11 Pre-Bid RFI Log-P20221008080 07182024.xlsx

XLSX spreadsheet 15 KB Posted

Attached to
Amendment 00002 for P2021008080 Atlanta Water Line Installation Services
Solicitation number
75D301-24-R-73077
Issued by

About this file

This document is a Pre-Bid Request for Information (RFI) Log for a federal contract opportunity to replace the existing copper water piping system and related components in Building 110 at the CDC's Chamblee Campus, with a Solicitation Number of 75D301-24-R-73077.

The key details from the RFI Log include:

  • The contracting officer is Mike Davis.
  • There are phasing requirements, and the building will be occupied throughout the project.
  • Temporary heating/cooling requirements are to follow the contract and specifications documents.
  • The period of performance may not be extended due to current market conditions unless the CDC agrees there are valid reasons.
  • Drawings and specifications will be provided after companies and individuals sign a Non-Disclosure Agreement.
  • The Buy American Act requirements apply, and the contractor must follow FAR 52.225-9.
  • Clarification is needed on the required tiles for the restrooms and water fountains.

The full scope of work is outlined in the attached Statement of Work, Specifications, and Drawings.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Pre-Bid RFI Log
Project : P20221008080 B110 Domestic Water Replacement - GACH0110
Contracting Officer: Mike DavisSolicitation No: 75D301-24-R-73077
RFI No.DescriptionCompany AuthorDate Received by the CDCResponse DateCDC Response
01Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?Mckenzie7/9/247/16/24It is not a requirement for superintendent, SSHO, or QC to be 3 sepearate individuals
02Are there any phasing requirements?Mckenzie7/9/247/16/24Yes. Follow the contract drawings.
03How many people will be in the building?Mckenzie7/9/247/16/24The building will be occupied at all time.
04Are there any temporary heating/cooling requirements?Mckenzie7/9/247/16/24Follow the contract and Specifications documents
05Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?Mckenzie7/9/247/16/24The current schedule duration provides ample time to accommodate the current market condition. Unless CDC agrees that there are some some valid reasons, the period of perfomance will not change.
06Can you provide as builds for pipe removal logistics?Mckenzie7/9/247/16/24Asbuilds will be provided after the project is awarded.
07Drawings are mentioned in the SOW & Solicitation, can you provide these drawings?Mckenzie7/9/247/16/24NDA for companies and for individuals who will have access to the contract documents will need to be sent to the contracting officer, Mike Davis in order to receive the Specifications and drawings.
08While going through the bid documents we have identified a couple of forms we need. Please see attached “Form Needed” document: Document tracking logEmery Associates7/11/247/16/24Document tracking log is attached.
09While going through the bid documents we have identified a couple of forms we need. Please see attached “Form Needed” document: Construction cost proposal formatEmery Associates7/11/247/16/24Construction cost proposal format is attached.
10Do all materials used for the replace project need to fall under the "Buy American Act."?Emery Associates7/15/247/16/24Follow FAR 52.225-9 Buy American-Construction Materials (Nov 2021) clause
11Can you please clarify / specify the Tiles required for the RestroomsEmery Associates7/16/24
12Can you please clarify / specify the Tiles required for the Water fountainsEmery Associates7/16/24

File details come from the government source that posted it. Updated .