Solicitation 75F40122R00051.pdf
PDF 1 MB Posted
- Attached to
- Bldg. 2 - Chiller Plant Construction and Associated Projects Federal contract opportunity
- Solicitation number
- 75F40122R00051
About this file
This is a pre-solicitation notice for an upcoming solicitation seeking a single contractor to complete the overall Bldg. 2 - Chiller Plant Construction and Associated Projects requirement. Key details include that the project involves construction at the Jefferson Laboratory Complex including building a new Bldg. 2, installing chillers, cooling towers, generators and demolishing and replacing infrastructure. Interested vendors must submit information by August 26th to attend an optional pre-proposal site visit on August 29th. The solicitation is expected to be awarded to a full and open competition with a projected value over $10,000,000.
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLICITATION, OFFER,
AND AWARD
2. TYPE OF SOLICITATION
6. PROJECT NO. 4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO.
PAGE OF PAGES
7. ISSUED BY CODE 8. ADDRESS OFFER TO
SOLICITATION
(Construction, Alteration, or Repair)
1. SOLICITATION NO. 3. DATE ISSUED
IMPORTANT -- The "offer" section on the reverse must be fully completed by offeror.
9.
INFORMATION
a. NAME b. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder."
CALL:
FOR
SEALED BID (IFB)
NEGOTIATED (RFP)
FDA/OO/OFBA/OAGS/DAP
OAGS - Field Operations Branch
3900 NCTR ROAD
JEFFERSON AR 72079
HFT-323
Howard.Nesmith@fda.hhs.gov
WILLIAM NESMITH 870-543-7459
1x 08/08/2022
75F40122R00051
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date)
Program/Project Title: Bldg. 2 - Chiller Plant Construction and Associated Projects
This requirement is being competed unrestricted and made available to Full and Open competition, meaning any qualified vendor regardless of size status may submit a proposal.
Project magnitude is more than $10,000,000.00.
IMPORTANT DATES & INFORMATION
ALL VISITORS MUST BE PRE-APPROVED
- Pre-proposal Conference/Site Visit August 29, 2022
- All firms interested in attending the pre-proposal conference/site visit must submit the following information by email to Howard.Nesmith@fda.hhs.gov no later than 2:00 pm Central Time, August 26, 2022:
1. Full name and telephone number of individual(s) attending;;
2. Company name, address, and telephone number;.
3. Certification of Vaccination Form.
- It is MANDATORY to wear a well-fitting face covering/mask on campus while indoors, regardless of risk factors or vaccination status.
Continued ...
11. The Contractor shall begin performance
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
award, notice to proceed. The performance period is mandatory negotiable. (See ________________________________________________.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and is not required.is, b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
d. Offers providing less than
12b. CALENDAR DAYSYES NO
(If "YES", indicate within how many calendar days after award in Item 12b.)
10 1095 calendar days and complete it within ________________ ________________ calendar days after receiving
FAR 52.211.10
10/11/2022
NSN 7540-01-155-3212
x x x x copies to perform the work required are due at the place specified in Item 8 by _____________ ___________________ (hour) local time calendar days for Government acceptance after the date offers are due will not be considered and will be rejected . _________________
STANDARD FORM 1442 (Rev. 4-85)
Prescribed by GSA
FAR(48 CFR) 53.236-1(d)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ____________________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in item 13d. Failure to insert any number means the offeror accepts the minimum in item 13d.)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NO. (Include area code)
16. REMITTANCE ADDRESS (Include only if different than item 14.)
CODE FACILITY CODE
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGEMENT OF AMENDMENTS
OFFER (Must be fully completed by offeror)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this document and return (Contractor is not required to sign this document.)
Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award.
No further contractual document is necessary.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31a. NAME OF CONTRACTING OFFICER (Type or print)
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. DATE
BY
2PAGE OF
FDA/OO/OFBA/OAGS/DAP
OAGS - Field Operations Branch
3900 NCTR ROAD
JEFFERSON AR 72079
HFT-323
REGINA R. WILLIAMS
28. NEGOTIATED AGREEMENT 29. AWARD
Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, copies to issuing office.)
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
STANDARD FORM 1442 (REV. 4-85) BACK
Continued...
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
3 58
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
75F40122R00051
- If you are immunocompromised or at high risk for severe illness wear a face covering/mask that provides you with greater protection.
- COVID testing is required for all visitors that are not vaccinated or have not provided their vaccination information.
- Contractors and visitors must show a completed/signed Certification of
Vaccination form (attached) or proof of a negative COVID-19 test result within the last 72 hours.
- All visitors are required to report to building #21 and present a valid government issued photo ID. The visitor(s) must sign the visitor log book and be screened via the metal detector.
- All the visitor?s possessions will also be screened. Food items, video/audio tapes, computer equipment, disks and other magnetic media are not affected by the x-ray machine and will be scanned.
- The guards will then issue a visitor badge.
- Visitors will turn in their visitor badge and sign-out on the log book upon exiting building #21.
Access to the facility shall not be granted if the visitor(s) refuses to cooperate with these security measures.
Site Visit
An organized pre-proposal conference/site visit has been scheduled for:
Day/Date: August 29, 2022
Time: 9:00 pm Central Time
Jefferson Laboratory Complex (NCTR)
3900 NCTR Road
Jefferson, AR, 72079
All firms interested in attending the pre-proposal conference/site visit must submit the following information by email to Howard.Nesmith@fda.hhs.gov no later than 2:00 pm Central Time, August 26, 2022:
1. Full name and telephone number of individual(s) attending;
2. Company name, address, and telephone number;
3. Certification of Vaccination Form.
Attachment J-13 Certification of Vaccination for contractor and visitor certification of vaccination attestation at all FDA facilities. All on-site contractors and visitors will be required to have a completed Certification of
Vaccination form on their person when entering a federal facility. If a contractor or visitor is not fully vaccinated, they must have in their possession documentation of a negative COVID-19 test result within the last 72 hours to show the Agency.
All attendees will be required to sign in at the security gate and present a driver?s license or other government issued identification in exchange for a
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO.
(A)
SUPPLIES/SERVICES
(B)
QUANTITY
(C)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
NAME OF OFFEROR OR CONTRACTOR
4 58
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
75F40122R00051 visitor?s identification card. All attendees will require escort to the conference room.
It is conceivable the Pre-proposal Conference/Site Visit will take several hours and cross over typical lunch hours. You are welcome to bring water for hydration. There are drink and snack vending machines located throughout the site and an on-site cafeteria featuring hot-line and grill. The closest off-site (gas station / food) is6 miles away.
DUE TO ELECTRONIC MEDIA ONLINE UPLOAD, DOWNLOAD, STORAGE, AND DELIVERY LIMITATIONS, THE BELOW LISTED DOCUMENTS WILL BE PROVIDED UPON EMAIL REQUEST SENT TO CONTRACT
SPECIALIST HOWARD.NESMITH@FDA.HHS CONTAINING THE FOLLOWING INFORMATION:
- RECIPIENTS NAME:
- RECIPIENTS EMAIL ADDRESS:
- RECIPIENTS PHONE NUMBER:
COMPANY?S NAME:
- STREET ADDRESS: (NO P. O. BOX)
- CITY:
- STATE:
- ZIP CODE:
DOCUMENTS WILL BE PROVIDED WITHIN 24 BUSINESS HOURS ON CD/DVD MEDIA DELIVERED VIA
UNITED PARCEL SERVICE (UPS) NEXT DAY AIR, SIGNATURE REQUIRED, WITH TRACKING
INFORMATION PROVIDED
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
FDA Solicitation No.: 75F40122R00051
Page | 3
Table of Contents
PART I- THE SCHEDULE 4
SECTION B- SUPPLIES OR SERVICES AND PRICES/COSTS 4
SECTION C- DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 8
SECTION D- PACKAGING AND MARKING 8
SECTION E- INSPECTION AND ACCEPTANCE 8
SECTION F- DELIVERIES OR PERFORMANCE 9
SECTION G- CONTRACT ADMINISTRATION DATA 11
SECTION H- SPECIAL CONTRACT REQUIREMENT 15
PART II- CONTRACT CLAUSES 37
SECTION I- CONTRACT CLAUSES 37
PART III- LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS 42
SECTION J- LIST OF ATTACHMENTS 42
PART IV- REPRESENTATION AND INSTRUCTIONS 43
SECTION K- REPRESENTATIONS, CERTIFICATIONS AND OTHER
STATEMENTS OF OFFERORS OR RESPONDENTS 43
SECTION L- INSTRUCTIONS, CONDITIONS AND NOTICES TO OFFERORS
OR RESPONDENTS 47
SECTION M- EVALUATION FACTORS FOR AWARD 55
Page | 4
PART I- THE SCHEDULE
SECTION B- SUPPLIES OR SERVICES AND PRICES/COSTS
B-1 Purpose
The U.S. Food and Drug Administration (FDA), National Center for Toxicological Research (NCTR) requires Bldg. 2 - Chiller Plant Construction and Associated Projects.
B-2 Compensation – Fixed Price Schedule
Contract Line Item
No.
Description Quantity Unit Price
Base Bid – During phase one of construction, following work shall be carried out
• Coordinate delivery schedule with vendor, unload and store government purchased four chillers (of 1500 ton each), one chiller (of 250 ton), two cooling towers (of 7664 GPM), one cooling tower (of 640 GPM), four generators (of 1500KW), one generator (of 2000 KW) and one generator (of 1000 kW).
• Removal of foundation of two big tanks and pipe stand on south side of two big tanks.
• Construction of new Bldg. 2.
• Installation of two chillers (of 1500 ton each), one chiller (of 250 ton), one cooling tower (of 7664 GPM) and one cooling tower (of 640 GPM) in Bldg. 2.
• Installation of four generators (of 1500 KW each) in Bldg. 2.
• Demolition and installation of campus chilled water lines except lines over roof of Bldg. 5B and 5C.
• Installation of two new chilled water pumps in mezzanine of Bldg. 14.
• Removal of 5,000 cubic feet underground concrete and back filling.
1 Job $_______
During phase two following work shall be performed
Page | 5
Option 1 –
• Installation of two chillers (of 1500 ton each) and one cooling tower (of 7664 GPM) in Bldg. 2.
• Demolition and installation of campus chilled water lines except lines over roof of
• Installation of new generator (of 1000 KW at new location near Bldg. 26) as replacement of existing generator serving Bldg. 26 located on south side of Bldg. 14.
• Installation of one new generator (of 2000 KW) as replacement of three existing generator on south side of Bldg. 53A.
0003 Option 2 –
• Replace MCC breaker in Bldg. 53A. 1 Job $_______
Option 3 –
• Demolition of Bldg. 13 including foundation.
Option 4 –
• Rerouting of steam, steam condensate and compressed air lines (to serve Bldg. 26) through mezzanine of Bldg. 14.
• Demolition of existing overhead steam, steam condensate, compressed air lines over Bldg. 6, their structural support and
• Demolition of Bldg. 6 including foundation.
Option 5 –
• Construction of canopies on west side of
Bldg. 14.
• Demolition of three chillers in Bldg. 5B.
• Demolition of entire solar system in Bldg.
5B including foundations (approx. 12 ft deep) for solar panels.
• Demolition of two chillers in Bldg. 53A and associated cooling tower on south side of Bldg. 53A.
• Demolition of three chillers in Bldg. 26 and associated cooling tower on south side of Bldg. 14.
Page | 6
Option 6 –
• Installation of chilled water lines over roof of Bldg. 5B and 5C.
• Installation of new roofing membranes over
• Cost proposal shall include cost of replacing
200 Sq. Ft deteriorated portion of lightweight concrete roof deck.
200 Sq. ft deteriorated portion of metal roof deck.
150 linear feet wooden blocking at edge of roof, expansion joint and roof curb in base bid.
Option 7 –
• Replace deteriorated portion of lightweight concrete roof deck (In accordance with FAR Clause 52.217-7)
Shall be exercised any time within the contract period of performance when exact quantity is known.
Work shall be completed if/when the option is exercised within the same period of performance of the contract.
SF
Option 8 –
• Replace deteriorated portion of metal roof deck known.
Work shall be completed if/when the option is
SF
Option 9 –
• Replace wooden blocking at edge of roof, expansion joint and roof curb in base bid.
Page | 7 known.
Work shall be completed if/when the option is
10 LF $_______
Option 10 –
• Removal of undergrade concrete known.
Work shall be completed if/when the option is
CF
For base bid and all options, cost proposal shall include cost for asbestos sampling (within work limits) performed as per provided attachments, cost for abatement of asbestos containing material so mentioned in attachment. Additional discovery of asbestos containing material during asbestos sampling performed by contractor shall be address by change order.
Work shall be completed in accordance with Attachments:
• Folder J-1: Bldg. 2_Chiller Plant o J-1a: Bldg. 2_Design Analysis o J-1b: Bldg. 2_Drawing o J-1c: Bldg. 2_Specification_Vol 1 o J-1d: Bldg. 2_Specification_Vol 2
• Folder J-2: Bldg. 6_Demo o J-2a: Bldg. 6_ Demo_Project Manual o J-2b: Bldg. 6_Demo_Drawing o J-2c: Bldg. 6_Old Drawings o J-2d: Bldg. 6_Overhead Lines_Asbestos Report
• Folder J-3: Bldg. 53A_MCC o J-3a: Bldg. 53A_MCC_Drawing o J-3b: Bldg. 53A_MCC_Project Manual
• J-4: Big Tanks and Overhead Lines Foundation
• J-5: Bldg. 5B_ Cooling Tower Drawing
• J-6: Bldg. 13 Old Drawing
• J-7: Bldg. 26_Cooling Tower Drawing
• J-8: Bldg. 53A_Cooling Tower Drawing
Page | 8
Total Price (CLIN 0001 – CLIN 0011) $_____________
SECTION C- DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
C-1 Scope of Work
Independently and not as an agent of the Government, the Contractor shall furnish the necessary management, supervision, personnel, materials, equipment, services, facilities, and otherwise do or provide all things necessary for or incident to the performance of the work set forth herein as in Section J, Attachment Folder J-1, J-2, J-3 & Files J-4, J-5, J-6, J-7, & J-8.
C-2 Government Furnished Property and Services
The Government will provide sufficient utilities, space on the campus to accommodate on-site portable construction office, supply storage, and access to secured facilities as needed. The Contractor shall pay for all temporary connections. No other property or services will be furnished by the Government.
SECTION D- PACKAGING AND MARKING
D-1 Marking Instructions for Reports
The contractor shall mark each shipment with its organization name, contract number, item number, and quantity (indicate partial or final shipment). As appropriate note on the face page of the report and when feasible on the binding (1) “one volume only” or (2) “volume 1 of 2, volume 2 of 2” etc.
D-2 Payment of Postage and Fees
All postage and fees related to distribution of deliverable including forms, reports, etc., shall be paid by the Contractor.
SECTION E- INSPECTION AND ACCEPTANCE
E-1 Inspection and Acceptance
Pursuant to the FAR 52.246-12, Inspection of Construction clause below, and upon notice by the Contractor that the work is substantially complete, final inspection and acceptance of all items called for by this contract shall be made by the Contracting Officer (CO) or his/her designated Contracting Officer’s Representative (COR). The Contractor shall be responsible for any countermeasures or corrective action, within the scope of this contract, which may be required by the CO as a result of such inspection.
Page | 9
E-2 - 52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The full text of a clause may also be accessed electronically at this address:
https://www.acquisition.gov/?q=browsefar
FAR
Clause No. Title and Date
52.246-12 Inspection of Construction (AUG 1996)
E-3 Government Inspectors
The work shall be conducted under the general direction of the CO and is subject to inspection by his/her COR to ensure compliance with the terms of the contract. No inspector is authorized to change any provision of the specifications without written authorization of the CO, nor shall the presence or absence of an inspector relieve the Contractor from any requirements of the contract. Contractor shall be required to work under the supervision of Government onsite construction administration personnel. Contractor shall comply with requirements, inspections and requests made by construction administration personnel with prior approval of COR.
SECTION F- DELIVERIES OR PERFORMANCE
F-1 Reports/Deliverables
Unless otherwise noted, all reports/deliverables shall be delivered to the attention of the Contract Specialist (CS), via email Howard.Nesmith@fda.hhs.gov, delivered or mailed to NCTR/OAGS, Building 50, Room 424, 3900 NCTR Road, Jefferson, AR 72079.
The Contractor shall submit the following reports/deliverables:
Scheduled Items Qty Due Dates
1. Performance and Payment Bonds (See Section G-5) 1 Within 20 calendar days after contract award
2. Pre-construction conference 1 Within 25 calendar days after contract award
3. Listing of Contractor Employees (See Section H-1) 1
Within 25 calendar days of contract award. Submit to NCTR Safety Office, Building 50, Room 304.
Provide updates as needed.
4. Certificate of Insurance (See Section H-6) 1 Within 25 calendar days after contract award. .
https://www.acquisition.gov/?q=browsefar mailto:Howard.Nesmith@fda.hhs.gov
Page | 10
5. Preliminary Construction Performance Schedule (See Section H- 9)
Not later than 10 calendar days after receipt of notice to proceed.
Submit to COR.
6. Schedule of Values 3 Within 30 calendar days after receipt of notice to proceed
7. Invoice 1 Monthly
8. Submittals 3 hard copies /1 electronic
Not later than 30 calendar days after receipt of notice to proceed.
9. Updates to construction schedule 2 Monthly with Invoice.
10. Certification Statement & Payrolls 1 Monthly with Invoice
11. Project Record Drawings/”as-builts” (See Section H-7 (L))
3 hard copies & 1 electronic copy in
AutoCAD
Not later than 30 calendar days prior to submission of final invoice
12. O & M Manuals 4 Not later than 30 calendar days
13. Warranties 4 Not later than 30 calendar days
14. Release of Claims 1 Submitted with final invoice.
15. COVID Attestation Form 1 per person
First day of arrival onto FDA property and kept on person and available upon request thereafter.
F-2 Notice Regarding the Use of Macros in Submitted Documents
The FDA does not accept documents which contain the use of macros. When submitting documents via email, DO NOT include .exe, .mso, or any other executable file types that could potentially trigger email security protections (i.e. email blocks, quarantine). Document submissions required throughout the award period(s) shall not have enabled macro functionality.
Any document(s) delivered having macro functionality will be deemed delinquent, if not corrected prior to the due date.
F-3 52.252-2 Clauses Incorporated by Reference. (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the CO will make their full text available. The full text of a clause may also be accessed electronically at this address:
Page | 11
FAR
Clause No. Title and Date 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) “…within 10 calendar days after the date the Contractor receives the notice to proceed…complete the entire work ready for use not later than 1,095 calendar days after receipt of the notice to proceed…” 52.242-14 Suspension of Work (APR 1984)
SECTION G- CONTRACT ADMINISTRATION DATA
G-1 Contracting Officer’s Representative (COR)
The COR responsible for the acceptance of work provided hereunder will be designated by separate correspondence. The term ‘‘COR’’ means the person who monitors the technical aspects of contract performance. The COR is not authorized to issue any instructions or directions which cause any increase or decrease in the scope of work which would result in the increase or decrease in the price of this contract, or changes in the delivery schedule or period of performance of this contract. If applicable, the COR is not authorized to receive or act upon any notification or revised cost estimate provided by the Contractor in accordance with the Limitation of Cost or Limitation of Funds Clauses of this contract.
G-2 Technical Guidance
A. Performance of the work under this contract shall be subject to the technical guidance of the COR. The term "technical guidance" is defined to include the following:
1. Providing information to the Contractor for assistance in the interpretation of drawings, specifications, or technical portions of the work description, other technical performance requirements; and
2. Review and, where required by the contract, approval of technical reports, drawings, specifications, and technical information to be delivered by the Contractor to the Government under the contract;
3. Perform technical evaluation as required;
4. Perform technical inspections and acceptances required by this contract; and
5. Assisting in the resolution of technical problems encountered during performance.
B. Technical guidance must be within the general scope of work stated in the contract. The
COR does not have the authority to, and may not, issue any technical direction which (1) constitutes an assignment of additional work outside the general scope of the contract; (2) constitutes a change as defined in the contract Clause entitled "Changes," (3) in any manner causes an increase or decrease in the total contract price; or (4) changes any of the expressed terms, conditions, or specifications of the contract.
Page | 12
C. All technical guidance shall be issued in writing by the COR or shall be confirmed by him/her in writing within five (5) working days.
D. The Contractor shall proceed promptly with the performance of technical guidance duly issued by the COR in the manner prescribed by this clause and within his/her authority under the provisions of this clause.
E. If, in the opinion of the Contractor, any instruction or direction issued by the COR is not within one of the categories as defined in B. (1) through B. (2) above, the Contractor shall not proceed but shall notify the CO, in writing, within five (5) working days after the receipt of any such instruction or direction. Upon receiving such notification from the Contractor, the CO shall determine whether or not a modification is necessary, take appropriate action and advise the Contractor accordingly. The Contractor shall thereupon proceed immediately with the direction given. Any failure of the parties to agree upon the nature of the instruction or direction, or upon the contract action to be taken with respect thereto, shall be subject to the provisions of the contract Clause entitled "Disputes."
The Contractor shall contact the FDA's COR prior to performance to arrange for the following:
Access to the Facility
G-3 Contract Administration
a. Howard Nesmith, Contract Specialist (CS) 3900 NCTR Road HFT-320, Rm 424 Jefferson, AR 72079 Phone: 870-543-7459 Email: Howard.Nesmith@fda.hhs.gov
b. Contractor’s Point of Contact (To be completed at time of award) Name:
Office:
Cell:
Email:
c. Technical Point of Contact-Contracting Officer’s Representative (COR) (To be completed at time of award) Name:
Office:
Email:
mailto:Howard.Nesmith@fda.hhs.gov
Page | 13
G-4 HHSAR 352.237-75 Key Personnel (December 2015)
The key personnel specified in this contract are considered to be essential to work performance.
At least 30 days prior to the contractor voluntarily diverting any of the specified individuals to other programs or contracts the Contractor shall notify the Contracting Officer and shall submit a justification for the diversion or replacement and a request to replace the individual. The request must identify the proposed replacement and provide an explanation of how the replacement's skills, experience, and credentials meet or exceed the requirements of the contract (including, when applicable, Human Subjects Testing requirements). If the employee of the contractor is terminated for cause or separates from the contractor voluntarily with less than thirty days’ notice, the Contractor shall provide the maximum notice practicable under the circumstances.
The Contractor shall not divert, replace, or announce any such change to key personnel without the written consent of the Contracting Officer. The contract will be modified to add or delete key personnel as necessary to reflect the agreement of the parties.
The positions cited below are key personnel.
Title
Project Manager
On-Site Superintendent
(End of clause)
G-5 Bonding Requirement
Acceptable Performance and Payment Bonds shall be furnished to the CS by the Contractor within twenty (20) calendar days after date of contract award. Notice to Proceed will not be given until all bond requirements are satisfactorily met. Bonds shall be delivered to:
howard.nesmith@fda.hhs.gov.
The penal amount of the performance bond shall be 100% of the original contract price.
The penal amount of the payment bond shall equal:
1. 100% of the original contract price; and
2. If the contract price increases, an additional amount equal to 100% of the increase; and
3. The amount of the Payment Bond must be no less than the amount of the Performance
Bond.
Any increase in the contract price shall require an increase in performance and payment bond.
The surety or sureties shall be acceptable to the Government and a “Power of Attorney” of the agent authorized to certify under the surety’s seal shall be furnished with the bond. Standard mailto:howard.nesmith@fda.hhs.gov
Page | 14
Form 25 “Performance Bond” and 25A “Payment Bond” can be obtained electronically at http://www.gsa.gov/portal/forms/type/SF. Contractors and sureties shall follow the instructions on the back of the form. See FAR Clause 52.228-15 included in Section I.
G-6 Reporting Matters Involving Fraud, Waste, and Abuse
Anyone who becomes aware of the existence or apparent existence of fraud, waste and abuse in FDA funded programs is encouraged to report such matters to the HHS Inspector General’s Office in writing or on the Inspector General’s Hotline. The toll-free number is 1-800-HHS-TIPS (1-800-447-8477). All telephone calls will be handled confidentially. The email address is HHStips@oig.hhs.gov and the mailing address is:
Office of Inspector General Department of Health and Human Services
Attn: HOTLINE 330 Independence Avenue, S.W.
Washington, D.C. 20201
Information regarding procedural matters is contained on the HHS/OIG website at:
http://oig.hhs.gov/fraud/
G-7 Contractor Performance Evaluation(s)
In accordance with Federal Acquisition Regulation (FAR) 42.15, FDA will complete annual and final contractor performance evaluations. Annual evaluations will be prepared to coincide with the anniversary date of the contract. Additional interim performance evaluations may be prepared at the CO’s discretion, as necessary. Final performance evaluations will be completed upon contract expiration.
FDA will utilize the Contractor Performance Assessment Reporting System (CPARS) in order to execute annual and final contractor performance evaluations. CPARS is a secure internet website located at www.cpars.gov. FDA will register the contractor in CPARS upon receipt of the name and email address of two (2) individuals who will be responsible for serving as the Contractor’s primary and alternate CPARS contacts. Once FDA registers the contractor in CPARS, the Contractor will receive an automated CPARS email message which contains User IDs and instructions for creating a password.
Once a performance evaluation is issued, the Contractor’s primary and alternate CPARS contact will receive an email instructing them to logon to CPARS in order to review the performance evaluation. The Contractor has 14 calendar days from the date of performance evaluation issuance in which to review the evaluation. If the Contractor is in agreement with the performance evaluation outcome, the evaluation becomes final. Should the Contractor disagree with the performance evaluation outcome, rebuttal comments must be submitted via the CPARS within 14 days from date the evaluation was issued by FDA. Any disagreement between the CO and the Contractor will be referred to a contracting official one level above the CO, whose decision will be final. Copies of each performance evaluation and contractor responses, if any, http://www.gsa.gov/portal/forms/type/SF mailto:HHStips@oig.hhs.gov http://oig.hhs.gov/fraud/ http://www.cpars.gov/
Page | 15 will be retained as part of the official contract file and will be used to support future award decisions.
Note: Effective January 15, 2019, the Past Performance Information Retrieval System (PPIRS) has been merged into CPARS. CPARS.gov is now the official source for past performance information. The PPIRS name will no longer be used except in the Federal Acquisition Regulation (FAR). Contractors may obtain CPARS training material and register for on-line training at https://www.cpars.gov/main/cparsmain.htm. There is no fee for registration or use of the CPARS system.
SECTION H- SPECIAL CONTRACT REQUIREMENT
H-1 Contractor Personnel Security Clearance Standards and Residency Requirements (October 2017)
1. BACKGROUND - The Office of the Assistant Secretary for Management and Budget, Department of Health and Human Services (DHHS), requires that Contractor employees (including subcontractors) who will be working in DHHS-owned or leased space and/or who will have access to DHHS equipment, and non-public privileged, proprietary, or trade secret information, must undergo a background investigation that results in a favorable determination.
Contractor employees who will work in DHHS-owned or leased space for less than thirty (30) days are considered visitors and are exempted from background investigation requirements; and therefore, will not be issued a Personal Identity Verification (PIV) Card. These contractor employees go through visitor screening each day and must be escorted at all times while in DHHS-owned or leased space.
2. GENERAL - The Contractor must submit the following items to the Contracting Officer’s Representative (COR), within five (5) business days of commencement of work under this contract:
• A roster of contractor employee names, identifying Key Personnel and Tier designation(s);
• Confirmation all individual employee security information has been submitted properly;
and
• "Contractor's Commitment to Protect Non-public Information Agreement" forms signed by each employee named in the roster.
Pursuant to HSPD-12, the Contractor must advise its prospective employees about the security and background requirements stated herein.
For any individual who does not obtain a favorable background investigation he/she must cease work on the contract immediately.
https://www.cpars.gov/main/cparsmain.htm
Page | 16
If a Contractor employee changes job responsibilities under this contract, the Contractor must notify the COR, and the Government will make a determination whether an additional security clearance is required.
In the event there are any proposed personnel changes in the Contractor’s staffing roster previously submitted to the COR, the Contractor must submit an updated roster to the COR, along with a brief explanation for the change. In turn, the COR will initiate the procedures stated herein to ensure any new contractor employees obtain a PIV card in a timely manner – prior to that individual commencing work under the contract.
Note: If the proposed personnel change is for a position designated Key Personnel under the contract, a complete justification – along with a resume or curriculum vitae – must be submitted to the Contracting Officer and COR for review and approval. If approved, the Contracting Officer will execute a Contract Modification prior to that individual commencing work under the contract.
3. BACKGROUND INVESTIGATIONS - With the exception of costs associated with fingerprinting Contractor employees outside of the FDA Personnel Security Office, the Government will conduct all required background investigations at no cost to the Contractor. The cost of fingerprinting Contractor employees at any location other than the FDA Personnel Security Office will be borne by the Contractor. Employees who hold or have previously held a Government security clearance must advise the FDA Personnel Security Staff of the details of such clearance.
Note: Background investigations will be conducted by the Office of Personnel Management
(OPM)
4. CONTRACT RISK DESIGNATION(S) - Contractor employees who will be in DHHS-owned or leased space for thirty (30) days or more must be able to obtain and shall obtain a PIV card pursuant to Homeland Security Presidential Directive-12 (HSPD-12) in order to access to DHHS-owned or leased property without an escort. (See Section 6 for details on the PIV Card process) However, in the event that work must commence before a security screening can be completed, contractor employees will be considered visitors, as described above, and allowed onto DHHS-owned or leased property, but must be escorted at all times.
All Contractor employees who undergo a background investigation are required to log onto the Office of Personnel Management’s (OPM’s) Electronic Questionnaire for Investigation Processing system (e-QIP) system. The FDA Personnel Security Specialist will provide access to the e-QIP as well as guidance as to which forms will be required. The forms required vary with the position risk designations for the contract.
All standard forms submitted to the FDA will be forwarded to the Office of Personnel Management (OPM) to initiate background investigations. The assigned FDA Personnel Security Specialist will resolve with the contractor employee any issues arising out of inaccurate or incomplete forms.
Page | 17
The Risk Designation(s) for this contract is/are Tier(s): ___1___
There are three (3) potential position risk designations, which are:
• Non-Sensitive Low Risk (Tier 1) - Positions which involve the lowest degree of adverse impact on the efficiency of the Agency. The forms set forth by the FDA Personnel Security Specialist are required for Non-Sensitive Low Risk Positions.
• Sensitive Moderate Risk (Tier 2) or Sensitive High Risk (Tier 4) - Public Trust Positions
- Positions in which the incumbent's actions or inaction could diminish public confidence in the integrity, efficiency, or effectiveness of assigned Government activities, whether or not actual damage occurs.
In order to access the e-QIP system, Contractor employees must provide the appropriate FDA Personnel Security Specialist with the following information: (a) full name; (b) position title; (c) social security number; (d) date of birth; (e) place of birth; (f) email address; and (g) phone number. This information will be provided on the e-QIP form that will be electronically sent to the employee. The FDA Personnel Security Specialist will use this information to enter each Contractor employee into the e-QIP system. Once this is done, each Contractor employee will receive an email that contains a web link to access the e-QIP system, as well as instructions and additional forms needed to initiate the background investigation.
A Contractor’s failure to comply with the e-QIP processing guidelines will result in that Contractor’s employees being denied access to FDA property until all security processing has been completed. Furthermore, any such noncompliance may detrimentally impact Contractor performance, Contractor performance evaluations, rights and remedies available at law and equity retained by the Government.
5. PERSONAL IDENTITY VERIFICATION (PIV) CARDS - All PIV Cards (and any other type of Government-issued Access Card) shall remain the property of the Federal Government. At any time, if a Contractor employee is terminated or otherwise ceases work under the contract, or no longer requires a PIV Card for contract performance purposes, the Contractor must collect the individual’s PIV card and immediately notify FDA Personnel Security Staff in writing, with copies to the respective COR and Contracting Officer. The Contractor must immediately return the PIV Card(s) to the COR.
Because PIV Cards, like other Government-issued Access Cards are Government property, Contractors and Contractor Employees are hereby placed on notice that any abuse, destruction, defacement, unauthorized transfer or withholding (i.e., failure to return to the Government) may be punishable to the greatest extent at law.
Unauthorized possession of a PIV Card, or any other type of Government-issued Access Card, and/or willfully allowing any other person to have or to use your Access Card, is prohibited and can be criminally prosecuted under 18 U.S.C. §§ 499 and 70I, which prohibit photographing or otherwise reproducing or possessing HHS identification cards in an unauthorized manner, under penalty of fine, imprisonment, or both. Wrongdoers may also be held financially responsible for
Page | 18 any/all civil and equitable remedies – to include, but not limited to, damages for any pecuniary loss suffered by the Government as a result of any of the above-listed actions or failure to act.
6. PIV CARD PROCESS - The COR will sponsor Contractor employees on the Form HHS 745 and HHS Smart Card Management System (SCMS) for the purpose of obtaining an FDA PIV Card. In order to obtain a PIV card, a Contractor employee must receive a favorable FBI fingerprint return and complete required security forms. The FDA Personnel Security Specialist will provide the Contractor employee(s) direction for scheduling fingerprinting appointments at the FDA location or other approved location.
During a fingerprint appointment, each contractor employee must present two (2) forms of identification in order to receive his or her PIV Card. One form of identification must be a government-issued photo identification document. Acceptable forms of identification are listed in Appendix A, provided below. An individual who receives an unfavorable report may appeal that finding by submitting a written request to the FDA Personnel Security Specialist.
Required background investigations may include, but are not limited to:
• Review of prior Government/military personnel records;
• Review of FBI records and fingerprint files;
• Searches of credit bureaus;
• Personal interviews; and
• Written inquiries covering the subject's background.
7. RESIDENCY REQUIREMENTS FOR FOREIGN NATIONALS - Under the requirements for Homeland Security Presidential Directive-12 (HSPD-12), OPM can complete a background investigation only for persons who have resided in the U.S. for a total of at least three (3) of the past five (5). The residency requirements apply only to foreign nationals. If any prospective foreign national contractor/subcontractor employee does not meet the residency requirements, he/she cannot qualify for a PIV Card under HSPD-12.
8. NON-PUBLIC DATA PROTECTION - The Contractor must protect the privacy of all information reported by or about Contractor employees and protect against unauthorized disclosure.
*Upon a favorable fingerprint return, the Contractor will be notified to return to the Badging and Credentialing Office for their building pass.
*Food and Drug Administration Badging and Credentialing Office 8:00 a.m. – 11:00 a.m. and 1:00 p.m. – 3:00 p.m., Eastern Time 10903 New Hampshire Avenue Building 32, Room 1205 Silver Spring, MD 20993 No appointment necessary Telephone: (301) 796-4000
Page | 19
A Contractor’s failure to comply with the e-QIP processing guidelines will result in that Contractor’s employees being denied access to FDA property until all security processing has been completed. Furthermore, any such noncompliance may detrimentally impact Contractor performance, Contractor performance evaluations, rights and remedies available at law and equity retained by the Government.
a. Contractor employees who will work in the Washington D.C. metro area shall, at the direction of the FDA COR or his/her designee, contact the Personnel Security Branch to schedule a fingerprinting appointment, or
b. Contractor employees who will work on the National Center for Toxicological Research facility shall contact the following to arrange for fingerprinting:
Food and Drug Administration National Center for Toxicological Research Office of Regulatory Compliance and Risk Management 3900 NCTR Road Bldg. 50, Room 304 Jefferson, AR 72079
Page | 20
Appendix A
H-2 Payments to Contractors
Progress payments will be made in accordance with the Clause 52.232-5 entitled "Payments Under Fixed-Price Construction Contracts (MAY 2014)" in Part II, Section I, supplemented as follows:
A. Before the first progress payment under the contract becomes due, the Contractor shall prepare a schedule, acceptable to the CO, of the estimated values of each principal category of the work which, when added together, will be used for determining progress payments and shall be in such detail as may be required by the CO. The cost of preparatory work, overhead, profit, bonds and insurance, taxes, warranties, as-built
Page | 21 drawings, etc., shall be prorated into items of work throughout the contract.
B. Separate payments for materials delivered on-site or to locations other than on-site as contemplated by FAR Clause 52.232-5(b)(2) will be made under this contract.
C. The Contractor, prior to receiving a progress or final payment under this contract, shall submit to the CO a certification that the Contractor has made payment from the proceeds of prior payments, or that it will make timely payment then due, to its Subcontractor and suppliers in accordance with contractual arrangements with them.
D. After completion of the work, and prior to final payment, the Contractor shall furnish to the CO a release of claims against the United States arising out of the Contractor, other than claims specifically excepted from the operation of the release.
H-3 Invoice Submission
Before formal invoice submission, the Contractor shall submit draft invoice to COR for review.
Upon approval from COR, contractor shall submit invoices in accordance with the following instructions:
CONTRACTOR SHALL SUBMIT ALL INVOICES AS FOLLOWS:
FDA Electronic Invoicing and Payment Requirements - Invoice Processing Platform (IPP) (Jan 2022)
a. All Invoice submissions for goods and or services must be made electronically through the U.S. Department of Treasury's Invoice Processing Platform System (IPP).
http://www.ipp.gov/vendors/index.htm
b. Invoice Submission for Payment means any request for contract financing payment or invoice payment by the Contractor. To constitute a proper invoice, the payment request must comply with the requirements identified in FAR 32.905(b), "Content of Invoices" and the applicable Payment clause included in this contract, or the clause 52.212-4 Contract Terms and Conditions - Commercial Items included in commercial items contracts. The IPP website address is: https://www.ipp.gov c.
1. The Agency will enroll the Contractors new to IPP. The Contractor must follow the IPP registration email instructions for enrollment to register the Collector Account for submitting invoice requests for payment. The Contractor Government Business Point of Contact (as listed in SAM) will receive Registration email from the Federal Reserve Bank of St. Louis (FRBSTL) within 3 - 5 business days of the contract award for new contracts or date of modification for existing contracts.
2. Registration emails are sent via email from ipp.noreply@mail.eroc.twai.gov. Contractor assistance with enrollment can be obtained by contacting the IPP Production Helpdesk via email to IPPCustomerSupport@fiscal.treasury.gov or phone (866) 973-3131.
http://www.ipp.gov/vendors/index.htm https://www.ipp.gov/ mailto:IPPCustomerSupport@fiscal.treasury.gov
Page | 22
3. The Contractor POC will receive two emails from IPP Customer Support, the first email contains the initial administrative IPP User ID. The second email, sent within 24 hours of receipt of the first email, contains a temporary password. You must log in with the temporary password within 30 days.
4. If your company is already registered to use IPP, you will not be required to re-register.
5. If the Contractor is unable to comply with the requirement to use IPP for submitting invoices for payment as authorized by HHSAR 332.7002, a written request must be submitted to the Contracting Officer to explain the circumstances that require the authorization of alternate payment procedures.
d. Invoices that include time and materials or labor hours Line Items must include supporting documentation to (1) substantiate the number of labor hours invoiced for each labor category, and (2) substantiate material costs incurred (when applicable).
e. Invoices that include cost-reimbursement Line Items must be submitted in a format showing expenditures for that month, as well as contract cumulative amounts. At a minimum the following cost information shall be included, in addition to supporting documentation to substantiate costs incurred.
- Direct Labor - include all persons, listing the person's name, title, number of hours worked, hourly rate, the total cost per person and a total amount for this category;
- Indirect Costs (i.e., Fringe Benefits, Overhead, General and Administrative, Other Indirects)- show rate, base and total amount;
- Consultants (if applicable) - include the name, number of days or hours worked, daily or hourly rate, and a total amount per consultant;
- Travel - include for each airplane or train trip taken the name of the traveler, date of travel, destination, the transportation costs including ground transportation shown separately and the per diem costs. Other travel costs shall also be listed;
- Subcontractors (if applicable) - include, for each subcontractor, the same data as required for the prime Contractor;
- Other Direct Costs - include a listing of all other direct charges to the contract, i.e., office supplies, telephone, duplication, postage; and
- Fee - amount as allowable in accordance with the Schedule and FAR 52.216-8 if applicable.
f. Contractor is required to attach an invoice log addendum to each invoice which shall include, at a minimum, the following information for contract administration and reconciliation purposes:
Page | 23
(a) list of all invoices submitted to date under the subject award, including the following:
(1) invoice number, amount, & date submitted
(2) corresponding payment amount & date received
(b) total amount of all payments received to date under the subject contract or order
(c) and, for definitized contracts or orders only, total estimated amounts yet to be invoiced for the current, active period of performance.
g. Payment of invoices will be made based upon acceptance by the Government of the entire task or the tangible product deliverable(s) invoiced. Payments shall be based on the Government certifying that satisfactory services were provided, and the Contractor has certified that labor charges are accurate.
h. If the services are rejected for failure to conform to the technical requirements of the task order, or any other contractually legitimate reason, the Contractor shall not be paid, or shall be paid an amount negotiated by the CO.
i. Payment to the Contractor will not be made for temporary work stoppage due to circumstances beyond the control of U.S. Food and Drug Administration such as acts of God, inclement weather, power outages, and results thereof, or temporary closings of facilities at which Contractor personnel are performing. This may, however, be justification for excusable delays.
j. The Contractor agrees that the submission of an invoice to the Government for payment is a certification that the services for which the Government is being billed, have been delivered in accordance with the hours shown on the invoices, and the services are of the quality required for timely and successful completion of the effort.
k. Questions regarding invoice payments that cannot be resolved by the IPP Helpdesk should be directed to the FDA Employee Resource and Information Center (ERIC) Helpdesk at 301-827- ERIC (3742) or toll-free 866-807-ERIC (3742); or, by email at ERIC@fda.hhs.gov. Refer to the Call-in menu options and follow the phone prompts to dial the option that corresponds to the service that's needed.
This is the start of the file's text. The full file is on GovTribe.