11 Pre-Bid RFI Log-P20221008080 07182024.xlsx
XLSX spreadsheet 15 KB Posted
- Solicitation number
- 75D301-24-R-73077
About this file
This document is a Pre-Bid Request for Information (RFI) Log for a federal contract opportunity to replace the existing copper water piping system and related components in Building 110 at the CDC's Chamblee Campus, with a Solicitation Number of 75D301-24-R-73077.
The key details from the RFI Log include:
- The contracting officer is Mike Davis.
- There are phasing requirements, and the building will be occupied throughout the project.
- Temporary heating/cooling requirements are to follow the contract and specifications documents.
- The period of performance may not be extended due to current market conditions unless the CDC agrees there are valid reasons.
- Drawings and specifications will be provided after companies and individuals sign a Non-Disclosure Agreement.
- The Buy American Act requirements apply, and the contractor must follow FAR 52.225-9.
- Clarification is needed on the required tiles for the restrooms and water fountains.
The full scope of work is outlined in the attached Statement of Work, Specifications, and Drawings.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 11 Pre-Bid RFI Log-P20221008080 08082024.xlsx | XLSX spreadsheet | |
| Amendment 00002 to 75D301-24-R-73077 signed.pdf | ||
| 13 Pre-Bid RFI Log-P20221008080 07262024.xlsx | XLSX spreadsheet | |
| 14 75D301-24-R-73077 Site Visit Notes.pdf | ||
| 12 Pre-Bid RFI Log-P20221008080 07242024.xlsx | XLSX spreadsheet | |
| A19 75D301-24-R-73077 Solicitation 07182024.pdf | ||
| 10 TEMPLATE - Document Tracking Log.xls | XLS spreadsheet | |
| 9 EXHIBIT A breakdown example.xlsx | XLSX spreadsheet | |
| Amendment 00001 to 75D301-24-R-73077 signed.pdf | ||
| 6 Visitors Request Form For Access To CDC Campuses.docx | DOCX document | |
| 75D301-24-R-73077 Solicitation.pdf | ||
| 4 Employee Non-Disclosure Agreement.docx | DOCX document | |
| 2 Davis Bacon WD GA20240305 03222024 rev 1.pdf | ||
| 6 Visitors Request Form For Access To CDC Campuses.docx | DOCX document | |
| 1 Statement of Work (SOW) P20221008080.pdf | ||
| 3 Contractors Non-Disclosure Agreement.docx | DOCX document | |
| 5 Past Performance Questionnaire.docx | DOCX document |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Pre-Bid RFI Log | |||||
| Project : P20221008080 B110 Domestic Water Replacement - GACH0110 | |||||
| Contracting Officer: Mike Davis | Solicitation No: 75D301-24-R-73077 | ||||
| RFI No. | Description | Company Author | Date Received by the CDC | Response Date | CDC Response |
| 01 | Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals? | Mckenzie | 7/9/24 | 7/16/24 | It is not a requirement for superintendent, SSHO, or QC to be 3 sepearate individuals |
| 02 | Are there any phasing requirements? | Mckenzie | 7/9/24 | 7/16/24 | Yes. Follow the contract drawings. |
| 03 | How many people will be in the building? | Mckenzie | 7/9/24 | 7/16/24 | The building will be occupied at all time. |
| 04 | Are there any temporary heating/cooling requirements? | Mckenzie | 7/9/24 | 7/16/24 | Follow the contract and Specifications documents |
| 05 | Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project? | Mckenzie | 7/9/24 | 7/16/24 | The current schedule duration provides ample time to accommodate the current market condition. Unless CDC agrees that there are some some valid reasons, the period of perfomance will not change. |
| 06 | Can you provide as builds for pipe removal logistics? | Mckenzie | 7/9/24 | 7/16/24 | Asbuilds will be provided after the project is awarded. |
| 07 | Drawings are mentioned in the SOW & Solicitation, can you provide these drawings? | Mckenzie | 7/9/24 | 7/16/24 | NDA for companies and for individuals who will have access to the contract documents will need to be sent to the contracting officer, Mike Davis in order to receive the Specifications and drawings. |
| 08 | While going through the bid documents we have identified a couple of forms we need. Please see attached “Form Needed” document: Document tracking log | Emery Associates | 7/11/24 | 7/16/24 | Document tracking log is attached. |
| 09 | While going through the bid documents we have identified a couple of forms we need. Please see attached “Form Needed” document: Construction cost proposal format | Emery Associates | 7/11/24 | 7/16/24 | Construction cost proposal format is attached. |
| 10 | Do all materials used for the replace project need to fall under the "Buy American Act."? | Emery Associates | 7/15/24 | 7/16/24 | Follow FAR 52.225-9 Buy American-Construction Materials (Nov 2021) clause |
| 11 | Can you please clarify / specify the Tiles required for the Restrooms | Emery Associates | 7/16/24 | ||
| 12 | Can you please clarify / specify the Tiles required for the Water fountains | Emery Associates | 7/16/24 |
File details come from the government source that posted it. Updated .