts described in the “Description of Work” addressed in Paragraph 1 of that same Questionnaire response required under Paragraph 1 of the Attachment J-11: Past Performance Evaluation Questionnaire.”

Please clarify the intent of this. For those offerors providing a CPARs in Questionnaire, is the intent to provide a narrative of the “Relevance to the Required Contract,” and address that relevance in the first paragraph when describing the description of work? Or, is the intent to complete Section 1.

Contractor Identification of the Past Performance Evaluation Questionnaire, but not sections 2 and 3? We assume the intent is the former but will need government confirmation.

The Offeror shall complete Section 1 of the questionniare.

It appears that qualifications for key personnel are requested in both the Part II – Technical proposal (item b.) and Part III Price Proposal (item g.). Please confirm this is the intent.

To prevent duplication provide the names of key personnel in the Part III Price Proposal. Part II required information remains unchanged.

Part III, Price Proposal indicates in regards to the Bid Guarantee to Submit original signed copies by mail to be received within 2 business days of solicitation close date.

Please identify the postal address that these should be sent to, as only the address for the electronic submission of the proposal is identified in the RFP

Mail the original signed document to:

Howard Nesmith, Contract Specialist (CS) 3900 NCTR Road HFT-320, Rm 424 Jefferson, AR 72079

With the design-bid-build nature of the procurement, typically qualified subcontractors will not receive vendor pricing for major components until the last minute. The Subcontracting Plan cannot be started until the bids are in and all proposals can be evaluated to assess qualifications and pricing. This will require the offeror to exclude many qualified bids that would otherwise benefit the government with a more cost-competitive price in an effort to complete and return this deliverable in time to meet the deadline. Because of this, many government entities instead either allow offerors to submit this within 24 hours of bid submission, or relegate this to a requirement for just the successful offeror. Therefore, with these circumstances, and the mutual interest of securing a best value, cost competitive pricing for the government, we respectfully request the government either allow this deliverable to be submitted within 24 hours of the proposal, or as a condition as the successful offeror.

The Government will allow the submittal within 24 hours of bid submission. Note that the HHS established small business subcontracting goals are identified as the minimum goals to be achieved in the resulting subcontracting plan for the contract. Plans that do not have a goal of meeting HHS goals may not be approved by the HHS SBA

PCR.

Please confirm whether it is acceptable for contractors to use their own format of the HHS Subcontracting Plan Template, as long as it meets the minimum requirements of FAR Subpart 19.7, and includes all requirements included in the HHS Subcontracting Template. This is a standard allowance by the federal government, and will enable offerors to complete the plan more efficiently and in a format that is easier for the government to review (as the nature of the template can result in lines moved, etc in awkward ways that will make it difficult to review).

The contractors can use their own format of the HHS Subcontracting Plan Template, as long as it meets the minimum requirements of FAR Subpart 19.7, and includes all requirements included in the HHS Subcontracting Template.

Where in the specs does it say the time frame for review of submittals by the Government? How long does the contractor have to resubmit a submittal if needed.

Government will try to responsd within 14 days with submittal reviews.

Allow 21 days if sequential review of submittals are needed for multiple submittals. Government will try to review each resubmittals within 14 days. No time extension or cost will be allowed for the time it takes to review submittals. Allow enough time to maintain construction schedule.

Is there any hazardous material report on the underground piping that has to be removed in the demolition phase of the chiller construction?

The district cooling pipe was installed around 2005 and does not contain hazardous materials.

11 Is there a preferred alarm or building controls company that the owner would like to use for the work?

Siemens - Powers of Arkansas for BMS, Fire Alarm is Johnson Controls/Siemens

12 Are there any restrictions on salvage of metal demolished on the project? There is no restrictions. Please keep record of recycled metal.

13 Is there a preferred waste disposal company that is working for NCTR? No preferred waste disposal company.

Can you issue the federal wage rates that are for this project?

https://sam.gov/wage-determination/AR20220036/3

See Updated Attachment J-9 Wage Decision dated September 16, 2022.

15 Please confirm that the million gallon large tanks have been drained and cleaned.

Both million gallon fuel oil tanks were drained and cleaned in 2003 - 2004. Documentation is not available.

Please confirm that the solar system has been drained and cleaned. If not, please provide a list of chemicals and concentrations added to the water.

This system was drained and decommissioned in 2000. No documentation https://sam.gov/wage-determination/AR20220036/3See%20Updated%20Attachment%20J-9%20Wage%20Decision%20dated%20September%2016,%202022.

https://sam.gov/wage-determination/AR20220036/3See%20Updated%20Attachment%20J-9%20Wage%20Decision%20dated%20September%2016,%202022.

https://sam.gov/wage-determination/AR20220036/3See%20Updated%20Attachment%20J-9%20Wage%20Decision%20dated%20September%2016,%202022.

https://sam.gov/wage-determination/AR20220036/3See%20Updated%20Attachment%20J-9%20Wage%20Decision%20dated%20September%2016,%202022.

17 Please provide a list of chemicals and concentrations added to chilled water systems and the cooling tower water systems

Chem-Aqua Chemical numbers

- 31855 Tower Corrosion Inhibitor

- 40215 Tower/Chilled Water Non-Oxidizing Biocide

- MB38 Tower Oxidizing Biocide -52885 Closed Loop Inhibitor

Chilled Water 50-100 ppb of PTSA (added automatically buy fluorometer) 50-100 ppm of Molydbenum 240 ppm of Isothiazoline (added by 40215 weekly)

Towers

100-200 ppb of PTSA (Added automatically from 31855) 240 ppm Isothiazoline (added by 40215 weekly) 1-2 ppm Chlorine (added 3x weekly from MB38)

Building 53A MCC Breaker Maintenance Project Manual, Section 01 1000 Summary of Work, Paragraph 1.03; Please confirm the Mechanical Contractor is not required to be the Prime Contractor.

Mechanical Contractor is not required to be the Prime Contractor.

Building 6 Demolition Project Manual, Section 01 91 13 General Commissioning Requirements; Please define which system are to be commissioned.

There is no system to commisioned as part of Bldg. 6 Demo.

Building 6 Demolition Project Manual, Section 02 4100 Demolition, Paragraph 3.01.C; indicates that the foundations and footings are to be removed a minimum of 3 feet below finished grade. Please confirm that foundations and footing are to be completely removed.

Foundations and footing shall be removed completely.

Building 2 Campus Chiller Plant Project Manual and Building 53A MMC Breaker Maintenance Project Manual; These project manuals do not contain Section 01 0913 General Commissioning Requirements. Please confirm no

Commissioning of equipment is required. Please find attached J-1d Bldg.

2_Specification_Commissionings (26 Pages), General Commissioning Specification, Commissioning of Plumbing System, Commissioning of HVAC System, & Commissioning Of Electrical Systems.

equipment/systems with respect to these scopes of work are to be commissioned.

Building 2 Campus Chiller Plant, Drawing MD2.07 indicates the tanks in room 22 are waste drain tanks; were these tanks converted to solar hot water tanks as shown on Drawing MD2.04? If not, please provide the installation drawings for the solar hot water tanks.

Those two tanks were solar hot water tanks then they were converted into waste drain tanks.

Building 2 Campus Chiller Plant, Drawing MD2.07, Section C-C and Section D-D indicate a concrete floor/roof deck above the tanks. If this is the correct, it may not be possible to remove the tanks through the metal plated roof as discussed at the site visit. Please provide the building structural drawings for this area of Building 5.

There is metal plates exactly above those of two tanks. Metal plates can be removed with help of crane and both the tanks can be removed through the opening of metal plates with help of crane. There is no drawing providing details of roof over those of two tanks.

Building 2 Campus Chiller Plant, Drawing MS1.01, clouded note near keyed note 6 indicates a new 10” steam valve is to be installed in the existing steam piping during the campus wide steam outage in April 2022. Please confirm if this valve was installed during the April 2022 outage. If not, please provide the expected campus wide steam outage date.

New 10" steam valve need to be installed. NCTR has a center wide steam outage every spring and fall, usually in April and September on a Saturday for maintenance. The replacement of this valve shall be done on either of these scheduled shutdowns.

If all piping/chiller removal options are not awarded, please provide a statement of work indicating how the new piping is to be terminated at the existing building chilled water systems.

In case of options of removal of existing chiller and chilled water piping inside and near the existing building are not awarded, connect new piping as shown on the plans. If necessary, remove enough of the existing piping to make the new connections. Cap existing chilled water piping and leave them abandon in place if they are not hindering the path of new piping as shown in plans.

Please confirm that the contractor is to provide only the fuel required for testing the new generators and that filling the fuel tanks will be by others.

NCTR would expect that the equipment would be turned over fueled and ready to run.

27 Please provide the delivery date of the Government furnished equipment (chillers, cooling towers, etc.)

Purchase order shall be placed once project is awarded. The Contractor and the Manufacturer shall set the delivery date. The contractor shall receive and install the machine.

Will pre-construction chilled water flow testing/measurement at the point of connection between the building chillers and the campus distribution piping be required?

NO

Will post-construction chilled water flow testing and balance at the point of connection between the building chilled water system and the campus distribution piping be required?

NO

Sheet E2.01- There are (2) 400amp disconnects shown at the cooling tower (same for Phase 2). Note says “verify provided with unit”…. Will these be supplied with the cooling tower? Or will the electrical contractor be responsible for these?

As the drawings currently indicate, the contractor should be prepared to provide 400 amp disconnects (the same for phase 2) – NEMA 3R stainless steel to match controls box.

Bld. 53 Demo sheet E6.04- Note says to “ remove dashed items within switchgear enclosure and turn over to NCTR for disposition”. The breakers are dashed, are they to be removed from the gear and turned over to NCTR? Or remain in place? If breakers are to be removed, what is the preferred method of covering the openings left once the breakers are removed?

The equipment referred to shall be abandoned in place. Contractor shall install permanent label on equipment stating that it is inactive and lock out.

Bld. 53 Sheet E2.06 shows the new generator and associated electrical gear in the area where the existing generators sit now. Please provide thoughts on how to maintain generator back up to the building while the new construction takes place

New generator shal be installed across the street to maintain the back up power requirement.

Please Clarify- Will ALL underground conduits need to be concrete encased? Including branch circuits, communications, etc…

Main circuitry, medium voltage and circuits serving distribution equipment

What is to happen with the existing generators when they are removed from Bld. 26, and Bld. 53? Are they to be turned over to the owner? If so, will the contractor be responsible for relocating them to a storage space on the facility? Please advise

NCTR will retain generators, please have them set in rally yard just North of Bldg 85.

35 Who is responsible for the fuel in the new generators? Contractor will be responsible.

36 Will there be generator load bank testing required? Is this paid for by the owner, with the purchase of the generators?

NCTR expects this will be performed by the installing contractor as proof of function. NCTR will order the generators and they will be installed by the supplying contractor.

37 Are the pad mount transformers at Buildings 26, and 13 to remain in place? If not, please elaborate. These are to remain in place.

Please clarify- Is the work shown on Sheets ED1.04 and E2.08 to be included in OPTION #6? These sheets are labeled “Bld. 5 roof”, but the work is associated with the solar plant demo, which is OPTION #5. Please advise

The work shown on Sheets ED1.04 and E2.08 to be included in OPTION #6. The work has nothing to do with solar plant demo.

Will the new 13.8kv Vista Switches need to be connected to the fiber loop that the existing switches have throughout the campus? If so, please provide conduit path, fiber type, software required etc…

Contractor shall bid this work as an additive alternate to the base bid.

There is no price request in original solicitation for new 13.8kv Vista Switches and related conduit and wiring. But bidder can submit the price as separate document along with their base bid.

Bld 5 Basement Lights- Note #4 Calls for one for one replacement of light fixtures, it also states approximately NINE, there are NINE fixtures in the walkway heading down to the basement, but there are several more in the basement tank area, are ALL of the fixtures to replace? Or only the NINE in the walkway?

Only the NINE in the walkway. Additional work may be addressed later on through change order

In regards to the existing generators being removed at Buildings 26 and 53, will NCTR be removing the fuel? Or is this the contractors responsibility?

It is the contractors responsibility

Will government require a dedicated on-site Quality Control Manager (QCM) and Site Safety Health Officer (SSHO) during construction?

It is the contractor decision.

43 Since the Trane chillers are being purchased by the government, we have several questions:

a. Have they been ordered? No

b. In order to provide a detailed schedule for the RFP what is the current lead time for the Trane chillers? No

c. Can the government provide preliminary submittal data for bidding purposes? Refer to "J-1a. Bldg. 2_Design Analysis.pdf" in DVD so provided

d. As it relates to the Factory Witness Testing of the Trane chillers, should the Prime contractor budget to attend the Factory Witness Testing?

No contractors at all will be required or invited to the testing by the gov.

e. Based on Drawing M6.01 (Chillers-Water Cooled Schedule) Note # 4 – “The contractor will be responsible for the full warranty of the chillers” and Specification Section (23 64 16 1.07-B) ‘Chiller manufacturer shall provide full ten (10) year parts, labor and refrigerant warranty’ and Specification Section (23 64 16 3.03) Manufacturers Field Services to include monitoring and maintenance services. This would result in the construction contract between the Government and Contractor to remain open for ten (10) years. Not to mention the contractor would need to have a bond open for ten (10) years, builders risk policy open for ten (10) years, etc. The Government is providing Trane with a Purchase Order for the chillers, extended warranty, maintenance and monitoring services not the contractor. The contractor can manage the one (1) year warranty but will find it difficult to manage the other nine (9) years as listed above. We formally request this be removed from spec.

The purchase of the chillers by the government will come with a warranty and startup. The standard warranty, as specified, will be sufficient. The spec will not be modified.

The construction contractor’s standard one year warranty is acceptable.

Extended warranties purchased by the government will be held between the government and the chiller manufacturer.”

f. Typically, the chiller refrigerant monitor and sample gas kit(s) are provided by the chiller manufacturer. Will this be Government furnished contractor installed?

Those items listed should be provided by the controls contractor since they control exhaust fans, louvers etc…

Are any other Major Assets (cooling towers, pumps, generators etc.) being purchased by the government other than the Trane Water Cooled Chillers?

Cooling towers and generators shall be purchased by government.

It is mentioned in several locations in the specification to ensure the roof warranty is not voided. Please provide contact information for the roof warranty holders.

Referring to new roof of Bldg. 5D and Bldg. 53s, NOACON construction is roof warranty holder.

Specification section (21 05 00 1.08-B) Fire Suppression – Please clarify ‘Correct defective work within a five (5) year period after the Date of Substantial Completion (DOSC). All defective work should have been completed prior to the issuance of the DOSC.

All defective work should have been completed prior to the issuance of the DOSC.

Specification section (21 11 00 1.09-B) Fire Suppression Piping

– Please clarify ‘Correct defective work within a five (5) year period after the Date of Substantial Completion. All defective work should have been completed prior to the issuance of the

DOSC

All defective work should have been completed prior to the issuance of the DOSC.

Specification section (23 09 23 1.07-B) Direct-Digital Control System for HVAC (DDC) - Please confirm that all DDC manufacturers will be required to provide five (5) year warranty for field programmable micro-processor based units. Is the DDC manufacturer to assume parts only?

Parts only for 5 years, standard 1 year warranty on entirety of installation

49 Does the FDA Jefferson Labs have a proprietary BAS controls contractor? If so, please provide contact information. Siemens- Powers of Arkansas- Ron McCarty 501-374-5420

Specification section (23 65 00 2.02-O) - Please clarify ‘Mechanical equipment shall be designed for five (5) year maintenance intervals’Will the contractor be responsible for filling the new fuel tanks or will the government be filling?

The contractor be responsible for filling the new fuel tanks

51 Will the government be providing a third-party Commissioning Agent? Refer to commissioning spec ( question # 21)

52 Specification section (26 32 36 1.5-D & 3.02-C) - Please clarify ‘’A longer warranty period is available to be purchased”

A 2 year warranty for the resistive load bank is acceptable. Please omit "’A longer warranty period is available to be purchased”.

Specification section (27 10 00 1.08-B) - Structured Cabling – Please clarify “Correct defective work within a two (2) year period after the Date of Substantial Completion (DOSC). All defective work should have been completed prior to the issuance of the DOSC.

Agree that any obvious defective issues would be found and corrected by date of substantial completion (DOSC), however, especially on structured cabling, some cables may go intermittent after DOSC due to pinching, etc. and this covers undiscovered issues or things that go wrong after DOSC up to 2 years.

Specification section (31 31 16 1.04-B) – Termite Control – Please confirm that the Termite warranty and the $25,000 repair threshold will be in the government’s name.

YES

Specification section (12 24 00 1.06-B) – Window Shades – Please confirm that government is requesting 25-year warranty for chain, hardware, fabric, and shadecloth.

YES

Specification section (07 52 00 1.09-C) – Roofing – Please confirm that the DIV 07 subcontractor will repair and replace components of the roofing system that fail in materials or workmanship within two (2) years from the date of Substantial Completion. The prime contractor will coordinate during the first year and the government will coordinate during the second year.

The prime contractor will coordinate during the first year and second year.

Specification section (02 65 00 4.02-A) – Underground Storage Tanks – Confirming that the existing fuel will be pumped or removed by the government? Does the government have estimated fuel-emulsions that can be used for bidding purposes?

There is no underground fuel storage tanks in this project.

58 Please confirm that delegated engineering for vibration and seismic will be required for this project. That is correct. Refer to spec section 23-0548.

Specification section (23 11 13 1.04-A) – Fuel Oil Piping – Please confirm that the contractor will be responsible for the final design of the fuel oil system.

Contractor will be responsible for the final design of the fuel oil system.

Specification section (23 11 13 2.01-A.3) – Fuel Oil Piping – Please clarify: ‘Provide certificate of compliance from Authority Having Jurisdiction (AHJ) indicating approval installation of fuel oil system. The AHJ is typically the government – please advise.

Certificate of compliance shall be obtained from state government.

There is a spec section 02 65 00 for underground storage tank removal. Are there any existing underground fuel tanks needing to be removed?

There is no underground fuel storage tanks in this project.

Drawing P5.03 tank detail shows a fuel polisher, but P1.01 does not show anything. Also, nothing about it in Section 23 11 13.

Fuel Polisher:

Simplex Smart Filter Model SF10

10 GPM

600 GPH

Tank Size 12,000-20,000 Gallons 25% Cycle Time in Hours 5-8.3 33% Cycle Time in Hours 6.6-11

0.75 HP

115/230-1-60V, 11 0/5.5A

2.0 NPT Pipe Size

66.25” W x 74” H x 42”D https://www.simplexdirect.com/Product.aspx?ProdID=29

Solicitation Page 51; Part II - Recent and Relevant Past Performance Information; Paragraph d); CPARS: We understand that if a CPARS evaluation exists, we may submit it in the proposal (in lieu of submitting a PPQ to the client for completion). Do the submitted CPARS evaluations count against the 25 page limit for the Technical Proposal?

Past Performance is not part of the Technical Proposal.

Solicitation Page 52; Part III - Price Proposal Instructions;

Paragraph h); Daily Mobilization Rate: Please confirm this is the Prime Contractor's rate ONLY and not that of the subcontractors.

This requirement is for a complete Daily Mobilization Rate for both Prime Contractor and Subcontractors.

Solicitation Page 52; Part III - Price Proposal Instructions;

Paragraph i); Small Business Subcontracting Plan: As pricing information tends to come in last minute, would the Government allow the Offeror to submit the finalized Small Business Subcontracting Plan the day after the proposal is due?

The Government will allow the submittal within 24 hours of bid submission.

Solicitation Page 52; Part III - Price Proposal Instructions;

Paragraph i); Small Business Subcontracting Plan: Attachment J-14: HHS Subcontracting Plan is not editable in its current state. Would the Government please provide an editable version of the Small Business Subcontracting Plan, or allow the Offeror to submit their own Plan (as long as it complies with FAR Clause 52.219(d))?

The Government will provide an editable Form. In addition the contractors can use their own format of the HHS Subcontracting Plan Template, as long as it meets the minimum requirements of FAR Subpart 19.7, and includes all requirements included in the HHS Subcontracting Template.

Revised Attachment J-14 HHS Subcontracting Plan Template Uploaded

The new generator for Building 53 is shown in the same location as the existing generator that needs to remain in service during construction. Please advise.

New generator shal be installed across the street to maintain the back up power requirement.

CLIN 0006 - Which pricing category does the demolition of the cooling tower south of building 5 belong? The other chiller demolitions include the associated cooling towers but 5B does not.

Please include cost of demolition of cooling tower on south side of Blsfg.

5B in option 5

CLIN 0001 - Demolition and installation of campus chilled water lines except lines over roof of Bldg. 5B and 5C. This item description also appears in CLIN 0002. Where does it belong?

CLIN 0001 require cost for demolition and installation of campus chilled water lines except lines over roof of Bldg. 5B and 5C in phase one (refer to drwaign sheet MD1.01, MS1.01).

CLIN 0002 require cost for demolition and installation of campus chilled water lines except lines over roof of Bldg. 5B and 5C in phase two (refer to MD 1.03 and MS 1.02) .

70 Have the fuel tanks that are to be removed been decontaminated? see response to #15

Section L-6 part III.d on PDF page 50 of the main solicitation states, “Bid Guarantee. Submit a bid guarantee in the form of a firm commitment as required by Section L-4 and Section I FAR Clause 52.228-1. Submit original signed copies by mail to be received within 2 business days of solicitation close date.”

Please confirm that the government is requesting hard copies of the bid guarantee to be submitted. If hard copies of the bid guarantee are required, will the government consider accepting bid guarantees that are postmarked prior to the proposal due date?

Yes - Mail the original signed document to:

Howard Nesmith, Contract Specialist (CS) 3900 NCTR Road HFT-320, Rm 424 Jefferson, AR 72079 Yes - Documents may be postmarked prior to the proposed due date.

On sheets E6.08 and E6.02 where the primary cables are called out, there is no mention of a ground wire to be installed with the medium voltage cables, Will a ground be required? If so, please provide conductor size, etc

Contractor shall pull separate ground in the cable. Size per NEC.

73 Have the big tanks been cleaned and ready for demolition? see response to #15

74 Will buildings 6 & 13 require mold remediation before demolition?

There are currently no EPA regulations or standards for airborne mold contaminants. Unlike asbestos and lead paint, mold is not a regulated hazardous material that requires disposal in a certified hazardous landfill.

Mold spoors pose a hazard to building occupants with specific mold allergies. The building can be demolished and disposed of in a standard construction landfill just like any other building without removing the mold in advance.

If the contractor’s means and methods for removal involves sending workers in the building prior to or during demolition, those workers must be given proper personal protective gear to meet all OSHA guidelines for worker safety.

Building 26 project scope calls for the direct replacement of an existing 1,000kW Caterpillar generator with a like kind. Inside the existing generator enclosure, there is an aftermarket Cutler Hammer breaker distribution cabinet. This is not a Caterpillar provided breaker line up. Please see attached photo. This cabinet contains a 2,000A breaker labeled “generator breaker”, a 1,600A breaker labeled “ARL Breaker”, and a smaller breaker at the bottom (amperage not listed), labeled “building 50 breaker”. This distribution cabinet will not be included in our generator package. We request that this be included in an RFI to the design engineer to address how they would like to handle this. It is our opinion that this existing breaker line up should be reproduced in a Nema 3R enclosure and placed outside of the new generator enclosure between the new generator and whatever loads it will be serving. It is our intention to provide a 1,000kW replacement generator with one (1) 1,600A gen mounted circuit breaker, which is the maximum amperage output capability for a 1,000kW generator when configured at 480V. If multiple loads are to be fed from this 1,600A gen mounted breaker, there must be some type of distribution between our generator output breaker and those downstream loads. This is not something we provide, but should be included in the installing electrical contractor’s scope of work. We are requesting the engineer to recommend how they would like for this additional distribution to be configured by the installing contractor based on the knowledge that it is our intention to provide a single 1,600A gen mounted circuit breaker.

Keyed note 3 says to “REPLACE EXISTING 1000 KW DIESEL GENERATOR

WITH NEW. MATCH GENERATOR RATING, DIESEL FUEL CAPACITY, AND

ANY OTHER SPECIAL EQUIPMENT PROVIDED WITH EXISTING

GENARATOR."

Contractor should replace the existing distribution panel with new NEMA 3R 2,000 amp distribution panel fitted with 1,600 amp breaker for Bldg. 26 and matching unknown breaker rating noted in RFI listed as “bldg. 50 breaker”. The bldg. 50 breaker is required.

Building 2 one line drawing E6.02 calls out a withstand rating of 100kAIC on the new 6,000A switchgear. Based on the size of the utility transformers, we are concluding this switchgear is to be “open transition”. Please confirm open transition is the intent of the design, or clarify if otherwise.

Correct – Open transition switches were expected. The system as noted on the sheet should be able to open a transformer feed in the event of a failure, start generator(s), synchronize, and connect to bus all automatically. The load bank would be used to manually test the generators.

Please clarify on Bld2 Plan sheet E6.01 if the 12 Strand Fiber is to be MultiMode and not singlemode like what is being installed from BLD 14. If Multimode please clarify what OM factor is being requested. OM1, OM2, OM3,OM4

Multi mode fiber is used within the building but single mode fiber is used between the buildings. 27-1000-

2.04 (2) calls out OM3 in the specs. but in any case – coordinate all work with FDA IT department (Donald Poore 870 543-7595)

Please Clarify on Bld2 Plan Sheet E6.01 if the (2) 12 Strand Singlemode Fiber going to BLD 14 are to be considered the (2) 24 Strand Singlemode Fibers listed on plans sheet E6.08 note 1.

Yes, single mode fiber is used to connect to bld. 14.

Please Clarify on Bld2 Plan Sheet E3.01 in the Minimum per data drop location is 4 Cat6A Data Cables per location. Plans Sheet E6.01 General Note 6. State a Minimum of 2 cable per location

In places where only a data symbol is noted then the minimum of 2 drops is sufficient, and in places where only the communications symbol are used then also the minimum of 2 is sufficient. In places with the combination data /voice then provide minimum of 4 drops.

On plan page M1.01 the design team did not size or show the pipe route for the chiller refrigerant relief piping for 2-CH-5.

Can you have them give us direction for this please?

Provide a maximum 15’-0” 1.25” relief line off the evaporator relief valve and a maximum 15’-0” 0.75” relief line off the condenser relief valve and combine into a 2” common relief. Run the 2” relief to the plan west directly below the overhead 30” CWR and terminate in a similar manner to 2- CH-1 and 2-CH2 relief vents.

81 CLIN 0001, Base Bid - 5,000 cubic feet underground concrete.

What is this referring to?

Sentence "Removal of 5,000 cubic feet underground concrete and back filling." is mentioned in CLIN 0001 as safety factor to address any unforeseen condition.

Is there an undercut allowance? Soil report references a recommended undercut, but cannot find anything specifically telling the contractor what to do.

No allowance shall be provided. But bidder shall provide trench unit price per cubic yard in place as separate line item in their cost proposal.

83 The brick & water table cast stone are in the spec. What product is desired for the cast stone masonry veneer?

Stone Masonry Veneer is per 04 7200 Cast Stone Masonry based on RockCast profiles and colors.

84 What brick is specified for the building 6/26 canopy? Brick per spec is 04 2000 Unit Masonry ACME Perla East Plant Blend.

Question 66 indicates the government will provide an editable form for the HHS Subcontracting Plan. This was not posted with the Amendment 04 documents. We respectfully request a copy of this form.

Revised Attachment J-14 HHS Subcontracting Plan Template Uploaded

Specification section 10 7119 provides information for removable flood barriers. There is no information on where these would be installed or how many are to be provided on the project. We also cannot locate these anywhere on the construction drawings. Please clarify where the removable flood barriers are to be provided and where they are indicated in the documents.“

The door schedule on A6.03 has added notes for 10” removable dams.

Those are to be the 10 7119.16 Removable Flood Barriers products.

We respectfully request a deadline extension of three weeks from the time all questions are answered, as bidders are unable to move forward on certain elements of their approach until receiving the RFI responses (which will, in turn require coordination with multiple parties and development of a best value technical approach and competitive pricing)

Response Date has been extended and is subject to change. The Response Date as posted in sam.gov will be the most current Response Date.

We understand a separate fiber line is required to connect Building 2 BMS to the campus BMS. Please provide the origination point, the routing and the fiber requirement for the BMS data fiber.

The BMS campus system fiber is shown to be in building 14 room1039 (verify with FDA) Follow same routing shown on E6.08 keyed note 1. In any case, coordinate all work with NCTR O&M Dept. (David Strain). Also, NCTR O&M dept plan change SM fiber to MM in the next few months. See attachment "for #88.pdf"

In the J-2b. Bldg. 6_Demo_Drawing set, sheet S-102, detail #3 and detail #5 indicate a CMU veneer around the support columns for the covered walkway. We do not see that this CMU product is specified anywhere. Please clarify the desired CMU veneer product to be used around these support columns.

Located in spec 04 2000 Unit Masonry part 2.01-A.

In the J-1b. Bldg. 2_Drawing set, sheet A2.01, all four details show a Stone Masonry Veneer around the base of the building. We do not see that this Stone Masonry Veneer product is specified anywhere. Please clarify the desired Stone

Stone Masonry Veneer is per 04 7200 Cast Stone Masonry based on RockCast profiles and colors.

Masonry Veneer product to be used around these support columns.

Drawing set J-4 Big Tanks and Overhead Lines Foundation sheet BKC-F-808-1 indicates two existing 25,000 barrel #6 fuel oil tanks to be removed. What is the metal thickness of the two existing 25,000 barrel #6 fuel oil tanks either in mils or inches?

3/8"

Are there any utility tap fees anticipated to be required for the new water and sanitary sewer lines? It is our understanding that the campus is on it’s own water and sewer system so we believe there will not be any required.

NCTR is self-contained and no permits will be required for connection.

Sheet CS1.03 shows “gravel paving” around the new cooling towers but there is no detail provided for gravel paving. Please provide clarification on the thickness and type of gravel required in this area.

Class 7 stone compacted to 8”

The Geotech report suggests there may need undercut below the building slab, and it may be needed under the paving structure. Would the owner add a unit price bid item for undercut of unsuitable material and replacement with select fill or BAB?

Bidder shall provide non trench unit price per cubic yard in place as separate line item in their cost proposal.

Sheet C5.01 detail 8 for the drainage swale doesn’t provide a thickness for the concrete. Please provide a detail indicating the thickness of this concrete.

6" thickness.

96 Please confirm that all Commissioning Services will be provided by the Government and supported by the contractor. Refer to #21 for response.

Please confirm that the Government provided 1000 KW and 2000 KW generators will be provided with a sub-base fuel tank (belly tank).

1000 KW and 2000 KW generators will be provided with a sub-base fuel tank (belly tank).

Is it acceptable to provide new breakers under option 2, CLIN 0003 in lieu of refurbishing the existing switchgear breakers to minimize power shutdowns during construction in that scope?

Provide new breakers under option 2, CLIN 0003 in lieu of refurbishing the existing switchgear breakers to minimize power shutdowns during construction in that scope.