Amendment_0005_70Z04724RPCNI0007 Rio Bayamon_pdf.pdf

PDF 268 KB Posted

Attached to
Design/Build Construction for San Juan Hurricane Rebuild Rio Bayamon at USCG Base San Juan, San Juan, PR (Phase 1-Reprocurement)
Solicitation number
70Z04724RPCNI0007
Issued by

About this file

This document is Amendment 0005 to the solicitation for the Design/Build Construction for San Juan Hurricane Rebuild Rio Bayamon at USCG Base San Juan, San Juan, PR (Phase 1-Reprocurement), Solicitation Number 70Z04724RPCNI0007.

The key details are:

  • The deadline to submit proposals has been extended to September 10, 2024 at 4:30 PM EST.
  • Responses to additional Requests for Information (RFIs) have been provided.
  • Revisions have been made to the specifications, including:
    • Increased coordination required with the local utility provider LUMA for documentation, permitting, and fees related to the 15kV switchgear and utility feeder extensions.
    • Responsibility for obtaining permits and paying any associated fees for the 15kV utility modifications has been clarified as the contractor's responsibility.
  • This is a design-build project posted exclusively for contractors on the current DHS/USCG National Multiple Award Construction Contract III (NMACC III - Pool 1).
  • The project is for rebuilding resilient shore facilities at USCG Sector San Juan that were damaged during Hurricane Maria. Phase 1 will focus on infrastructure, utilities distribution, and resiliency for the Rio Bayamon Housing sites, including a new campus-wide generator system and water storage/distribution.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

DESIGN/BUILD SAN JUAN HURRICANE REBUILD RIO BAYAMON at USCG BASE SAN JUAN, SAN JUAN, PR (PHASE-1

REPROCUREMENT)

Description of Amendment 0005 is continued on the next page.

NA

Contracting Division USCG, Facilities Design and Construction Center 5505 Robin Hood Road, Suite K Norfolk, VA 23513-2431

NA

70Z04724RPCNI0007

1 2

8/27/2024

06/06/2024

PROJECT NUMBER: 10878151

TITLE: DESIGN/BUILD SAN JUAN HURRICANE REBUILD RIO BAYAMON at USCG

BASE SAN JUAN, SAN JUAN, PR (PHASE-1 REPROCUREMENT)

AMENDMENT NUMBER: 0005

SOLICITATION NUMBER 70Z04724RPCNI0007 IS AMENDED AS FOLLOWS:

Amendment 0005 is published for the following:

1. To update the deadline to submit Proposals to September 10, 2024, at 4:30 PM (EST)

2. To provide responses to additional RFI’s.

3. To provide revised verbiage below to be incorporated into the 10878151 Specifications document.

Current verbiage

1.13.2.1.7 Provide 15kV class switchgear (‘MSG1’) equipped with four (4) draw[1]out circuit breakers and digital multi-function relaying. Coordinate revenue meter installation with the local utility provider, LUMA. The 15kV class switchgear shall be utilized for the generator and existing dual utility feeders to integrate into the existing 13.2kv loop. One (1) circuit breaker shall be dedicated for utility feeder #1; one (1) dedicated for utility feeder #2; one (1) dedicated for step-up transformer input; one (1) dedicated for output to 15kV switch ‘SU-1’. Switchgear enclosure shall be walk-in and resistant to hurricane winds. Provide 15kV underground feeder from ‘MSG1’ to ‘SU-1’.

Replace with

1.13.2.1.7 Provide 15kV class switchgear (‘MSG1’) equipped with four (4) draw[1]out circuit breakers and digital multi-function relaying. Contractor must coordinate early on with Luma to verify required documentation, permitting and is responsible for any fees LUMA may have that would be associated with installment of the switchgear. The 15kV class switchgear shall be utilized for the generator and existing dual utility feeders to integrate into the existing 13.2kv loop. One (1) circuit breaker shall be dedicated for utility feeder #1; one (1) dedicated for utility feeder #2; one (1) dedicated for step-up transformer input; one (1) dedicated for output to 15kV switch ‘SU-1’. Switchgear enclosure shall be walk-in and resistant to hurricane winds. Provide

15kV underground feeder from ‘MSG1’ to ‘SU-1’.

1.13.2.1.8 Coordinate utility feeder #1 and #2 extension to ‘MSG1’ with local utility provider, LUMA. This scope shall assume all duct bank and feeder extensions to ‘MSG1’ shall be provided by this contractor.

1.13.2.1.8 The contractor must coordinate early on for the extension of utility feeder #1 and #2 to

‘MSG1’ with local utility provider, LUMA. The contractor is responsible for LUMA requirements for documentation, permits and any possible fees pertaining to the extension of the feeders. This scope shall assume all duct bank and feeder extensions to ‘MSG1’ shall be provided by this contractor.

Demolish and replace two (2) 15kV 4-way sectionalizing switches, ‘SU-1’ and ‘SU-2’ serving the existing 13.2kV loop. Coordinate 15kV utility modifications including metering with the local utility provider, LUMA. Provide all 15kV underground work between ‘RBH-1’ electrical equipment (step-up transformer, 15kV switchgear) and ‘SU-1’. (SECTION 01800_1.1 - Page 2)

Demolish and replace two (2) 15kV 4-way sectionalizing switches, ‘SU-1’ and ‘SU-2’ serving the existing 13.2kV loop. The contactor must coordinate early on the 15kV utility modifications including metering with the local utility provider, LUMA and is responsible for acquiring any necessary permits including any associated fees. Provide all 15kV underground work between

‘RBH-1’ electrical equipment (step-up transformer, 15kV switchgear) and ‘SU-1’. (SECTION

01800_1.1 - Page 2)

END OF AMENDMENT LANGUAGE

Note

Failure to Acknowledge amendments may be cause for rejection of your offer.

SF30 Amend 0005 Rio Bayamon
Amendment 0005 Rio Bayamon housing PG2_v1

File details come from the government source that posted it. Updated .