AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
87 1
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
00005 01/31/2018 211878PJT00
6. ISSUED BY 7. ADMINISTRATED BY (If other than Item 6)
USCG CEU JUNEAU DET
SEATTLE 915 SECOND AVE, RM
2664 SEATTLE, WA 98174-1011
SAME AS BLOCK 6
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
70Z08718RPJT90000
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
*TO BE COMPLETED BY VENDOR IF NOT COMPLETE 10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended is not extended.
NOTE: Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Item 8 and 15, and returning 1 copies of the amendment; (b) acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hours and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS, IT MODIFIES THE CONTRACT/ORDER NO.
AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT/ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
USCG Air Station Kodiak Construction Services For Design/Build Repairs to the Hangar I Fire Protection Systems.
AMEND SOLICITATION 70Z08718RPJT90000 AS FOLLOWS:
See Continuation Pages
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign)
BY
(Signature of Contracting Officer)
HSBrubeck Typewritten Text
HSBrubeck Typewritten Text
HSBrubeck Typewritten Text
A. CHANGES TO THE TASK ANNOUNCEMENT/SOLICITATION
1. The proposal due date is changed from February 6, 2018 at 2:00 PM Pacific to February 16, 2018 at
2:00 PM Pacific.
2. Delete all references to Vets 100 and replace with Vets 4214.
3. Delete Section L7 in the solicitation and replace with the following:
L.7 SUBMISSION OF PROPOSALS
(a) Offerors shall submit proposals, in response to this solicitation, in two separate volumes as follows:
VOLUME I, TECHNICAL. Include all information required for evaluation, excluding any reference to price. Address all required evaluation criteria, as specified herein.
VOLUME II, PRICE. Include all information required for evaluation as well as the required completed solicitation sections. Include the bid bonds in this volume.
(b) Responses shall be submitted in hard copy format. Provide one (1) original hard copy of the bid bond, one (1) printed original proposal (Vol. I &II), and one (1) electronic copy on a CD/DVD (offerors shall ensure that proposal disks are virus free, and free of password protection) to the Contracting Officer, Heather Brubeck at
U.S. Coast Guard FD&CC Det. Seattle ATTN: Heather Brubeck 915 2nd Ave., Room 2664 Seattle, WA 98174
(c) Proposal Format: Do not exceed the page limitations set forth below. Technical Proposals shall be printed 8 ½” x 11”. A page is defined as one face of a sheet of paper containing information. The construction schedule may be presented on 11-in. by 17-in. page size. All pages submitted will be considered as part of the page count with the following exceptions: cover letter (limited to 1 page), schedule, resumes, JV paperwork, front cover, back cover and divider pages/tabs, pages defining acronyms, and past performance submissions. Typing shall not be less than 12 font.
Total page limitation for technical proposals is 20 pages. Individual resumes shall not exceed 2 pages.
(d) Requirements for Proposal Content: The proposal shall concisely describe the Offeror’s response to the requirements of the solicitation. Elaborate artwork or other aids are not necessary. Additionally, use of general or vague statements such as “standard procedures will be used” or “good business practices will be employed” is not acceptable.
B. CHANGES TO SPECIFICATIONS AND CLARIFICATIONS: See upcoming Amendment 0006
C. ANSWERS TO PROPOSER QUESTIONS:
Q. Per the RFP, proposal packages shall be submitted to heather.s.brubeck@uscg.mil. Please advise on where to include the Bid Bond – Volume 1 or Volume 2. Also, are we required to submit the original bid bond?
A. See Amendment 005A2.
Q. Will Liquidated Damages be assessed as part of this project? If so, in what amount?
A. No.
Q. The solicitation page 37/39, paragraph L.8.1 calls for “Proof of Current VETS-100” to be submitted with the price proposal. An internet search found that the VETS-100/100A has been replaced by the VETS-4214 and that form must be submitted between Aug. 1 and Sept. 30 for all contractors that have contracts that meet the requirement for submitting reports.
A. See above section A.
Q. The Veterans' Employment and Training Service 4212 Service Desk was contacted (their response is attached for reference) and they advised that “If a company is not subject to the regulatory requirements under the Vietnam Era Veterans' Readjustment Assistance Act (VEVRAA), they are exempt from the requirement to file a VETS-4212. A notification informing the VETS-4212 Service Desk that a company does not have to file a VETS-4212 report is not required”. As a contractor that has not had a past contract requirement to submit a VETS-100 or 4214, please confirm proposals will be considered responsive. Is a brief explanation in the proposal acceptable?
A. Vets 4212 or an explanation for exemption is acceptable.
Q. Page 36 and 37 describe “Factor 3” submittal requirements as including “a conceptual design and construction schedule.” Are you asking for a conceptual design to be submitted with each proposal (if so, what are the requirements of the design – narrative, drawings, and otherwise)? Or are you simply asking for a schedule, and only a schedule, that includes both design phase and construction phase tasks?
A. A project schedule. See sections L and M for details and necessary items it should include to be considered technically acceptable.
Q. Is there any possibility of the closing date for the solicitation being extended?
A. See above section A.
Q. Do covers, title pages, tabs or table of contents count against the 20 page limit of the technical proposal?
A. See above section A.
Q. Within the solicitation, there is reference to both mailing the proposal, and emailing the proposal. Would you please confirm the manner in which proposals are to be submitted?
A. See above section A.
Q. For the purpose of this response, we have entered into a Teaming Agreement with our major sub-contractor.
Should the Teaming Agreement be included with our proposal? If so, we ask that this document not count against the 20 page limit of the technical proposal.
A. See above section A.
Q The solicitation requires submission of a 20% offer guarantee. Amendment 1 requires all proposal be submitted electronically via email. Will a scanned copy of the offer guarantee included in the electronic proposal be acceptable, or shall hardcopies be mailed? Where in Volume 1 or Volume 2 shall the offer guarantee be included?
A. See above section A.
END OF AMENDMENT 0005
L.7 SUBMISSION OF PROPOSALS