Combined 70Z04724RPCNI0007 Rio Bayamon Phase I_RFI Log - responses v2.pdf

PDF 207 KB Posted

Attached to
Design/Build Construction for San Juan Hurricane Rebuild Rio Bayamon at USCG Base San Juan, San Juan, PR (Phase 1-Reprocurement)
Solicitation number
70Z04724RPCNI0007
Issued by

About this file

This document is an RFI (Request for Information) log related to a federal Design/Build construction contract opportunity for rebuilding hurricane-damaged shore facilities at the U.S. Coast Guard Sector San Juan in Rio Bayamon, Puerto Rico. The key details are:

The contract will be awarded to a contractor on the current DHS/USCG National Multiple Award Construction Contract III (NMACC III - Pool 1). Phase 1 of the project will focus on infrastructure, utilities distribution, and resiliency, including a new campus-wide generator system and water storage/distribution system. The solicitation required compliance with the Green Building Initiative's Guiding Principles, but third-party certification is not required. The contractor is responsible for integrating new Advanced Metering Infrastructure (AMI) data points into the existing DAS system. The solicitation was amended multiple times, extending the proposal due date and performance period. Contractors had questions regarding noise mitigation requirements, fuel storage, seismic criteria, fast-tracking the design, and utility coordination that were addressed by the government.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date Posted ID # Document Page Section Paragraph Answered Through

1 TOA PG. 3 RFP Part 1 PoP

The current period of performance of 389 calendar days will not be adequate to satisfy the Government’s design submittal requirements, manage the procurement of long lead items and perform the construction works. To mitigate this risk to the Government, and to enable the offeror to complete the design and construction in accordance with the Government requirements, will the Government please consider increasing the overall period of performance to a minimum of 831 calendar days?

The period of performace has been extended to 783 days. 6/21/24 8/7/2024 Amenment

2 Contracting Task Order Announcement

Subcontractors and suppliers have notified us that preparations of quotations for this Design-Build project will take more time than projects that are already fully designed. Information obtained from the site visit last week is being analyzed and incorporated into project narratives and estimates. Please consider extending the proposal due date by two weeks to allow for development and submission of accurate and cost competitive proposals.

Original proposal due date was extended to 9 August 2024. Please monitor SAM.gov and email for amendments to orignal solicitation. 7/16/24 7/30/2024 Amenment

3 Contracting Task Order Announcement

The Contract performance period is identified as 389 calendar days.

This performance period is insufficient for a Design-Build project with significant long lead equipment such as transformers and generators.

Assuming nine months for design, 12 months for long lead equipment, and six months for contract completion beyond delivery of long lead equipment, please revise the contract performance period to 27 months / 821 calendar days.

The period of performace has been extended to 783 days. 7/16/24 8/7/2024 Amenment

4 Electrical E-601 For reconnection purposes, please provide the size/description of the existing electrical feeders (Sheet Key Note #2) that runs from SU-1 & SU-2 up to existing Pad Mounted Transformers (Housing Cluster)

Exisiting sizes will need to be investigated by the design builld contractor. A separate site visit can be arranged to confirm this information. 7/16/24 7/30/2024 Amenment

5 Electrical E-606 Is the Contractor required to conduct elecrical testing on the existing primary feeders (that will be reconnected) running from SU-1 & SU-2 up to the new Pad Mounted Transformers? Please advise.

No, testing the existing cables is not part of the scope, however this was discussed with the Government during RFP document phase. "High Pot" testing may damage the existing cables. IF the DB believes cables should be tested this will require further disucssions with the government.

7/16/24 7/30/2024 Amenment

6 Electrical E-003

Since it is not shown or defined on the One Line Diagram (Sheet E- 610), Please clarify the purpose of the ''electrical feeder'' running from the Gate House up to the Lift Station Pump Vault shown on the Partial Electrical Site Plan (Sheet E-003) and also provide the description and size (conduits & wires) of this ''electrical feeder''.

Its for continuity of service to the gate house to correct the voltage issue at the gate house, as they it currently gets two different voltages from the generator and source transformer.

7/16/24 7/30/2024 Amenment

7 Electrical Section 01800

1.13 Page 5

Please confirm generator's diesel tanks: 1.2MW RNH-1 (10,000 gals) & 230kW RBH-2 (936 gals) shall not be completely filled with fuel by the contractor under this task order.

Confirmed 7/16/24 7/30/2024 Amenment

Fire Protection/Life

Safety

01800 Para 1.4;

1.10; 1.11

As the water storage tank will serve fire water demand as well as domestic water demand, please confirm whether it needs to be fully compliant with NFPA, including number of manways Yes, it needs to be fully compliant with NFPA including number of manways. 7/16/24 7/30/2024 Amenment

Electrical 01800 Para 1.13 To ensure the competing D/B contractors are consistently accounting for utility coordination fees, please provide an allowance for PREPA fees for disconnection of existing transformers and connection of primary to new transformers

The contractor is responsible to account for possible utility fees, coordinate with local utility companies and include the cost in the proposal 7/16/24 7/30/2024 Amenment

Environmental Please confirm no lead paint is present at any areas to be affected by this project LBP surveying was excluded from RBH during design. 7/16/24 7/30/2024 Amenment

Environmental Please confirm no PCBs are present at any areas to be affected by this project PCB surveying was excluded from RBH during design. 7/16/24 7/30/2024 Amenment

RFI Log - 70Z04724RPCNI0007: Design/Build San Juan Hurricane Rebuild Rio Bayamon at Base San Juan, San Juan, PR (Phase 1-Reprocurement)

Discipline Date Submitted

Question Gov't Response Include the following email addresses on all correspondence: Yolanda.l.davis@uscg.mil, sharan.a.lind@uscg.mil

RFP Reference

General Please confirm that there is no DBA waiver, and that the cost of DBA insurance must be included in addition to any locally required workmen's compensation programs

There is no DBA waiver. 7/16/24 8/7/2024 Amenment

13 7 1800 1.3.1.1

The RFP states that the project shall require compliance with the Guiding Principles and verification of documentation demonstrating compliance with the Guiding Principles shall be provided by the Green Building Initiative's (GBI) Guiding Principles Compliance Assessment Program. Further it states that the Contractor shall register and pay all fees associated with third-party review and certification. Due to the scope of the project and limited building square footage, please confirm that third-party building certification is not required for the project.

Third party building certification is not required for this project. 7/16/24 7/30/2024 Amenment

Section

01800/01900

1.3.1 Reference

to Attachment

C Page 2 & Attachment C page 10 2-4.2.2 Noise

Mitigation

Table 2-1 Generator Noise Level Regulation

a) Would the Noise Zone for this Project be considered Residential for both Generators to be installed; or will the Generator located at the Pump House be classified differently? The site is mainly residential, however the Government may clasify it differently to allow for greater dB levels. Final decision by the Government. 7/16/24 7/30/2024 Amenment

Section 01800

1.3.1 Reference

to Attachment

C Page 2 & Attachment C page 10 2-4.2.2 Noise

Mitigation

Table 2-1 Generator Noise Level- The max Dba for any noise zone is 72 Dba. All Major manufacturers we have contacted state the best Dba they can achieve will be 72.

a) Will this meet the requirement of the project?

b) If not, will Table 2-1 be the only basis considered?

Utilize sound attenuating enclosure providing the best practical attenuation.

Notify the Government that 72 Dba is the max achievable attenuation. The Government will need to evaluate table 2-1 vs. other site dBA requirements.

7/16/24 7/30/2024 Amenment

Section 01800

1.13 Page 5 &

1.13.15.1 page

Table 2 Fuel Utilization Requires the 230KW RBH-2 to have a Subbase Tank sized for 58.6 hrs assuming 100% use for 58.6 Hrs. Section

1.13.15.1 calls for a subbase tank for RBH-2 to support 48 hrs at 100% as a minimum. What is the required level of fuel storage required?

48hrs minimum is required. Closest nominal tank size provides above 48hrs depending on manufacturer. 7/16/24 7/30/2024 Amenment

Section

01800 1.8 Specs

1.8.2.5.3 Design

Load Criteria

Please confirm Under Occupancy (Risk) Category - Utility Foundations and structures IV and All other Foundations and Structures are II for seismic requirements. Does this apply to all exterior mounted Electrical Switchgear and Generator enclosures?

All other foundations and structures are Category II for seismic requirements. 7/16/24 7/30/2024 Amenment

18 N/A N/A N/A

In order to provide competitive and accurate pricing, we are requesting minimum 2-week extension to the bid date after all PPIs have been responded to and sent to the contractor. refer to RFI no. 2 7/16/24 7/30/2024 Amenment

19 24 1.13.16 1.13.16.1

Will the Government please provide a technician to integrate Advanced Metering Infrastructure data points from the new installed meters to the existing DAS Obvious Model A8812? The RFP calls for the provision of MODBUS current transformers / meters compatible with the existing (AMI) but does not specify who is responsible for integrating the new data points (metering data) with the existing system.

The contractor is responsible for installation of equipment. USCG and this contractor will need to coordinate with "Obvious" for a technicion to integrate the new componenents into the existing system.

7/16/24 7/30/2024 Amenment

20 5 1802 2.1.1

Section 01802 subpart 2.1.1 states that the contractor can choose to fast track the project with the design and construction between Phase I Sitework, Geotechnical, Foundation, and Civil work and Phase II Structural, Building Enclosure, and Remaining work. The subpart also states that design packages, and fast tracking, shall include a 35%, 65%, Final, and Corrected Final. Subpart 2.1.2.2 states the Government shall have a 14 day calendar review for the 35% and Corrected Final, and 21 day review for the 65% and Final submittals. The Period of Performance for the project is currently 389 calendar days. Please confirm it is acceptable to provide a fast track design for the entire scope of the project and only submit a 65%, Final, and Correct Final design in order to meet the Period of Performance.

Contractor is to comply with section 01802 as stated, the period of performance will be extended.

7/3/24 8/21/24 Amendment

21 4 1802 1.8.4

Section 01802 subpart 1.8.4 states that prior to the 65% design submittal, the Contractor and his design team shall meet at the project site and conduct a customer design presentation to update the customer on the design for the project. Due to scope of the project, please confirm it is acceptable to conduct the Customer Design Presentation virtually in-lieu of at the project site.

Contractor is to comply with section 01802 as stated, if this is a concern the contractor should capture the travel costs with their bid.

7/3/24 8/23/24 Amendment

22 N/A Section 1.10.2.1

N/A

RFP Section 1.10.2.1 – Fire Detection and Mass Notification defines the requirement for these systems to be installed in the Pump House.

The project drawings have nothing provided for the Fire Alarm System, not even a one line.

Will the Government please confirm if the intent is for the DB contractor to include/provide the FPE for the design of this Fire Alarm System?

Refer to the specfication 1.10 for Fire Alarm RFP requirements. Exact device quantity, locations and one-line shall be provided by the DB contractor. DB shall provide FPE.

7/3/24 8/23/24 Amendment

23 N/A Section

1.13.2.1.17 N/A

This section states to provide 15 KV class Switchgear (MSG1) equipped with 4 draw out breakers and Digital multi-function relaying.

a) What functions are being required as part of the relaying?

b) Are these relays to be monitored from any point?

c) If so, what is the location the information will be sent to?

The DB shall select digital multifunction relay and perform power systems study and derive all the relay settings. a) would like a digital multifunction relay for overcurrent; lockout functionality for each circuit breaker - integrated with differential relaying encompassing the bus. b & c)all monitoring will remain local in the switchgear house 7/3/24 8/23/24 Amendment

24 N/A Section 1.13.2.9

N/A

This section states to provide meters with wireless communications compatible with the existing AMI Infrastructure.

a) Please identify the metering manufacturer that is present onsite and system requirements.

b) Please provide acceptable manufacturers.

Refer to electrical specification section 1.13.16 and Attachment D, Configuration Standard Technical Order "Advanced Metering Infrastructure SILC-CSTO-36-11 31 17 11-01". CSTO documents indcate exact make and model of all required components CT's / meters, Tranceivers. Existing Data Acquisition Server manufacturer is Leviton/ Obvious model A8812 with AcquiSuite software.

7/3/24 8/23/24 Amendment

25 N/A Utility / General

N/A From the LUMA Utility what is the available Fault Current? This information needs to be used in the development of the Coordination Study.

Contractor shall be responbisble for consulting with LUMA to acquire fault current.

7/3/24 8/23/24 Amendment

26 N/A Utility / General

N/A

a) Does Luma have requirements or standard design/manufacturers for the Transclosures required for this project?

b) If so, please forward the required information?

Contractor shall be responbisble for consulting with Luma to aquire compliance information from Luma. Note - refer to the drawings, transclosures will not be utilized. 7/3/24 8/23/24 Amendment

27 N/A Electrical /

General N/A

Existing to be reused Medium Voltage Conductor sizes have not been provided. What is the size of the existing to remain MV loop conductor size?

Field verify 7/3/24 8/23/24 Amendment

28 N/A Electrical /

General N/A

Will the Government please confirm if the existing MV Loop that is to remain is a 3 or 4 wire system?

The understanding is it is a 3 wire at SU switches, but each phase is serviced by one conductor with ground derived at transformer. 7/3/24 8/23/24 Amendment

29 N/A Electrical /

General N/A

Will the Government please confirm if the Medium Voltage Primary System is a Loop system?

It is a loop system. Each phase creates a loop for a select group of transformers, refer to E-606. 7/3/24 8/23/24 Amendment

30 N/A

Section 1.13.9

Medium Voltage

Transformer s

N/A

This section supplies information on the functional requirement for the medium voltage transformers. Please supply the structural requirements for the transformer housing and Tank.

Tank: Sealed, with welded-on cover. Designed to withstand internal pressure of not less than 7 psi (50 kPa) without permanent distortion and 15 psig (104 kPa) without rupture. Comply with IEEE C57.12.36.

Enclosure Integrity: Comply with IEEE C57.12.28 for pad-mounted enclosures that contain energized electrical equipment in excess of 600 V that may be exposed to public. Integral skid mounting frame, suitable to allow skidding or rolling of transformer in any direction, and with provision for anchoring frame to pad.

2) Fabricate front sill, hood, and tank base of single-compartment transformers from stainless steel in accordance with ASTM A167, Type 304 or 304L

7/3/24 8/23/24 Amendment

31 N/A Electrical /

General N/A

Due to the lead-times associated with the MV transformers, will refurbished copper or aluminum wound transformers be allowable?

Transformers shall be new and in compliance with the UFC.

7/3/24 8/23/24 Amendment

32 E-001 N/A N/A

Sheet E-001 identifies RBH-8 Generator to be removed as being 220 Y/127V single-phase and is designated as being Housing Cluster X,Y,Z .

a) Will the Government please confirm if this is the correct information for the Voltage associated with the generator?

b) Please confirm that all new transformers for Housing Clusters T,U,V,W will be 13.2 to 120/240v Single-Phase and KVA is to remain the same for each cluster.

The generator is being demolished due to kVA capacity and incorrect voltage.

Refer to the new work plans. Secondary voltage of transformers 120/240v single phase is correct and kVA remains the same for each cluster. Primary voltage of cluster transformers is 7.62kV.

7/3/24 8/23/24 Amendment

33 N/A N/A N/A Please confirm if a (new) Automated Diesel Exhaust Fluid System serving the generator is desired, or if DEF will be maintained manually.

Engines are Tier 2 , not equipped with a DEF system. DEF system not in scope.

7/25/24 8/23/24 Amendment

34 M-101 Conceptual

Plans

The plans indicate (6) 55-Gallon drums of NaCIO to supply the domestic water treatment system. Please confirm the drums and chemicals will be purchased by the facility.

Contractor shall provide drums and chemicals as shown.

7/25/24 8/23/24 Amendment

35 C-104 Conceptual

Plans

a) Please confirm if Contractor is to provide a (new) containment pad for fuel delivery trucks.

b) If so, please provide approximate size based on the trucks that will be delivering fuel to the 10,000-gallon storage tank.

The filling service will be the same as existing, no new containment pad.

7/25/24 8/23/24 Amendment

36 N/A N/A N/A Please confirm if Contractor is to provide a (new) Deisel Fuel Polisher Yes, provide new deisel fuel polisher.

7/25/24 8/23/24 Amendment

Proposal RFI's

File details come from the government source that posted it. Updated .