13 Pre-Bid RFI Log-P20221008080 07262024.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Amendment 00002 for P2021008080 Atlanta Water Line Installation Services
Solicitation number
75D301-24-R-73077
Issued by

About this file

This document is a Pre-Bid Request for Information (RFI) Log for a federal contract opportunity related to the replacement of the domestic water system in Building 110 at the CDC's Chamblee Campus. The solicitation number is 75D301-24-R-73077.

The key details include:

  • The work involves replacing the existing copper water piping system and related components in Building 110, including installing parallel CPVC water lines, new ball valves, and replacement equipment.
  • The contract has phasing requirements that must be followed as per the contract drawings.
  • Potential bidders had the opportunity to submit RFIs, which the CDC responded to, covering topics such as personnel requirements, temporary heating/cooling, material lead times, as-built drawings, and required forms.
  • The CDC emphasized that the current period of performance provides ample time to accommodate market conditions and that extensions are unlikely unless there are valid reasons.
  • Potential bidders were provided guidance on accessing the contract drawings and specifications, which are subject to a non-disclosure agreement.
  • The bid submission deadline is August 9, 2024, and only one site walkthrough was scheduled on July 11, 2024.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Pre-Bid RFI Log
Project : P20221008080 B110 Domestic Water Replacement - GACH0110
Contracting Officer: Mike DavisSolicitation No: 75D301-24-R-73077
RFI No.DescriptionCompany AuthorDate Received by the CDCResponse DateCDC Response
01Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?Mckenzie7/9/247/16/24It is not a requirement for superintendent, SSHO, or QC to be 3 separate individuals
02Are there any phasing requirements?Mckenzie7/9/247/16/24Yes. Follow the contract drawings.
03How many people will be in the building?Mckenzie7/9/247/16/24The building will be occupied at all time.
04Are there any temporary heating/cooling requirements?Mckenzie7/9/247/16/24Follow the contract and Specifications documents
05Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?Mckenzie7/9/247/16/24The current schedule duration provides ample time to accommodate the current market condition. Unless CDC agrees that there are some some valid reasons, the period of performance will not change.
06Can you provide as builds for pipe removal logistics?Mckenzie7/9/247/16/24As-builts will be provided after the project is awarded.
07Drawings are mentioned in the SOW & Solicitation, can you provide these drawings?Mckenzie7/9/247/16/24NDA for companies and for individuals who will have access to the contract documents will need to be sent to the contracting officer, Mike Davis in order to receive the Specifications and drawings.
08While going through the bid documents we have identified a couple of forms we need. Please see attached “Form Needed” document: Document tracking logEmery Associates7/11/247/16/24Document tracking log is attached.
09While going through the bid documents we have identified a couple of forms we need. Please see attached “Form Needed” document: Construction cost proposal formatEmery Associates7/11/247/16/24Construction cost proposal format is attached.
10Do all materials used for the replace project need to fall under the "Buy American Act."?Emery Associates7/15/247/16/24Follow FAR 52.225-9 Buy American-Construction Materials (Nov 2021) clause
11Can you please clarify / specify the Tiles required for the RestroomsEmery Associates7/16/247/26/24Provide an allowance of $12 per square feet for material and labor to replace wall tiles on wet walls only
12Can you please clarify / specify the Tiles required for the Water fountainsEmery Associates7/16/247/26/24Provide an allowance of $20 per square feet to replace glass wall for material and labor.
13Can someone please let me know what size paper I need to print to in order to have the scale correctly representedA.S.M. McClain Enterprises7/24/247/24/24The PDF file size for the contract drawings is 24"x36"
14Will we be able to put a container near the loading doc to store materials.A.S.M. McClain Enterprises7/24/247/26/24The loading dock at 110 does not have sufficient space to store material. We may allow to use the area behind 105.
15When is the deadline for submission of bid.A.S.M. McClain Enterprises7/24/247/26/24The bids are due on August 09, 2024.
16Can there be another walk through.A.S.M. McClain Enterprises7/24/247/26/24Only one date was established in the solicitation for site walkthrough which was July 11, 2024.
17Are there draws after each phase.A.S.M. McClain Enterprises7/24/247/26/24The phasing drawings are included in the contract drawings
18Can we park at the loading dock area.A.S.M. McClain Enterprises7/24/247/26/24Contractors can park at the lot in front of 105 or the parking deck.
19How high are the ceilings in the Labs 7A.S.M. McClain Enterprises7/24/247/26/24The celling height in the lab floors is above 9 ft.
20How much time after each demolition will we have to do the repairs.A.S.M. McClain Enterprises7/24/247/26/24Follow the phasing plans for direction. There is a note on the duration of work in the lab areas.

File details come from the government source that posted it. Updated .